Monthly State Let Construction Report For Bryan District As Of Jul 13, 2015 Page 2 Of 3

Last Update: Monday, July 13, 2015
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyGRIMES
Highway SH 30
From AT THE INTERSECTION OF SH 30
To AND FM 244
CSJ 0212-04-033
Proj ID STP 1402(194)
Work Type CONSTRUCT GRADE SEPARATION
 
0.833 5718784.14 0.00 0.00 0.0
Work Order 09-30-14
Work Began 00-00-00
Work Completed  
Time Computed 10-16-14
Contract Working Days 251
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0212-04-033
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143023
Totals 5718784.14 0.00 0.00 0.0

CountyROBERTSON
Highway FM 485
From AT THE LITTLE BRAZOS RIVER
To .
CSJ 0262-03-025
Proj ID BR 2015(606)
Work Type GR, STRS, BASE AND SURFACE
 
0.465 3216161.51 97306.91 164425.32 5.1
Work Order 04-10-15
Work Began 04-20-15
Work Completed  
Time Computed 04-20-15
Contract Working Days 111
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0262-03-025
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02153018
Totals 3216161.51 97306.91 164425.32 5.1

CountyGRIMES
Highway SH 90
From 0.2 MILES NORTH OF BNSF RR OVERPASS
To 1.4 MILES NORTH OF CR 150
CSJ 0315-02-045
Proj ID STP 1402(097)
Work Type REHABILITATE EXISTING ROAD
 
4.001 4087491.38 123499.10 1368264.89 33.4
Work Order 10-30-14
Work Began 01-28-15
Work Completed  
Time Computed 01-28-15
Contract Working Days 125
Addl Days Granted 0
Working Days Charged 59
Percent Time Used 47
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0315-02-045
COWBELL TRAFFIC SERVICES, INC. (0.28%)
CEN TEX HYDROSEED, INC.(1.06%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.94%)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.51%)
PAVETEX ENGINEERING & TESTING, INC.(0.47%)
NIXON ENGINEERING(0.00%)
Contract # 08143216
Totals 4087491.38 123499.10 1368264.89 33.4

CountyGRIMES
Highway SH 90
From MADISON COUNTY LINE
To THE SOUTH CITY LIMITS OF BEDIAS
CSJ 0315-02-047
Proj ID STP 1502(235)
Work Type REHABILITATE EXISTING ROAD
 
6.871 7051873.09 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 168
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0315-02-047
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153227
Totals 7051873.09 0.00 0.00 0.0

CountyGRIMES
Highway SH 90
From 1.4 MILES NORTH OF CR 150
To SOUTH CITY LIMITS OF BEDIAS
CSJ 0315-02-049
Proj ID STP 1402(098)
Work Type REHABILITATE EXISTING ROAD
 
2.617 3129292.87 514265.25 721483.05 23.0
Work Order 10-30-14
Work Began 01-28-15
Work Completed  
Time Computed 01-28-15
Contract Working Days 135
Addl Days Granted 0
Working Days Charged 21
Percent Time Used 15
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0315-02-049
CPAVE, INC.(0.73%)
CEN TEX HYDROSEED, INC.(1.19%)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.50%)
WILLOW CITY SIGN & RAIL, INC.(4.65%)
NIXON ENGINEERING(0.00%)
Contract # 08143024
Totals 3129292.87 514265.25 721483.05 23.0

CountyBRAZOS
Highway SH 105
From AT THE BRAZOS RIVER
To .
CSJ 0315-05-026
Proj ID BR 2014(643)
Work Type GRADING, STRUCTURES, BASE AND SURF
 
3.289 23601410.92 351720.08 10075554.16 42.6
Work Order 07-02-14
Work Began 09-30-14
Work Completed  
Time Computed 09-30-14
Contract Working Days 443
Addl Days Granted 0
Working Days Charged 81
Percent Time Used 18
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0315-05-026
CHOCTAW ERECTORS, INC. (7.06%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.19%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.15%)
ATS DRILLING, INC. (7.09%)
HOUSTON SAWING & DRILLING(0.06%)
BIG CREEK CONSTRUCTION, LTD. (6.72%)
MINE SERVICE, INC. (5.33%)
GEOSOURCE, INC.(0.94%)
RICE ENVIRONMENTAL SERVICES(1.93%)
PERFORMANCE EQUIPMENT(0.25%)
MESA ROD BUSTERS, INC. (0.53%)
EPCS ENVIRONMENTAL LLC (1.52%)
MCL CONTRACTING, LLC (0.25%)
S & K TRUCKING (0.00%)
Contract # 05143202
Totals 23601410.92 351720.08 10075554.16 42.6

CountyWASHINGTON
Highway SH 105
From 1.34 MILES WEST OF FM 2193
To THE BRAZOS COUNTY LINE
CSJ 0315-06-038
Proj ID STP 1502(007)HES
Work Type SAFETY TREAT FIXED OBJECTS
 
