Monthly State Let Construction Report For Corpus Christi District As Of Mar 13, 2024 Page 3 Of 5

Last Update: Wednesday, March 13, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyKARNES
HighwaySH 119
FromWILSON COUNTY LINE
ToDEWITT COUNTY LINE
CSJ0359-04-005
Proj IDC 359-4-5
Work TypeSUPER-2 HIGHWAY
 
11.19020496430.4719832905.8896.7
Work Order09-18-20
Work Began10-19-20
Work Completed
Time Computed10-01-20
Contract Working Days465
Addl Days Granted16
Working Days Charged478
Percent Time Used99
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0359-04-005
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.79)
GEOSOURCE, INC. (0.57)
HIGHWAY BARRICADES AND SERVICES, LLC (1.39)
J & M CONTRACTING, COMPANY (6.79)
LONE STAR EROSION CONTROL (0.90)
TRP CONSTRUCTION GROUP, LLC (0.30)
TEX OP CONSTRUCTION, LP (0.14)
K. L. DURHAM CONSTRUCTION, L.L.C. (0.91)
CK NEWBERRY, LLC (0.04)
FUQUAY, INC. (0.12)
WEST TEXAS ROCK RESOURCES, LLC (0.08)
Contract #08203002
Totals20496430.470.0019832905.8896.7

CountyREFUGIO
HighwayUS 77
From.9 MI S OF HENDERSON LN
To.132 MI S OF MELON CREEK BRIDGE
CSJ0371-02-074
Proj IDC 371-2-74
Work TypeOVERLAY
 
6.8406969370.925477546.7178.6
CountyREFUGIO
HighwayUS 77
From.132 MI S OF MELON CREEK BRIDGE
ToHOUSTON ST.
CSJ0371-03-120
Proj IDC 371-3-120
Work TypeOVERLAY
 
1.1002331228.942125421.2891.1
Work Order06-30-22
Work Began09-06-22
Work Completed
Time Computed08-01-22
Contract Working Days170
Addl Days Granted0
Working Days Charged173
Percent Time Used101
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0371-02-074
HIGHWAY BARRICADES AND SERVICES, LLC (2.43)
LONE STAR EROSION CONTROL (0.04)
BEAVER BOYS SERVICES LLC (2.59)
WEST TEXAS ROCK RESOURCES, LLC (0.12)
Contract #06223213
Totals9300599.860.007602967.9981.7

CountySAN PATRICIO
HighwayBU 77-T
FromON BU77T FROM W 4TH STREET
To770 FT S OF HELM ST
CSJ0372-03-009
Proj IDSTP 2023(313)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
279198.00286951.5499.9
CountyNUECES
HighwayFM 70
FromON FM70 FROM US77
ToFM 892
CSJ1558-03-110
Proj IDSTP 2023(314)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
7.483701243.00645996.6492.2
Work Order03-06-23
Work Began04-10-23
Work Completed
Time Computed02-01-23
Contract Working Days99
Addl Days Granted7
Working Days Charged107
Percent Time Used100
Contractor(s)
J E CONSTRUCTION SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0372-03-009
HIGHWAY BARRICADES AND SERVICES, LLC (3.31)
MALDONADO-BURKETT, LLP (15.04)
VIDEO PIPELINE INSPECTIONS, INC. (0.90)
DIAMOND CORE DRILLING (0.06)
BUFFALO UNDERGROUND COMPANY (1.32)
HYDROMAX, LLC (1.59)
Contract #12223027
Totals980441.000.00932948.1895.2

CountyNUECES
HighwaySH 44
FromCONTROL BREAK/AGUA DULCE CREEK
ToCONCHO ST.
CSJ0373-02-097
Proj IDF 2024(126)
Work TypeSEAL COAT
 
22.8744274964.920.000.0
Work Order12-05-23
Work Began00-00-00
Work Completed
Time Computed01-01-24
Contract Working Days24
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
COX PAVING OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0373-02-097
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10233210
Totals4274964.920.000.000.0

