AVERAGE LOW BID UNIT PRICE - CONSTRUCTION - CORPUS CHRISTI DISTRICT

Last Update: Friday, January 2, 2015
ITEMS 1122 2001 TO 1122 2057
Items Items Bid Code Range
0100 - 0193
0216 - 0275
0310 - 0354
0400 - 0496
0500 - 0560
0610 - 0690
0760 - 0760
1122 - 1122
2214 - 2214
3142 - 3268
4174 - 4174
5367 - 5369
6007 - 6834
8020 - 8942
1122 2001 - 1122 2057
Item No Description Units December 31, 2014 Twelve Month Moving Usage
Quantity Avg Bid Quantity Avg Bid
1122 2001 ROCK FILTER DAMS (INSTALL) (TY 1) LF 80.000 32.03000 142.000 32.03000 2
1122 2002 ROCK FILTER DAMS (INSTALL) (TY 2) LF     1,676.000 20.08019 2
1122 2003 ROCK FILTER DAMS (INSTALL) (TY 3) LF     38.000 85.01000 1
1122 2005 ROCK FILTER DAMS (INSTALL) (TY 1) CY     33.600 133.00000 1
1122 2006 ROCK FILTER DAMS (INSTALL) (TY 2) CY     20.000 77.74000 2
1122 2009 ROCK FILTER DAMS (REMOVE) LF 80.000 12.60000 1,856.000 6.70733 4
1122 2010 ROCK FILTER DAMS (REMOVE) CY     53.600 34.49701 3
1122 2016 CONSTRUCTION EXITS (INSTALL) (TY 1) SY 78.000 27.30000 1,482.000 20.83789 9
1122 2017 CONSTRUCTION EXITS (INSTALL) (TY 2) SY     312.000 23.30000 2
1122 2019 CONSTRUCTION EXITS (REMOVE) SY 78.000 13.13000 1,794.000 18.64783 11
1122 2024 BACKHOE WORK (EROSION & SEDM CONT) HR     24.000 65.00000 1
1122 2037 TEMPORARY SEDIMENT CONTROL FENCE INSTL LF 100.000 10.00000 43,593.000 1.99775 8
1122 2048 BIOGRD EROSN CONT LOGS (12" DIA) INSTAL LF     6,935.000 4.69739 10
1122 2049 BIOGRD EROSN CONT LOGS (18" DIA) INSTAL LF 880.000 6.29000 6,444.000 6.17396 10
1122 2056 BIODEGRADBLE EROSION CONTROL LOGS REMO LF 880.000 1.38000 13,379.000 1.28882 16
1122 2057 TEMPORARY SEDIMENT CONTROL FENCE REMOV LF 100.000 10.00000 18,397.000 .63049 6