Monthly State Let Construction Report For Dallas District As Of Sep 15, 2016 Page 3 Of 8

Last Update: Thursday, September 15, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyNAVARRO
Highway US 287
From FM 637 NORTH, EAST OF FM 739
To CR 2040 IN MILDRED
CSJ 0122-01-039
Proj ID STP 1502(090)
Work Type WIDEN ROADWAY; PVMT MKGS
 
2.871 3949887.50 1850.64 3689198.67 93.5
Work Order 07-22-15
Work Began 09-08-15
Work Completed  
Time Computed 08-22-15
Contract Working Days 120
Addl Days Granted 82
Working Days Charged 207
Percent Time Used 102
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0122-01-039
CROSS ROADS, L.P.(0.69%)
ACU CONSTRUCTION LLC (0.32%)
FORTSON CONTRACTING, INC.(0.78%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.07%)
PREMIER PAVING, LTD. ( 19.69%)
DUSTROL, INC.(0.48%)
DURABLE SPECIALTIES, INC.(0.76%)
USA SWPPP INSPECTIONS, INC.(1.34%)
BRENDA PRICE TRUCKING(2.76%)
OSCAR ORDUNO, INC. (1.45%)
LONE STAR BARRIER SERVICES, LLC(0.11%)
Contract # 05153039
Totals 3949887.50 1850.64 3689198.67 93.5

CountyDENTON
Highway US 380
From WEST OF BONNIE BRAE ST
To US 377
CSJ 0134-09-034
Proj ID STP 2013(181)
Work Type STRUCTURES, BASE, PAVEMENT
 
1.625 15088445.93 662503.54 11423747.85 75.7
Work Order 04-03-13
Work Began 11-07-14
Work Completed  
Time Computed 12-29-13
Contract Working Days 420
Addl Days Granted 25
Working Days Charged 449
Percent Time Used 100
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0134-09-034
BUYERS BARRICADES, INC.(0.27%)
FORTSON CONTRACTING, INC.(0.10%)
IOWA BRIDGE & CULVERT, LC(0.23%)
MIKE ALBERT, INC.( 12.30%)
ROADWAY SOLUTIONS, INC.(6.58%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.09%)
TRANSPORT TRUST(0.43%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.56%)
TEX OP CONSTRUCTION, LP(0.30%)
CEN CONCRETE CONSTRUCTION COMPANY, INC.(4.33%)
LINDAMOOD DEMOLITION, INC. (0.41%)
TOMAS REYES TRUCKING, INC. (0.37%)
W.O.E. CONSTRUCTION(0.33%)
BREDA COMPANY, INC.(0.61%)
SOUTHEAST GRINDING & GROOVING, LLC (0.07%)
Contract # 11123002
Totals 15088445.93 662503.54 11423747.85 75.7

CountyDENTON
Highway US 380
From WEST OF FM 156
To IH 35
CSJ 0134-09-063
Proj ID NH 2012(635)
Work Type GR, STR, DRAINAGE, PVMT, C & G, SIGNS
 
