Monthly Local Let Maintenance Report For Bryan District As Of Sep 21, 2017 Page 3 Of 5

Last Update: Friday, September 22, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyWASHINGTON
HighwaySH0105
FromVARIOUS
ToVARIOUS
CSJ6312-70-001
Proj IDSUP - 631270001
Work TypeLITTER PICKUP
 
0.010116769.6255648.4147.6
Work Order01-03-17
Work Began12-14-16
Work Completed
Time Computed12-20-16
Contract Working Days365
Addl Days Granted0
Working Days Charged261
Percent Time Used71
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6312-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161715
Totals116769.620.0055648.4147.6

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6312-71-001
Proj IDSUP - 631271001
Work TypeLITTER PICKUP
 
0.010395432.40251953.0263.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-14-16
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged260
Percent Time Used71
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6312-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161716
Totals395432.4024424.79251953.0263.7

CountyLEON
HighwayIH0045
FromVARIOUS
ToVARIOUS
CSJ6312-72-001
Proj IDSUP - 631272001
Work TypeLITTER PICKUP AND DISPOSAL
 
0.010124173.4277424.7362.3
Work Order01-25-17
Work Began12-14-16
Work Completed
Time Computed01-25-17
Contract Working Days365
Addl Days Granted0
Working Days Charged260
Percent Time Used71
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6312-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161717
Totals124173.420.0077424.7362.3

CountyBURLESON
HighwaySH0021
FromVARIOUS
ToVARIOUS
CSJ6312-73-001
Proj IDSUP - 631273001
Work TypeLITTER PICKUP
 
0.010106366.6263644.8459.8
Work Order12-14-16
Work Began12-14-16
Work Completed
Time Computed12-14-16
Contract Working Days365
Addl Days Granted0
Working Days Charged255
Percent Time Used69
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6312-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161718
Totals106366.620.0063644.8459.8

CountyMILAM
HighwayUS0077
FromVARIOUS
ToVARIOUS
CSJ6312-74-001
Proj IDSUP - 631274001
Work TypeLITTER PICKUP AND DISPOSAL
 
0.010122475.6871129.6558.0
Work Order12-28-16
Work Began12-14-16
Work Completed
Time Computed12-28-16
Contract Working Days365
Addl Days Granted0
Working Days Charged261
Percent Time Used71
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6312-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161719
Totals122475.680.0071129.6558.0

CountyFREESTONE
HighwayUS0084
FromVARIOUS
ToVARIOUS
CSJ6312-75-001
Proj IDSUP - 631275001
Work TypeLITTER PICKUP AND DISPOSAL
 
0.01081261.4449364.9460.7
Work Order12-29-16
Work Began12-14-16
Work Completed
Time Computed12-29-16
Contract Working Days365
Addl Days Granted0
Working Days Charged255
Percent Time Used69
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6312-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161720
Totals81261.440.0049364.9460.7

CountyROBERTSON
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6312-76-001
Proj IDSUP - 631276001
Work TypeLITTER PICKUP AND DISPOSAL
 
0.010120266.6657883.3348.1
Work Order01-03-17
Work Began12-14-16
Work Completed
Time Computed01-03-17
Contract Working Days365
Addl Days Granted0
Working Days Charged255
Percent Time Used69
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6312-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161721
Totals120266.6631641.8657883.3348.1

CountyWALKER
HighwayIH0045
FromVARIOUS
ToVARIOUS
CSJ6312-77-001
Proj IDSUP - 631277001
Work TypeLITTER PICKUP
 
0.010109859.3464030.8758.2
Work Order01-18-17
Work Began12-14-16
Work Completed
Time Computed01-18-17
Contract Working Days365
Addl Days Granted0
Working Days Charged257
Percent Time Used70
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6312-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161722
Totals109859.3411351.2064030.8758.2

CountyMADISON
HighwaySH0075
FromVARIOUS
ToVARIOUS
CSJ6312-78-001
Proj IDSUP - 631278001
Work TypeLITTER PICKUP
 
0.01091192.2441935.5645.9
Work Order12-20-16
Work Began12-14-16
Work Completed
Time Computed12-20-16
Contract Working Days365
Addl Days Granted0
Working Days Charged258
Percent Time Used70
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6312-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161723
Totals91192.240.0041935.5645.9

CountyGRIMES
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6312-79-001
Proj IDSUP - 631279001
Work TypeLITTER PICKUP
 
