Monthly State Let Construction Report For Bryan District As Of Mar 13, 2024 Page 1 Of 5

Last Update: Wednesday, March 13, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyROBERTSON
HighwayUS 79
From0.1 MI S OF 5TH STREET
To0.1 MI N OF 5TH STREET
CSJ0049-07-069
Proj IDSTP 2024(610)VRU
Work TypeSAFETY IMPROVEMENT PROJECTS
 
467833.550.000.0
CountyROBERTSON
HighwayUS 190
From0.3 MI N OF SAN GABRIEL ACCESS DRIVEWAY
To0.4 MI S OF SAN GABRIEL ACCESS DRIVEWAY
CSJ0049-08-077
Proj IDF 2024(611)
Work TypeTRAFFIC CONTROL DEVICES
 
435233.750.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days73
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ELECNOR BELCO ELECTRIC, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0049-07-069
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01243036
Totals903067.300.000.000.0

CountyROBERTSON ETC
HighwayUS 190 ETC
FromFM 391
ToBRADFORD STREET
CSJ0049-08-074
Proj IDSTP 2022(856)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
4264422.034471196.9899.9
Work Order09-20-22
Work Began01-19-23
Work Completed
Time Computed12-19-22
Contract Working Days211
Addl Days Granted0
Working Days Charged204
Percent Time Used96
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0049-08-074
ALLSTATE SIGNAL & CONSTRUCTION, LLC (26.88)
CEN TEX HYDROSEED, INC. (1.93)
STRIPE LINES, INC. (1.59)
Contract #08223221
Totals4264422.0336072.184471196.9899.9

CountyBRAZOS
HighwayBS 6-R
From15TH STREET
ToFM 158
CSJ0049-09-076
Proj IDF 2022(857)
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
0.754284960.00377072.0693.3
CountyBRAZOS
HighwayBS 6-R
FromSH 21
ToFM 158
CSJ0049-09-083
Proj IDSTP 2022(858)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.977730947.27698234.8295.5
CountyBRAZOS
HighwayBS 6-R
FromFM 158
ToFM 60
CSJ0050-01-083
Proj IDF 2022(857)
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
4.1121.250.000.0
CountyBRAZOS
HighwayBS 6-R
FromFM 158
ToFM 60
CSJ0050-01-088
Proj IDSTP 2022(858)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
4.1254220936.544115534.9597.5
Work Order09-21-22
Work Began02-20-23
Work Completed
Time Computed12-20-22
Contract Working Days119
Addl Days Granted65
Working Days Charged161
Percent Time Used87
Contractor(s)
BRAZOS PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0049-09-076
CEN TEX HYDROSEED, INC. (0.21)
HIGHWAY 1 LLC (5.79)
LONESTAR TRAFFIC SAFETY, LLC (0.27)
SPEEDY PAVING (6.02)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC. (9.72)
BATTEN DRILLING, INC. (0.00)
Contract #08223008
Totals5236845.0656155.365190841.8397.0

CountyBRAZOS
HighwayBS 6-R
FromOLD HEARNE ROAD
To15TH STREET
CSJ0049-09-087
Proj IDC 49-9-87
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
4137992.913883762.8295.7
Work Order01-20-22
Work Began05-13-22
Work Completed
Time Computed04-20-22
Contract Working Days151
Addl Days Granted0
Working Days Charged239
Percent Time Used158
Contractor(s)
LARRY YOUNG PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0049-09-087
BROCK CONSTRUCTION, LLC (0.24)
CEN TEX HYDROSEED, INC. (2.20)
CITYLYNX, INC. (24.49)
ELLIOTT CONSTRUCTION, LLC (0.00)
STRIPE LINES, INC. (2.58)
LANDSHARK HYDROEXCAVATION SERVICES, INC. (0.16)
HORSESHOE CONSTRUCTION, INC. (2.08)
JOHN WRIGHT CONSTRUCTION (0.65)
SARVICUS LLC (25.73)
BATTEN DRILLING, INC. (0.82)
Contract #12213210
Totals4137992.91176662.923883762.8295.7

