Monthly State Let Construction Report For Bryan District As Of Nov 20, 2014 Page 1 Of 3

Last Update: Thursday, November 20, 2014
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyBRAZOS
Highway SH 6
From FM 158
To FM 2818
CSJ 0049-12-087
Proj ID DMO 2013(257)
Work Type UPGRADE FREEWAY RAMPS
 
6.300 9587817.87 700463.92 6155113.73 64.1
Work Order 02-19-13
Work Began 05-16-13
Work Completed  
Time Computed 05-16-13
Contract Working Days 288
Addl Days Granted 126
Working Days Charged 241
Percent Time Used 58
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0049-12-087
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC.(8.62%)
COWBELL TRAFFIC SERVICES, INC. (0.08%)
FLASHER EQUIPMENT COMPANY(1.41%)
FORTSON CONTRACTING, INC.(0.67%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.85%)
WILLOW CITY SIGN & RAIL, INC.(2.31%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(2.10%)
PRIME ECO GROUP, INC.(0.00%)
PAVETEX ENGINEERING & TESTING, INC.(0.00%)
TRAFCO INDUSTRIES, INC.(0.00%)
BUYERS BARRICADES, INC.(0.00%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00%)
Contract # 12123005
Totals 9587817.87 700463.92 6155113.73 64.1

CountyBRAZOS
Highway SH 6
From FM 60
To ROCK PRAIRIE ROAD
CSJ 0049-12-091
Proj ID NH 2014(455)
Work Type HMA OVERLAY
 
4.824 1420898.48 11456.00 1226461.40 86.3
Work Order 03-14-14
Work Began 08-10-14
Work Completed  
Time Computed 06-12-14
Contract Working Days 46
Addl Days Granted 0
Working Days Charged 42
Percent Time Used 91
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0049-12-091
ROADSAFE TRAFFIC SYSTEMS, INC. (3.59%)
A BROTHERS MILLING, LLC(1.88%)
PRIMATE CONSTRUCTION, INC. (1.58%)
WEST TEXAS RUMBLE STRIP(0.28%)
FORTSON CONTRACTING, INC.(1.65%)
Contract # 02143005
Totals 1420898.48 11456.00 1226461.40 86.3

CountyGRIMES
Highway SH 6
From 0.41 MILE NORTH OF FM 3090
To 0.5 MILE SOUTH OF SP 515 / SH 105
CSJ 0050-03-090
Proj ID STP 1302(048)SB
Work Type FRTG ROADS, U - TURNS AND PED. IMP.
 
3.470 4575220.78 245169.53 1965149.45 42.9
Work Order 01-09-14
Work Began 04-09-14
Work Completed  
Time Computed 04-09-14
Contract Working Days 162
Addl Days Granted 10
Working Days Charged 106
Percent Time Used 61
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0050-03-090
FARR FOUNDATION, INC.(6.89%)
CEN TEX HYDROSEED, INC.(1.35%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.89%)
BORING & TUNNELING COMPANY OF AMERICA, INC.(0.22%)
SCOTT DERR PAINTING CO, LLC(0.92%)
KELLYSTONE, INC(2.14%)
MURRAY CONSTRUCTION(0.56%)
A BRUSH ABOVE SERVICES, LLC(0.42%)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC.(5.44%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.38%)
ACCESS DATA SUPPLY, INC. (0.00%)
TRUCKS UNLIMITED (0.00%)
Contract # 09133018
Totals 4575220.78 245169.53 1965149.45 42.9

CountyWALKER
Highway SH 75 ETC
From GRAHAM ROAD
To THE MONTGOMERY COUNTY LINE
CSJ 0110-01-037
Proj ID STP 2014(027)
Work Type SEAL COAT
 
210.517 6858556.70 115302.51 6385299.14 93.2
Work Order 10-30-13
Work Began 06-02-14
Work Completed  
Time Computed 06-02-14
Contract Working Days 46
Addl Days Granted 0
Working Days Charged 56
Percent Time Used 121
Contractor(s)
NEWMAN & KENG PAVING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0110-01-037
COWBELL TRAFFIC SERVICES, INC. (0.12%)
D. I. J. CONSTRUCTION, INC.( 14.72%)
BRYDL CONTRACTING, INC.(0.84%)
Contract # 09133235
Totals 6858556.70 115302.51 6385299.14 93.2

CountyBURLESON
Highway SH 21
From THE EAST END OF YEGUA CREEK BRIDGE
To THE WEST CITY LIMITS OF CALDWELL.
CSJ 0116-02-041
Proj ID NH 2014(588)
Work Type OVERLAY
 
