Monthly State Let Construction Report For Bryan District As Of Mar 10, 2015 Page 3 Of 3

Last Update: Wednesday, March 11, 2015
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyFREESTONE
Highway CR
From ON COUNTY ROAD 352 (LOCAL CR 1041)
To AT TEHUACANA CREEK
CSJ 0917-20-011
Proj ID BR 96(480)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.104 448406.84 1260.00 474051.50 100.0
Work Order 01-17-14
Work Began 03-14-14
Work Completed 09-22-14
Time Computed 02-02-14
Contract Working Days 83
Addl Days Granted 0
Working Days Charged 81
Percent Time Used 97
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0917-20-011
CEN TEX HYDROSEED, INC.(1.02%)
FORTSON CONTRACTING, INC.(2.71%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.94%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.64%)
JUST GROOVING, LTD.(0.39%)
REDROD STEEL AND CABLE, LLC(0.40%)
Contract # 10133010
Totals 448406.84 1260.00 474051.50 100.0

CountyFREESTONE
Highway PW
From AT THE FAIRFIELD LAKE STATE PARK
To .
CSJ 0917-20-034
Proj ID C 917-20-34
Work Type RECONSTRUCT ROADWAYS AND CAMPSITES
 
7.000 1574868.18 19070.87 1621401.83 100.0
Work Order 09-10-13
Work Began 09-17-13
Work Completed 10-06-14
Time Computed 09-17-13
Contract Working Days 118
Addl Days Granted 37
Working Days Charged 165
Percent Time Used 106
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-20-034
N-LINE TRAFFIC MAINTENANCE, L.P. (0.20%)
SPEEDY PAVING(8.14%)
STRIPING TECHNOLOGY, L.P.(0.30%)
Contract # 06133011
Totals 1574868.18 19070.87 1621401.83 100.0

CountyWALKER
Highway PW
From AT THE HUNTSVILLE STATE PARK
To .
CSJ 0917-27-043
Proj ID C 917-27-43
Work Type RECONSTRUCT EXISTING RV PULLOUTS
 
1.000 262456.50 0.00 267578.76 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-13-14
Work Began 07-10-14
Work Completed 10-07-14
Time Computed 07-07-14
Contract Working Days 39
Addl Days Granted 0
Working Days Charged 34
Percent Time Used 87
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0917-27-043
CEN TEX HYDROSEED, INC.(4.80%)
Contract # 04143019
Totals 262456.50 0.00 267578.76 100.0

CountyMADISON
Highway CR
From ON CR 253 (ROCKY RIDGE LANE)
To AT POOLES CREEK AND RELIEF
CSJ 0917-31-015
Proj ID BR 2012(335)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.236 653336.52 0.00 0.00 0.0
Work Order 01-05-15
Work Began 00-00-00
Work Completed  
Time Computed 01-21-15
Contract Working Days 158
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CDM HOLDINGS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0917-31-015
M & D FOUNDATION DRILLING INDUSTRIES, INC. (7.10%)
DUSTIN ALLEN, INC. (5.58%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.86%)
Contract # 10143011
Totals 653336.52 0.00 0.00 0.0

CountyFREESTONE
Highway FM 416
From THE NAVARRO COUNTY LINE
To FM 488
CSJ 0998-05-009
Proj ID STP 2014(645)HES
Work Type PROVIDE ADDITIONAL PAVEMENT WIDTH
 
5.990 1235167.98 264467.09 1149636.04 93.0
Work Order 07-08-14
Work Began 10-14-14
Work Completed  
Time Computed 10-06-14
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 74
Percent Time Used 61
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0998-05-009
ROADSAFE TRAFFIC SYSTEMS, INC. (0.71%)
TEXAS ALTERNATIVE GRASSER, INC.(0.36%)
SAN-ANN-CO., INC.(0.45%)
STRIPING TECHNOLOGY, L.P.(3.71%)
Contract # 05143009
Totals 1235167.98 264467.09 1149636.04 93.0

CountyBRAZOS
Highway FM 1179
From KENT STREET
To FM 2818
CSJ 1316-01-059
Proj ID STP 2015(635)
Work Type HMA OVERLAY
 
2.726 2436656.96 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 172
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 1316-01-059
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01153227
Totals 2436656.96 0.00 0.00 0.0

CountyWALKER
Highway FM 1375
From SH 150
To GOURD CREEK ROAD
CSJ 1402-01-032
Proj ID STP 2014(746)HES
Work Type PROVIDE ADDITIONAL PAVEMENT WIDTH
 