CountyBRAZOS ETC
HighwayUS 190 ETC
From0.43 MI S OF FM 2818
To0.61 MI S OF FM 2818
CSJ0049-09-089
Proj IDSTP 2022(860)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
5909647.305776629.9397.7
Work Order09-20-22
Work Began01-17-23
Work Completed
Time Computed12-19-22
Contract Working Days178
Addl Days Granted0
Working Days Charged179
Percent Time Used100
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0049-09-089
CEN TEX HYDROSEED, INC. (1.96)
BROCK CONSTRUCTION, LLC (0.61)
J & M CONTRACTING, COMPANY (12.64)
MILSTEAD HIGHWAY SERVICES, LLC (1.94)
PINNACLE GRINDING AND GROOVING LLC (0.17)
STRIPE LINES, INC. (1.92)
PROFESSIONAL TRAFFIC CONTROL LLC (0.17)
THIRD COAST SERVICES LLC (0.13)
Contract #08223216
Totals5909647.3059352.915776629.9397.7

CountyBRAZOS ETC
HighwayUS 190 ETC
FromON US 190 WFR FROM OSR
ToBS 6R
CSJ0049-09-095
Proj IDF 2024(097)
Work TypeSEAL COAT
 
3.86324509977.032989863.7812.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-16-23
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days135
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
D. I. J. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0049-09-095
INTERSTATE BARRICADES & MARKINGS, INC. (1.83)
RED SIXTEEN CONSTRUCTION, INC (1.71)
Contract #10233005
Totals24509977.03867576.822989863.7812.1

CountyBRAZOS
HighwayUS 190 ETC
FromON US 190 WFR
ToAT ELM FORK CREEK
CSJ0049-09-096
Proj IDBR 2023(632)
Work TypeBRIDGE MAINTENANCE
 
1888555.001672681.6188.5
Work Order06-14-23
Work Began07-18-23
Work Completed
Time Computed07-14-23
Contract Working Days170
Addl Days Granted0
Working Days Charged128
Percent Time Used75
Contractor(s)
MB WESTERN INDUSTRIAL CONTRACTING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0049-09-096
DIIBS SPECIALISTS, LLC (7.09)
MACIAS SPECIALTY CONTRACTING LLC (10.76)
BROCK CONSTRUCTION, LLC (1.02)
CHEROKEE SERVICES (3.18)
S & S BRIDGE PAINTING, INC. (18.26)
LONESTAR TRAFFIC SAFETY, LLC (0.74)
AWP SAFETY (0.10)
SAPO ENGINEERING CONSULTANTS, LLC (2.73)
Contract #05233232
Totals1888555.00161956.171672681.6188.5

CountyROBERTSON ETC
HighwayFM 46 ETC
FromFALLS COUNTY LINE
ToSH 14
CSJ0049-14-014
Proj IDF 2021(768)
Work TypeTRAFFIC CONTROL DEVICES
 
16.2762552415.922553445.8099.9
Work Order06-22-22
Work Began08-25-22
Work Completed
Time Computed07-22-22
Contract Working Days65
Addl Days Granted0
Working Days Charged100
Percent Time Used153
Contractor(s)
STRIPE LINES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0049-14-014
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04223014
Totals2552415.920.002553445.8099.9

CountyROBERTSON ETC
HighwaySH 14 ETC
FromFM 46
ToSH 6
CSJ0049-15-014
Proj IDF 2022(080)
Work TypeSEAL COAT
 
4.82714704110.3513973211.6795.0
Work Order12-30-21
Work Began04-18-22
Work Completed
Time Computed04-18-22
Contract Working Days122
Addl Days Granted0
Working Days Charged101
Percent Time Used82
Contractor(s)
D. I. J. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0049-15-014
RED SIXTEEN CONSTRUCTION, INC (0.86)
INTERSTATE BARRICADES & MARKINGS, INC. (1.27)
MEMCO STAFFING, LLC (0.06)
Contract #10213001
Totals14704110.35162586.1013973211.6795.0

CountyBRAZOS ETC
HighwayBS 6-R ETC
FromAT WALTON DRIVE/NEW MAIN DRIVE
To.WA
CSJ0050-01-087
Proj IDSTP 2021(024)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.6001136623.601208287.1399.9
Work Order11-19-20
Work Began04-20-21
Work Completed
Time Computed02-17-21
Contract Working Days158
Addl Days Granted0
Working Days Charged168
Percent Time Used106
Contractor(s)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0050-01-087
AREA WIDE PROTECTIVE, INC. (1.66)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (3.47)
LINEAR TRAFFIC MARKINGS LLC (0.48)
PALOMARES CONSTRUCTION, INC. (1.40)
A. L. HELMCAMP, INC. (8.13)
Contract #10203019
Totals1136623.600.001208287.1399.9

