AVERAGE LOW BID UNIT PRICE - CONSTRUCTION - CORPUS CHRISTI DISTRICT
Last Update: Friday, May 3, 2013
| ITEMS 100 2002 TO 169 2002 |
| Item No |
Description |
Units |
April 30, 2013 |
Twelve Month Moving |
Usage |
| Quantity |
Avg Bid |
Quantity |
Avg Bid |
| 100 2002 |
PREPARING ROW |
STA |
99.500 |
300.00000 |
758.700 |
764.18664 |
11 |
| 100 2009 |
PREPARING ROW (TREE) (6" TO 24" DIA) |
EA |
|
|
3.000 |
1,139.70000 |
1 |
| 104 2001 |
REMOVING CONC (PAV) |
SY |
|
|
1,550.000 |
20.00000 |
1 |
| 104 2009 |
REMOVING CONC (RIPRAP) |
SY |
1,644.000 |
8.40000 |
8,778.420 |
8.98666 |
7 |
| 104 2010 |
REMOVING CONC (RIPRAP) |
CY |
|
|
743.000 |
56.10945 |
2 |
| 104 2014 |
REMOVING CONC (FOUNDATIONS) |
CY |
|
|
10.000 |
100.00000 |
1 |
| 104 2015 |
REMOVING CONC (SIDEWALKS) |
SY |
68.000 |
16.50000 |
86.000 |
15.01395 |
2 |
| 104 2017 |
REMOVING CONC (DRIVEWAYS) |
SY |
566.000 |
11.25000 |
1,987.000 |
8.71535 |
4 |
| 104 2021 |
REMOVING CONC (CURB) |
LF |
|
|
2,478.000 |
3.76158 |
2 |
| 104 2022 |
REMOVING CONC (CURB AND GUTTER) |
LF |
175.000 |
8.30000 |
385.000 |
4.82000 |
2 |
| 104 2023 |
REMOVING CONC (CTB) |
LF |
|
|
991.000 |
11.84000 |
1 |
| 104 2028 |
REMOVING CONC (MISC) |
SY |
33.000 |
16.00000 |
1,059.000 |
11.45654 |
4 |
| 104 2044 |
REMOVING CONC (FLUME) |
SY |
|
|
62.000 |
8.90000 |
1 |
| 105 2014 |
REMOVING STAB BASE & ASPH PAV (7" - 12") |
SY |
|
|
334.000 |
20.00000 |
1 |
| 106 2001 |
OBLITERATING ABANDONED ROAD |
STA |
|
|
3.500 |
290.00000 |
1 |
| 110 2001 |
EXCAVATION (ROADWAY) |
CY |
13,559.000 |
3.40000 |
213,515.000 |
4.96792 |
10 |
| 110 2002 |
EXCAVATION (CHANNEL) |
CY |
|
|
80,918.000 |
4.77118 |
2 |
| 112 2001 |
SUBGRADE WIDENING (ORD COMP) |
STA |
|
|
22.220 |
833.43834 |
2 |
| 112 2002 |
SUBGRADE WIDENING (DENS CONT) |
STA |
|
|
1,379.720 |
581.37821 |
4 |
| 132 2004 |
EMBANKMENT (FINAL) (DENS CONT) (TY B) |
CY |
|
|
6,247.000 |
4.44000 |
1 |
| 132 2005 |
EMBANKMENT (FINAL) (ORD COMP) (TY C) |
CY |
|
|
400.000 |
6.40000 |
1 |
| 132 2006 |
EMBANKMENT (FINAL) (DENS CONT) (TY C) |
CY |
19,590.000 |
4.10000 |
730,079.000 |
6.10634 |
10 |
| 134 2001 |
BACKFILL (TY A) |
STA |
803.000 |
130.00000 |
1,452.320 |
140.12911 |
4 |
| 134 2002 |
BACKFILL (TY B) |
STA |
|
|
612.930 |
69.88323 |
2 |
| 134 2004 |
BACKFILL (TY A OR B) |
STA |
|
|
2,058.500 |
113.64274 |
4 |
| 158 2002 |
SPEC EXCAV WORK (BACKHOE) |
HR |
|
|
28.000 |
125.00000 |
1 |
| 160 2003 |
FURNISHING AND PLACING TOPSOIL (4") |
SY |
|
|
107,304.000 |
.57072 |
2 |
| 160 2005 |
FURNISHING AND PLACING TOPSOIL |
CY |
|
|
33.000 |
125.00000 |
1 |
| 161 2026 |
COMPOST MANUF TOPSOIL (BOS OR PB) (6") |
SY |
|
|
510.000 |
5.00000 |
1 |
| 162 2002 |
BLOCK SODDING |
SY |
|
|
4,477.000 |
5.24578 |
4 |
| 164 2021 |
CELL FBR MLCH SEED (PERM) (RURAL) (SANDY) |
SY |
|
|
131,884.000 |
.20295 |
2 |
| 164 2023 |
CELL FBR MLCH SEED (PERM) (RURAL) (CLAY) |
SY |
|
|
49,368.000 |
.22164 |
2 |
| 164 2024 |
CELL FBR MLCH SEED (PERM) (RURAL) (CLAY) |
AC |
|
|
42.430 |
910.00000 |
1 |
| 164 2033 |
DRILL SEEDING (PERM) (RURAL) (SANDY) |
SY |
|
|
19,707.000 |
.14000 |
1 |
| 164 2035 |
DRILL SEEDING (PERM) (RURAL) (CLAY) |
SY |
20,490.000 |
.29000 |
660,258.000 |
.10283 |
8 |
| 166 2002 |
FERTILIZER |
TON |
.800 |
910.00000 |
28.080 |
776.78063 |
10 |
| 168 2001 |
VEGETATIVE WATERING |
MG |
327.600 |
24.00000 |
19,733.080 |
14.01684 |
16 |
| 169 2001 |
SOIL RETENTION BLANKETS (CL 1) (TY A) |
SY |
|
|
90,101.000 |
.80495 |
2 |
| 169 2002 |
SOIL RETENTION BLANKETS (CL 1) (TY B) |
SY |
|
|
2,820.000 |
2.35000 |
1 |