4.702 39346679.90 253726.98 39701601.19 99.9
Work Order 03-12-13
Work Began 05-28-13
Work Completed  
Time Computed 05-28-13
Contract Working Days 755
Addl Days Granted 70
Working Days Charged 824
Percent Time Used 99
Contractor(s)
TEXAS STERLING CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0134-09-063
BROCK ENVIRONMENTAL, LLC (0.23%)
BUYERS BARRICADES, INC.(0.19%)
FORTSON CONTRACTING, INC.(0.67%)
THELIN RECYCLING COMPANY, L.P. (0.29%)
CRAIG OLDEN, INC.(0.26%)
JAGOE-PUBLIC COMPANY ( 13.71%)
NORTH TEXAS BOMANITE, INC. (0.70%)
TEXAS INLETS, INC. (2.35%)
TEX OP CONSTRUCTION, LP(0.64%)
TRAC-WORK, INC.(1.82%)
WYLIE DRILLING & DRAINAGE, INC.(1.19%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.08%)
CHOCTAW ERECTORS, INC. (0.76%)
INDEPENDENT UTILITY CONSTRUCTION INCORPORATED(1.04%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.94%)
INLET STRUCTURE SPECIALTIES LTD. (0.96%)
MCL CONTRACTING, LLC (1.02%)
W.O.E. CONSTRUCTION(4.07%)
ALLIED DRILLING COMPANY(0.01%)
TX DOWN UNDER CONSTRUCTION LLC (0.04%)
SAR TRANSPORTATION, LLC(1.04%)
GRANADOS (0.73%)
DCCS, LLC(0.23%)
SCOTT DERR PAINTING CO, LLC(0.06%)
SOUTHEAST GRINDING & GROOVING, LLC (0.00%)
GLOBAL FENCE AND GATE, LLC (0.04%)
MOBILE ENTERPRISES, INC. (0.08%)
A-CORE CONCRETE CUTTING, INC.(0.02%)
BRENDA PRICE TRUCKING(0.11%)
Contract # 07123002
Totals 39346679.90 253726.98 39701601.19 99.9

CountyCOLLIN
Highway US 380
From CR 73 (LOVERS LANE)
To COIT RD (CR 72/CR 74)
CSJ 0135-02-044
Proj ID C 135-2-44
Work Type GR, DR, STR, PAV, SIGN, PAV MRKS, CON PAV
 
3.440 17277016.95 164986.86 17034634.52 98.8
Work Order 08-07-14
Work Began 09-08-14
Work Completed  
Time Computed 08-23-14
Contract Working Days 380
Addl Days Granted 51
Working Days Charged 460
Percent Time Used 106
Contractor(s)
MARIO SINACOLA & SONS EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0135-02-044
IRON CONCRETE CONSTRUCTION COMPANY, INC. (2.87%)
MIKE ALBERT, INC.(2.96%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.14%)
FORTSON CONTRACTING, INC.(0.40%)
FNH CONSTRUCTION, LLC(1.79%)
TEXOP CONSTRUCTION (0.56%)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.(2.15%)
JAGOE-PUBLIC COMPANY ( 31.18%)
W.O.E. CONSTRUCTION(1.66%)
UNION ELECTRICAL CONTRACTOR, INC.(0.05%)
TISEO PAVING CO. (0.42%)
TX DOWN UNDER CONSTRUCTION LLC (0.10%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.53%)
SOUTHWEST CONSTRUCTION COMPANY (0.06%)
HALL BROTHERS, INC.(1.15%)
SOUTHEAST GRINDING & GROOVING, LLC (0.03%)
ACRE PRO, LLC(0.02%)
Contract # 06143001
Totals 17277016.95 164986.86 17034634.52 98.8

CountyCOLLIN
Highway US 380
From WEST OF CR 608 IN FARMERSVILLE
To EAST OF FLOYD RD
CSJ 0135-05-025
Proj ID C 135-5-25
Work Type GR, STRS, PVT, CUL, CURB AND GTRS
 
1.307 18186687.16 0.00 18973078.58 99.9
Work Order 05-10-12
Work Began 11-05-12
Work Completed  
Time Computed 11-05-12
Contract Working Days 551
Addl Days Granted 266
Working Days Charged 817
Percent Time Used 100
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0135-05-025
BREDA COMPANY, INC.(0.68%)
CONCRETE CUTTING BY BOND (0.21%)
CRAIG OLDEN, INC.(1.58%)
DUSTROL, INC.(0.63%)
FORTSON CONTRACTING, INC.(0.28%)
JUST GROOVING, LTD.(0.01%)
K & S UTILITY CONTRACTORS, INC.(4.42%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(6.11%)
SCOTT DERR PAINTING CO, LLC(0.01%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.11%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.04%)
WYLIE DRILLING & DRAINAGE, INC.(7.43%)
MCL CONTRACTING, LLC (0.77%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.18%)
BRENDA PRICE TRUCKING(0.02%)
SOUTHEAST GRINDING & GROOVING, LLC (0.01%)
GIBSON & ASSOCIATES, INC.(0.24%)
Contract # 07113204
Totals 18186687.16 0.00 18973078.58 99.9