28.050 1124478.00 74702.00 74702.00 6.6
Work Order 06-01-15
Work Began 06-29-15
Work Completed  
Time Computed 06-25-15
Contract Working Days 124
Addl Days Granted 0
Working Days Charged 2
Percent Time Used 1
Contractor(s)
3LW MANAGEMENT, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0315-06-038
R K STEPHENS CONSTRUCTION, LLC (5.67%)
CEN TEX HYDROSEED, INC.(2.43%)
Contract # 04153242
Totals 1124478.00 74702.00 74702.00 6.6

CountyLEON
Highway SH 7
From CR 348
To FM 39
CSJ 0335-03-046
Proj ID STP 2015(607)
Work Type REHABILITATE EXISTING ROAD
 
1.562 1443902.82 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-03-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 59
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0335-03-046
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02153204
Totals 1443902.82 0.00 0.00 0.0

CountyLEON
Highway SH 7
From 1.5 MI EAST OF US 79
To 1.5 MI WEST OF CR 348
CSJ 0335-03-048
Proj ID STP 1502(236)
Work Type REHABILITATE EXISTING ROAD
 
8.467 2827001.88 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 87
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0335-03-048
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153038
Totals 2827001.88 0.00 0.00 0.0

CountyWALKER
Highway SH 150
From SH 75
To THE SAN JACINTO COUNTY LINE
CSJ 0395-01-029
Proj ID STP 2015(159)
Work Type GRADING, STRUCTURES, BASE AND SURF
 
8.012 5846147.45 1232005.40 3325963.07 56.8
Work Order 11-03-14
Work Began 02-02-15
Work Completed  
Time Computed 02-01-15
Contract Working Days 148
Addl Days Granted 0
Working Days Charged 76
Percent Time Used 51
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0395-01-029
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC.(0.81%)
CEN TEX HYDROSEED, INC.(0.14%)
J & M CONTRACTING, COMPANY (3.72%)
WATERS CONSTRUCTION CO., INC.(9.52%)
WILLOW CITY SIGN & RAIL, INC.(1.07%)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.40%)
MURRAY CONSTRUCTION(0.59%)
Contract # 09143207
Totals 5846147.45 1232005.40 3325963.07 56.8

CountyLEON
Highway FM 542
From US 79
To 1.8 MILES SOUTHEAST OF CR 242
CSJ 0426-03-039
Proj ID STP 2014(644)HES
Work Type PROVIDE ADDITIONAL PAVEMENT WIDTH
 
6.408 1887337.85 22093.10 1788654.78 100.0
Work Order 07-22-14
Work Began 09-08-14
Work Completed 06-23-15
Time Computed 08-07-14
Contract Working Days 119
Addl Days Granted 0
Working Days Charged 119
Percent Time Used 100
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0426-03-039
FORTSON CONTRACTING, INC.(3.72%)
N-LINE TRAFFIC MAINTENANCE, L.P. (2.61%)
SAN-ANN-CO., INC.(1.25%)
STRIPING TECHNOLOGY, L.P.(2.17%)
TEXAS ALTERNATIVE GRASSER, INC.(0.37%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00%)
Contract # 05143225
Totals 1887337.85 22093.10 1788654.78 100.0

CountyBURLESON
Highway FM 50
From THE BNSF RAILROAD
To THE WASHINGTON COUNTY LINE
CSJ 0457-01-056
Proj ID STP 2014(340)
Work Type REHABILITATE EXISTING ROAD
 
1.361 1532334.42 324420.26 1688424.11 99.9
Work Order 03-03-14
Work Began 07-01-14
Work Completed  
Time Computed 06-01-14
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 102
Percent Time Used 102
Contractor(s)
GLENN FUQUA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0457-01-056
J & M CONTRACTING, COMPANY (3.86%)
CEN TEX HYDROSEED, INC.(1.82%)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.05%)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC.(0.52%)
Contract # 01143207
Totals 1532334.42 324420.26 1688424.11 99.9

CountyBRAZOS
Highway FM 60
From SH 6
To FM 158
CSJ 0506-01-082
Proj ID STP 2004(74)
Work Type GRADING, STRUCTURES, BASE AND SURFA
 
1.747 7633962.49 0.00 7584073.47 99.5
Work Order 07-23-12
Work Began 08-04-12
Work Completed  
Time Computed 08-04-12
Contract Working Days 296
Addl Days Granted 26
Working Days Charged 338
Percent Time Used 104
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0506-01-082
JEFFERY BAILEY TRUCKING, INC.(1.17%)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC.(3.69%)
FLASHER EQUIPMENT COMPANY(0.73%)
KELLYSTONE, INC(1.12%)
TEX OP CONSTRUCTION, LP(0.39%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.36%)
HEMPHILL PILE DRIVING CO., A CORP. (0.96%)
ROADWAY SPECIALTIES, INC.(0.38%)
CEN TEX HYDROSEED, INC.(0.95%)
WEBBER-BALKE FOUNDATION COMPANY, INC.(0.97%)
MESA ROD BUSTERS, INC. (0.73%)
RIOS TRUCKING CO.(0.00%)
PRIMATE CONSTRUCTION, INC. (0.31%)
Contract # 05123205
Totals 7633962.49 0.00 7584073.47 99.5

