Monthly Local Let Maintenance Report For Brownwood District As Of Jun 10, 2015 Page 2 Of 4

Last Update: Wednesday, June 10, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountySTEPHENS
Highway US0180
From VARIOUS
To VARIOUS
CSJ 6253-61-001
Proj ID SUP - 625361001
Work Type STATE USE PICNIC AREA MAINTENANCE
 
0.001 68800.00 1855.00 44640.00 64.8
Work Order 03-01-13
Work Began 03-01-13
Work Completed  
Time Computed 03-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 791
Percent Time Used 108
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6253-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01132332
Totals 68800.00 1855.00 44640.00 64.8

CountyEASTLAND
Highway SH0112
From N/A
To N/A
CSJ 6254-27-001
Proj ID SUP - 625427001
Work Type STATE USE JANITORIAL
 
0.001 45026.20 1185.90 36163.30 80.3
Work Order 01-01-13
Work Began 01-01-13
Work Completed  
Time Computed 01-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 821
Percent Time Used 112
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6254-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01132330
Totals 45026.20 1185.90 36163.30 80.3

CountyCOLEMAN
Highway SH0206
From COLEMAN MAINTENANCE OFFICE
To " "
CSJ 6255-40-001
Proj ID SUP - 625540001
Work Type STATE USE JANITORIAL
 
0.001 21863.80 668.78 18525.23 84.7
Work Order 03-01-13
Work Began 03-01-13
Work Completed  
Time Computed 03-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 791
Percent Time Used 108
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6255-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02132330
Totals 21863.80 668.78 18525.23 84.7

CountyBROWN
Highway US0067
From VARIOUS
To VARIOUS
CSJ 6256-19-001
Proj ID SUP - 625619001
Work Type STATE USE PICNIC AREA MAINTENANCE
 
0.001 110815.00 3910.00 84200.00 75.9
Work Order 03-01-13
Work Began 03-01-13
Work Completed  
Time Computed 03-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 791
Percent Time Used 108
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6256-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02132331
Totals 110815.00 3910.00 84200.00 75.9

CountyEASTLAND
Highway IH0020
From VARIOUS
To VARIOUS
CSJ 6256-20-001
Proj ID SUP - 625620001
Work Type STATE USE PICNIC AREA MAINTENANCE
 
0.001 156100.00 4845.00 124380.00 79.6
Work Order 03-01-13
Work Began 03-01-13
Work Completed  
Time Computed 03-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 790
Percent Time Used 108
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6256-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02132332
Totals 156100.00 4845.00 124380.00 79.6

CountyMCCULLOCH
Highway US0377
From MCCULLOCH COUNTY MAINTENACE OFFICE
To "
CSJ 6256-21-001
Proj ID SUP - 625621001
Work Type STATE USE JANITORIAL & CUSTODIAL SERVICE
 
0.001 16723.52 265.60 11780.96 70.4
Work Order 03-01-13
Work Began 03-01-13
Work Completed  
Time Computed 03-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 699
Percent Time Used 95
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6256-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02132333
Totals 16723.52 265.60 11780.96 70.4

CountyCOLEMAN
Highway US0067
From VARIOUS
To VARIOUS
CSJ 6259-65-001
Proj ID SUP - 625965001
Work Type STATE USE PICNIC AREA MAINTENANCE
 
0.001 82500.00 2725.00 54700.00 66.3
Work Order 09-01-13
Work Began 09-01-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 638
Percent Time Used 87
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6259-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08132330
Totals 82500.00 2725.00 54700.00 66.3

CountyMCCULLOCH
Highway US0377
From VARIOUS
To VARIOUS
CSJ 6259-66-001
Proj ID SUP - 625966001
Work Type STATE USE PICNIC AREA MAINTENANCE
 
0.001 91100.00 2280.00 64530.00 70.8
Work Order 09-01-13
Work Began 09-01-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 564
Percent Time Used 77
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6259-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08132331
Totals 91100.00 2280.00 64530.00 70.8

CountyBROWN
Highway US0183
From N/A
To N/A
CSJ 6259-67-001
Proj ID SUP - 625967001
Work Type STATE USE JANITORIAL BWD AREA OFC
 
0.001 14258.72 488.68 10598.70 74.3
Work Order 10-01-13
Work Began 10-01-13
Work Completed  
Time Computed 10-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 608
Percent Time Used 83
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6259-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08132332
Totals 14258.72 488.68 10598.70 74.3

CountyBROWN
Highway US0183
From VARIOUS
To VARIOUS
CSJ 6259-68-001
Proj ID SUP - 625968001
Work Type STATE USE JANITORIAL BROWN CO MAINT OFC
 
0.001 13816.80 841.70 10051.00 72.7
Work Order 10-01-13
Work Began 10-01-13
Work Completed  
Time Computed 10-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 608
Percent Time Used 83
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6259-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08132333
Totals 13816.80 841.70 10051.00 72.7

CountyMILLS
Highway US0084
From VARIOUS
To VARIOUS
CSJ 6259-69-001
Proj ID SUP - 625969001
Work Type STATE USE JANITORIAL MILLS CO MAINT OFC
 
