Monthly Local Let Maintenance Report For Corpus Christi District As Of Apr 12, 2024 Page 4 Of 6

Last Update: Friday, April 12, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyREFUGIO
HighwayUS0077
FromVARIOUS
To.
CSJ6443-90-001
Proj IDMMC - 644390001
Work TypeHOT-MIX COLD-LAID
 
0.010325500.00154036.0547.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-22-23
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted180
Working Days Charged284
Percent Time Used78
Contractor(s)
BRAUNTEX MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6443-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05231606
Totals325500.000.00154036.0547.3

CountyNUECES
HighwayIH0037
FromVARIOUS IN NUECES & SAN PATRICIO COUNTY
To.
CSJ6444-38-001
Proj IDSUP - 644438001
Work TypeLITTER REMOVAL
 
0.010228315.93164877.3472.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-01-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged335
Percent Time Used91
Contractor(s)
WORKQUEST
NC MHMR INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6444-38-001
NC MHMR INDUSTRIES (0.00)
Contract #04231631
Totals228315.9315404.80164877.3472.2

CountyARANSAS
HighwaySH0188
FromVARIOUS
To.
CSJ6445-35-001
Proj IDMMC - 644535001
Work TypeAGGREGATE
 
0.010254322.00244978.6896.3
Work Order07-11-23
Work Began07-11-23
Work Completed
Time Computed07-17-23
Contract Working Days180
Addl Days Granted180
Working Days Charged275
Percent Time Used76
Contractor(s)
MARTIN MARIETTA MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6445-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06231608
Totals254322.0037553.05244978.6896.3

CountyKARNES
HighwayUS0181
FromVARIOUS
To.
CSJ6445-39-001
Proj IDMMC - 644539001
Work TypeAGGREGATE
 
0.010251275.0047039.0118.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-26-23
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted180
Working Days Charged250
Percent Time Used69
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6445-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06231606
Totals251275.000.0047039.0118.7

CountyJIM WELLS
HighwayUS0281
FromVARIOUS
To.
CSJ6445-41-001
Proj IDMMC - 644541001
Work TypeAGGREGATE
 
0.010248350.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-21-23
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted180
Working Days Charged224
Percent Time Used62
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6445-41-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06231607
Totals248350.000.000.000.0

CountyLIVE OAK
HighwayUS0281
FromVARIOUS
To.
CSJ6445-43-001
Proj IDMMC - 644543001
Work TypeHOT-MIX COLD-LAID
 
0.010272160.00272084.9199.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-23
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted180
Working Days Charged211
Percent Time Used58
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6445-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06231605
Totals272160.000.00272084.9199.9

CountyJIM WELLS
HighwayUS0281
FromVARIOUS
To.
CSJ6448-31-001
Proj IDMMC - 644831001
Work TypeHOT MIX
 
0.010295150.00181051.3961.3
Work Order09-07-23
Work Began09-07-23
Work Completed
Time Computed09-12-23
Contract Working Days180
Addl Days Granted180
Working Days Charged206
Percent Time Used57
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6448-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07231601
Totals295150.0068877.90181051.3961.3

CountyLIVE OAK
HighwayUS0059
FromVARIOUS
To.
CSJ6448-33-001
Proj IDMMC - 644833001
Work TypeHOT MIX
 
0.010304420.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-23
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted180
Working Days Charged211
Percent Time Used58
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6448-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07231603
Totals304420.000.000.000.0

CountyKARNES
HighwayUS0181
FromVARIOUS
To.
CSJ6448-35-001
Proj IDMMC - 644835001
Work TypeHYDRAULIC CEMENT
 
0.010268700.006125.002.2
Work Order10-12-23
Work Began10-12-23
Work Completed
Time Computed10-23-23
Contract Working Days180
Addl Days Granted180
Working Days Charged172
Percent Time Used47
Contractor(s)
TOUCHSTONE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6448-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09231604
Totals268700.000.006125.002.2

CountyNUECES
HighwaySH0358
FromVARIOUS
To.
CSJ6448-85-001
Proj IDMMC - 644885001
Work TypeEMULSION
 
0.01054720.007064.5212.9
Work Order12-01-23
Work Began12-01-23
Work Completed
Time Computed12-01-23
Contract Working Days180
Addl Days Granted0
Working Days Charged122
Percent Time Used67
Contractor(s)
ERGON ASPHALT & EMULSIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6448-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09231603
Totals54720.000.007064.5212.9

