Monthly State Let Construction Report For Dallas District As Of Dec 10, 2014 Page 3 Of 9

Last Update: Wednesday, December 10, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyKAUFMAN
Highway IH 20 ETC
From FM 2932
To SP 557
CSJ 0095-14-023
Proj ID NH 2015(170)
Work Type SEAL COAT, PVMT MKGS
 
210.557 10697868.93 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-14-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 153
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0095-14-023
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143011
Totals 10697868.93 0.00 0.00 0.0

CountyDENTON
Highway US 380
From DENTON/WISE COUNTY LINE ROAD
To WEST OF FM 156
CSJ 0134-09-029
Proj ID STP 2012(184)SB
Work Type GR, STR, DRAINAGE, BASE, PVMT, AND
 
7.860 26379472.05 0.00 26454917.91 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-22-12
Work Began 05-14-12
Work Completed  
Time Computed 05-14-12
Contract Working Days 588
Addl Days Granted 6
Working Days Charged 593
Percent Time Used 99
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0134-09-029
GLENN THURMAN, INC.( 14.17%)
HIGHWAY TECHNOLOGIES, INC. (1.04%)
BROCK ENVIRONMENTAL, LLC (0.65%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.42%)
CEN CONCRETE CONSTRUCTION COMPANY, INC.(2.02%)
DUSTROL, INC.(0.64%)
FORTSON CONTRACTING, INC.(0.87%)
MIKE ALBERT, INC.(2.69%)
MURRAY CONSTRUCTION(0.35%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.85%)
IOWA BRIDGE & CULVERT, LC(0.33%)
TEXAS SHAFTS, INC. (0.15%)
MCL CONTRACTING, LLC (0.01%)
LKT & ASSOCIATES (2.33%)
BUYERS BARRICADES, INC.(0.09%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.79%)
CLARK CONSTRUCTION OF TEXAS, INC.(0.76%)
DURABLE SPECIALTIES, INC.(0.03%)
Contract # 12113201
Totals 26379472.05 0.00 26454917.91 99.9

CountyDENTON
Highway US 380
From WEST OF BONNIE BRAE ST
To US 377
CSJ 0134-09-034
Proj ID STP 2013(181)
Work Type STRUCTURES, BASE, PAVEMENT
 
1.625 15088445.93 87509.26 289689.26 1.9
Work Order 04-03-13
Work Began 11-07-14
Work Completed  
Time Computed 12-29-13
Contract Working Days 420
Addl Days Granted 0
Working Days Charged 10
Percent Time Used 2
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0134-09-034
BUYERS BARRICADES, INC.(0.27%)
FORTSON CONTRACTING, INC.(0.10%)
IOWA BRIDGE & CULVERT, LC(0.23%)
MIKE ALBERT, INC.( 12.30%)
ROADWAY SOLUTIONS, INC.(6.58%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.09%)
TRANSPORT TRUST(0.43%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.56%)
TEX OP CONSTRUCTION, LP(0.30%)
CEN CONCRETE CONSTRUCTION COMPANY, INC.(4.33%)
LINDAMOOD DEMOLITION, INC. (0.41%)
Contract # 11123002
Totals 15088445.93 87509.26 289689.26 1.9

CountyDENTON
Highway US 380
From WEST OF FM 156
To IH 35
CSJ 0134-09-063
Proj ID NH 2012(635)
Work Type GR, STR, DRAINAGE, PVMT, C & G, SIGNS
 
