Monthly State Let Maintenance Report For Beaumont District As Of Jul 14, 2017 Page 2 Of 3

Last Update: Monday, July 17, 2017
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyJEFFERSON
HighwayUS0069
FromJEFFERSON, HARDIN, AND ORANGE COUNTIES
ToJEFFERSON, HARDIN, AND ORANGE COUNTIES
CSJ6302-17-001
Proj IDRMC - 630217001
Work TypeMILL & INLAY/OVERLAY
 
0.0012081958.21501819.9024.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-12-17
Work Completed
Time Computed00-00-00
Contract Working Days79
Addl Days Granted0
Working Days Charged12
Percent Time Used15
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6302-17-001
DUSTROL, INC. (16.71)
STRIPE-A-ZONE, INC. (0.35)
CRABTREE BARRICADE SYSTEMS, INC. (4.97)
Contract #01174230
Totals2081958.21501819.90501819.9024.1

CountyCHAMBERS
HighwayIH0010
FromVARIOUS LOCATIONS IN CHAMBERS COUNTY
ToVARIOUS LOCATIONS IN CHAMBERS COUNTY
CSJ6302-43-001
Proj IDRMC - 630243001
Work TypePLANE AND OVERLAY
 
1.000635039.52641070.0599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-24-17
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted0
Working Days Charged32
Percent Time Used71
Contractor(s)
FORDE CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6302-43-001
A-1 EROSION CONTROL, LLC (0.50)
JMHP, INC. (5.17)
STRIPE LINES, INC. (2.84)
ENVIRONMENTAL ALLIES, L.P. (5.13)
Contract #11164210
Totals635039.52202400.13641070.0599.9

CountyJEFFERSON
HighwayUS0069
FromJEFFERSON, HARDIN, AND ORANGE COUNTIES
ToJEFFERSON, HARDIN, AND ORANGE COUNTIES
CSJ6304-63-001
Proj IDRMC - 630463001
Work TypeRUBBER ASPHALT CRACKSEALING
 
0.001353063.00377873.37100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-09-17
Work Completed06-02-17
Time Computed00-00-00
Contract Working Days16
Addl Days Granted0
Working Days Charged8
Percent Time Used50
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6304-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10164015
Totals353063.000.00377873.37100.0

CountyORANGE
HighwayIH0010
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ6305-18-001
Proj IDRMC - 630518001
Work TypeDITCH CLEANING
 
0.001482508.35480234.4599.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-09-17
Work Completed
Time Computed00-00-00
Contract Working Days74
Addl Days Granted0
Working Days Charged63
Percent Time Used85
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6305-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01174019
Totals482508.3519471.50480234.4599.5

CountyCHAMBERS
HighwayIH0010
FromVARIOUS LOCATIONS IN CHAMBERS COUNTY
ToAND LIBERTY COUNTY
CSJ6305-40-001
Proj IDRMC - 630540001
Work TypeCLEAN AND SEAL JOINTS AND CRACKS
 
100.000155611.20127324.40100.0
CountyLIBERTY
HighwayUS0059
FromVARIOUS LOCATIONS IN LIBERTY COUNTY
ToVARIOUS LOCATIONS IN LIBERTY COUNTY
CSJ6305-40-002
Proj IDRMC - 630540002
Work TypeCLEAN AND SEAL JOINTS AND CRACKS
 
100.000127014.00128395.60100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-27-17
Work Completed05-10-17
Time Computed00-00-00
Contract Working Days30
Addl Days Granted0
Working Days Charged9
Percent Time Used30
Contractor(s)
GREENPAK SOLUTIONS, LIMITED LIABILITY COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6305-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12164019
Totals282625.200.00255720.00100.0

CountyJEFFERSON
HighwaySH0073
FromTAYLORS BAYOU
ToSH82
CSJ6307-41-001
Proj IDRMC - 630741001
Work TypeOVERLAY ROADWAY
 
3.207624886.230.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days28
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FORDE CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-41-001
STRIPE LINES, INC. (4.53)
STRIPE-A-ZONE, INC. (0.00)
Contract #02174215
Totals624886.230.000.000.0

CountyJASPER
HighwayFM0254
FromJASPER,NEWTON,TYLER,LIBERTY
ToAND CHAMBERS COUNTIES
CSJ6308-26-001
Proj IDRMC - 630826001
Work TypeSEAL COAT
 
39.2361177089.581501272.8399.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-01-17
Work Completed
Time Computed00-00-00
Contract Working Days30
Addl Days Granted9
Working Days Charged16
Percent Time Used41
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6308-26-001
BRYDL CONTRACTING, INC. (0.81)
Contract #11164018
Totals1177089.58626450.391501272.8399.9

CountyHARDIN
HighwaySH0105
FromHARDIN AND JEFFERSON COUNTIES
ToHARDIN AND JEFFERSON COUNTIES
CSJ6308-39-001
Proj IDRMC - 630839001
Work TypeFULL DEPTH CONCRETE PAVEMENT REPAIR
 
0.001344550.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-06-17
Work Completed
Time Computed00-00-00
Contract Working Days28
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6308-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01174231
Totals344550.000.000.000.0

CountyLIBERTY
HighwayFM2518
FromLOCATIONS IN LIBERTY,JEFFERSON,HARDIN,
ToORANGE,JASPER AND NEWTON COUNTIES
CSJ6309-84-001
Proj IDRMC - 630984001
Work TypeASPHALTIC PAVEMENT PRESERVATION TREATMEN
 