CountyNUECES
HighwaySH0358
FromVARIOUS
To.
CSJ6448-87-001
Proj IDMMC - 644887001
Work TypeAGGREGATE
 
0.010187700.000.000.0
Work Order12-13-23
Work Began12-01-23
Work Completed
Time Computed12-13-23
Contract Working Days180
Addl Days Granted0
Working Days Charged122
Percent Time Used67
Contractor(s)
MARTIN MARIETTA MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6448-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09231601
Totals187700.000.000.000.0

CountyGOLIAD
HighwayUS0059
FromVARIOUS
To.
CSJ6451-87-001
Proj IDMMC - 645187001
Work TypeHOT-MIX COLD-LAID
 
0.010259538.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-07-23
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged146
Percent Time Used81
Contractor(s)
COLORADO MATERIALS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6451-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09231602
Totals259538.000.000.000.0

CountyREFUGIO
HighwayUS0077
FromVARIOUS
To.
CSJ6453-53-001
Proj IDMMC - 645353001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010269893.8021233.687.8
Work Order11-15-23
Work Began11-16-23
Work Completed
Time Computed11-15-23
Contract Working Days180
Addl Days Granted0
Working Days Charged137
Percent Time Used76
Contractor(s)
MARTIN MARIETTA MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6453-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10231601
Totals269893.800.0021233.687.8

CountyARANSAS
HighwaySH0035
FromVARIOUS
To.
CSJ6453-55-001
Proj IDMMC - 645355001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010265701.00129269.2048.6
Work Order11-15-23
Work Began11-15-23
Work Completed
Time Computed11-15-23
Contract Working Days180
Addl Days Granted0
Working Days Charged138
Percent Time Used76
Contractor(s)
MARTIN MARIETTA MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6453-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10231608
Totals265701.0096820.97129269.2048.6

CountyNUECES
HighwayUS0181
FromVARIOUS
To.
CSJ6453-95-001
Proj IDRMC - 645395001
Work TypeDRAINAGE SYSTEM CLEANING
 
0.010293350.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged60
Percent Time Used16
Contractor(s)
MAKO CONTRACTING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6453-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10231605
Totals293350.000.000.000.0

CountyBEE
HighwayUS0059
FromVARIOUS
To.
CSJ6454-97-001
Proj IDRMC - 645497001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.010235432.00299561.0999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days34
Addl Days Granted0
Working Days Charged15
Percent Time Used44
Contractor(s)
AMERICAN INFRASTRUCTURE MAINTENANCE MANAGEMENT LLC
SUBCONTRACTOR(S) FOR CCSJ: 6454-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09231606
Totals235432.00299561.09299561.0999.9

CountyJIM WELLS
HighwayUS0281
FromVARIOUS
To.
CSJ6455-29-001
Proj IDMMC - 645529001
Work TypeFLEXIBLE BASE
 
0.010274232.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-01-23
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged152
Percent Time Used84
Contractor(s)
COLORADO MATERIALS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6455-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09231607
Totals274232.000.000.000.0

CountyKLEBERG
HighwayUS0077
FromVARIOUS
To.
CSJ6455-31-001
Proj IDMMC - 645531001
Work TypeFLEXIBLE BASE
 
0.010303318.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-01-23
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged122
Percent Time Used67
Contractor(s)
COLORADO MATERIALS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6455-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09231608
Totals303318.000.000.000.0

CountyLIVE OAK
HighwayUS0059
FromVARIOUS
To.
CSJ6455-33-001
Proj IDMMC - 645533001
Work TypeFLEXIBLE BASE
 
0.010273000.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-01-23
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged152
Percent Time Used84
Contractor(s)
COLORADO MATERIALS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6455-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09231609
Totals273000.000.000.000.0

CountyKLEBERG
HighwayBU0077V
FromVARIOUS LOCATIONS ON BU0077V
To.
CSJ6456-21-001
Proj IDBPM - 645621001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.010194210.00149106.0076.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days51
Addl Days Granted0
Working Days Charged33
Percent Time Used64
Contractor(s)
ICOS MANAGEMENT, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6456-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10231606
Totals194210.0027000.00149106.0076.7

page 1 | page 2 | page 3 | page 4 | page 5 | page 6