CountyDENTON
Highway US 377 ETC
From LOOP 288
To US 380
CSJ 0135-10-055
Proj ID NH 2016(582)
Work Type FULL DEPTH CONCRETE REPAIR
 
46.368 5166236.40 419038.51 419038.51 8.1
Work Order 03-30-16
Work Began 08-10-16
Work Completed  
Time Computed 06-13-16
Contract Working Days 244
Addl Days Granted 0
Working Days Charged 54
Percent Time Used 22
Contractor(s)
SILVER CREEK CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0135-10-055
TEXOP CONSTRUCTION (1.40%)
JAGOE-PUBLIC COMPANY ( 20.19%)
TRP CONSTRUCTION GROUP, LLC( 14.57%)
COWBOY TRUCKING(0.64%)
Contract # 01163216
Totals 5166236.40 419038.51 419038.51 8.1

CountyCOLLIN
Highway US 380
From WEST OF CR 26 (DENTON COUNTY LINE)
To EAST OF SH 289 (CONTROL-SECT BREAK)
CSJ 0135-11-018
Proj ID C 135-11-18
Work Type GR, DR, STR, PAV, SIGN, PAV MRKS, CON PAV
 
2.593 57978706.51 3027175.84 14705840.68 25.3
Work Order 01-22-15
Work Began 03-14-16
Work Completed  
Time Computed 10-19-15
Contract Working Days 772
Addl Days Granted 0
Working Days Charged 135
Percent Time Used 17
Contractor(s)
MARIO SINACOLA & SONS EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0135-11-018
SCOTT DERR PAINTING CO, LLC(0.03%)
AUSTIN BRIDGE & ROAD SERVICES, LP(7.89%)
TEXAS SHAFTS, INC. (1.96%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.89%)
BROCK ENVIRONMENTAL, LLC (0.22%)
FORTSON CONTRACTING, INC.(0.06%)
ALLIANCE GEOTECHNICAL GROUP(0.10%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.07%)
DUSTROL, INC.(0.26%)
IRON CONCRETE CONSTRUCTION COMPANY, INC. (0.63%)
STRIPING TECHNOLOGY, L.P.(0.56%)
INDUS CONSTRUCTION, L.P. (0.16%)
W.O.E. CONSTRUCTION(1.43%)
ANTIGO CONSTRUCTION, INC.(0.15%)
INTEGRATED ROADWAY SERVICES, INC.(2.16%)
Contract # 11143001
Totals 57978706.51 3027175.84 14705840.68 25.3

CountyNAVARRO
Highway SH 31
From 3.2 MILES WEST OF FM 2555
To 3.7 MILES EAST OF IH 45
CSJ 0162-11-001
Proj ID STP 1502(488)
Work Type GR STRS BASE & SURF
 
18.060 105980139.92 0.00 845560.00 0.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-07-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 1,033
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SUNDT CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0162-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11153201
Totals 105980139.92 0.00 845560.00 0.7

CountyELLIS
Highway BU 287S
From SPUR 437
To MCKINNEY ST
CSJ 0172-12-005
Proj ID C 172-12-5
Work Type INSTALL CONTINUOUS LEFT TURN LANE
 
0.227 1615401.35 0.00 0.00 0.0
CountyELLIS
Highway FM 66
From 0.475 MI W OF GREATHOUSE RD
To 0.375 MI E OF GREATHOUSE RD
CSJ 0596-02-042
Proj ID STP 2015(846)HES
Work Type ADD LEFT TURN LANE
 
