Monthly Local Let Maintenance Report For Bryan District As Of Sep 21, 2017 Page 4 Of 5

Last Update: Friday, September 22, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyMILAM
HighwayUS0079
FromVARIOUS
ToVARIOUS
CSJ6315-09-001
Proj IDRMC - 631509001
Work TypePICNIC AREA MAINTENANCE
 
0.00125570.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TWO SISTER'S CONST CO.
SUBCONTRACTOR(S) FOR CCSJ: 6315-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03171703
Totals25570.000.000.000.0

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6316-40-001
Proj IDSUP - 631640001
Work TypeCONCRETE_FLATWORK
 
0.00148158.2145087.4693.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-27-17
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged123
Percent Time Used33
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6316-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04171701
Totals48158.210.0045087.4693.6

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6318-09-001
Proj IDSUP - 631809001
Work TypeDISTRICT YARD MAINTENANCE OLD COMP/RUCON
 
0.00118000.002500.0013.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-01-17
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged123
Percent Time Used33
Contractor(s)
TIBH INDUSTRIES, INC.
JUNCTION FIVE-O-FIVE
SUBCONTRACTOR(S) FOR CCSJ: 6318-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04171702
Totals18000.000.002500.0013.8

CountyMILAM
HighwayUS0079
FromVARIOUS
ToVARIOUS
CSJ6318-44-001
Proj IDRMC - 631844001
Work TypePICNIC AREA MAINTENANCE
 
0.00138700.002995.807.7
Work Order08-02-17
Work Began08-08-17
Work Completed
Time Computed08-09-17
Contract Working Days365
Addl Days Granted0
Working Days Charged24
Percent Time Used6
Contractor(s)
ROAD DOCTORS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6318-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06171702
Totals38700.002995.802995.807.7

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6318-47-001
Proj IDSUP - 631847001
Work TypeYARD MAINTENANCE
 
0.01014902.435158.7934.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-01-17
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged123
Percent Time Used33
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6318-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04171703
Totals14902.43736.975158.7934.6

CountyFREESTONE
HighwayUS0084
FromTRM OFFSET 0742 + 0.163
ToTRM OFFSET 0742 + 0.163
CSJ6318-66-001
Proj IDRMC - 631866001
Work TypeREMOVE AND REPLACE CROSS DRAINAGE
 
0.001233742.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days25
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BECK-REIT & SONS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6318-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08171701
Totals233742.000.000.000.0

CountyBRAZOS
HighwaySH0021
FromVARIOUS
ToVARIOUS
CSJ6318-72-001
Proj IDRMC - 631872001
Work TypeCLEANING AND SEALING CRACKS
 
0.001116918.700.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days35
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GREENPAK SOLUTIONS, LIMITED LIABILITY COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6318-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171707
Totals116918.700.000.000.0

CountyWASHINGTON
HighwayUS0290
FromVARIOUS
ToVARIOUS
CSJ6318-73-001
Proj IDRMC - 631873001
Work TypeCLEANING AND SEALING CRACKS
 
0.001153946.640.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days40
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GREENPAK SOLUTIONS, LIMITED LIABILITY COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6318-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171706
Totals153946.640.000.000.0

CountyFREESTONE
HighwayUS0084
FromVARIOUS
ToVARIOUS
CSJ6318-74-001
Proj IDRMC - 631874001
Work TypeCLEANING AND SEALING CRACKS
 
0.001123927.880.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days38
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GREENPAK SOLUTIONS, LIMITED LIABILITY COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6318-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171705
Totals123927.880.000.000.0

CountyGRIMES
HighwayBS0006S
FromVARIOUS
ToVARIOUS
CSJ6320-24-001
Proj IDSUP - 632024001
Work TypeBUILDING JANITORIAL
 
0.0017505.84470.806.2
Work Order07-19-17
Work Began07-28-17
Work Completed
Time Computed07-25-17
Contract Working Days372
Addl Days Granted0
Working Days Charged38
Percent Time Used10
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6320-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06171703
Totals7505.84470.80470.806.2

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6320-25-001
Proj IDSUP - 632025001
Work TypeTREE REMOVAL
 
