Monthly State Let Construction Report For Dallas District As Of Nov 22, 2017 Page 1 Of 8

Last Update: Wednesday, November 22, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyDALLAS
HighwaySH 180 ETC
FromTARRANT COUNTY LINE
ToSL 12
CSJ0008-08-075
Proj IDNH 2017(192)
Work TypeSEAL COAT
 
87.9792234365.601630784.8372.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-22-16
Work Began09-11-17
Work Completed
Time Computed00-00-00
Contract Working Days92
Addl Days Granted0
Working Days Charged31
Percent Time Used33
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0008-08-075
BARRICADES PLUS, LLC (4.43)
Contract #10163217
Totals2234365.60601886.951630784.8372.9

CountyDALLAS
HighwaySH 78
FromGARLAND RD FROM SOUTH OF TRANQUILLA
ToSP 244 (NORTHWEST HIGHWAY)
CSJ0009-02-045
Proj IDCM 2009(433)
Work Type9 INTERSECTION IMPROVEMENTS
 
2.8636587481.9656112.730.8
CountyDALLAS
HighwaySH 78
FromGARLAND RD FROM SOUTH OF TRANQUILLA
ToSP 244 (NORTHWEST HIGHWAY)
CSJ0009-02-056
Proj IDCM 2010(230)
Work TypeROW ACQ RELO ASSIST & UTIL ADJ
 
0.0011192134.570.000.0
Work Order04-20-15
Work Began00-00-00
Work Completed
Time Computed08-18-15
Contract Working Days491
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LONE STAR CIVIL CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0009-02-045
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02153028
Totals7779616.530.0056112.730.7

CountyDALLAS
HighwaySH 66
FromWESTERN CITY LIMIT OF ROWLET
ToDALROCK RD
CSJ0009-03-045
Proj IDNH 1702(443)
Work TypeLANDSCAPE ENHANCEMENT
 
4.4841398334.69278386.0019.9
CountyROCKWALL
HighwaySH 66
FromDALROCK ROAD
ToHERITAGE PARKWAY
CSJ0009-04-068
Proj IDNH 1702(443)
Work TypeLANDSCAPE ENHANCEMENT
 
0.890351665.3136403.0510.3
Work Order07-14-17
Work Began08-07-17
Work Completed
Time Computed08-07-17
Contract Working Days253
Addl Days Granted0
Working Days Charged58
Percent Time Used22
Contractor(s)
AALC, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0009-03-045
BUYERS BARRICADES, INC. (0.79)
DOWN UNDER CONSTRUCTION (2.76)
WRECKHOUSE DEMOLITION, LLC (10.00)
KICKER UNDERGROUND CONSTRUCTION, LLC (3.25)
Contract #06173245
Totals1750000.00125857.01314789.0517.9

CountyROCKWALL
HighwaySH 66
From0.1 MILE WEST OF FM 1141
ToCOLLIN COUNTY LINE
CSJ0009-04-061
Proj IDSTP 2016(819)HES
Work TypeGR, BASE, PVMT, PVMT MKGS, SIGNS
 
8.92510521700.235578948.7153.0
CountyROCKWALL
HighwaySH 66
FromFM 1141
ToE COUNTY LINE ROAD (COUNTY LINE)
CSJ0009-04-065
Proj IDCC 9-4-65
Work TypeADD TURN LANES
 
8.7722605686.77926634.5835.5
CountyCOLLIN
HighwaySH 66
FromROCKWALL COUNTY LINE
ToHUNT COUNTY LINE
CSJ0009-05-011
Proj IDSTP 2016(820)
Work TypeGR,BASE, PVMT, PVMT MKGS, SIGNS
 
2.1562744978.34238810.538.6
Work Order12-07-16
Work Began03-22-17
Work Completed
Time Computed03-20-17
Contract Working Days505
Addl Days Granted0
Working Days Charged152
Percent Time Used30
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0009-04-061
MICA CORPORATION (0.62)
SYNERGY SIGNS & SERVICES, LLC (0.91)
FORTSON CONTRACTING, INC. (1.21)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (3.05)
TEX OP CONSTRUCTION, LP (4.72)
DUSTROL, INC. (1.01)
DALLAS LITE AND BARRICADE INC. (0.48)
C & J TREE SERVICE (0.26)
TOTAL HIGHWAY MAINTENANCE, LLC (1.28)
J & M CONTRACTING, COMPANY (9.93)
DURABLE SPECIALTIES, INC. (0.56)
ALTUS TRAFFIC MANAGEMENT LLC (0.06)
Contract #03163001
Totals15872365.341038298.106744393.8242.4