0.200 469654.30 0.00 103696.00 22.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 159
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0596-02-042
STRIPING TECHNOLOGY, L.P.(1.35%)
GJ SEEDING, LLC(1.78%)
SYNERGY SIGNS & SERVICES, LLC(0.24%)
W.O.E. CONSTRUCTION(0.60%)
BRENDA PRICE TRUCKING(4.28%)
TEX OP CONSTRUCTION, LP(1.22%)
PREMIER PAVING, LTD. ( 14.43%)
ALTUS TRAFFIC MANAGEMENT LLC (0.86%)
DURABLE SPECIALTIES, INC.( 19.76%)
STRIPING SYSTEMS, INC. (0.04%)
Contract # 07153223
Totals 2085055.65 0.00 103696.00 4.9

CountyKAUFMAN
Highway SH 34
From US 175 INTERCHANGE
To SH 243 (MULBERRY STREET) IN KAUFMAN
CSJ 0173-03-015
Proj ID DMO 1102(478)
Work Type GR, STRS & SURF
 
1.842 23009384.99 336447.64 22352358.54 97.1
Work Order 09-12-14
Work Began 01-26-15
Work Completed  
Time Computed 01-10-15
Contract Working Days 506
Addl Days Granted 5
Working Days Charged 418
Percent Time Used 81
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0173-03-015
RUSSO CORPORATION(1.57%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.22%)
K & S UTILITY CONTRACTORS, INC.( 12.07%)
USA SWPPP INSPECTIONS, INC.(1.78%)
RONE ENGINEERING SERVICES, LTD (0.17%)
MELS ELECTRIC, L.P.(1.11%)
INDUS CONSTRUCTION, L.P. (0.59%)
HOUSTON SAWING & DRILLING(0.03%)
SCOTT DERR PAINTING CO (0.07%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.59%)
DUSTROL, INC.(0.05%)
ENCINO LANDSCAPE, INC. (1.50%)
GWG WOOD GROUP (0.30%)
FORTSON CONTRACTING, INC.(0.52%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.42%)
W.O.E. CONSTRUCTION(4.42%)
LONE STAR BARRIER SERVICES, LLC(0.44%)
MCL CONTRACTING, LLC (0.09%)
ALTUS TRAFFIC MANAGEMENT LLC (0.00%)
NORTH TEXAS TRUCKING, INC. (1.22%)
IOWA BRIDGE & CULVERT, LC(1.05%)
HOLY BROS SERVICES LP(0.02%)
RICE TUNNELING & BORING, INC.(0.04%)
LEHMAN & ASSOCIATES CONCRETE, INC(1.60%)
TX DOWN UNDER CONSTRUCTION LLC (0.00%)
PENHALL COMPANY(0.05%)
Contract # 03143202
Totals 23009384.99 336447.64 22352358.54 97.1

CountyDENTON
Highway IH 35E
From STATE SCHOOL RD/MAYHILL RD(FM 2499)
To SL 288
CSJ 0196-01-106
Proj ID STP 2017(083)MM
Work Type GRADE SEPARATION
 
1.693 26586308.86 0.00 0.00 0.0
CountyDENTON
Highway IH 35E
From STATE SCHOOL RD/MAYHILL RD(FM 2499)
To SL 288
CSJ 0196-01-107
Proj ID NH 1602(621)
Work Type ROW UTILITIES
 
1.693 916770.10 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 442
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
OHL USA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0196-01-106
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09163202
Totals 27503078.96 0.00 0.00 0.0

CountyDENTON
Highway IH 35E
From GARDEN RIDGE
To HIGHLAND VILLAGE ROAD
CSJ 0196-02-123
Proj ID C 196-2-123
Work Type HIKE & BIKE TRAILS W / BRIDGES
 
