AVERAGE LOW BID UNIT PRICE - CONSTRUCTION - CORPUS CHRISTI DISTRICT

Last Update: Wednesday, July 2, 2014
ITEMS 500 2001 TO 560 2032
Items Items Bid Code Range
0100 - 0193
0216 - 0275
0305 - 0354
0400 - 0496
0500 - 0560
0610 - 0690
0730 - 0760
1122 - 1122
2214 - 2214
3142 - 3270
4174 - 4174
5369 - 5369
6006 - 6834
8188 - 8942
500 2001 - 560 2032
Item No Description Units June 30, 2014 Twelve Month Moving Usage
Quantity Avg Bid Quantity Avg Bid
500 2001 MOBILIZATION LS 4.000 113,568.55500 22.000 629,538.76136 21
502 2001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 33.000 2,593.32121 214.000 4,816.68374 21
502 2004 OFF - DUTY POLICE OFFICER (TY 3) HR     24.000 103.83000 1
502 2047 OFF - DUTY POLICE OFFICER HR     2,824.000 62.81530 4
508 2002 CONSTRUCTING DETOURS SY 298.000 25.00000 24,582.000 27.62045 3
512 2004 PORT CTB (FUR & INST) (SNGL SLP) (TY 1) LF     12,340.000 43.06259 3
512 2008 PORT CTB (FUR & INST) (LOW PROF) (TY 1) LF 840.000 40.71429 7,800.000 19.80513 4
512 2009 PORT CTB (FUR & INST) (LOW PROF) (TY 2) LF 120.000 41.66667 400.000 22.66000 4
512 2022 PORT CTB (MOVE) (SNGL SLP) (TY 1) LF     54,100.000 4.54662 2
512 2026 PORT CTB (MOVE) (LOW PROF) (TY 1) LF 60.000 18.27000 8,480.000 2.71441 3
512 2027 PORT CTB (MOVE) (LOW PROF) (TY 2) LF 40.000 13.70000 320.000 8.61250 3
512 2040 PORT CTB (REMOVE) (SNGL SLP) (TY 1) LF     12,340.000 5.68582 3
512 2044 PORT CTB (REMOVE) (LOW PROF) (TY 1) LF 840.000 15.51000 7,800.000 6.31646 4
512 2045 PORT CTB (REMOVE) (LOW PROF) (TY 2) LF 120.000 21.48000 400.000 10.16400 4
512 2048 PORT CTB (FUR & INST) (F - SHAPE) (TY 1) LF     14,550.000 45.40206 2
512 2050 PORT CTB (MOVE) (F - SHAPE) (TY 1) LF     13,560.000 2.85973 2
512 2052 PORT CTB (REMOVE) (F - SHAPE) (TY 1) LF     14,550.000 5.19794 2
514 2004 PERM CONC TRF BARR (SGL SLP) (TY 1) (42" LF     3,435.000 42.08000 1
514 2006 PERM CONC TRF BARR (SGL SLP) (TY 3) (42" LF     200.000 134.93000 1
514 2015 PERM CONC TRF BARR (F - SHAPE) (TY 1) LF     1,290.000 71.00000 1
514 2042 PERM CONC TRF BARR (SLG SLP) (TY 1) (MOD) LF     2,500.000 183.73000 1
514 2068 PERM CTB (SGL SLP) TY3 (36") (MOD) LF     190.000 212.86000 1
529 2001 CONC CURB (TY I) LF     826.000 9.57000 1
529 2002 CONC CURB (TY II) LF 16.000 35.49000 1,754.000 15.97340 4
529 2004 CONC CURB & GUTTER (TY II) LF     50.000 48.38000 1
529 2006 CONC CURB (MONO) (TY II) LF     10,936.000 9.08083 2
529 2007 CONC CURB (DOWEL) LF     4,122.000 10.30000 1
529 2009 CONCRETE CURB (SPECIAL) LF     2,795.000 24.00000 1
529 2010 CONC CURB AND GUTTER (TY II) (REINF) LF     30,945.000 19.00729 2
529 2016 CONC CURB (TY F) LF     16,497.000 26.38618 2
529 2018 CONC CURB (MONO) (TY II) (SPECIAL) LF     2,212.000 13.75000 1
530 2005 INTERSECTIONS (ACP) SY     69,975.000 13.49193 6
530 2006 INTERSECTIONS (SURF TREAT) SY     1,119.000 28.67000 1
530 2010 DRIVEWAYS (CONC) SY 351.000 45.00000 6,784.000 56.78847 4
530 2011 DRIVEWAYS (ACP) SY 2,150.000 17.00000 24,111.000 33.04358 7
530 2012 DRIVEWAYS (SURF TREAT) SY 97.000 53.83000 4,446.000 39.23100 5
530 2017 TURNOUTS (ACP) SY     3,011.000 74.15961 3
530 2018 TURNOUTS (SURF TREAT) SY     319.000 36.99000 1
530 2030 DRIVEWAYS (ACP) (TYPE 1) SY     638.000 31.71000 1