4.702 39346679.90 1813056.40 16564083.27 42.0
Work Order 03-12-13
Work Began 05-28-13
Work Completed  
Time Computed 05-28-13
Contract Working Days 755
Addl Days Granted 70
Working Days Charged 379
Percent Time Used 45
Contractor(s)
TEXAS STERLING CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0134-09-063
BROCK ENVIRONMENTAL, LLC (0.23%)
BUYERS BARRICADES, INC.(0.19%)
FORTSON CONTRACTING, INC.(0.67%)
THELIN RECYCLING COMPANY, L.P. (0.29%)
CRAIG OLDEN, INC.(0.26%)
JAGOE-PUBLIC COMPANY ( 13.71%)
NORTH TEXAS BOMANITE, INC. (0.70%)
TEXAS INLETS, INC. (2.35%)
TEX OP CONSTRUCTION, LP(0.64%)
TRAC-WORK, INC.(1.82%)
WYLIE DRILLING & DRAINAGE, INC.(1.19%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.08%)
CHOCTAW ERECTORS, INC. (0.76%)
INDEPENDENT UTILITY CONSTRUCTION INCORPORATED(1.04%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.94%)
INLET STRUCTURE SPECIALTIES LTD. (0.96%)
MCL CONTRACTING, LLC (1.02%)
W.O.E. CONSTRUCTION(4.07%)
ALLIED DRILLING COMPANY(0.01%)
TX DOWN UNDER CONSTRUCTION LLC (0.04%)
SAR TRANSPORTATION, LLC(1.04%)
GRANADOS (0.73%)
DCCS, LLC(0.23%)
Contract # 07123002
Totals 39346679.90 1813056.40 16564083.27 42.0

CountyCOLLIN
Highway US 380
From CR 73 (LOVERS LANE)
To COIT RD (CR 72/CR 74)
CSJ 0135-02-044
Proj ID C 135-2-44
Work Type GR, DR, STR, PAV, SIGN, PAV MRKS, CON PAV
 
3.440 17277016.95 874534.91 2440784.22 14.1
Work Order 08-07-14
Work Began 09-08-14
Work Completed  
Time Computed 08-23-14
Contract Working Days 380
Addl Days Granted 0
Working Days Charged 60
Percent Time Used 15
Contractor(s)
MARIO SINACOLA & SONS EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0135-02-044
IRON CONCRETE CONSTRUCTION COMPANY, INC. (2.87%)
MIKE ALBERT, INC.(2.96%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.14%)
FORTSON CONTRACTING, INC.(0.40%)
Contract # 06143001
Totals 17277016.95 874534.91 2440784.22 14.1

CountyCOLLIN
Highway US 380 ETC
From LAKE FOREST DRIVE
To SH 5
CSJ 0135-02-054
Proj ID NH 2014(392)
Work Type FULL DEPTH REPAIR
 
44.157 917408.10 25256.49 903004.41 100.0
Work Order 04-25-14
Work Began 05-19-14
Work Completed 11-20-14
Time Computed 05-11-14
Contract Working Days 104
Addl Days Granted 2
Working Days Charged 106
Percent Time Used 100
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0135-02-054
W.O.E. CONSTRUCTION(3.73%)
BRENDA PRICE TRUCKING(3.77%)
ALTUS TRAFFIC MANAGEMENT LLC (0.49%)
BTA SERVICES, LTD. (0.86%)
Contract # 02143206
Totals 917408.10 25256.49 903004.41 100.0

CountyCOLLIN
Highway US 380
From WEST OF CR 608 IN FARMERSVILLE
To EAST OF FLOYD RD
CSJ 0135-05-025
Proj ID C 135-5-25
Work Type GR, STRS, PVT, CUL, CURB AND GTRS
 
1.307 18186687.16 655765.70 15696461.08 86.3
Work Order 05-10-12
Work Began 11-05-12
Work Completed  
Time Computed 11-05-12
Contract Working Days 551
Addl Days Granted 156
Working Days Charged 601
Percent Time Used 85
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0135-05-025
BREDA COMPANY, INC.(0.68%)
CONCRETE CUTTING BY BOND (0.21%)
CRAIG OLDEN, INC.(1.58%)
DUSTROL, INC.(0.63%)
FORTSON CONTRACTING, INC.(0.28%)
JUST GROOVING, LTD.(0.01%)
K & S UTILITY CONTRACTORS, INC.(4.42%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(6.11%)
SCOTT DERR PAINTING CO, LLC(0.01%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.11%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.04%)
WYLIE DRILLING & DRAINAGE, INC.(7.43%)
MCL CONTRACTING, LLC (0.77%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.18%)
BRENDA PRICE TRUCKING(0.02%)
SOUTHEAST GRINDING & GROOVING, LLC (0.01%)
GIBSON & ASSOCIATES, INC.(0.24%)
Contract # 07113204
Totals 18186687.16 655765.70 15696461.08 86.3

CountyDENTON
Highway US 377
From AT FISH TRAP / MOSELEY RD
To .
CSJ 0135-10-053
Proj ID NH 2015(065)G
Work Type TRAFFIC SIGNAL INSTALLATION
 