9.954 5811633.87 361597.03 361597.03 6.2
Work Order 07-25-14
Work Began 10-23-14
Work Completed  
Time Computed 08-10-14
Contract Working Days 160
Addl Days Granted 0
Working Days Charged 8
Percent Time Used 5
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0116-02-041
COWBELL TRAFFIC SERVICES, INC. (0.42%)
D. I. J. CONSTRUCTION, INC.(2.26%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.95%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.19%)
TEXAS TRUCKING COMPANY, INC. (3.02%)
PAVETEX ENGINEERING & TESTING, INC.(0.83%)
Contract # 04143202
Totals 5811633.87 361597.03 361597.03 6.2

CountyBRAZOS
Highway SH 21
From DEMOCRAT ROAD
To FM 974
CSJ 0117-02-028
Proj ID C 117-2-28
Work Type WIDEN NON - FREEWAY FACILITY
 
5.416 13287731.94 2000.00 12974156.76 97.6
Work Order 10-18-12
Work Began 11-08-12
Work Completed  
Time Computed 11-07-12
Contract Working Days 288
Addl Days Granted 5
Working Days Charged 286
Percent Time Used 97
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0117-02-028
TEXAS ALTERNATIVE GRASSER, INC.(0.31%)
SOUTHEAST GRINDING & GROOVING, LLC (0.05%)
SCR CONSTRUCTION CO., INC. (0.50%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.15%)
M & M INDUSTRIAL PAINTING(0.04%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.13%)
FORTSON CONTRACTING, INC.(1.69%)
FLASHER EQUIPMENT COMPANY(0.87%)
COWBELL TRAFFIC SERVICES, INC. (0.11%)
AMERICAN REMEDIATION OPTIONS, INC. (0.31%)
MESA ROD BUSTERS, INC. (0.08%)
Contract # 08123003
Totals 13287731.94 2000.00 12974156.76 97.6

CountyMADISON
Highway US 190
From MADISON AVE. IN NORTH ZULCH
To FM 978
CSJ 0117-04-038
Proj ID NH 1402(087)
Work Type REHABILITATE EXISTING ROAD
 
12.268 4647858.87 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-10-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 91
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0117-04-038
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143231
Totals 4647858.87 0.00 0.00 0.0

CountyFREESTONE
Highway SH 75 ETC
From US 84
To THE LEON COUNTY LINE
CSJ 0166-03-031
Proj ID STP 2015(165)
Work Type SEAL COAT
 
258.040 9728740.48 0.00 0.00 0.0
Work Order 10-09-14
Work Began 00-00-00
Work Completed  
Time Computed 10-25-14
Contract Working Days 52
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
NEWMAN & KENG PAVING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0166-03-031
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143007
Totals 9728740.48 0.00 0.00 0.0

CountyWALKER
Highway SH 75
From AT THE INTERCHANGE WITH IH 45 AND
To FM 1791
CSJ 0166-08-043
Proj ID STP 2013(777)
Work Type UPGRADE INTERCHANGE TO STANDARDS
 
0.799 8789231.37 97167.34 4257086.15 48.1
Work Order 07-31-13
Work Began 11-14-13
Work Completed  
Time Computed 10-29-13
Contract Working Days 270
Addl Days Granted 7
Working Days Charged 115
Percent Time Used 41
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0166-08-043
HAYWOOD BAKER(4.67%)
WILLOW CITY SIGN & RAIL, INC.(1.24%)
CEN TEX HYDROSEED, INC.(1.09%)
SCOTT DERR PAINTING CO, LLC(0.12%)
J & M CONTRACTING, COMPANY ( 38.40%)
THIRD COAST SERVICES LLC (4.59%)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.10%)
WATERS CONSTRUCTION CO., INC.(0.40%)
Contract # 05133002
Totals 8789231.37 97167.34 4257086.15 48.1

CountyMILAM
Highway US 190
From THE BELL COUNTY LINE
To 1.7 MILES WEST OF FM 486
CSJ 0185-02-034
Proj ID NH 2013(379)
Work Type REHABILITATE EXISTING ROADWAY
 
27.116 5587875.87 153.00 5373775.36 97.1
Work Order 05-02-13
Work Began 05-23-13
Work Completed  
Time Computed 05-18-13
Contract Working Days 138
Addl Days Granted 0
Working Days Charged 189
Percent Time Used 136
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0185-02-034
ROADWAY SPECIALTIES, INC.(3.11%)
D. I. J. CONSTRUCTION, INC.(2.27%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (0.92%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.42%)
PENHALL COMPANY(0.31%)
ROADWAY CONSTRUCTION, LLC(0.59%)
PRIME ECO GROUP, INC.(0.00%)
Contract # 02133220
Totals 5587875.87 153.00 5373775.36 97.1

