Monthly Local Let Maintenance Report For Brownwood District As Of Jul 14, 2017 Page 3 Of 5

Last Update: Monday, July 17, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyCOMANCHE
HighwaySH0036
FromVARIOUS
ToVARIOUS
CSJ6285-87-001
Proj IDSUP - 628587001
Work TypeSU-ALDERSGATE-PICNIC
 
0.00154135.0025144.0046.4
Work Order05-01-15
Work Began05-01-15
Work Completed
Time Computed05-01-15
Contract Working Days730
Addl Days Granted735
Working Days Charged792
Percent Time Used54
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6285-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03152334
Totals54135.001058.0025144.0046.4

CountySTEPHENS
HighwayUS0183
FromVARIOUS
ToVARIOUS
CSJ6286-79-001
Proj IDRMC - 628679001
Work TypeROADSIDE MOWING
 
0.001178607.70192736.5999.9
Work Order06-30-15
Work Began07-07-15
Work Completed
Time Computed07-07-15
Contract Working Days58
Addl Days Granted58
Working Days Charged65
Percent Time Used56
Contractor(s)
FOUR R OILFIELD SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6286-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04152303
Totals178607.700.00192736.5999.9

CountyLAMPASAS
HighwayUS0190
FromVARIOUS
ToVARIOUS
CSJ6286-80-001
Proj IDRMC - 628680001
Work TypeROADSIDE MOWING
 
0.001250431.56298762.6899.9
Work Order06-02-17
Work Began07-01-15
Work Completed
Time Computed06-09-17
Contract Working Days60
Addl Days Granted60
Working Days Charged21
Percent Time Used17
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6286-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04152304
Totals250431.5663299.52298762.6899.9

CountyMILLS
HighwayUS0084
FromVARIOUS
ToVARIOUS
CSJ6286-81-001
Proj IDRMC - 628681001
Work TypeROADSIDE MOWING
 
0.001258264.69146005.6957.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-20-15
Work Began07-20-15
Work Completed
Time Computed11-27-15
Contract Working Days64
Addl Days Granted0
Working Days Charged17
Percent Time Used26
Contractor(s)
SQUARE G, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6286-81-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04152305
Totals258264.690.00146005.6957.0

CountySTEPHENS
HighwayUS0180
FromVARIOUS
ToVARIOUS
CSJ6287-02-001
Proj IDSUP - 628702001
Work TypeSU-ALDERSGATE-LITTER REMOVAL
 
0.00163764.8115060.8523.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-01-15
Work Began05-01-15
Work Completed
Time Computed05-01-15
Contract Working Days365
Addl Days Granted0
Working Days Charged154
Percent Time Used42
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6287-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03152330
Totals63764.810.0015060.8523.6

CountyMILLS
HighwayUS0084
FromVARIOUS
ToVARIOUS
CSJ6287-03-001
Proj IDSUP - 628703001
Work TypeSU-ALDERSGATE-LITTER REMOVAL
 
0.00126347.6624959.1194.7
Work Order05-01-15
Work Began05-01-15
Work Completed
Time Computed05-01-15
Contract Working Days730
Addl Days Granted0
Working Days Charged792
Percent Time Used108
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6287-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03152331
Totals26347.660.0024959.1194.7

CountySAN SABA
HighwayUS0190
FromVARIOUS
ToVARIOUS
CSJ6287-04-001
Proj IDSUP - 628704001
Work TypeSU-ALDERSGATE-LITTER REMOVAL
 
0.00131575.1635718.9599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-15-15
Work Began05-01-15
Work Completed
Time Computed05-01-15
Contract Working Days730
Addl Days Granted35
Working Days Charged762
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6287-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03152332
Totals31575.160.0035718.9599.9

CountyEASTLAND
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6287-05-001
Proj IDSUP - 628705001
Work TypeSU-ALDERSGATE-PICNIC
 
0.001176400.00130180.0073.7
Work Order05-01-15
Work Began05-01-15
Work Completed
Time Computed05-01-15
Contract Working Days730
Addl Days Granted735
Working Days Charged792
Percent Time Used54
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6287-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03152335
Totals176400.005705.00130180.0073.7

CountySTEPHENS
HighwayUS0180
FromVARIOUS
ToVARIOUS
CSJ6287-11-001
Proj IDSUP - 628711001
Work TypeSU-ALDERSGATE-PICNIC
 
0.00177225.0055620.0072.0
Work Order05-01-15
Work Began05-01-15
Work Completed
Time Computed05-01-15
Contract Working Days730
Addl Days Granted65
Working Days Charged792
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6287-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03152336
Totals77225.002030.0055620.0072.0

CountyMILLS
HighwayUS0084
FromVARIOUS
ToVARIOUS
CSJ6287-12-001
Proj IDSUP - 628712001
Work TypeSU-ALDERSGATE-PICNIC
 
0.00142500.0033580.0079.0
Work Order05-01-15
Work Began05-01-15
Work Completed
Time Computed05-01-15
Contract Working Days730
Addl Days Granted735
Working Days Charged792
Percent Time Used54
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6287-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03152337
Totals42500.001330.0033580.0079.0