CountyGRIMES
HighwaySH 6
FromAT FM 2
To.
CSJ0050-03-096
Proj IDSTP 2021(770)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.40018052622.0012108707.9767.0
Work Order09-16-21
Work Began11-01-21
Work Completed
Time Computed11-01-21
Contract Working Days579
Addl Days Granted0
Working Days Charged396
Percent Time Used68
Contractor(s)
LARRY YOUNG PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0050-03-096
ALLSTATE SIGNAL & CONSTRUCTION, LLC (1.47)
DIIBS SPECIALISTS, LLC (0.86)
JB PINNACLE GROUP, LLC (0.99)
PINNACLE GRINDING AND GROOVING LLC (0.16)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.23)
D. I. J. CONSTRUCTION, INC. (1.08)
LONESTAR TRAFFIC SAFETY, LLC (0.30)
TEXAS STERLING CONSTRUCTION CO. (3.19)
TORO BRAVO CONSTRUCTION, LLC (0.32)
BATTEN DRILLING, INC. (0.92)
TOM-MAC, INC. (0.73)
WATERS CONSTRUCTION COMPANY, INC. (0.83)
Contract #08213005
Totals18052622.00498417.7812108707.9767.0

CountyGRIMES
HighwaySH 6
FromBRAZOS COUNTY LINE
ToWALLER COUNTY LINE
CSJ0050-03-100
Proj IDC 50-3-100
Work TypeOVERLAY
 
14.3835798125.917357130.9199.9
Work Order08-17-18
Work Began08-12-19
Work Completed
Time Computed11-15-18
Contract Working Days72
Addl Days Granted95
Working Days Charged177
Percent Time Used105
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0050-03-100
AREA WIDE PROTECTIVE, INC. (0.12)
BATTERSON,LLP (3.03)
CPAVE, INC. (3.60)
DUSTROL, INC. (4.21)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.35)
Contract #07183040
Totals5798125.910.007357130.9199.9

CountyGRIMES
HighwaySH 6
From0.3 MI N OF FM 2988
To0.1 MI S OF FM 2988
CSJ0050-03-109
Proj IDSTP 2B23(029)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
620873.55238250.8838.3
CountyGRIMES
HighwayFM 149
FromSH 90
To0.2 MI E OF FM 2562
CSJ0720-01-044
Proj IDSTP 2B23(029)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
4951395.50986601.0019.9
Work Order09-07-23
Work Began11-08-23
Work Completed
Time Computed11-08-23
Contract Working Days232
Addl Days Granted0
Working Days Charged56
Percent Time Used24
Contractor(s)
LARRY YOUNG PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0050-03-109
CEN TEX HYDROSEED, INC. (2.10)
DIIBS SPECIALISTS, LLC (1.10)
HIGHWAY 1 LLC (2.39)
MURRAY CONSTRUCTION (1.04)
PROFESSIONAL TRAFFIC CONTROL LLC (0.12)
WATERS CONSTRUCTION COMPANY, INC. (2.03)
JB PINNACLE GROUP, LLC (0.00)
Contract #08233231
Totals5572269.05347856.931224851.8821.9

CountyGRIMES
HighwaySH 6 ETC
FromON SH 6 SB
ToAT BS 6S NB
CSJ0050-03-114
Proj IDBR 2B23(226)
Work TypeBRIDGE MAINTENANCE
 
2245311.70452162.6520.1
Work Order10-23-23
Work Began01-17-24
Work Completed
Time Computed11-22-23
Contract Working Days164
Addl Days Granted0
Working Days Charged22
Percent Time Used13
Contractor(s)
SCR CIVIL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0050-03-114
S & S BRIDGE PAINTING, INC. (6.68)
JB PINNACLE GROUP, LLC (11.09)
JE CASEY, LLC (3.24)
HIGHWAY 1 LLC (3.10)
DUSTROL, INC. (1.00)
J. H. ODEN CONTRACTING COMPANY (2.07)
NELSON INDUSTRIAL SERVICES, INC. (1.20)
LONESTAR TRAFFIC SAFETY, LLC (1.13)
Contract #09233018
Totals2245311.70433766.65452162.6520.1

