Monthly State Let Construction Report For Bryan District As Of Oct 14, 2014 Page 3 Of 3

Last Update: Tuesday, October 14, 2014
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyWALKER
Highway FM 1791
From 3.5 MILES SOUTH OF SH 30
To THE MONTGOMERY COUNTY LINE
CSJ 1706-01-025
Proj ID STP 2014(933)HES
Work Type PROVIDE ADDITIONAL PAVEMENT WIDTH
 
9.092 3187515.87 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-24-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 328
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1706-01-025
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143239
Totals 3187515.87 0.00 0.00 0.0

CountyWALKER
Highway FM 1696
From THE GRIMES COUNTY LINE
To SH 75
CSJ 1809-02-024
Proj ID STP 2014(214)HES
Work Type PROVIDE ADDITIONAL PAVEMENT WIDTH
 
13.806 4305079.51 198512.58 2625372.67 60.9
Work Order 01-09-14
Work Began 04-21-14
Work Completed  
Time Computed 04-09-14
Contract Working Days 212
Addl Days Granted 0
Working Days Charged 101
Percent Time Used 47
Contractor(s)
GLENN FUQUA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1809-02-024
ROADSAFE TRAFFIC SYSTEMS, INC. (2.54%)
CEN TEX HYDROSEED, INC.(3.83%)
J & M CONTRACTING, COMPANY (0.30%)
Contract # 11133017
Totals 4305079.51 198512.58 2625372.67 60.9

CountyMILAM
Highway FM 2269
From FM 485
To 0.3 MILE NORTH OF US 190
CSJ 2133-03-019
Proj ID STP 2014(057)HES
Work Type PROVIDE ADDITIONAL PAVEMENT WIDTH
 
9.762 3309494.89 0.00 2086169.89 63.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-09-14
Work Began 03-17-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 197
Addl Days Granted 0
Working Days Charged 127
Percent Time Used 64
Contractor(s)
GLENN FUQUA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2133-03-019
J & M CONTRACTING, COMPANY ( 12.78%)
CEN TEX HYDROSEED, INC.(3.32%)
ROADSAFE TRAFFIC SYSTEMS, INC. (4.05%)
ROADWAY SPECIALTIES, INC.(5.08%)
Contract # 10133017
Totals 3309494.89 0.00 2086169.89 63.0

CountyBRAZOS
Highway FM 2818
From AT THE INTERSECTION OF FM 2818
To AND FM 1179
CSJ 2399-01-060
Proj ID STP 1102(237)SB
Work Type CONSTRUCT GRADE SEPARATION
 
1.293 14139148.97 366066.92 13284703.19 94.8
Work Order 10-21-11
Work Began 02-20-12
Work Completed  
Time Computed 02-20-12
Contract Working Days 316
Addl Days Granted 14
Working Days Charged 419
Percent Time Used 126
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 2399-01-060
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC.(1.74%)
FLASHER EQUIPMENT COMPANY(0.43%)
FORTSON CONTRACTING, INC.(0.22%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.03%)
HIGHWAY TECHNOLOGIES, INC. (1.22%)
KELLYSTONE, INC(0.42%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.34%)
MAGNUM TUNNELING, LLC(0.11%)
SOUTH TEXAS PAINTING COMPANY (0.89%)
TEX OP CONSTRUCTION, LP(0.63%)
WEBBER BARRIER SERVICES, INC.(0.45%)
WILLOW CITY SIGN & RAIL, INC.(0.39%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.61%)
INDUS CONSTRUCTION, L.P. (0.52%)
MESA ROD BUSTERS, INC. (0.02%)
AUSTIN LAND SERVICE(0.09%)
D. I. J. CONSTRUCTION, INC.(0.90%)
A BRUSH ABOVE SERVICES, LLC(0.09%)
Contract # 08113004
Totals 14139148.97 366066.92 13284703.19 94.8