CountyDALLAS
HighwayIH 30
FromIH 635
ToCHAHA RD.
CSJ0009-11-227
Proj IDCM 1402(021)
Work TypeITS INSTALLATION
 
8.4002749311.962213833.7480.5
Work Order05-08-15
Work Began08-10-15
Work Completed
Time Computed08-06-15
Contract Working Days200
Addl Days Granted0
Working Days Charged153
Percent Time Used76
Contractor(s)
MICA CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0009-11-227
LAYFIELD CONSTRUCTION, INC (0.49)
BUYERS BARRICADES, INC. (1.25)
DYNAMIC VISION CO., INC. (3.88)
KLP COMMERCIAL, LLC (3.65)
WOLFE CONSTRUCTION GROUP, INC. (0.17)
PANIOLO CONSTRUCTION SERVICES, LLC (0.63)
Contract #08143015
Totals2749311.960.002213833.7480.5

CountyDALLAS
HighwayIH 30
FromAT ST FRANCIS
To.
CSJ0009-11-233
Proj IDSTP 1602(322)HES
Work TypeCONSTRUCT PEDESTRIAN OVER/UNDERPASS
 
0.1742254488.45580641.2525.7
Work Order09-15-16
Work Began05-12-17
Work Completed
Time Computed09-15-16
Contract Working Days247
Addl Days Granted0
Working Days Charged85
Percent Time Used34
Contractor(s)
RAMA ENTERPRISES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0009-11-233
TOTAL HIGHWAY MAINTENANCE, LLC (1.03)
WYLIE DRILLING & DRAINAGE, INC. (2.08)
BOWMAN ENGINEERING & CONSTRUCTION, INC. (0.10)
ODUM SERVICES, L.P. (1.67)
Contract #07163026
Totals2254488.459000.00580641.2525.7

CountyROCKWALL
HighwayIH 30
FromAT FM 3549
To.
CSJ0009-12-072
Proj IDPTF 2015(062)
Work TypeSTR, GRD, BASE & CONC PAVT
 
1.70432882301.0011711609.4935.6
Work Order08-05-16
Work Began09-20-16
Work Completed
Time Computed09-20-16
Contract Working Days600
Addl Days Granted0
Working Days Charged324
Percent Time Used54
Contractor(s)
SEMA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0009-12-072
HAYDON BUILDING CORP. (19.74)
TOTAL HIGHWAY MAINTENANCE, LLC (0.82)
SOUTH TEXAS PAINTING COMPANY (0.24)
K & S UTILITY CONTRACTORS, INC. (7.08)
FARR FOUNDATION, INC. (0.73)
MARCOM"S MOWING SERVICE, LLC (0.13)
HOUSTON SAWING & DRILLING (0.01)
MEL"S ELECTRIC SERVICE, INC. (1.48)
PRIMATE CONSTRUCTION, INC. (0.07)
WOLFE CONSTRUCTION GROUP, INC. (0.85)
MCL CONTRACTING, LLC (0.09)
LINDAMOOD DEMOLITION, INC. (0.19)
WYLIE DRILLING & DRAINAGE, INC. (0.46)
FORTSON CONTRACTING, INC. (0.28)
BRJ PAVING INCORPORATION (1.01)
PREMIER PAVING, LTD. (11.94)
RAMBO CONTRACTING, INC. (1.24)
PERFORMANCE EQUIPMENT SERVICE (1.47)
W.O.E. CONSTRUCTION (0.15)
ROYAL REBAR (0.44)
OSCAR ORDUNO, INC. (0.57)
ROADWAY SPECIALTIES, INC. (0.07)
FISHER SAND & GRAVEL CO. (0.72)
BOWMAN ENGINEERING & CONSULTING, INC (0.02)
URBAN INFRACONSTRUCTION, LLC. (0.01)
SLATON BROTHERS, INC. (2.86)
Contract #02163002
Totals32882301.001625666.9411711609.4935.6

CountyROCKWALL
HighwayIH 30
FromINTERCHANGE AT ERBY CAMPBELL BLVD
To.
CSJ0009-12-074
Proj IDIM 0301(058)
Work TypeSTR,GRD,BASE,CON PVMT,SIGNS,MRKS
 