0.001 10957.73 415.60 9166.25 83.6
Work Order 10-01-13
Work Began 10-01-13
Work Completed  
Time Computed 10-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 551
Percent Time Used 75
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6259-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08132334
Totals 10957.73 415.60 9166.25 83.6

CountyEASTLAND
Highway IH0020
From VARIOUS
To VARIOUS
CSJ 6265-77-001
Proj ID RMC - 626577001
Work Type ROADSIDE MOWING
 
367.820 259802.50 0.00 323058.75 99.9
Work Order 12-03-13
Work Began 12-10-13
Work Completed  
Time Computed 12-10-13
Contract Working Days 85
Addl Days Granted 0
Working Days Charged 72
Percent Time Used 84
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6265-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10132301
Totals 259802.50 0.00 323058.75 99.9

CountySAN SABA
Highway US0190
From N/A
To N/A
CSJ 6267-26-001
Proj ID SUP - 626726001
Work Type STATE USE JANITORIAL - SAN SABA
 
0.001 21886.00 809.00 11583.00 52.9
Work Order 01-01-14
Work Began 00-00-00
Work Completed  
Time Computed 01-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 166
Percent Time Used 22
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6267-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11132330
Totals 21886.00 809.00 11583.00 52.9

CountyBROWN
Highway US0183
From N/A
To N/A
CSJ 6268-63-001
Proj ID SUP - 626863001
Work Type STATE USE JANITORIAL - DIST OFC
 
0.001 60473.00 0.00 36723.50 60.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-01-14
Work Began 00-00-00
Work Completed  
Time Computed 03-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 191
Percent Time Used 26
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6268-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12132330
Totals 60473.00 0.00 36723.50 60.7

CountyBROWN
Highway US0067
From BROWN COUNTY
To BROWN COUNTY
CSJ 6270-71-001
Proj ID RMC - 627071001
Work Type ROADSIDE MOWING
 
326.700 288805.20 0.00 133404.06 46.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-24-14
Work Began 00-00-00
Work Completed  
Time Computed 10-31-14
Contract Working Days 95
Addl Days Granted 0
Working Days Charged 25
Percent Time Used 26
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6270-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04142301
Totals 288805.20 0.00 133404.06 46.1

CountyMCCULLOCH
Highway US0190
From VARIOUS
To VARIOUS
CSJ 6270-97-001
Proj ID RMC - 627097001
Work Type REMOVAL / DISPOSAL OF DRIFTWOOD / DEBRIS
 
0.001 245768.20 0.00 541408.50 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-16-14
Work Began 06-16-14
Work Completed  
Time Computed 06-23-14
Contract Working Days 45
Addl Days Granted 75
Working Days Charged 84
Percent Time Used 70
Contractor(s)
DEKALB TREE SPECIALIST
SUBCONTRACTOR(S) FOR CCSJ: 6270-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05142301
Totals 245768.20 0.00 541408.50 99.9

CountyBROWN
Highway US0377
From VARIOUS
To VARIOUS
CSJ 6272-68-001
Proj ID SUP - 627268001
Work Type STATE - USE LITTER PICKUP AND DISPOSAL
 
0.001 96521.52 490.82 45760.76 47.4
Work Order 06-01-14
Work Began 06-01-14
Work Completed  
Time Computed 06-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 373
Percent Time Used 51
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6272-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04142330
Totals 96521.52 490.82 45760.76 47.4

CountyBROWN
Highway US0377
From DISTRICT-WIDE
To DISTRICT-WIDE
CSJ 6273-26-001
Proj ID RMC - 627326001
Work Type TRAFFIC SIGNAL MAINTENANCE (WILL - CALL)
 
0.001 379430.00 0.00 107795.72 28.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-18-15
Work Began 11-17-14
Work Completed  
Time Computed 05-25-15
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 11
Percent Time Used 11
Contractor(s)
WILLIS ELECTRIC CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 6273-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06142301
Totals 379430.00 0.00 107795.72 28.4

CountyBROWN
Highway US0377
From DISTRICT-WIDE
To DISTRICT-WIDE
CSJ 6273-28-001
Proj ID RMC - 627328001
Work Type REPAIR MBGF (WILL - CALL) (AS NEEDED)
 
0.001 300575.00 0.00 43040.00 14.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-08-15
Work Began 04-14-15
Work Completed  
Time Computed 04-15-15
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 16
Percent Time Used 10
Contractor(s)
LONE STAR BARRIER SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6273-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01152301
Totals 300575.00 0.00 43040.00 14.3

CountyBROWN
Highway US0067
From US 67 WESTBOUND
To BROWN/COMANCHE COUNTY LINE
CSJ 6274-92-001
Proj ID RMC - 627492001
Work Type MILL AND INLAY
 
0.758 284123.78 0.00 645004.30 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-04-14
Work Began 08-04-14
Work Completed  
Time Computed 08-11-14
Contract Working Days 20
Addl Days Granted 20
Working Days Charged 18
Percent Time Used 45
Contractor(s)
PRATER EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6274-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07142301
Totals 284123.78 0.00 645004.30 99.9

page 1 | page 2 | page 3 | page 4