CountyWASHINGTON
Highway SH 36
From 0.094 MI NORTH OF UNION PACIFIC RR
To 0.234 MI SOUTH OF BIG SANDY CREEK
CSJ 0186-06-077
Proj ID NH 2013(947)
Work Type REHABILITATE EXISTING ROAD
 
0.650 3601986.58 108490.26 1125713.27 31.2
Work Order 10-22-13
Work Began 11-01-13
Work Completed  
Time Computed 11-01-13
Contract Working Days 282
Addl Days Granted 0
Working Days Charged 167
Percent Time Used 59
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0186-06-077
TEXAS ALTERNATIVE GRASSER, INC.(0.98%)
ENVIRONMENTAL SAFETY SERVICES, INC.(1.01%)
KELLYSTONE, INC(0.99%)
CEN TEX HYDROSEED, INC.(2.20%)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.50%)
SIEMENS INDUSTRY, INC. (5.67%)
ODUM SERVICES, L.P.(0.86%)
MURRAY CONSTRUCTION(0.36%)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC.(5.82%)
AUSTIN LAND SERVICE(0.18%)
Contract # 07133040
Totals 3601986.58 108490.26 1125713.27 31.2

CountyWASHINGTON
Highway US 290
From SH 36
To FM 389
CSJ 0186-06-078
Proj ID NH 2014(339)
Work Type OVERLAY (REHABILITATION)
 
1.605 410932.50 0.00 459041.97 100.0
CountyWASHINGTON
Highway US 290
From SH 36
To FM 389
CSJ 0186-06-079
Proj ID NH 2014(339)
Work Type OVERLAY
 
1.605 613160.64 1820.00 650601.28 100.0
Work Order 02-14-14
Work Began 06-05-14
Work Completed 11-14-14
Time Computed 05-15-14
Contract Working Days 34
Addl Days Granted 0
Working Days Charged 31
Percent Time Used 91
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0186-06-078
A BROTHERS MILLING, LLC(3.65%)
D. I. J. CONSTRUCTION, INC.(3.01%)
WEST TEXAS RUMBLE STRIP(0.42%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.45%)
Contract # 01143025
Totals 1024093.14 1820.00 1109643.25 100.0

CountyROBERTSON
Highway US 79
From US 79 AT THE INTERSECTION
To WITH FM 1644
CSJ 0204-09-053
Proj ID NH 2013(887)
Work Type CONSTRUCT PROTECTED LEFT - TURN LANE
 
1.506 1018765.87 16486.60 1045536.17 99.9
Work Order 10-21-13
Work Began 12-02-13
Work Completed  
Time Computed 12-02-13
Contract Working Days 124
Addl Days Granted 3
Working Days Charged 127
Percent Time Used 100
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0204-09-053
FLASHER EQUIPMENT COMPANY(3.81%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.24%)
TEXAS ALTERNATIVE GRASSER, INC.(0.20%)
WILLOW CITY SIGN & RAIL, INC.(3.07%)
NIXON ENGINEERING(0.00%)
Contract # 07133233
Totals 1018765.87 16486.60 1045536.17 99.9

CountyLEON
Highway US 79
From THE 5-LANE SECTION WEST OF IH 45
To 0.5 MILE WEST OF CR 329
CSJ 0205-04-044
Proj ID HP 2012(729)
Work Type REHABILITATE EXISTING ROAD
 
2.600 5087927.87 235172.08 3645622.51 71.6
CountyZERO COUNTIES
Highway  
From  
To  
CSJ 0205-06-029
Proj ID  
Work Type  
 
  0.00 20297.20 607677.10 0.0
Work Order 09-20-13
Work Began 11-04-13
Work Completed  
Time Computed 11-04-13
Contract Working Days 326
Addl Days Granted 50
Working Days Charged 212
Percent Time Used 56
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0205-04-044
FORTSON CONTRACTING, INC.(1.89%)
INTERSTATE BARRICADES & MARKINGS, INC. (0.50%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.36%)
ROADWAY CONSTRUCTION, INC. (2.81%)
SAN-ANN-CO., INC.(0.21%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.52%)
TREVWAY, INC.(4.63%)
TRAFCO INDUSTRIES, INC.(0.06%)
Contract # 07133226
Totals 5087927.87 255469.28 4253299.61 83.5

CountyWALKER
Highway SH 30
From AT THE INTERSECTION OF SH 30
To AND FM 1791
CSJ 0212-02-037
Proj ID STP 2012(010)SB
Work Type CONSTRUCT GRADE SEPARATION
 