0.001 256066.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-28-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0135-10-053
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143021
Totals 256066.00 0.00 0.00 0.0

CountyCOLLIN
Highway US 380
From WEST OF CR 26 (DENTON COUNTY LINE)
To EAST OF SH 289 (CONTROL-SECT BREAK)
CSJ 0135-11-018
Proj ID C 135-11-18
Work Type GR, DR, STR, PAV, SIGN, PAV MRKS, CON PAV
 
2.593 57978706.51 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 772
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MARIO SINACOLA & SONS EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0135-11-018
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11143001
Totals 57978706.51 0.00 0.00 0.0

CountyCOLLIN
Highway FM 3537
From SH 289
To FM 2478
CSJ 0135-12-025
Proj ID C 135-12-25
Work Type WDN GR STRS & SURF
 
4.055 23788820.89 860969.36 15901507.33 66.8
Work Order 10-21-11
Work Began 06-17-13
Work Completed  
Time Computed 04-18-12
Contract Working Days 680
Addl Days Granted 0
Working Days Charged 381
Percent Time Used 56
Contractor(s)
TEXAS STERLING CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0135-12-025
ARLINGTON PAVERS, INC. (0.43%)
CONCRETE CUTTING BY BOND (0.33%)
DALLAS LITE AND BARRICADE INC. (0.24%)
FORTSON CONTRACTING, INC.(0.39%)
INDUS CONSTRUCTION, L.P. (0.96%)
INLET STRUCTURE SPECIALTIES LTD. (5.42%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY( 17.27%)
ROADWAY SOLUTIONS, INC.(6.35%)
TEX OP CONSTRUCTION, LP(0.64%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.33%)
USA EROSION, INC.(1.69%)
W.O.E. CONSTRUCTION(0.65%)
ALLIANCE GEOTECHNICAL GROUP(0.21%)
HAYWOOD BAKER(0.53%)
TEXAS STAR TRANSPORT, LP (1.24%)
CHRISTINE"S CONCERTE SAWING & SEALING LLC(0.34%)
LAUGHLEY BRIDGE & CONSTRUCTION, INC. (0.24%)
RG PAINTING(0.00%)
Contract # 06113007
Totals 23788820.89 860969.36 15901507.33 66.8

CountyNAVARRO
Highway SH 31
From 28TH STREET
To 15TH ST IN THE CITY OF CORSICANA
CSJ 0162-04-047
Proj ID C 162-4-47
Work Type STRM SEWERS & INLETS;REP CONC PAV;ADA
 
1.351 9138952.54 0.00 9670430.08 99.9
Work Order 09-14-10
Work Began 07-22-11
Work Completed  
Time Computed 03-13-11
Contract Working Days 532
Addl Days Granted 105
Working Days Charged 764
Percent Time Used 119
Contractor(s)
LONE STAR CIVIL CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0162-04-047
DALLAS LITE AND BARRICADE INC. (0.51%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.98%)
ALLSTATE SIGNAL & CONSTRUCTION, LLC(0.98%)
BIG CREEK CONSTRUCTION, LTD. (8.65%)
UNDERGROUND COALITION, INC.( 12.39%)
A BROTHERS (0.97%)
RIVER CITIES SAWING, LLC (0.00%)
INDUS CONSTRUCTION, L.P. (0.49%)
W.O.E. CONSTRUCTION(0.41%)
C & C DIRECTIONAL BORING (0.07%)
INLET STRUCTURE SPECIALTIES LTD. (2.35%)
DANRIDGE CONSTRUCTION, LLC.(2.45%)
C.T. AND S. METALWORKS, INC. (0.08%)
Contract # 08103003
Totals 9138952.54 0.00 9670430.08 99.9

CountyNAVARRO
Highway SH 31
From 34TH STREET
To 28TH STREET IN CORSICANA
CSJ 0162-04-055
Proj ID NH 2015(392)
Work Type FULL DEPTH CONC REP; OVERLAY
 
7.410 4312718.88 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 200
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0162-04-055
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12143019
Totals 4312718.88 0.00 0.00 0.0