530 2031 DRIVEWAYS (ACP) (TYPE 2) SY     1,592.000 21.90000 1
531 2003 CONC SIDEWALKS (5') (6") LF     98.000 30.00000 1
531 2004 CONC SIDEWALKS (6") SY 748.000 41.65904 748.000 41.65904 2
531 2005 CURB RAMPS (TY 1) EA     6.000 1,100.00000 1
531 2009 CURB RAMPS (TY 6) EA     2.000 1,100.00000 1
531 2010 CURB RAMPS (TY 7) EA     2.000 1,100.00000 1
531 2015 CONC SIDEWALKS (4") SY     920.000 40.65000 1
531 2024 CONC SIDEWALK (5") SY     28,706.000 46.36567 2
531 2054 CURB RAMPS SY 20.000 1,868.24000 1,489.500 118.12326 3
531 2071 CURB RAMPS (TY 7) SY 104.000 145.00000 104.000 145.00000 1
533 2003 SHOULDER TEXTURING (MILLED) LF     126,030.000 .19000 1
533 2006 SHOULDER TEXTURING (MILLED) (ASPHALT) LF     679,605.000 .16317 6
540 2001 MTL W - BEAM GD FEN (TIM POST) LF 225.000 28.89164 21,346.500 17.15764 7
540 2002 MTL W - BEAM GD FEN (STEEL POST) LF     323.000 37.97000 1
540 2011 MTL BEAM GD FEN TRANS (THRIE - BEAM) EA     29.000 1,359.78552 5
540 2012 MTL BEAM GD FEN TRANS (TL2) EA 8.000 866.40000 8.000 866.40000 2
540 2014 MTL W - BEAM GD FEN (LOW FILL CULVERT) LF     420.000 46.07000 1
540 2015 MTL W - BEAM GD FEN (TIM POST) RADIUS RAIL LF     112.500 23.14000 1
540 2044 DOWNSTREAM ANCHOR TERMINAL (DAT) SECTION EA 2.000 1,101.10000 30.000 879.68067 4
540 2045 MTL BM GD FEN (LONG SPAN SYSTEM) LF     1,475.000 22.14441 3
540 2051 DWNSTRM ANCH TERM (DAT) SECT W / MOW STRI EA 2.000 1,185.00000 2.000 1,185.00000 1
542 2001 REMOVING METAL BEAM GUARD FENCE LF     14,178.000 1.43478 4
542 2002 REMOVING TERMINAL ANCHOR SECTION EA     59.000 97.81356 3
544 2001 GUARDRAIL END TREATMENT (INSTALL) EA     68.000 1,902.14706 3
544 2003 GUARDRAIL END TREATMENT (REMOVE) EA     25.000 259.51440 2
544 2004 GDRAIL END TRT (INST) (WOOD POST) (TY I) EA 2.000 2,285.00000 2.000 2,285.00000 1
544 2005 GDRAIL END TRT (INST) (WOOD POST) (TY II) EA 2.000 2,356.20000 41.000 2,169.94049 4
545 2001 CRASH CUSH ATTEN (INSTL) EA     19.000 15,762.37368 4
545 2002 CRASH CUSH ATTEN (MOVE & RESET) EA     77.000 945.00818 2
545 2003 CRASH CUSH ATTEN (REMOVE) EA     11.000 797.64636 2
545 2049 CRASH CUSH ATTEN (INSTL) (WORK ZONE) EA     26.000 8,923.84615 3
545 2050 CRASH CUSH ATTEN (MOV & RESET) (WORK ZONE) EA     18.000 1,344.44444 2
545 2051 CRASH CUSH ATTEN (REMOVE) (WORK ZONE) EA     26.000 456.68077 3
552 2001 WIRE FENCE (TY A) LF 951.000 16.36540 951.000 16.36540 2
552 2005 GATE (TY 1) EA 1.000 671.00000 1.000 671.00000 1
560 2004 MAILBOX INSTALL - S (WC - POST) TY 3 FND EA     7.000 741.42857 2
560 2006 MAILBOX INSTALL - S (RR - POST) TY 4 FND - T EA     28.000 185.47214 4
560 2007 MAILBOX INSTALL - D (TWW - POST) TY 4 FND - T EA     1.000 205.00000 1
560 2008 MAILBOX INSTALL - M (TWW - POST) TY 4 FND - T EA     2.000 410.00000 1
560 2009 MAILBOX INSTALL - M (TWG - POST) TY 1 FND EA     3.000 350.00000 1
560 2021 MAILBOX INSTALL - S (TWG - POST) TY 2 FND - TB EA     20.000 170.00000 1
560 2022 MAILBOX INSTALL - D (TWG - POST) TY 2 FND - TB EA     3.000 195.00000 1
560 2023 MAILBOX INSTALL - M (TWG - POST) TY 2 FND - TB EA     4.000 330.00000 1
560 2025 MAILBOX INSTALL - D (RR - POST) TY 4 FND - T EA     2.000 300.00000 1
560 2032 MAILBOX INSTALLTION (SINGLE) INSTALL ONL EA 7.000 200.00000 7.000 200.00000 1