CountyWALKER ETC
HighwaySH 19 ETC
From0.4 MI N OF SH 30
ToIH 45
CSJ0109-09-066
Proj IDF 2023(144)
Work TypeSEAL COAT
 
23496228.9720377174.3686.7
Work Order12-05-22
Work Began04-24-23
Work Completed
Time Computed04-24-23
Contract Working Days135
Addl Days Granted0
Working Days Charged114
Percent Time Used84
Contractor(s)
D. I. J. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0109-09-066
RED SIXTEEN CONSTRUCTION, INC (0.82)
MEMCO STAFFING, LLC (0.06)
Contract #10223004
Totals23496228.97253970.1420377174.3686.7

CountyWALKER ETC
HighwaySH 19 ETC
From0.4 MI N OF SH 30
ToIH 45
CSJ0109-09-068
Proj IDF 2B23(022)
Work TypeTRAFFIC CONTROL DEVICES
 
4204817.531620564.1038.5
Work Order09-14-23
Work Began01-09-24
Work Completed
Time Computed10-14-23
Contract Working Days100
Addl Days Granted0
Working Days Charged28
Percent Time Used28
Contractor(s)
D. I. J. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0109-09-068
SURFACE PREPARATION TECHNOLOGIES, LLC (1.41)
Contract #08233225
Totals4204817.531459728.541620564.1038.5

CountyWALKER
HighwaySH 75
FromAT 2793
To.
CSJ0110-01-049
Proj IDF 2021(717)
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
0.200946421.731245903.8899.9
Work Order09-29-21
Work Began12-16-21
Work Completed
Time Computed12-16-21
Contract Working Days47
Addl Days Granted0
Working Days Charged96
Percent Time Used204
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0110-01-049
STRIPE LINES, INC. (5.65)
CEN TEX HYDROSEED, INC. (2.93)
COLD CREEK CONSTRUCTION, LTD (3.92)
J & M CONTRACTING, COMPANY (4.05)
AREA WIDE PROTECTIVE, INC. (1.90)
STRIPE-A-ZONE, LLC (1.32)
Contract #07213042
Totals946421.736755.001245903.8899.9

CountyWASHINGTON ETC
HighwayUS 290 ETC
From0.1 MI W OF FM 390
To0.1 MI E OF FM 2679
CSJ0114-09-089
Proj IDF 2021(776)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2.6001254827.801040820.1482.9
Work Order09-21-21
Work Began04-26-22
Work Completed
Time Computed12-20-21
Contract Working Days199
Addl Days Granted0
Working Days Charged185
Percent Time Used92
Contractor(s)
CITYLYNX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0114-09-089
SEMPER STRIPING LLC (2.75)
Contract #08213250
Totals1254827.80231812.491040820.1482.9

CountyWASHINGTON ETC
HighwayUS 290 ETC
From0.1 MI W OF FM 1948
To0.1 MI E OF FM 1948
CSJ0114-09-090
Proj IDSTP 2022(622)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
286956.50265154.8392.4
Work Order07-11-22
Work Began06-15-23
Work Completed
Time Computed10-09-22
Contract Working Days118
Addl Days Granted0
Working Days Charged112
Percent Time Used94
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0114-09-090
SEMPER STRIPING LLC (5.23)
HIGHWAY 1 LLC (5.27)
Contract #06223039
Totals286956.501500.00265154.8392.4

CountyWASHINGTON
HighwayUS 290
From1.5 MI E OF FM 1155
To1 MI W OF FM 1155
CSJ0114-10-101
Proj IDF 2023(761)
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
4792165.56393000.008.2
CountyWASHINGTON
HighwaySH 36
From0.62 MI S OF FM 109
To0.91 MI S FM 109
CSJ0187-01-052
Proj IDF 2023(761)
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
1762176.80490815.3027.8
Work Order08-03-23
Work Began01-05-24
Work Completed
Time Computed11-01-23
Contract Working Days179
Addl Days Granted0
Working Days Charged18
Percent Time Used10
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0114-10-101
STRIPE LINES, INC. (2.58)
CEN TEX HYDROSEED, INC. (1.22)
J & M CONTRACTING, COMPANY (9.62)
THIRD COAST SERVICES LLC (6.77)
Contract #06233615
Totals6554342.36842415.30883815.3013.4

page 1 | page 2 | page 3 | page 4 | page 5