0.873 13817770.18 0.00 13564262.10 99.1
Work Order 11-16-11
Work Began 12-14-11
Work Completed  
Time Computed 12-02-11
Contract Working Days 357
Addl Days Granted 224
Working Days Charged 680
Percent Time Used 117
Contractor(s)
DOUGHTIE CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0212-02-037
SOUTHWEST ENVIRONMENT SERVICES LLC (0.39%)
A & A CONSTRUCTION (0.66%)
HIGHWAY TECHNOLOGIES, INC. (0.20%)
FARR FOUNDATION, INC.( 11.04%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.05%)
RG PAINTING(0.15%)
WEBBER BARRIER SERVICES, INC.(3.40%)
W. W. FOUNDATION DRILLING, LTD.(1.25%)
SAN-ANN-CO., INC.(0.14%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.64%)
HIGHWAY TECHNOLOGIES, INC. (0.36%)
BIG CREEK CONSTRUCTION, LTD. ( 12.88%)
DUSTROL, INC.(1.15%)
NORTH TEXAS REBAR, LLC (0.34%)
BATTERSON,LLP(0.37%)
ROADWAY CONSTRUCTION, LLC(0.67%)
SOUTHEAST GRINDING & GROOVING, LLC (0.26%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00%)
Contract # 09113003
Totals 13817770.18 0.00 13564262.10 99.1

CountyGRIMES
Highway SH 30
From AT THE INTERSECTION OF SH 30
To AND FM 244
CSJ 0212-04-033
Proj ID STP 1402(194)
Work Type CONSTRUCT GRADE SEPARATION
 
0.833 5718784.14 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-30-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 251
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0212-04-033
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143023
Totals 5718784.14 0.00 0.00 0.0

CountyGRIMES
Highway SH 90
From 0.2 MILES NORTH OF BNSF RR OVERPASS
To 2.6 MILES SOUTH OF FM 39
CSJ 0315-02-044
Proj ID STP 2013(176)
Work Type REHABILITATE EXISTING ROAD
 
4.148 4287390.79 0.00 4290406.25 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-11-13
Work Began 02-20-13
Work Completed 09-18-14
Time Computed 02-22-13
Contract Working Days 145
Addl Days Granted 27
Working Days Charged 149
Percent Time Used 86
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0315-02-044
CEN TEX HYDROSEED, INC.(1.72%)
MURRAY CONSTRUCTION(0.46%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.34%)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.42%)
ROADWAY SPECIALTIES, INC.(1.63%)
SCR CONSTRUCTION CO., INC. (1.00%)
PAVETEX ENGINEERING & TESTING, INC.(0.03%)
Contract # 11123012
Totals 4287390.79 0.00 4290406.25 100.0

CountyGRIMES
Highway SH 90
From 0.2 MILES NORTH OF BNSF RR OVERPASS
To 1.4 MILES NORTH OF CR 150
CSJ 0315-02-045
Proj ID STP 1402(097)
Work Type REHABILITATE EXISTING ROAD
 
4.001 4087491.38 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-30-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 125
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0315-02-045
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143216
Totals 4087491.38 0.00 0.00 0.0

CountyGRIMES
Highway SH 90
From 1.4 MILES NORTH OF CR 150
To SOUTH CITY LIMITS OF BEDIAS
CSJ 0315-02-049
Proj ID STP 1402(098)
Work Type REHABILITATE EXISTING ROAD
 
2.617 3129292.87 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-30-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 135
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0315-02-049
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143024
Totals 3129292.87 0.00 0.00 0.0

CountyBRAZOS
Highway SH 105
From AT THE BRAZOS RIVER
To .
CSJ 0315-05-026
Proj ID BR 2014(643)
Work Type GRADING, STRUCTURES, BASE AND SURF
 
3.289 23601410.92 1843950.23 2071221.23 8.7
Work Order 07-02-14
Work Began 09-30-14
Work Completed  
Time Computed 09-30-14
Contract Working Days 443
Addl Days Granted 0
Working Days Charged 22
Percent Time Used 4
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0315-05-026
CHOCTAW ERECTORS, INC. (7.06%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.19%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.15%)
ATS DRILLING, INC. (7.09%)
HOUSTON SAWING & DRILLING(0.06%)
BIG CREEK CONSTRUCTION, LTD. (6.72%)
MINE SERVICE, INC. (5.33%)
GEOSOURCE, INC.(0.94%)
RICE ENVIRONMENTAL SERVICES(1.93%)
PERFORMANCE EQUIPMENT(0.25%)
MESA ROD BUSTERS, INC. (0.53%)
EPCS ENVIRONMENTAL LLC (1.52%)
MCL CONTRACTING, LLC (0.25%)
Contract # 05143202
Totals 23601410.92 1843950.23 2071221.23 8.7

page 1 | page 2 | page 3