Monthly State Let Construction Report For Dallas District As Of Apr 10, 2015 Page 3 Of 9

Last Update: Friday, April 10, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyKAUFMAN
Highway US 80
From AT PROPOSED FORNEY PARKWAY
To .
CSJ 0095-04-064
Proj ID C 95-4-64
Work Type GR, STR, DRAINAGE, PVMT, SIGNS
 
1.030 17050215.03 23285.41 19317448.12 99.9
Work Order 03-06-12
Work Began 04-09-12
Work Completed  
Time Computed 03-22-12
Contract Working Days 473
Addl Days Granted 82
Working Days Charged 555
Percent Time Used 100
Contractor(s)
HAYDON BUILDING CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0095-04-064
BEAIRD DRILLING(2.99%)
BUYERS BARRICADES, INC.(0.19%)
DUSTROL, INC.(0.14%)
FORTSON CONTRACTING, INC.(0.57%)
PEACHTREE CONSTRUCTION, LTD. (3.69%)
STAR OPERATIONS, INC.(1.93%)
STORM WATER MANAGEMENT, INC. (0.08%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.32%)
SOUTH TEXAS PAINTING COMPANY (1.00%)
CONCRETE CUTTING BY BOND (0.07%)
USA SWPPP INSPECTIONS, INC.(0.66%)
W. W. FOUNDATION DRILLING, LTD.(2.82%)
J.L. STEEL REINFORCING, LLC(1.20%)
COWBOY TRUCKING(0.00%)
CHRISTINE"S CONCERTE SAWING & SEALING LLC(0.06%)
SUNNYVALE FENCE COMPANY(0.10%)
Contract # 01123202
Totals 17050215.03 23285.41 19317448.12 99.9

CountyDALLAS
Highway US 80
From IH 30
To TOWN EAST BLVD
CSJ 0095-10-053
Proj ID NH 2015(391)
Work Type CONCRETE FULL DEPTH REPAIR
 
2.686 1322287.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-24-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 105
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SILVER CREEK CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0095-10-053
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12143210
Totals 1322287.50 0.00 0.00 0.0

CountyKAUFMAN
Highway FM 688
From US 80
To FM 548
CSJ 0095-11-008
Proj ID STP 2015(842)
Work Type SPT BS REP, MILL, LVLUP, OV PAV MRKS
 
2.313 832284.88 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 61
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0095-11-008
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04153223
Totals 832284.88 0.00 0.00 0.0

CountyDALLAS
Highway IH 20
From I.H. 635
To SEAGOVILLE ROAD.
CSJ 0095-13-025
Proj ID IM 0205(146)
Work Type GRADING, PAVING, SIGNING, LANDSCAPING
 
0.841 4972861.19 0.00 4938967.91 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-21-12
Work Began 10-01-12
Work Completed 02-10-15
Time Computed 10-01-12
Contract Working Days 147
Addl Days Granted 70
Working Days Charged 217
Percent Time Used 100
Contractor(s)
HAYDON BUILDING CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0095-13-025
NORTH TEXAS REBAR, LLC (0.68%)
FORTSON CONTRACTING, INC.(1.00%)
INTEGRATED ROADWAY SERVICES, INC.(1.49%)
S & S PAINTING (0.25%)
W.O.E. CONSTRUCTION(0.21%)
AXIS CONTRACTING, INC. (8.00%)
HOUSTON SAWING & DRILLING(0.05%)
USA SWPPP INSPECTIONS, INC.(0.47%)
DUSTROL, INC.(0.54%)
DALLAS LITE AND BARRICADE INC. (0.28%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.23%)
THELIN RECYCLING COMPANY, L.P. (0.24%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(9.28%)
W. W. FOUNDATION DRILLING, LTD.(2.12%)
THE ANCHOR GROUP, INC. (0.78%)
NORTH TEXAS REBAR, LLC (0.09%)
COWBOY TRUCKING(0.40%)
MCALLISTER"S LANDSCAPE MANAGEMENT(3.25%)
S & S BRIDGE PAINTING, INC.(0.25%)
STAR OPERATIONS, INC.(0.24%)
Contract # 05123247
Totals 4972861.19 0.00 4938967.91 100.0

CountyKAUFMAN
Highway IH 20 ETC
From FM 2932
To SP 557
CSJ 0095-14-023
Proj ID NH 2015(170)
Work Type SEAL COAT, PVMT MKGS
 
210.557 10697868.93 359184.78 2257902.23 21.1
Work Order 10-14-14
Work Began 00-00-00
Work Completed  
Time Computed 12-13-14
Contract Working Days 153
Addl Days Granted 0
Working Days Charged 28
Percent Time Used 18
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0095-14-023
STRIPE-A-ZONE, INC.( 11.94%)
Contract # 09143011
Totals 10697868.93 359184.78 2257902.23 21.1

CountyDENTON
Highway US 380
From DENTON/WISE COUNTY LINE ROAD
To WEST OF FM 156
CSJ 0134-09-029
Proj ID STP 2012(184)SB
Work Type GR, STR, DRAINAGE, BASE, PVMT, AND
 