0.001 4679649.00 0.00 0.00 0.0
CountyDENTON
Highway CS
From PHASE 3 A-TRAIN RAIL TRAIL-SWISHER
To RD IN LAKE DALLAS TO KELTON RD
CSJ 0918-46-272
Proj ID STP 2014(158)TE
Work Type BICYCLE AND PEDESTRIAN FACILITY
 
1.520 2039766.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 420
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-46-272
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07163214
Totals 6719415.00 0.00 0.00 0.0

CountyDALLAS
Highway IH 35E
From SP 348
To VALLEY VIEW LANE
CSJ 0196-03-256
Proj ID NH 1502(507)
Work Type MILL, INLAY, PAV MRKS, FDR - CP
 
4.279 7335235.42 161817.62 5882749.46 80.6
Work Order 07-16-15
Work Began 08-27-15
Work Completed  
Time Computed 08-16-15
Contract Working Days 133
Addl Days Granted 0
Working Days Charged 160
Percent Time Used 120
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0196-03-256
O. TREVINO CONSTRUCTION, LLC (9.19%)
MARCOM"S MOWING SERVICE, LLC (0.06%)
STRIPING TECHNOLOGY, L.P.(1.52%)
DUSTROL, INC.( 21.16%)
SCR CONSTRUCTION CO., INC. ( 10.17%)
CROSSROADS, L.P. (0.17%)
W.O.E. CONSTRUCTION(0.46%)
BRENDA PRICE TRUCKING(0.21%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.18%)
PANNELL INDUSTRIES, INC. (0.16%)
Contract # 06153059
Totals 7335235.42 161817.62 5882749.46 80.6

CountyDALLAS
Highway SL 354
From MANANA DRIVE
To NORTH OF ROYAL LANE
CSJ 0196-06-028
Proj ID STP 2014(655)MM
Work Type PEDESTRIAN STRUCTURES AND SIDEWALKS
 
1.704 4677810.85 38009.51 4287037.84 94.5
CountyDALLAS
Highway SL 354
From MANANA DRIVE
To NORTH OF ROYAL LANE
CSJ 0196-06-029
Proj ID RW 196-6-29
Work Type ACQUISITION AND UTILITIES
 
1.614 172634.00 0.00 97669.96 56.5
Work Order 09-25-14
Work Began 11-04-14
Work Completed  
Time Computed 10-11-14
Contract Working Days 220
Addl Days Granted 49
Working Days Charged 409
Percent Time Used 152
Contractor(s)
THE FAIN GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0196-06-028
STORM WATER MANAGEMENT, INC. (0.99%)
ATS DRILLING, INC. (4.28%)
BUYERS BARRICADES, INC.(0.63%)
S & S BRIDGE PAINTING, INC.(0.12%)
COWTOWN REDI MIX, INC. ( 10.52%)
ORNELAS & SON"S TRUCKING (0.99%)
BEAN ELECTRICAL, INC.(2.39%)
TEXAS STAR CONCRETE SERVICES, LLC(0.25%)
MCL CONTRACTING, LLC (0.19%)
SUPER SURFACE, INC.(2.59%)
INSITUFORM TECHNOLOGIES, LLC (0.47%)
W.O.E. CONSTRUCTION(0.26%)
CLASSIC STEEL, LLC (3.44%)
BROWN"S CONCRETE CONSTRUCTION COMPANY(5.15%)
ESTRADA CONCRETE (6.38%)
AD CONCRETE(1.92%)
Contract # 07143042
Totals 4850444.85 38009.51 4384707.80 93.1

CountyDALLAS
Highway US 175
From IH 45
To EAST OF BEXAR ST
CSJ 0197-02-122
Proj ID STP 2016(884)MM
Work Type GRADING, STRUCTURES, PVMT, SIGNS
 
3.929 101441294.02 836779.55 14664578.58 14.4
CountyDALLAS
Highway US 175
From IH 45
To EAST OF BEXAR ST
CSJ 0197-02-123
Proj ID ROW 197-2-123
Work Type JOINT BID UTILITIES
 