CountyCOLEMAN
HighwaySH0206
FromCOLEMAN CO MAINT OFFICE
To***
CSJ6287-13-001
Proj IDSUP - 628713001
Work TypeSTATE USE-JANITORIAL-JCI/CFLR
 
0.00125425.0821126.4983.0
Work Order05-01-15
Work Began05-01-15
Work Completed
Time Computed05-01-15
Contract Working Days730
Addl Days Granted66
Working Days Charged792
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6287-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03152338
Totals25425.08770.1921126.4983.0

CountyMCCULLOCH
HighwayUS0377
FromMCCULLOCH CO MAINT OFFICE
To***
CSJ6287-14-001
Proj IDSUP - 628714001
Work TypeSTATE USE-JANITORIAL-JCI/CFLR
 
0.00114862.7212513.6884.1
Work Order05-01-15
Work Began05-01-15
Work Completed
Time Computed05-01-15
Contract Working Days730
Addl Days Granted70
Working Days Charged792
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6287-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03152339
Totals14862.72292.1612513.6884.1

CountyBROWN
HighwayUS0084
FromDISTRICT-WIDE
To***
CSJ6287-33-001
Proj IDRMC - 628733001
Work TypeBRIDGE MAINTENANCE (CALL-OUT)
 
0.001434750.00750332.5099.9
Work Order04-05-17
Work Began10-27-15
Work Completed
Time Computed04-12-17
Contract Working Days75
Addl Days Granted85
Working Days Charged136
Percent Time Used85
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 6287-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07152301
Totals434750.000.00750332.5099.9

CountyBROWN
HighwayUS0183
FromBWD DIST OFFICE COMPLEX
To***
CSJ6287-35-001
Proj IDSUP - 628735001
Work TypeSTATE USE-MOWING-JCI/CFLR
 
0.00134000.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-01-15
Work Began05-01-15
Work Completed
Time Computed05-01-15
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6287-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03152340
Totals34000.000.000.000.0

CountyEASTLAND
HighwayIH0020
FromEASTBOUND REST AREA ON IH20
To***
CSJ6287-46-001
Proj IDRMC - 628746001
Work TypeTREE TRIMMING AND REMOVAL AT REST AREA
 
0.00117458.0017624.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-15-17
Work Began03-15-17
Work Completed
Time Computed03-22-17
Contract Working Days15
Addl Days Granted0
Working Days Charged4
Percent Time Used26
Contractor(s)
KAM DAILY LAWN SERVICE AND DEMOLITION WORK
SUBCONTRACTOR(S) FOR CCSJ: 6287-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02172301
Totals17458.000.0017624.0099.9

CountyBROWN
HighwayUS0183
FromDISTRICT OFFICE COMPLEX
To****
CSJ6291-89-001
Proj IDSUP - 629189001
Work TypeSTATE USE-JANITORIAL-JCI/CFLR
 
0.001119629.7265451.5554.7
Work Order08-01-15
Work Began08-01-15
Work Completed
Time Computed08-01-15
Contract Working Days730
Addl Days Granted0
Working Days Charged700
Percent Time Used95
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6291-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07152330
Totals119629.724159.2265451.5554.7

CountyCOLEMAN
HighwayUS0084
FromVARIOUS
To***
CSJ6294-18-001
Proj IDSUP - 629418001
Work TypeSTATE USE-PICNIC-JCI/CFLR
 
0.00190472.0065491.0072.3
Work Order09-01-15
Work Began09-01-15
Work Completed
Time Computed09-01-15
Contract Working Days730
Addl Days Granted0
Working Days Charged669
Percent Time Used91
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6294-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08152330
Totals90472.003403.0065491.0072.3

CountyMCCULLOCH
HighwayUS0377
FromVARIOUS
To***
CSJ6294-19-001
Proj IDSUP - 629419001
Work TypeSTATE USE-PICNIC-JCI/CFLR
 
0.00194927.0076368.0080.4
Work Order09-01-15
Work Began09-01-15
Work Completed
Time Computed09-01-15
Contract Working Days730
Addl Days Granted0
Working Days Charged700
Percent Time Used95
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6294-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08152331
Totals94927.003349.0076368.0080.4

CountyBROWN
HighwayUS0183
FromBROWNWOOD AREA OFFICE
To***
CSJ6294-64-001
Proj IDSUP - 629464001
Work TypeSTATE USE JANITORIAL-JCI/CFLR
 
0.00118241.4412007.8165.8
Work Order10-01-15
Work Began10-01-15
Work Completed
Time Computed10-01-15
Contract Working Days730
Addl Days Granted0
Working Days Charged639
Percent Time Used87
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6294-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09152330
Totals18241.44514.2012007.8165.8

CountyBROWN
HighwayUS0183
FromBROWN COUNTY MAINTENANCE OFFICE
To***
CSJ6294-65-001
Proj IDSUP - 629465001
Work TypeSTATE USE JANITORIAL-CFLR/JCI
 
0.00117461.6010637.2060.9
Work Order10-01-15
Work Began10-01-15
Work Completed
Time Computed10-01-15
Contract Working Days730
Addl Days Granted0
Working Days Charged639
Percent Time Used87
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6294-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09152331
Totals17461.60466.0010637.2060.9

page 1 | page 2 | page 3 | page 4 | page 5