1.38319988908.6227836024.06100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-28-12
Work Began05-28-13
Work Completed10-03-17
Time Computed09-24-12
Contract Working Days503
Addl Days Granted122
Working Days Charged625
Percent Time Used100
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0009-12-074
FORTSON CONTRACTING, INC. (1.59)
STRAIGHT LINE SAWING & SEALING (0.22)
MASTERPIECE GRINDING & GROOVING, LLC (0.02)
STRIPING TECHNOLOGY, L.P. (0.95)
SOUTHERN CRUSHED CONCRETE LLC (0.10)
FOUNDATION DRILLERS, INC. (1.19)
SOUTHERN CRUSHED CONCRETE LLC (0.10)
WEBBER BARRIER SERVICES, LLC. (0.61)
PREMIER PAVING, LTD. (16.34)
DUSTROL, INC. (0.33)
INDUS CONSTRUCTION, L.P. (0.70)
USA SWPPP INSPECTIONS, INC. (0.78)
BUYERS BARRICADES, INC. (0.23)
VENUS CONSTRUCTION (4.59)
MILLER AND MILLER CUSTOM SERVICES, LLC (5.50)
B.G. WILLIAMS ASPHALT, LTD (0.47)
ANCORTEX, INC. (0.19)
RICE TUNNELING & BORING, INC. (0.09)
MELS ELECTRIC, L.P. (1.28)
HIGH QUALITY ELECTRIC (0.07)
SOUTH TEXAS PAINTING COMPANY (0.05)
HERDEZ TRUCKING, INC. (7.39)
INTEGRATED ROADWAY SERVICES, INC. (0.12)
A-CORE CONCRETE CUTTING OF TEXAS, INC. (0.02)
Contract #01123002
Totals19988908.620.0027836024.06100.0

CountyROCKWALL
HighwayIH 30
FromAT FM 551
To.
CSJ0009-12-078
Proj IDC 9-12-78
Work TypeSTR,GRD,BASE,CONC PVMT,SIGNS,MRKS
 
2.57230862690.3731670777.39100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-10-13
Work Began06-10-14
Work Completed10-03-17
Time Computed06-08-14
Contract Working Days505
Addl Days Granted20
Working Days Charged525
Percent Time Used100
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0009-12-078
TEX OP CONSTRUCTION, LP (1.00)
BUYERS BARRICADES, INC. (0.19)
INTEGRATED ROADWAY SERVICES, INC. (1.36)
K & S UTILITY CONTRACTORS, INC. (3.27)
WEBBER BARRIER SERVICES, LLC. (0.75)
W.O.E. CONSTRUCTION (1.06)
SIGNATURE CONTRACTING SERVICES, L.L.C. (0.54)
INDUS CONSTRUCTION, L.P. (0.54)
STRIPING TECHNOLOGY, L.P. (0.69)
G.W. PEOPLES CONTRACTING COMPANY, INC. (0.05)
PREMIER PAVING, LTD. (10.01)
B.G. WILLIAMS ASPHALT, LTD (0.19)
ANTIGO CONSTRUCTION, INC. (0.15)
ANCORTEX, INC. (16.50)
WYLIE DRILLING & DRAINAGE, INC. (0.66)
DCCS, LLC (0.71)
RAMBO CONTRACTING, INC. (0.12)
HERDEZ TRUCKING, INC. (2.77)
INDUS ROAD & BRIDGE, INC (3.50)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.61)
RG PAINTING (0.13)
A CORE CONCRETE (0.01)
Contract #07133203
Totals30862690.370.0031670777.39100.0

CountyROCKWALL
HighwayIH 30
FromDALLAS COUNTY LINE
ToHUNT COUNTY LINE
CSJ0009-12-212
Proj IDNH 1702(084)
Work TypePAVEMENT REPAIR & PAVEMENT MARKINGS
 
14.9932315893.57733299.4431.6
Work Order06-14-17
Work Began09-05-17
Work Completed
Time Computed09-05-17
Contract Working Days121
Addl Days Granted0
Working Days Charged37
Percent Time Used30
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0009-12-212
TOTAL HIGHWAY MAINTENANCE, LLC (8.48)
W.O.E. CONSTRUCTION (4.20)
BRENDA PRICE TRUCKING (5.89)
DUSTROL, INC. (1.16)
ALTUS TRAFFIC MANAGEMENT LLC (0.14)
Contract #05173035
Totals2315893.57413949.15733299.4431.6