CountyJIM WELLS
HighwaySH 141
FromUS 281
ToKLEBERG COUNTY LINE
CSJ0383-03-024
Proj IDC 383-3-24
Work TypeSUPER-2 HIGHWAY
 
2.3294687049.080.000.0
CountyKLEBERG
HighwaySH 141
FromJIM WELLS COUNTY LINE
ToSANTA GERTRUDIS AVE.
CSJ0383-04-060
Proj IDC 383-4-60
Work TypeSUPER-2 HIGHWAY
 
10.29020146776.220.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-02-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days332
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0383-03-024
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (1.49)
FOREMOST PAVING, INC. (3.90)
PERFORMANCE EQUIPMENT SERVICE (0.42)
TEXAS ICON CONSTRUCTION, LLC (0.37)
DEPENDABLE FENCE (0.58)
HIGHWAY BARRICADES AND SERVICES, LLC (2.88)
SOIL TECH ADVANCE INC. (0.64)
Contract #01243003
Totals24833825.300.000.000.0

CountySAN PATRICIO
HighwaySH 234
FromON SH234 FROM IH37SB FRTG
ToCR 1969 (CR 33/CR 1065)
CSJ0507-01-021
Proj IDSTP 2024(813)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3.224508478.200.000.0
CountySAN PATRICIO
HighwaySH 234
FromIH 37 SB FRONTAGE RD
ToIH 37 NB FRONTAGE RD
CSJ0507-01-022
Proj IDF 2024(954)
Work TypeREHABILITATION OF EXISTING ROAD
 
0.7092438603.970.000.0
CountySAN PATRICIO
HighwaySH 234
FromCR 1068 (CR 2015)
ToIH 37 NB FRONTAGE RD
CSJ0507-01-025
Proj IDF 2024(954)
Work TypeOVERLAY
 
3.9472545149.070.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days175
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
J. CARROLL WEAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0507-01-021
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03243013
Totals5492231.240.000.000.0

CountySAN PATRICIO
HighwaySH 234
FromUS 77
ToCR 2015
CSJ0507-01-023
Proj IDF 2023(607)
Work TypeOVERLAY
 
1.8013026453.851489636.7649.2
Work Order05-10-23
Work Began06-26-23
Work Completed
Time Computed07-01-23
Contract Working Days130
Addl Days Granted10
Working Days Charged120
Percent Time Used85
Contractor(s)
CK NEWBERRY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0507-01-023
SOIL TECH ADVANCE INC. (0.99)
HIGHWAY BARRICADES AND SERVICES, LLC (1.97)
LONE STAR EROSION CONTROL (1.07)
STX CIVIL (21.92)
MURRAY CONSTRUCTION (0.67)
Contract #04233217
Totals3026453.85140537.611489636.7649.2

CountyGOLIAD
HighwaySH 239
From0.2 MI WEST OF FM 2442
ToFM 81
CSJ0516-02-029
Proj IDSTP 2021(377)
Work TypeREHABILITATION OF EXISTING ROAD
 
7455639.897647149.7599.9
Work Order03-19-21
Work Began06-30-21
Work Completed
Time Computed04-01-21
Contract Working Days246
Addl Days Granted110
Working Days Charged374
Percent Time Used105
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0516-02-029
FLASHER EQUIPMENT COMPANY (0.76)
HIGHWAY BARRICADES AND SERVICES, LLC (1.48)
INTERSTATE CONCRETE & STEEL SERVICES INCORPORATED (3.03)
LISKA CONSTRUCTION COMPANY, INC. (25.77)
LONE STAR EROSION CONTROL (2.06)
TRP CONSTRUCTION GROUP, LLC (0.35)
COLD CREEK CONSTRUCTION, LTD (0.95)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.00)
MCL CONTRACTING, LLC (0.00)
JB PINNACLE GROUP, LLC (0.00)
TORO BRAVO CONSTRUCTION, LLC (0.17)
HERMANOS STEEL, LLC (0.00)
Contract #02213007
Totals7455639.8958341.467647149.7599.9

