Monthly State Let Maintenance Report For Bryan District As Of Apr 12, 2024 Page 2 Of 3

Last Update: Friday, April 12, 2024
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBRAZOS
HighwaySH0021
FromVARIOUS
ToVARIOUS
CSJ6438-49-001
Proj IDBPM - 643849001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.010538850.00151753.5028.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-08-23
Work Completed
Time Computed00-00-00
Contract Working Days40
Addl Days Granted0
Working Days Charged12
Percent Time Used30
Contractor(s)
GARRET SHIELDS INFRASTRUCTURE
SUBCONTRACTOR(S) FOR CCSJ: 6438-49-001
DIAMOND ELITE BARRICADES, LLC (0.00)
Contract #10234006
Totals538850.00151753.50151753.5028.1

CountyLEON
HighwayIH0045
FromVARIOUS
ToVARIOUS
CSJ6438-55-001
Proj IDBPM - 643855001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.010442895.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-13-24
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged6
Percent Time Used10
Contractor(s)
GARRET SHIELDS INFRASTRUCTURE
SUBCONTRACTOR(S) FOR CCSJ: 6438-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11234005
Totals442895.000.000.000.0

CountyWASHINGTON
HighwaySH0036
FromVARIOUS
ToVARIOUS
CSJ6439-18-001
Proj IDRMC - 643918001
Work TypeMILL AND INLAY
 
0.0101297678.001107603.6885.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged213
Percent Time Used29
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6439-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06234004
Totals1297678.00390542.401107603.6885.3

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6439-20-001
Proj IDRMC - 643920001
Work TypeMILL AND INLAY
 
0.0101293480.001176972.5890.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged213
Percent Time Used29
Contractor(s)
BRAZOS PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6439-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05234006
Totals1293480.0082682.361176972.5890.9

CountyWALKER
HighwayIH0045
FromVARIOUS
ToVARIOUS
CSJ6439-22-001
Proj IDRMC - 643922001
Work TypeMILL AND INLAY
 
0.0101747300.002011959.3199.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged213
Percent Time Used29
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6439-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05234205
Totals1747300.000.002011959.3199.9

CountyWASHINGTON
HighwaySH0036
FromVARIOUS
ToVARIOUS
CSJ6439-30-001
Proj IDRMC - 643930001
Work TypeSPOT BASE REPAIR
 
0.0101067637.50265754.7524.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged182
Percent Time Used49
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6439-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05234007
Totals1067637.5050912.00265754.7524.8

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6439-32-001
Proj IDRMC - 643932001
Work TypeSPOT BASE REPAIR
 
0.0101557750.00661580.9742.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged213
Percent Time Used58
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6439-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05234206
Totals1557750.00303690.84661580.9742.4

CountyWALKER
HighwayIH0045
FromVARIOUS
ToVARIOUS
CSJ6439-34-001
Proj IDRMC - 643934001
Work TypeSPOT BASE REPAIR
 
0.0103254250.001169079.3335.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged213
Percent Time Used29
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6439-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06234005
Totals3254250.00404050.051169079.3335.9

CountyGRIMES
HighwaySH0030
From~ 1.94 MI W. OF FM 244
ToFM 2562
CSJ6441-31-001
Proj IDRMC - 644131001
Work TypeMILL AND INLAY
 
0.0105669015.776778926.6899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-18-23
Work Completed
Time Computed00-00-00
Contract Working Days48
Addl Days Granted0
Working Days Charged48
Percent Time Used100
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 6441-31-001
STRIPE LINES, INC. (0.00)
PROFESSIONAL TRAFFIC CONTROL LLC (0.00)
DUSTIN ALLEN, INC. (0.00)
WILLIAMS ROAD, LLC (0.00)
Contract #06234006
Totals5669015.772700.006778926.6899.9

CountyGRIMES
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6441-94-001
Proj IDMMC - 644194001
Work TypeHOT MIX
 
0.010377600.00293273.4477.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-16-23
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted180
Working Days Charged229
Percent Time Used63
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 6441-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06234008
Totals377600.00102007.98293273.4477.6