0.00130219.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-21-17
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6320-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06171704
Totals30219.000.000.000.0

CountyMADISON
HighwaySH0075
FromVARIOUS
ToVARIOUS
CSJ6321-01-001
Proj IDSUP - 632101001
Work TypeMADISON JANITORIAL
 
0.0106003.91400.286.6
Work Order08-01-17
Work Began08-01-17
Work Completed
Time Computed08-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged28
Percent Time Used7
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6321-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07171701
Totals6003.91400.28400.286.6

CountyWASHINGTON
HighwaySH0105
FromVARIOUS
ToVARIOUS
CSJ6321-46-001
Proj IDSUP - 632146001
Work TypePICNIC AREA MAINTENANCE
 
0.00135833.362786.407.7
Work Order08-07-17
Work Began08-01-17
Work Completed
Time Computed08-07-17
Contract Working Days365
Addl Days Granted0
Working Days Charged31
Percent Time Used8
Contractor(s)
TIBH INDUSTRIES, INC.
JUNCTION FIVE-O-FIVE
SUBCONTRACTOR(S) FOR CCSJ: 6321-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07171702
Totals35833.362786.402786.407.7

CountyWASHINGTON
HighwaySH0105
FromVARIOUS
ToVARIOUS
CSJ6321-54-001
Proj IDSUP - 632154001
Work TypeBUILDING JANITORIAL
 
0.00117219.37912.905.3
Work Order08-07-17
Work Began08-02-17
Work Completed
Time Computed08-07-17
Contract Working Days364
Addl Days Granted0
Working Days Charged30
Percent Time Used8
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6321-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07171703
Totals17219.37912.90912.905.3

CountyBURLESON
HighwaySH0021
FromVARIOUS
ToVARIOUS
CSJ6321-70-001
Proj IDRMC - 632170001
Work TypeCLEANING AND SEALING CRACKS
 
0.00192087.170.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days28
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GREENPAK SOLUTIONS, LIMITED LIABILITY COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6321-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171704
Totals92087.170.000.000.0

CountyBRAZOS
HighwayUS0190
FromVARIOUS
ToVARIOUS
CSJ6322-06-001
Proj IDSUP - 632206001
Work TypeLITTER PICKUP & DISPOSAL
 
0.0011393354.120.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6322-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07171704
Totals1393354.120.000.000.0

CountyLEON
HighwayUS0079
FromVARIOUS
ToVARIOUS
CSJ6322-88-001
Proj IDSUP - 632288001
Work TypePICNIC AREA MAINTENANCE FOR LEON COUNTY
 
0.00138028.240.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-13-17
Work Began09-13-17
Work Completed
Time Computed09-13-17
Contract Working Days364
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6322-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08171702
Totals38028.240.000.000.0

CountyBURLESON
HighwayFM0050
FromVARIOUS
ToVARIOUS
CSJ6322-89-001
Proj IDSUP - 632289001
Work TypePICNIC/CAR POOL MAINT IN BURLESON COUNTY
 
0.00132332.320.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-02-17
Work Began00-00-00
Work Completed
Time Computed09-02-17
Contract Working Days364
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6322-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08171703
Totals32332.320.000.000.0

CountyROBERTSON
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6322-90-001
Proj IDSUP - 632290001
Work TypePICNIC AREA & WEIGH STATION MAINTENANCE
 
0.01026528.980.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days364
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TIBH INDUSTRIES, INC.
JUNCTION FIVE-O-FIVE
SUBCONTRACTOR(S) FOR CCSJ: 6322-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08171704
Totals26528.980.000.000.0

CountyGRIMES
HighwayBS0006S
FromVARIOUS
ToVARIOUS
CSJ6322-92-001
Proj IDSUP - 632292001
Work TypePICNIC AREA MAINTENANCE IN GRIMES COUNTY
 
0.00141135.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-31-17
Work Began09-02-17
Work Completed
Time Computed09-02-17
Contract Working Days364
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6322-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08171705
Totals41135.000.000.000.0

page 1 | page 2 | page 3 | page 4 | page 5