5.643 2371297.26 98791.00 1951472.62 82.2
Work Order 08-13-14
Work Began 08-25-14
Work Completed  
Time Computed 08-25-14
Contract Working Days 105
Addl Days Granted 9
Working Days Charged 97
Percent Time Used 85
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1402-01-032
CEN TEX HYDROSEED, INC.(1.53%)
J & M CONTRACTING, COMPANY (8.57%)
INTERSTATE BARRICADES & MARKINGS, INC. (2.61%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.29%)
WATERS CONSTRUCTION CO., INC.( 13.72%)
WILLOW CITY SIGN & RAIL, INC.(1.91%)
Contract # 06143042
Totals 2371297.26 98791.00 1951472.62 82.2

CountyWALKER
Highway FM 1791
From 3.5 MILES SOUTH OF SH 30
To THE MONTGOMERY COUNTY LINE
CSJ 1706-01-025
Proj ID STP 2014(933)HES
Work Type PROVIDE ADDITIONAL PAVEMENT WIDTH
 
9.092 3187515.87 222989.23 222989.23 6.9
Work Order 09-24-14
Work Began 02-13-15
Work Completed  
Time Computed 12-23-14
Contract Working Days 328
Addl Days Granted 0
Working Days Charged 29
Percent Time Used 8
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1706-01-025
COLD CREEK CONSTRUCTION, LTD (4.71%)
CEN TEX HYDROSEED, INC.(5.07%)
HIGHWAY 19 CONSTRUCTION, LLC (8.11%)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.45%)
TEXAS ALTERNATIVE GRASSER, INC.(0.70%)
WILLOW CITY SIGN & RAIL, INC.(2.09%)
Contract # 07143239
Totals 3187515.87 222989.23 222989.23 6.9

CountyWALKER
Highway FM 1696
From THE GRIMES COUNTY LINE
To SH 75
CSJ 1809-02-024
Proj ID STP 2014(214)HES
Work Type PROVIDE ADDITIONAL PAVEMENT WIDTH
 
13.806 4305079.51 82055.66 3408956.42 79.1
Work Order 01-09-14
Work Began 04-21-14
Work Completed  
Time Computed 04-09-14
Contract Working Days 212
Addl Days Granted 0
Working Days Charged 179
Percent Time Used 84
Contractor(s)
GLENN FUQUA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1809-02-024
ROADSAFE TRAFFIC SYSTEMS, INC. (2.54%)
CEN TEX HYDROSEED, INC.(3.83%)
J & M CONTRACTING, COMPANY (0.30%)
Contract # 11133017
Totals 4305079.51 82055.66 3408956.42 79.1

CountyMILAM
Highway FM 2269
From FM 485
To 0.3 MILE NORTH OF US 190
CSJ 2133-03-019
Proj ID STP 2014(057)HES
Work Type PROVIDE ADDITIONAL PAVEMENT WIDTH
 
9.762 3309494.89 0.00 3070280.10 92.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-09-14
Work Began 03-17-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 197
Addl Days Granted 0
Working Days Charged 186
Percent Time Used 94
Contractor(s)
GLENN FUQUA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2133-03-019
J & M CONTRACTING, COMPANY ( 12.78%)
CEN TEX HYDROSEED, INC.(3.32%)
ROADSAFE TRAFFIC SYSTEMS, INC. (4.05%)
ROADWAY SPECIALTIES, INC.(5.08%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.54%)
Contract # 10133017
Totals 3309494.89 0.00 3070280.10 92.7

CountyBRAZOS
Highway FM 2818
From AT THE INTERSECTION OF FM 2818
To AND FM 1179
CSJ 2399-01-060
Proj ID STP 1102(237)SB
Work Type CONSTRUCT GRADE SEPARATION
 
1.293 14139148.97 20825.32 13677666.09 97.7
Work Order 10-21-11
Work Began 02-20-12
Work Completed  
Time Computed 02-20-12
Contract Working Days 316
Addl Days Granted 14
Working Days Charged 433
Percent Time Used 131
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 2399-01-060
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC.(1.74%)
FLASHER EQUIPMENT COMPANY(0.43%)
FORTSON CONTRACTING, INC.(0.22%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.03%)
HIGHWAY TECHNOLOGIES, INC. (1.22%)
KELLYSTONE, INC(0.42%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.34%)
MAGNUM TUNNELING, LLC(0.11%)
SOUTH TEXAS PAINTING COMPANY (0.89%)
TEX OP CONSTRUCTION, LP(0.63%)
WEBBER BARRIER SERVICES, INC.(0.45%)
WILLOW CITY SIGN & RAIL, INC.(0.39%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.61%)
INDUS CONSTRUCTION, L.P. (0.52%)
MESA ROD BUSTERS, INC. (0.02%)
AUSTIN LAND SERVICE(0.09%)
D. I. J. CONSTRUCTION, INC.(0.90%)
A BRUSH ABOVE SERVICES, LLC(0.09%)
BEDO CONSTRUCTION PRODUCTS, INC. (0.00%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.00%)
Contract # 08113004
Totals 14139148.97 20825.32 13677666.09 97.7

page 1 | page 2 | page 3