CountyNAVARRO
Highway FM 709
From WACO ST. NEAR DAWSON
To 0.7 MILE NORTH OF FM 2555
CSJ 0162-09-035
Proj ID STP 2013(828)HES
Work Type GR, BASE, PVMT, PVMT MARKINGS
 
21.446 4787587.88 158734.06 3850587.66 80.4
Work Order 09-26-13
Work Began 10-23-13
Work Completed  
Time Computed 10-23-13
Contract Working Days 276
Addl Days Granted 0
Working Days Charged 275
Percent Time Used 99
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0162-09-035
J & M CONTRACTING, COMPANY (6.13%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.81%)
TEXAS ALTERNATIVE GRASSER, INC.(0.46%)
SAN-ANN-CO., INC.(0.92%)
STRIPING TECHNOLOGY, L.P.(2.77%)
ALPHA EROSION PRODUCTS, LLC(0.06%)
Contract # 07133232
Totals 4787587.88 158734.06 3850587.66 80.4

CountyNAVARRO
Highway SH 31
From IH 45
To FM 1393
CSJ 0163-01-061
Proj ID STP 2013(778)
Work Type OVERLAY
 
19.693 11564843.88 11174.00 10997085.59 95.0
Work Order 08-19-13
Work Began 09-24-13
Work Completed  
Time Computed 09-24-13
Contract Working Days 317
Addl Days Granted 0
Working Days Charged 304
Percent Time Used 95
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0163-01-061
SIGNATURE CONTRACTING SERVICES, L.L.C. (0.30%)
COWBELL TRAFFIC SERVICES, INC. (0.26%)
LONE STAR BARRIER SERVICES, LLC(0.11%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.19%)
O. TREVINO CONSTRUCTION, LLC ( 13.78%)
STRIPING TECHNOLOGY, L.P.(1.88%)
Contract # 06133204
Totals 11564843.88 11174.00 10997085.59 95.0

CountyKAUFMAN
Highway SH 34 ETC
From 0.418 MI N OF ELLIS CO LINE
To 1.732 MI SW OF FM 1388
CSJ 0173-02-070
Proj ID STP 2014(647)HESG
Work Type PROFILE PAVEMENT MARKINGS
 
67.094 838275.06 38783.75 96709.59 11.5
Work Order 06-16-14
Work Began 09-22-14
Work Completed  
Time Computed 08-15-14
Contract Working Days 61
Addl Days Granted 0
Working Days Charged 48
Percent Time Used 78
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0173-02-070
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05143022
Totals 838275.06 38783.75 96709.59 11.5

CountyKAUFMAN
Highway SH 34
From US 175 INTERCHANGE
To SH 243 (MULBERRY STREET) IN KAUFMAN
CSJ 0173-03-015
Proj ID DMO 1102(478)
Work Type GR, STRS & SURF
 
1.842 23009384.99 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-12-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 506
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AUSTIN BRIDGE & ROAD, LP
SUBCONTRACTOR(S) FOR CCSJ: 0173-03-015
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03143202
Totals 23009384.99 0.00 0.00 0.0

CountyKAUFMAN
Highway SH 34
From AIRPORT RD
To HIGH ST IN TERRELL
CSJ 0173-04-024
Proj ID RW 173-4-24
Work Type ACQUISITION OF ROW
 
0.303 663290.10 0.00 696025.56 99.9
CountyKAUFMAN
Highway SH 34
From AIRPORT RD
To HIGH ST. IN TERRELL
CSJ 0173-04-025
Proj ID STP 2011(798)
Work Type GR, PVMT, & GRADE SEP RR O / P
 