CountyGOLIAD
HighwaySH 239
FromFM 81
ToN INTERS. OF FM 2043
CSJ0516-02-031
Proj IDF 2022(257)
Work TypeREHABILITATION OF EXISTING ROAD
 
10110262.669277136.3091.7
Work Order02-16-22
Work Began05-02-22
Work Completed
Time Computed03-01-22
Contract Working Days225
Addl Days Granted88
Working Days Charged312
Percent Time Used99
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0516-02-031
EGGEMEYER LAND CLEARING, LLC (0.28)
LISKA CONSTRUCTION COMPANY, INC. (12.56)
TORO BRAVO CONSTRUCTION, LLC (0.00)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.13)
TERRA CONSTRUCTION LLC (3.81)
BARRICADES UNLIMITED (0.19)
HIGHWAY BARRICADES AND SERVICES, LLC (0.40)
FLASHER EQUIPMENT COMPANY (1.10)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.10)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.00)
TORO BRAVO CONSTRUCTION, LLC (0.00)
DIIBS SPECIALISTS, LLC (0.41)
TEXAS GUARDRAIL CONTRACTORS LLC (2.54)
Contract #01223203
Totals10110262.660.009277136.3091.7

CountyNUECES
HighwaySH 358
FromNILE STREET
ToAYERS STREET
CSJ0617-01-170
Proj IDNH 1602(259)
Work TypeGRADE,BASE,SURF,STRS
 
3.99142716098.6751594013.5999.9
CountyNUECES
HighwaySH 358
From.2 MI N OF LEOPARD
To.2 MI E OF FLOUR BLUFF DRIVE
CSJ0617-01-189
Proj IDSTP 1602(260)HES
Work TypeIMPROVE TRAFFIC SIGNALS
 
14.9733940168.903655843.2892.7
CountyNUECES
HighwaySH 358
From180 FT W OF DODDS ST.
ToCLARE DR.
CSJ0617-01-191
Proj IDSTP 1602(261)HES
Work TypeIMPROVE MEDIAN BARR, SFT LIGHTING
 
4.8603158509.102355772.8074.5
CountyNUECES
HighwayPR 22
FromINTERSECTION OF SH 358
To0.1 MI E OF WALDRON RD.
CSJ0617-02-071
Proj IDSTP 1602(406)HES
Work TypeIMPROVE TRAFFIC SIGNAL & INTER SIGN
 
0.670145374.80128123.8588.1
Work Order10-25-17
Work Began01-15-18
Work Completed
Time Computed12-24-17
Contract Working Days871
Addl Days Granted167
Working Days Charged1,040
Percent Time Used100
Contractor(s)
BAY LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0617-01-170
PERFORMANCE EQUIPMENT SERVICE (0.41)
SOIL-TECH, INC. (0.21)
HIGHWAY BARRICADES AND SERVICES, LLC (1.10)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (9.02)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (1.23)
TAHOE TRUCKING, INC. (0.86)
ANGEL BROTHERS ENTERPRISES, LTD. (1.49)
D & C CONCRETE CUTTING, INC. (0.00)
FARR FOUNDATION, INC. (3.19)
SCR CONSTRUCTION CO., INC. (0.24)
LIGHT IT UP ELECTRIC (1.62)
W. W. FOUNDATION DRILLING, LTD. (1.25)
WOODSTOCK TREE SURGEONS (0.01)
ATS DRILLING, INC. (0.25)
G & E ESCOBEDO CONSTRUCTION, INC. (0.38)
ACME READY MIX LTD., LLP (6.84)
SCOTT DERR PAINTING CO, LLC (0.10)
WEBBER BARRIER SERVICES, LLC. (1.92)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.02)
HB FARMER FOUNDATION, LLC (1.66)
A.Z. REBAR CONSTRUCTION, INC. (0.09)
MUNOZ FOUNDATION DRILLING, INC. (0.12)
CAMACHO DEMOLITION, LLC (0.05)
SOIL TECH ADVANCE INC. (0.14)
KELLER NORTH AMERICA, INC. (0.87)
TEXAS MATERIALS GROUP, INC. (1.49)
SCR CIVIL CONSTRUCTION, LLC (0.24)
BIG III SERVICES, LTD. (0.06)
URETEK USA, INC. (0.18)
Contract #05173002
Totals49960151.470.0057733753.5299.9