1.600 2445346.00 500466.51 500466.51 20.4
Work Order 05-09-16
Work Began 06-20-16
Work Completed  
Time Computed 06-20-16
Contract Working Days 819
Addl Days Granted 0
Working Days Charged 48
Percent Time Used 5
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0197-02-122
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.37%)
DALLAS LITE AND BARRICADE INC. (0.19%)
STRIPING TECHNOLOGY, L.P.(0.35%)
URBAN INFRACONSTRUCTION, LLC (0.25%)
Q. ROBERTS TRUCKING INCORPORATED (0.28%)
ATS DRILLING, INC. (3.35%)
RENAISSANCE CONTRACTORS, INC.(4.76%)
SIGMA ENVIRONMENTAL SOLUTIONS, INC.(3.36%)
POINT BLANK SAFETY SERVICES, LLC (0.43%)
MCL CONTRACTING, LLC (0.16%)
ANTIGO CONSTRUCTION, INC.(0.11%)
CLEMONS TRUCKING (0.11%)
D.E.E.R. TRUCKING, LLC (0.11%)
BOWMAN ENGINEERING & CONSULTING, INC (4.42%)
UNDER CONSTRUCTION INC.(0.10%)
ACU CONSTRUCTION LLC (0.08%)
THELIN RECYCLING COMPANY, L.P. (0.05%)
W. W. FOUNDATION DRILLING, LTD.(0.38%)
Contract # 02163043
Totals 103886640.02 1337246.06 15165045.09 14.5

CountyKAUFMAN
Highway US 175
From DALLAS COUNTY LINE
To E OF FM 148
CSJ 0197-03-071
Proj ID NH 1602(106)
Work Type HMAC OV, BASE REP
 
4.432 1913970.30 259566.34 259566.34 13.5
Work Order 06-27-16
Work Began 08-23-16
Work Completed  
Time Computed 07-27-16
Contract Working Days 122
Addl Days Granted 0
Working Days Charged 9
Percent Time Used 7
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0197-03-071
TRP CONSTRUCTION GROUP, LLC(3.02%)
DALLAS LITE AND BARRICADE INC. (0.56%)
O. TREVINO CONSTRUCTION, LLC (8.11%)
Contract # 05163016
Totals 1913970.30 259566.34 259566.34 13.5

CountyKAUFMAN
Highway US 175
From KINGS CREEK
To 0.2 MI E OF SH 34
CSJ 0197-04-078
Proj ID NH 2015(651)
Work Type LANDSCAPE DEVELOPMENT
 
5.396 278866.65 0.00 264431.05 94.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-07-15
Work Began 08-25-15
Work Completed  
Time Computed 05-08-15
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 36
Percent Time Used 80
Contractor(s)
AALC, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0197-04-078
BUYERS BARRICADES, INC.(0.45%)
Contract # 03153021
Totals 278866.65 0.00 264431.05 94.8

CountyCOLLIN
Highway SH 78
From BUSINESS 78
To FM 6
CSJ 0281-01-030
Proj ID C 281-1-030
Work Type GRADING, DRAINAGE, AND PAVEMENT
 