CountyBRAZOS
Highway FM 60
From SH 47
To FM 2154
CSJ 0506-01-102
Proj ID NH 2015(705)
Work Type REHABILITATE EXISTING ROAD
 
2.720 1565192.94 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-08-15
Work Began 00-00-00
Work Completed  
Time Computed 08-07-15
Contract Working Days 37
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0506-01-102
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03153004
Totals 1565192.94 0.00 0.00 0.0

CountyBRAZOS
Highway FM 60
From TARROW STREET
To SH 6 WEST FRONTAGE ROAD
CSJ 0506-01-103
Proj ID NH 1502(140)
Work Type HMA OVERLAY
 
1.147 1327052.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 37
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0506-01-103
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05153209
Totals 1327052.00 0.00 0.00 0.0

CountyROBERTSON
Highway FM 1373
From AT ALLIGATOR SLOUGH
To .
CSJ 0540-06-015
Proj ID BR 1502(142)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.208 1204459.20 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-01-15
Work Began 00-00-00
Work Completed  
Time Computed 08-01-15
Contract Working Days 155
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0540-06-015
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05153042
Totals 1204459.20 0.00 0.00 0.0

CountyMILAM
Highway FM 486
From AT SAN GABRIEL RIVER
To .
CSJ 0590-05-027
Proj ID BR 2012(706)
Work Type GR, STRS, BASE AND SURFACE
 
0.176 1943618.46 0.00 2076451.63 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-24-12
Work Began 10-31-12
Work Completed 11-14-14
Time Computed 10-10-12
Contract Working Days 263
Addl Days Granted 0
Working Days Charged 270
Percent Time Used 102
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0590-05-027
N-LINE TRAFFIC MAINTENANCE, L.P. (0.34%)
RICE ENVIRONMENTAL SERVICES(0.49%)
D. I. J. CONSTRUCTION, INC.(0.75%)
PRIMATE CONSTRUCTION, INC. (0.34%)
S & S BRIDGE PAINTING, INC.(0.17%)
ENVIRONMENTAL SAFETY SERVICES, INC.(7.07%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.98%)
GK CONSTRUCTION, LLC (1.08%)
BEAIRD DRILLING(3.67%)
JOY LATTIMER, LLC. (0.00%)
PANTHER CREEK TRANSPORTATION, INC. (0.00%)
PANTHER CREEK TRANSPORTATION, INC. (0.87%)
K.L. DURHAM CONSTRUCTION, LLC(0.30%)
BIG CREEK CONSTRUCTION, LTD. (2.76%)
Contract # 08123227
Totals 1943618.46 0.00 2076451.63 100.0

CountyGRIMES
Highway FM 244
From CR 170
To CR 171
CSJ 0643-04-028
Proj ID STP 1402(102)
Work Type MISCELLANEOUS WORK
 
5.175 2156938.65 655906.65 1661576.19 77.0
Work Order 09-22-14
Work Began 01-21-15
Work Completed  
Time Computed 12-21-14
Contract Working Days 86
Addl Days Granted 0
Working Days Charged 69
Percent Time Used 80
Contractor(s)
GLENN FUQUA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0643-04-028
J & M CONTRACTING, COMPANY ( 12.18%)
CEN TEX HYDROSEED, INC.(2.05%)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.96%)
PLANTERSVILLE WATER SERVICES, INC. (0.91%)
Contract # 08143013
Totals 2156938.65 655906.65 1661576.19 77.0

CountyGRIMES
Highway FM 244
From SH 30
To FM 3090
CSJ 0643-05-046
Proj ID STP 1502(012)HES
Work Type INCREASE SUPERELEVATION
 
2.396 1787891.25 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-30-15
Work Began 00-00-00
Work Completed  
Time Computed 09-29-15
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0643-05-046
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04153015
Totals 1787891.25 0.00 0.00 0.0

CountyBURLESON
Highway FM 60
From 1.2 MILES WEST OF FM 2039
To 0.62 MILE EAST OF OLD RIVER
CSJ 0648-03-050
Proj ID C 648-3-50
Work Type GRADING, STRUCTURES, BASE AND SURFA
 
3.984 10487720.87 349409.02 6515144.43 62.1
Work Order 02-19-14
Work Began 04-07-14
Work Completed  
Time Computed 04-07-14
Contract Working Days 227
Addl Days Granted 0
Working Days Charged 167
Percent Time Used 73
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0648-03-050
BLUE STAR BARRICADES, INC. (0.26%)
COWBELL TRAFFIC SERVICES, INC. (0.07%)
D. I. J. CONSTRUCTION, INC.(0.65%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.52%)
MURRAY CONSTRUCTION(0.38%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.16%)
TEXAS ALTERNATIVE GRASSER, INC.(0.30%)
PRIME ECO GROUP, INC.(0.00%)
PIPE WHOLESALERS OF TEXAS, INC.(0.00%)
COMEN ENTERPRISE (0.36%)
Contract # 12133003
Totals 10487720.87 349409.02 6515144.43 62.1

page 1 | page 2 | page 3