1.032 14656545.90 18663.50 15275846.49 99.9
Work Order 06-14-11
Work Began 10-04-11
Work Completed  
Time Computed 09-12-11
Contract Working Days 440
Addl Days Granted 162
Working Days Charged 554
Percent Time Used 92
Contractor(s)
AUI CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0173-04-025
DUSTROL, INC.(0.51%)
HAYWARD BAKER, INC.(1.49%)
INLET STRUCTURE SPECIALTIES LTD. (3.97%)
NORTH TEXAS REBAR, LLC (7.18%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(6.66%)
SCOTT DERR PAINTING CO (0.90%)
STORM WATER MANAGEMENT, INC. (0.68%)
T-BAR FENCE, INC.(0.48%)
TEXAS SHAFTS, INC. (1.11%)
DURABLE SPECIALTIES, INC.(2.31%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.86%)
THELIN RECYCLING CO., LLC(0.23%)
TRAC-WORK, INC.(1.46%)
CROSSROADS, L.P. (0.26%)
MCALLISTER"S LANDSCAPE MANAGEMENT(0.67%)
RIVER CITIES SAWING, LLC (0.29%)
RAIL LABOR PROVIDERS (0.05%)
STRAIGHT LINE SAWING & SEALING (0.19%)
EL CALA CONSTRUCTION LLC (2.11%)
S1 SOD (0.32%)
WEBBER BARRIER SERVICES, LLC.(0.57%)
ARLINGTON PAVERS, INC. (0.04%)
SUNNYVALE FENCE COMPANY(0.75%)
AQUA BORE(0.01%)
Contract # 03113211
Totals 15319836.00 18663.50 15971872.05 99.9

CountyKAUFMAN
Highway SH 34
From US 80
To N. FRANCES STREET IN TERRELL
CSJ 0173-05-032
Proj ID STP 2013(665)
Work Type HOT MIX OVLY, BASE, BLADE, PAV MARKS
 
0.977 1979270.82 68309.64 1578424.24 79.7
Work Order 08-19-13
Work Began 01-06-14
Work Completed  
Time Computed 12-17-13
Contract Working Days 152
Addl Days Granted 8
Working Days Charged 135
Percent Time Used 84
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0173-05-032
MELS ELECTRIC, L.P.(1.30%)
INLET STRUCTURE SPECIALTIES LTD. (0.70%)
BUYERS BARRICADES, INC.(1.16%)
CHRISTINE"S CONCERTE SAWING & SEALING LLC(0.11%)
DUSTROL, INC.(4.17%)
PEACHTREE CONSTRUCTION, LTD. ( 38.86%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (2.46%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.97%)
BRENDA PRICE TRUCKING(1.45%)
Contract # 05133023
Totals 1979270.82 68309.64 1578424.24 79.7

CountyDALLAS
Highway IH 35E
From EMPIRE CENTRAL
To SL 12
CSJ 0196-03-267
Proj ID NH 2014(654)
Work Type INSTALLATION OF ITS SYSTEM
 
2.832 364833.69 11288.28 261087.08 71.5
Work Order 06-10-14
Work Began 09-11-14
Work Completed  
Time Computed 08-09-14
Contract Working Days 60
Addl Days Granted 10
Working Days Charged 69
Percent Time Used 98
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0196-03-267
TOTAL HIGHWAY MAINTENANCE, LLC (2.00%)
INTEGRATED ROADWAY SERVICES, INC.( 20.13%)
ADVANCED FIBER SERVICES(3.21%)
ALTUS TRAFFIC MANAGEMENT LLC (1.42%)
Contract # 05143231
Totals 364833.69 11288.28 261087.08 71.5

CountyDALLAS
Highway SL 354
From MANANA DRIVE
To NORTH OF ROYAL LANE
CSJ 0196-06-028
Proj ID STP 2014(655)MM
Work Type PEDESTRIAN STRUCTURES AND SIDEWALKS
 
1.704 4677810.85 258055.67 258055.67 5.5
CountyDALLAS
Highway SL 354
From MANANA DRIVE
To NORTH OF ROYAL LANE
CSJ 0196-06-029
Proj ID RW 196-6-29
Work Type ACQUISITION AND UTILITIES
 
1.614 172634.00 0.00 0.00 0.0
Work Order 09-25-14
Work Began 11-04-14
Work Completed  
Time Computed 10-11-14
Contract Working Days 220
Addl Days Granted 0
Working Days Charged 29
Percent Time Used 13
Contractor(s)
THE FAIN GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0196-06-028
STORM WATER MANAGEMENT, INC. (0.99%)
ATS DRILLING, INC. (4.28%)
BUYERS BARRICADES, INC.(0.63%)
S & S BRIDGE PAINTING, INC.(0.12%)
COWTOWN REDI MIX, INC. ( 10.52%)
ORNELAS & SON"S TRUCKING (0.99%)
BEAN ELECTRICAL, INC.(2.39%)
Contract # 07143042
Totals 4850444.85 258055.67 258055.67 5.3