2.563 24832811.20 4408.50 25763966.10 99.9
Work Order 06-15-12
Work Began 12-13-12
Work Completed  
Time Computed 12-12-12
Contract Working Days 630
Addl Days Granted 139
Working Days Charged 857
Percent Time Used 111
Contractor(s)
MARIO SINACOLA & SONS EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0281-01-030
STORM WATER MANAGEMENT, INC. (0.35%)
INTEGRATED ROADWAY SERVICES, INC.(1.79%)
TEX OP CONSTRUCTION, LP(0.61%)
FOUNDATION DRILLERS, INC.(1.05%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY( 12.22%)
FORTSON CONTRACTING, INC.(0.03%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (0.05%)
J.L. STEEL REINFORCING, LLC(1.02%)
W.O.E. CONSTRUCTION(0.36%)
ALLIANCE GEOTECHNICAL GROUP(0.09%)
SCOTT DERR PAINTING CO (0.14%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.76%)
GREAT WESTERN ERECTORS (0.06%)
LONE STAR MANHOLE & STRUCTURES, LLC(3.52%)
AMERICAN INTERLOCK & MODULAR CONSTRUCTION, INC.(0.03%)
USA SWPPP INSPECTIONS, INC.(0.19%)
JET UNDERGROUND UTILITIES, INC.(1.23%)
TEXAS ENVIRONMENTAL MANAGEMENT, INC(0.54%)
SOUTHEAST GRINDING & GROOVING, LLC (0.02%)
J. E. GUZMAN CONSTRUCTION, INC.(0.53%)
IRON CONCRETE CONSTRUCTION COMPANY, INC. (1.35%)
T-BAR FENCE, INC.(0.07%)
INFINITY PLUMBING & IRRIGATION (0.11%)
Contract # 04123201
Totals 24832811.20 4408.50 25763966.10 99.9

CountyCOLLIN
Highway SH 78
From SPRING CREEK PKWY
To SH 205
CSJ 0281-02-039
Proj ID C 281-2-39
Work Type WDN GR STRS & SURF
 
3.349 21337007.60 1265905.09 11391532.12 53.3
Work Order 08-28-12
Work Began 09-12-13
Work Completed  
Time Computed 05-25-13
Contract Working Days 630
Addl Days Granted 77
Working Days Charged 569
Percent Time Used 80
Contractor(s)
GLENN THURMAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0281-02-039
CONCRETE CUTTING BY BOND (0.33%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY( 15.66%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.92%)
BUYERS BARRICADES, INC.(0.25%)
DT CONSTRUCTION SERVICES (2.63%)
LARRETT, INC.( 11.16%)
INTEGRATED ROADWAY SERVICES, INC.(2.02%)
INDUS CONSTRUCTION, L.P. (0.68%)
DUSTROL, INC.(1.51%)
ENVIRONMENTAL STANDARDS, INC.(2.51%)
COPPELL CONSTRUCTION CO., INC. ( 12.74%)
TEXAS SHAFTS, INC. (1.32%)
MCL CONTRACTING, LLC (0.07%)
IOWA BRIDGE & CULVERT, LC(0.77%)
MEADE SERVICING GROUP, INC.(2.52%)
W.O.E. CONSTRUCTION(0.29%)
CACTUS ABATEMENT & DEMOLITION, LLC (0.16%)
Contract # 06123202
Totals 21337007.60 1265905.09 11391532.12 53.3

CountyDENTON
Highway FM 51
From AT BLOCKER CREEK
To .
CSJ 0312-02-016
Proj ID BR 2013(603)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.303 2575804.40 149904.15 1792865.03 69.6
Work Order 04-10-15
Work Began 07-30-15
Work Completed  
Time Computed 06-09-15
Contract Working Days 316
Addl Days Granted 0
Working Days Charged 276
Percent Time Used 87
Contractor(s)
IOWA BRIDGE & CULVERT, LC
SUBCONTRACTOR(S) FOR CCSJ: 0312-02-016
ALTUS TRAFFIC MANAGEMENT LLC (0.36%)
DUSTROL, INC.(0.88%)
ENVIRONMENTAL SAFETY SERVICES, INC.(4.57%)
FARR FOUNDATION, INC.(1.58%)
FORTSON CONTRACTING, INC.(1.78%)
GRANBURY EXCAVATING, INC.( 11.18%)
PEACHTREE CONSTRUCTION, LTD. (6.11%)
PENHALL COMPANY(0.22%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.65%)
USA SWPPP INSPECTIONS, INC.(2.11%)
W. W. FOUNDATION DRILLING, LTD.(5.33%)
Contract # 02153023
Totals 2575804.40 149904.15 1792865.03 69.6