CountyROCKWALL
HighwayIH 30
FromSH 205
ToJOHN KING BLVD
CSJ0009-12-214
Proj IDCC 9-12-214
Work TypePVMT, PVMT MKGS, SIGNS
 
0.7463485857.423457198.82100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-26-16
Work Began07-10-16
Work Completed10-09-17
Time Computed07-05-16
Contract Working Days155
Addl Days Granted0
Working Days Charged165
Percent Time Used106
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0009-12-214
BOWMAN ENGINEERING & CONSTRUCTION, INC. (0.40)
CROSS ROADS, L.P. (0.41)
FORTSON CONTRACTING, INC. (1.19)
HIGHWAY INTELLIGENT TRAFFIC SYSTEMS, INC (5.23)
PREMIER PAVING, LTD. (8.98)
SCOTT DERR PAINTING CO, LLC (0.10)
TEX OP CONSTRUCTION, LP (2.16)
TOTAL HIGHWAY MAINTENANCE, LLC (1.53)
USA SWPPP INSPECTIONS, INC. (1.33)
W.O.E. CONSTRUCTION (0.15)
SHERON STONE DBA DOUBLE-S CONSTRUCTION (0.04)
BRENDA PRICE TRUCKING (3.82)
DOWN UNDER CONSTRUCTION (0.04)
Contract #04163204
Totals3485857.420.003457198.82100.0

CountyROCKWALL
HighwayIH 30
FromDALLAS COUNTY LINE
ToHUNT COUNTY LINE
CSJ0009-12-216
Proj IDCM 2017(081)
Work TypeINSTALLATION OF WIRELESS ITS SYSTEM
 
14.9931105995.621095547.2599.0
Work Order10-21-16
Work Began02-07-17
Work Completed
Time Computed01-19-17
Contract Working Days70
Addl Days Granted0
Working Days Charged65
Percent Time Used92
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0009-12-216
ALTUS TRAFFIC MANAGEMENT LLC (4.66)
ODUM SERVICES, L.P. (0.73)
DALLAS FOUNDATION DRILLING CO., INC. (1.74)
TX DOWN UNDER CONSTRUCTION LLC (1.22)
Contract #09163016
Totals1105995.620.001095547.2599.0

CountyCOLLIN
HighwayUS 75
FromPGBT
ToPARK BLVD
CSJ0047-06-133
Proj IDSTP 1502(083)MM
Work TypeSTR, PVMT, SIGNS, PVMT MKGS
 
1.39137466722.1814285176.4738.1
Work Order02-26-16
Work Began05-09-16
Work Completed
Time Computed05-09-16
Contract Working Days750
Addl Days Granted0
Working Days Charged432
Percent Time Used57
Contractor(s)
ZACHRY CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0047-06-133
MOBILE ENTERPRISES, INC. (0.11)
HIRSCHFELD STEEL CO. (2.12)
HEIDENFELS ENTERPRISES (2.95)
HERDEZ TRUCKING, INC. (2.44)
MICA CORPORATION (5.14)
TOTAL HIGHWAY MAINTENANCE, LLC (1.49)
ANTIGO CONSTRUCTION, INC. (0.15)
EROSION CONTROL MANAGEMENT SERVICES (0.25)
UNDER CONSTRUCTION INC. (0.14)
PREMIER PAVING, LTD. (3.74)
PANIOLO CONSTRUCTION SERVICES, LLC (1.65)
ANCORTEX, INC. (8.32)
ROYAL REBAR (5.66)
DURABLE SPECIALTIES, INC. (1.36)
LAYFIELD CONSTRUCTION, INC (0.15)
RG PAINTING, INC. (0.12)
ACT SAW CUTTING & REMOVAL (0.00)
A-CORE CONCRETE CUTTING, INC. (0.10)
Contract #11153202
Totals37466722.18591083.5414285176.4738.1

CountyCOLLIN
HighwayUS 75
FromSPRING CREEK PARKWAY
ToSH 121 (SAM RAYBURN TOLLWAY)
CSJ0047-06-139
Proj IDC 47-6-139
Work TypeGRADE, PAVEMENT, DRAINAGE, STRUCTUR
 