CountyNUECES
HighwaySH 358
FromAYERS
ToAIRLINE
CSJ0617-01-207
Proj IDF 2B23(116)
Work TypeOVERLAY
 
4825099.343064223.7763.5
Work Order08-03-23
Work Began11-06-23
Work Completed
Time Computed08-01-23
Contract Working Days59
Addl Days Granted0
Working Days Charged45
Percent Time Used76
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0617-01-207
HIGHWAY BARRICADES AND SERVICES, LLC (3.27)
SOIL TECH ADVANCE INC. (0.16)
K. L. DURHAM CONSTRUCTION, L.L.C. (4.82)
DEPENDABLE FENCE (2.26)
Contract #06233424
Totals4825099.341180054.673064223.7763.5

CountyNUECES
HighwaySH 358
FromAYERS
ToWEST PT
CSJ0617-01-211
Proj IDF 2024(736)
Work TypeOVERLAY
 
1.8776746376.700.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-06-24
Work Began00-00-00
Work Completed
Time Computed04-01-24
Contract Working Days86
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0617-01-211
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02243020
Totals6746376.700.000.000.0

CountyNUECES
HighwayPR 22
FromAT INTERS. OF GIWW BRIDGE/PR22
To.
CSJ0617-02-001
Proj IDBR 2021(752)
Work TypeBRIDGE MAINTENANCE
 
0.9038685850.359535850.5299.9
Work Order09-16-21
Work Began12-01-21
Work Completed
Time Computed10-01-21
Contract Working Days346
Addl Days Granted56
Working Days Charged406
Percent Time Used100
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0617-02-001
1 PRIORITY ENVIRONMENTAL SERVICES, LLC (2.77)
SOIL TECH ADVANCE INC. (0.99)
AREA WIDE PROTECTIVE, INC. (0.44)
HIGHWAY BARRICADES AND SERVICES, LLC (0.55)
MACIAS SPECIALTY CONTRACTING LLC (4.28)
NELSON INDUSTRIAL SERVICES, INC. (0.35)
TEXAS ICON CONSTRUCTION, LLC (0.11)
TEXOP CONSTRUCTION (0.73)
SCR CIVIL CONSTRUCTION, LLC (18.38)
INFRASTRUCTURE MAINTENANCE SERVICES, INC. (7.94)
MALDONADO-BURKETT, LLP (0.03)
ADVANCED DIVING AND SALVAGE CORPORATION (0.00)
A-CORE CONCRETE CUTTING, INC. (0.14)
Contract #08213002
Totals8685850.35828722.049535850.5299.9

CountyKARNES
HighwayFM 81
FromSH 80 IN HELENA
ToFM 627
CSJ0691-01-040
Proj IDF 2021(753)
Work TypeREHABILITATION OF EXISTING ROAD
 
7699689.267587474.4699.9
Work Order08-25-21
Work Began11-08-21
Work Completed
Time Computed09-01-21
Contract Working Days232
Addl Days Granted39
Working Days Charged447
Percent Time Used164
Contractor(s)
CK NEWBERRY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0691-01-040
HIGHWAY BARRICADES AND SERVICES, LLC (0.86)
INTERSTATE CONCRETE & STEEL SERVICES INCORPORATED (1.25)
LONE STAR EROSION CONTROL (2.26)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.06)
MURRAY CONSTRUCTION (1.27)
PINNACLE GRINDING AND GROOVING LLC (0.11)
SOIL TECH ADVANCE INC. (0.21)
BEAVER BOYS SERVICES LLC (0.43)
BARRICADES UNLIMITED (0.10)
TIERRA LEASE SERVICE, LLC (0.19)
GREGORY PILE DRIVING, INC. (3.81)
TORO BRAVO CONSTRUCTION, LLC (0.00)
SPECIALTY RENTAL SERVICES LLC (0.11)
TEXAS MATERIALS GROUP, INC. (20.81)
Contract #07213008
Totals7699689.26395142.847587474.4699.9