0.010130588.1661889.4547.3
Work Order01-04-17
Work Began12-14-16
Work Completed
Time Computed01-12-17
Contract Working Days365
Addl Days Granted0
Working Days Charged261
Percent Time Used71
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6312-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161724
Totals130588.160.0061889.4547.3

CountyWASHINGTON
HighwayFM0389
From@ LITTLE SANDY CREEK
To@ LITTLE SANDY CREEK
CSJ6313-93-001
Proj IDRMC - 631393001
Work TypeCHANNEL AND SCOUR REPAIR
 
0.001146712.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days20
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
OPPORTUNITY EXCAVATION/CONCRETE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6313-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02171701
Totals146712.000.000.000.0

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6314-43-001
Proj IDSUP - 631443001
Work TypeDISTRICT COMPLEX BUILDING JANITORIAL
 
0.00183029.8450290.1460.5
Work Order02-01-17
Work Began02-01-17
Work Completed
Time Computed02-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged212
Percent Time Used58
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6314-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01171702
Totals83029.847340.3250290.1460.5

CountyWALKER
HighwayIH0045
FromVARIOUS
ToVARIOUS
CSJ6314-44-001
Proj IDSUP - 631444001
Work TypeBUILDING JANITORIAL
 
0.01020834.0013171.6063.2
Work Order02-01-17
Work Began02-01-17
Work Completed
Time Computed02-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged208
Percent Time Used56
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6314-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01171703
Totals20834.002873.4013171.6063.2

CountyLEON
HighwayUS0079
FromVARIOUS
ToVARIOUS
CSJ6314-45-001
Proj IDSUP - 631445001
Work TypeBUILDING JANITORIAL
 
0.01012349.626915.0355.9
Work Order02-10-17
Work Began02-01-17
Work Completed
Time Computed02-10-17
Contract Working Days365
Addl Days Granted0
Working Days Charged202
Percent Time Used55
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6314-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01171704
Totals12349.62887.286915.0355.9

CountyBRAZOS
HighwayFM0974
FromVARIOUS
ToVARIOUS
CSJ6314-46-001
Proj IDSUP - 631446001
Work TypeREMOVAL & DISPOSAL OF SCRAP TIRE & FRAG
 
0.01091911.1153018.6857.6
Work Order02-09-17
Work Began02-11-17
Work Completed
Time Computed02-11-17
Contract Working Days365
Addl Days Granted0
Working Days Charged202
Percent Time Used55
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6314-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01171705
Totals91911.1110195.9053018.6857.6

CountyBRAZOS
HighwayFM0974
FromVARIOUS
ToVARIOUS
CSJ6314-48-001
Proj IDSUP - 631448001
Work TypeBUILDING JANIT BRAZOS COUNTY WORLD TECH
 
0.00124870.7210902.6043.8
Work Order03-09-17
Work Began03-12-17
Work Completed
Time Computed03-12-17
Contract Working Days365
Addl Days Granted0
Working Days Charged172
Percent Time Used47
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6314-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02171703
Totals24870.721540.2410902.6043.8

CountyWALKER
HighwayFM0247
FromFM 247 & FM 2821
ToFM 247 & FM 2821
CSJ6314-49-001
Proj IDSUP - 631449001
Work TypePARK & RIDE MOW & LITTER PICKUP - RUCON
 
0.0105033.842995.0859.4
Work Order03-06-17
Work Began03-02-17
Work Completed
Time Computed03-06-17
Contract Working Days365
Addl Days Granted0
Working Days Charged179
Percent Time Used49
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6314-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02171704
Totals5033.84544.562995.0859.4

CountyWASHINGTON
HighwayUS0290
FromVARIOUS
ToVARIOUS
CSJ6314-89-001
Proj IDRMC - 631489001
Work TypeINSTALL/REMOVE RAISED PAVEMENT MARKERS
 
0.001248362.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days80
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6314-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05171703
Totals248362.000.000.000.0

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6314-90-001
Proj IDRMC - 631490001
Work TypeINSTALL/REMOVE RAISED PAVEMENT MARKERS
 
0.001249203.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days80
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BRYDL CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6314-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05171704
Totals249203.000.000.000.0

CountyWALKER
HighwaySH0030
FromVARIOUS
ToVARIOUS
CSJ6314-91-001
Proj IDRMC - 631491001
Work TypeINSTALL/REMOVE RAISED PAVEMENT MARKERS
 
0.001243381.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days80
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BRYDL CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6314-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05171705
Totals243381.000.000.000.0

page 1 | page 2 | page 3 | page 4 | page 5