6.50947531666.9451273571.0899.9
Work Order03-04-14
Work Began04-24-14
Work Completed
Time Computed03-20-14
Contract Working Days766
Addl Days Granted104
Working Days Charged870
Percent Time Used100
Contractor(s)
MCM
SUBCONTRACTOR(S) FOR CCSJ: 0047-06-139
DALLAS LITE AND BARRICADE INC. (3.21)
RUSSO CORPORATION (0.66)
TOTAL HIGHWAY MAINTENANCE, LLC (1.07)
INTEGRATED ROADWAY SERVICES, INC. (12.66)
FORTSON CONTRACTING, INC. (0.79)
GHB EQUIPMENT COMPANY, L.L.C. (0.36)
W.O.E. CONSTRUCTION (7.22)
USA SWPPP INSPECTIONS, INC. (1.34)
ROBERTS TRUCKING (1.66)
SIERRA HORIZONTAL BORING, LLC (0.05)
SLATON BROTHERS, INC. (14.18)
CRAIG OLDEN, INC. (3.06)
JAGOE-PUBLIC COMPANY (3.57)
GREENER PASTURES LANDSCAPE, INC. (1.25)
Contract #12133001
Totals47531666.94151279.9251273571.0899.9

CountyCOLLIN
HighwayUS 75
FromDALLAS COUNTY LINE
ToFM 3038
CSJ0047-06-159
Proj IDNH 2017(885)
Work TypeFULL DEPTH CONCRETE REPAIR
 
14.601564877.00300786.9553.2
CountyCOLLIN
HighwayUS 75
FromFM 3038
ToTELEPHONE RD
CSJ0047-14-083
Proj IDNH 2017(885)
Work TypeFULL DEPTH CONCRETE REPAIR
 
5.86292932.009600.0010.3
Work Order04-24-17
Work Began09-07-17
Work Completed
Time Computed09-07-17
Contract Working Days74
Addl Days Granted0
Working Days Charged36
Percent Time Used48
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0047-06-159
W.O.E. CONSTRUCTION (8.47)
BRENDA PRICE TRUCKING (3.12)
Contract #03173022
Totals657809.00153420.91310386.9547.1

CountyCOLLIN
HighwayUS 75
FromDALLAS/COLLIN COUNTY LINE
ToPGBT
CSJ0047-06-160
Proj IDNH 2017(886)
Work TypeCLEAN&PAINT CONCRETE BARRIER & WALL
 
1.184176823.60207015.1299.9
CountyDALLAS
HighwayUS 75
FromIH 635
ToDALLAS/COLLIN COUNTY LINE
CSJ0047-07-233
Proj IDNH 2017(886)
Work TypeCLEAN&PAINT CONCRETE BARRIER & WALL
 
5.283505877.00509362.8099.9
Work Order04-26-17
Work Began05-31-17
Work Completed
Time Computed05-31-17
Contract Working Days104
Addl Days Granted0
Working Days Charged63
Percent Time Used60
Contractor(s)
S & S BRIDGE PAINTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0047-06-160
SCR CIVIL CONSTRUCTION, LLC (19.98)
Contract #03173223
Totals682700.6010600.00716377.9299.9

CountyDALLAS
HighwayUS 75
FromSP 366/WOODALL RODGERS FWY
ToIH 635 IN DALLAS
CSJ0047-07-229
Proj IDNH 2016(511)
Work TypeLANDSCAPE
 
9.113834793.50274680.8035.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-15-16
Work Began11-29-16
Work Completed
Time Computed10-31-16
Contract Working Days148
Addl Days Granted0
Working Days Charged181
Percent Time Used122
Contractor(s)
DBI SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0047-07-229
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08163219
Totals834793.500.00274680.8035.3

CountyCOLLIN
HighwayUS 75
FromTELEPHONE RD (CR 275)
ToNORTH OF MELISSA ROAD
CSJ0047-14-068
Proj IDC 47-14-68
Work TypeGRADING, BASE, PVMT, STR, SIGNS
 