CountyMADISON
HighwayIH0045
FromVARIOUS
ToVARIOUS
CSJ6441-95-001
Proj IDMMC - 644195001
Work TypeHOT MIX
 
0.010389800.00330693.8484.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-20-23
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted180
Working Days Charged225
Percent Time Used62
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 6441-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06234009
Totals389800.0048800.68330693.8484.8

CountyWALKER
HighwaySH0030
FromVARIOUS
ToVARIOUS
CSJ6442-16-001
Proj IDRMC - 644216001
Work TypeRAISED PAVEMENT MARKERS
 
0.010293308.0096846.3233.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-13-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged232
Percent Time Used63
Contractor(s)
BRYDL CONTRACTING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6442-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06234010
Totals293308.000.0096846.3233.0

CountyWALKER
HighwayIH0045
FromVARIOUS
ToVARIOUS
CSJ6442-24-001
Proj IDMMC - 644224001
Work TypeHOT MIX
 
0.010623600.00151977.0024.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-07-24
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged54
Percent Time Used30
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 6442-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12234011
Totals623600.00151977.00151977.0024.3

CountyWASHINGTON
HighwaySH0036
FromVARIOUS
ToVARIOUS
CSJ6442-30-001
Proj IDMMC - 644230001
Work TypeHOT MIX
 
0.010677300.00261680.9138.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-20-23
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted180
Working Days Charged225
Percent Time Used62
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 6442-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06234013
Totals677300.0041988.24261680.9138.6

CountyMILAM
HighwaySH0036
FromVARIOUS
ToVARIOUS
CSJ6442-38-001
Proj IDMMC - 644238001
Work TypeWINTER WEATHER MATERIAL
 
0.010341200.0031885.499.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-11-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged173
Percent Time Used47
Contractor(s)
SOUTHWEST ENVIROTX PARTNERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6442-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08234015
Totals341200.000.0031885.499.3

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6442-50-001
Proj IDRMC - 644250001
Work TypeTRAFFIC CONTROL SERVICES
 
0.0102053200.00754737.0036.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-26-23
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged219
Percent Time Used30
Contractor(s)
PROFESSIONAL TRAFFIC CONTROL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6442-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06234016
Totals2053200.00120135.00754737.0036.7

CountyWASHINGTON
HighwayUS0290
FromVARIOUS
ToVARIOUS
CSJ6443-08-001
Proj IDRMC - 644308001
Work TypeTRAFFIC CONTROL SERVICES
 
0.0102044500.00478378.7523.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-26-23
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged219
Percent Time Used30
Contractor(s)
PROFESSIONAL TRAFFIC CONTROL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6443-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06234017
Totals2044500.0071358.75478378.7523.3

CountyGRIMES
HighwaySH0030
FromVARIOUS
ToVARIOUS
CSJ6443-26-001
Proj IDMMC - 644326001
Work TypeWINTER WEATHER MATERIAL
 
0.010551200.0034559.516.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-11-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged173
Percent Time Used47
Contractor(s)
SOUTHWEST ENVIROTX PARTNERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6443-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08234212
Totals551200.000.0034559.516.2

CountyBRAZOS
HighwayUS0190
FromVARIOUS
ToVARIOUS
CSJ6444-52-001
Proj IDRMC - 644452001
Work TypeINSTALLATION OF DRIVEWAY PIPE
 
0.010949656.0014801.001.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-08-23
Work Completed
Time Computed00-00-00
Contract Working Days731
Addl Days Granted0
Working Days Charged206
Percent Time Used28
Contractor(s)
DIGG COMMERCIAL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6444-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06234407
Totals949656.000.0014801.001.5

CountyWASHINGTON
HighwaySH0036
FromVARIOUS
ToVARIOUS
CSJ6445-31-001
Proj IDMMC - 644531001
Work TypeHYDRAULIC CEMENT
 
0.010393592.8036228.799.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-26-23
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted180
Working Days Charged219
Percent Time Used60
Contractor(s)
TOUCHSTONE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6445-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06234408
Totals393592.800.0036228.799.2

page 1 | page 2 | page 3