8.560353399.9572899.8220.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-12-17
Work Completed
Time Computed00-00-00
Contract Working Days30
Addl Days Granted0
Working Days Charged7
Percent Time Used23
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6309-84-001
INTERSTATE BARRICADES & MARKINGS, INC. (14.27)
Contract #01174232
Totals353399.9570057.8272899.8220.6

CountyNEWTON
HighwayUS0190
FromVARIOUS LOCATIONS - US 190(NEWTON) &
ToUS 96 (KIRBYVILLE)
CSJ6310-16-001
Proj IDRMC - 631016001
Work TypeMILL & INLAY/OVERLAY
 
1.002970890.10741091.2076.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-15-17
Work Completed
Time Computed00-00-00
Contract Working Days30
Addl Days Granted0
Working Days Charged20
Percent Time Used66
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6310-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01174233
Totals970890.10458342.44741091.2076.3

CountyLIBERTY
HighwayUS0090
FromVARIOUS
ToVARIOUS
CSJ6310-61-001
Proj IDRMC - 631061001
Work TypeLIBERTY ~ ROW MOWING
 
355.000555351.2877249.6013.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-01-17
Work Completed
Time Computed00-00-00
Contract Working Days186
Addl Days Granted0
Working Days Charged22
Percent Time Used11
Contractor(s)
ANGEL LADY SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6310-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03174010
Totals555351.2877249.6077249.6013.9

CountyJASPER
HighwayFM2799
From0.32 MILES EAST OF FM 3414, EAST
ToTO FM 777
CSJ6310-74-001
Proj IDRMC - 631074001
Work TypeREHABILITATE EXISTING ROADWAY
 
1.220538722.709876.001.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-14-17
Work Completed
Time Computed00-00-00
Contract Working Days30
Addl Days Granted0
Working Days Charged5
Percent Time Used16
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6310-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03174011
Totals538722.709876.009876.001.8

CountyJEFFERSON
HighwayUS0069
FromDISTRICT WIDE
ToDISTRICT WIDE
CSJ6310-80-001
Proj IDRMC - 631080001
Work TypeTRAFFIC CONTROL SERVICES
 
0.0011398989.0866140.114.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-01-17
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged30
Percent Time Used8
Contractor(s)
AREA WIDE PROTECTIVE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6310-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02174017
Totals1398989.0866140.1166140.114.7

CountyJASPER
HighwayUS0096
FromVARIOUS LOCATIONS
ToIN JASPER COUNTY
CSJ6310-86-001
Proj IDRMC - 631086001
Work TypeJASPER ~ ROW MOWING
 
328.700583673.62130612.5322.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-06-17
Work Completed
Time Computed00-00-00
Contract Working Days186
Addl Days Granted0
Working Days Charged9
Percent Time Used4
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6310-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03174012
Totals583673.62130612.53130612.5322.3

CountyCHAMBERS
HighwayIH0010
FromROW MOWING IN
ToCHAMBERS COUNTY
CSJ6311-74-001
Proj IDRMC - 631174001
Work TypeANAHUAC ~ ROW MOWING
 
328.300590284.0021240.003.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-12-17
Work Completed
Time Computed00-00-00
Contract Working Days186
Addl Days Granted0
Working Days Charged9
Percent Time Used4
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03174210
Totals590284.0021240.0021240.003.5

CountyHARDIN
HighwayUS0069
FromVARIOUS LOCATIONS
ToVARIOUS
CSJ6312-01-001
Proj IDRMC - 631201001
Work TypeKOUNTZE ~ ROW MOWING
 
250.000463360.200.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-05-17
Work Completed
Time Computed00-00-00
Contract Working Days186
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6312-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03174211
Totals463360.200.000.000.0

CountyJEFFERSON
HighwayUS0069
FromVARIOUS
ToVARIOUS
CSJ6312-06-001
Proj IDRMC - 631206001
Work TypePT ARTHUR ~ ROW MOWING
 
144.000439852.202700.000.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-01-17
Work Completed
Time Computed00-00-00
Contract Working Days132
Addl Days Granted0
Working Days Charged1
Percent Time Used0
Contractor(s)
WAYNE YANCEY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6312-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03174212
Totals439852.200.002700.000.6

CountyORANGE
HighwayIH0010
FromVARIOUS ROADWAYS
ToVARIOUS
CSJ6312-10-001
Proj IDRMC - 631210001
Work TypeORANGE ~ ROW MOWING
 
342.600453866.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-20-17
Work Completed
Time Computed00-00-00
Contract Working Days108
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6312-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03174213
Totals453866.500.000.000.0

CountyNEWTON
HighwaySS0272
FromSH 12/SH 87
ToSS 272
CSJ6313-09-001
Proj IDRMC - 631309001
Work TypeSS 272 OVERLAY/SH 87 MILL & INLAY
 
1.392538466.010.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days16
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6313-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05174208
Totals538466.010.000.000.0

CountyCHAMBERS
HighwayIH0010
FromCHAMBERS, LIBERTY, JEFFERSON COUNTIES
ToCHAMBERS, LIBERTY, JEFFERSON COUNTIES
CSJ6313-38-001
Proj IDRMC - 631338001
Work TypeMETAL BEAM GUARD FENCE REPAIRS
 
0.001445531.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6313-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06174207
Totals445531.000.000.000.0

page 1 | page 2 | page 3