3.14663579301.8563741748.7199.9
Work Order11-16-12
Work Began09-09-13
Work Completed
Time Computed08-03-13
Contract Working Days920
Addl Days Granted69
Working Days Charged989
Percent Time Used100
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0047-14-068
ANTIGO CONSTRUCTION, INC. (0.07)
ARTEX ELECTRIC, INC. (0.83)
DUSTROL, INC. (1.19)
FORTSON CONTRACTING, INC. (0.42)
JAGOE-PUBLIC COMPANY (15.30)
J.L. STEEL REINFORCING, LLC (0.91)
LONE STAR MANHOLE & STRUCTURES, LLC (0.37)
SCOTT DERR PAINTING CO, LLC (0.22)
TOTAL HIGHWAY MAINTENANCE, LLC (0.55)
W.O.E. CONSTRUCTION (0.27)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.93)
WYLIE DRILLING & DRAINAGE, INC. (0.69)
CRAIG OLDEN, INC. (0.29)
COWBOY TRUCKING (0.62)
TRANSPORT TRUST (0.00)
SIGNATURE CONTRACTING SERVICES, L.L.C. (0.01)
J.L. STEEL REINFORCING, LLC (0.03)
BRENDA PRICE TRUCKING (2.31)
THELIN RECYCLING COMPANY, L.P. (0.11)
SOUTHEAST GRINDING & GROOVING, LLC (0.02)
HENSON FOUNDATION DRILLING INCORPORATED DBA CENTRAL CAISSON (0.03)
DURABLE SPECIALTIES, INC. (0.02)
Contract #08123001
Totals63579301.85205573.6063741748.7199.9

CountyCOLLIN
HighwayUS 75
FromNORTH OF MELISSA RD
ToSOUTH OF FM 455 INTERCHANGE
CSJ0047-14-069
Proj IDC 47-14-69
Work TypeGRADING, BASE, PVMT, STR, SIGNS
 
5.94779417673.4333051587.2641.6
Work Order03-16-16
Work Began07-05-16
Work Completed
Time Computed06-14-16
Contract Working Days884
Addl Days Granted0
Working Days Charged390
Percent Time Used44
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0047-14-069
DALLAS LITE AND BARRICADE INC. (0.18)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.41)
GJ SEEDING, LLC (0.28)
HOUSTON SAWING & DRILLING (0.02)
JAGOE-PUBLIC COMPANY (0.86)
LAYFIELD CONSTRUCTION, INC (0.48)
MICA CORPORATION (1.11)
NE-TEX CONSTRUCTION, LTD. (0.15)
NORTH TEXAS CONTRACTING, INC. (4.64)
PANIOLO CONSTRUCTION SERVICES, LLC (1.22)
ROYAL REBAR (1.72)
SOUTHERN CROSS CONTRACTORS, LLC (0.39)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (4.00)
TEXAS SHAFTS, INC. (0.92)
RMI WORLDWIDE, LLC (0.09)
STRIPING TECHNOLOGY, L.P. (0.67)
RG PAINTING (0.07)
LMH SAW & SEAL, LLC (0.25)
MCL CONTRACTING, LLC (0.04)
ANCORTEX, INC. (0.19)
W.O.E. CONSTRUCTION (1.72)
HULCHER SERVICES INC. (0.02)
Contract #12153234
Totals79417673.431687855.7533051587.2641.6

CountyCOLLIN
HighwayUS 75
FromSOUTH OF US 380
ToNORTH OF FM 455
CSJ0047-14-080
Proj IDCM 2017(920)
Work TypeINSTALLATION OF WIRELESS ITS
 
10.258966634.970.000.0
CountyDALLAS
HighwayIH 20
FromIH 635
ToKAUFMAN COUNTY LINE
CSJ0095-13-037
Proj IDCM 2017(920)
Work TypeINSTALLATION OF WIRELESS ITS
 
6.415697636.68704577.9299.9
CountyKAUFMAN
HighwayIH 20
FromDALLAS COUNTY LINE
ToROSEHILL RD
CSJ0095-14-026
Proj IDCM 2017(920)
Work TypeINSTALLATION OF WIRELESS ITS
 
12.895830467.700.000.0
CountyKAUFMAN
HighwayIH 20
FromROSEHILL RD
ToVAN ZANDT COUNTY LINE
CSJ0495-01-072
Proj IDCM 2017(920)
Work TypeINSTALLATION OF WIRELESS ITS
 
14.044919417.690.000.0
Work Order07-20-17
Work Began10-18-17
Work Completed
Time Computed10-18-17
Contract Working Days218
Addl Days Granted0
Working Days Charged6
Percent Time Used2
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0047-14-080
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (1.71)
ALTUS TRAFFIC MANAGEMENT LLC (1.46)
COMEN ENTERPRISE LLC (1.87)
DALLAS FOUNDATION DRILLING CO., INC. (1.34)
TX DOWN UNDER CONSTRUCTION LLC (1.13)
Contract #06173209
Totals3414157.04304995.46704577.9220.6