CountyKARNES
HighwayFM 81
FromFM 627
ToFM 2773
CSJ0691-01-044
Proj IDF 2023(101)
Work TypeREHABILITATION OF EXISTING ROAD
 
1.9224887025.521890219.1838.6
Work Order10-11-22
Work Began01-16-23
Work Completed
Time Computed11-01-22
Contract Working Days186
Addl Days Granted0
Working Days Charged169
Percent Time Used90
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0691-01-044
LONE STAR EROSION CONTROL (1.37)
DIIBS SPECIALISTS, LLC (1.81)
ACEE CONSTRUCTION LLC. (13.91)
TEXAS MATERIALS GROUP, INC. (12.67)
TORO BRAVO CONSTRUCTION, LLC (0.62)
GREGORY PILE DRIVING, INC. (3.53)
HIGHWAY BARRICADES AND SERVICES, LLC (1.28)
Contract #09223033
Totals4887025.523500.001890219.1838.6

CountyNUECES
HighwayVA
FromVARIOUS LOCATIONS IN CC DISTRICT
To.
CSJ0916-00-212
Proj IDSTP 2019(673)
Work TypeSIGN REPLACEMENT
 
0.1001847391.501245274.1189.4
Work Order04-25-19
Work Began10-01-19
Work Completed
Time Computed05-24-19
Contract Working Days120
Addl Days Granted0
Working Days Charged638
Percent Time Used531
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0916-00-212
ON THE ROAD CONSTRUCTION, LLC (0.94)
Contract #03193229
Totals1847391.501913.501245274.1189.4

CountyNUECES
HighwayVA
FromAT VARIOUS LOCATION IN CC DISTRICT
To.
CSJ0916-00-223
Proj IDC 916-00-223
Work TypeTRAFFIC CONTROL DEVICES
 
0.1001937895.49750911.6238.7
Work Order07-17-23
Work Began00-00-00
Work Completed
Time Computed03-01-23
Contract Working Days174
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HIGHWAY BARRICADES AND SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0916-00-223
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01233013
Totals1937895.490.00750911.6238.7

CountyNUECES
HighwayVA
FromAT VARIOUS LOCATIONS IN CC DISTRICT
To.
CSJ0916-00-228
Proj IDF 2B23(210)
Work TypeTRAFFIC CONTROL DEVICES
 
0.1005294911.602721940.8151.4
Work Order10-25-23
Work Began11-15-23
Work Completed
Time Computed10-01-23
Contract Working Days83
Addl Days Granted0
Working Days Charged50
Percent Time Used60
Contractor(s)
HIGHWAY BARRICADES AND SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0916-00-228
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08233038
Totals5294911.601052891.382721940.8151.4

CountyNUECES
HighwayVA
FromVARIOUS LOCATION IN CC DISTRICT
To.
CSJ0916-00-232
Proj IDF 2021(698)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1230250.601131896.6796.4
Work Order12-01-21
Work Began02-16-22
Work Completed
Time Computed08-01-21
Contract Working Days237
Addl Days Granted0
Working Days Charged317
Percent Time Used133
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0916-00-232
G & E ESCOBEDO CONSTRUCTION, INC. (2.23)
Contract #06213228
Totals1230250.601325.551131896.6796.4

CountyNUECES
HighwayVA
FromAT VARIOUS LOCATIONS IN CORPUS DISTRICT
To.
CSJ0916-00-242
Proj IDC 916-00-242
Work TypeTRAFFIC CONTROL DEVICES
 
916587.75518104.4956.5
Work Order07-20-23
Work Began02-05-24
Work Completed
Time Computed08-01-23
Contract Working Days80
Addl Days Granted3
Working Days Charged13
Percent Time Used15
Contractor(s)
MALDONADO-BURKETT, LLP
SUBCONTRACTOR(S) FOR CCSJ: 0916-00-242
SAFETY FIRST TRAFFIC SOLUTIONS, LLC (2.52)
Contract #06233032
Totals916587.75222725.39518104.4956.5