7.860 26379472.05 2705.00 26490901.07 99.9
Work Order 02-22-12
Work Began 05-14-12
Work Completed  
Time Computed 05-14-12
Contract Working Days 588
Addl Days Granted 6
Working Days Charged 593
Percent Time Used 99
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0134-09-029
GLENN THURMAN, INC.( 14.17%)
HIGHWAY TECHNOLOGIES, INC. (1.04%)
BROCK ENVIRONMENTAL, LLC (0.65%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.42%)
CEN CONCRETE CONSTRUCTION COMPANY, INC.(2.02%)
DUSTROL, INC.(0.64%)
FORTSON CONTRACTING, INC.(0.87%)
MIKE ALBERT, INC.(2.69%)
MURRAY CONSTRUCTION(0.35%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.85%)
IOWA BRIDGE & CULVERT, LC(0.33%)
TEXAS SHAFTS, INC. (0.15%)
MCL CONTRACTING, LLC (0.01%)
LKT & ASSOCIATES (2.33%)
BUYERS BARRICADES, INC.(0.09%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.79%)
CLARK CONSTRUCTION OF TEXAS, INC.(0.76%)
DURABLE SPECIALTIES, INC.(0.03%)
Contract # 12113201
Totals 26379472.05 2705.00 26490901.07 99.9

CountyDENTON
Highway US 380
From WEST OF BONNIE BRAE ST
To US 377
CSJ 0134-09-034
Proj ID STP 2013(181)
Work Type STRUCTURES, BASE, PAVEMENT
 
1.625 15088445.93 235082.89 2134182.83 14.1
Work Order 04-03-13
Work Began 11-07-14
Work Completed  
Time Computed 12-29-13
Contract Working Days 420
Addl Days Granted 0
Working Days Charged 87
Percent Time Used 20
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0134-09-034
BUYERS BARRICADES, INC.(0.27%)
FORTSON CONTRACTING, INC.(0.10%)
IOWA BRIDGE & CULVERT, LC(0.23%)
MIKE ALBERT, INC.( 12.30%)
ROADWAY SOLUTIONS, INC.(6.58%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.09%)
TRANSPORT TRUST(0.43%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.56%)
TEX OP CONSTRUCTION, LP(0.30%)
CEN CONCRETE CONSTRUCTION COMPANY, INC.(4.33%)
LINDAMOOD DEMOLITION, INC. (0.41%)
TOMAS REYES TRUCKING, INC. (0.37%)
Contract # 11123002
Totals 15088445.93 235082.89 2134182.83 14.1

CountyDENTON
Highway US 380
From WEST OF FM 156
To IH 35
CSJ 0134-09-063
Proj ID NH 2012(635)
Work Type GR, STR, DRAINAGE, PVMT, C & G, SIGNS
 
4.702 39346679.90 320401.36 22570016.55 57.3
Work Order 03-12-13
Work Began 05-28-13
Work Completed  
Time Computed 05-28-13
Contract Working Days 755
Addl Days Granted 70
Working Days Charged 463
Percent Time Used 56
Contractor(s)
TEXAS STERLING CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0134-09-063
BROCK ENVIRONMENTAL, LLC (0.23%)
BUYERS BARRICADES, INC.(0.19%)
FORTSON CONTRACTING, INC.(0.67%)
THELIN RECYCLING COMPANY, L.P. (0.29%)
CRAIG OLDEN, INC.(0.26%)
JAGOE-PUBLIC COMPANY ( 13.71%)
NORTH TEXAS BOMANITE, INC. (0.70%)
TEXAS INLETS, INC. (2.35%)
TEX OP CONSTRUCTION, LP(0.64%)
TRAC-WORK, INC.(1.82%)
WYLIE DRILLING & DRAINAGE, INC.(1.19%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.08%)
CHOCTAW ERECTORS, INC. (0.76%)
INDEPENDENT UTILITY CONSTRUCTION INCORPORATED(1.04%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.94%)
INLET STRUCTURE SPECIALTIES LTD. (0.96%)
MCL CONTRACTING, LLC (1.02%)
W.O.E. CONSTRUCTION(4.07%)
ALLIED DRILLING COMPANY(0.01%)
TX DOWN UNDER CONSTRUCTION LLC (0.04%)
SAR TRANSPORTATION, LLC(1.04%)
GRANADOS (0.73%)
DCCS, LLC(0.23%)
SCOTT DERR PAINTING CO, LLC(0.06%)
SOUTHEAST GRINDING & GROOVING, LLC (0.00%)
GLOBAL FENCE AND GATE, LLC (0.04%)
Contract # 07123002
Totals 39346679.90 320401.36 22570016.55 57.3

CountyCOLLIN
Highway US 380
From CR 73 (LOVERS LANE)
To COIT RD (CR 72/CR 74)
CSJ 0135-02-044
Proj ID C 135-2-44
Work Type GR, DR, STR, PAV, SIGN, PAV MRKS, CON PAV
 
3.440 17277016.95 338033.91 4086465.13 23.6
Work Order 08-07-14
Work Began 09-08-14
Work Completed  
Time Computed 08-23-14
Contract Working Days 380
Addl Days Granted 0
Working Days Charged 145
Percent Time Used 38
Contractor(s)
MARIO SINACOLA & SONS EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0135-02-044
IRON CONCRETE CONSTRUCTION COMPANY, INC. (2.87%)
MIKE ALBERT, INC.(2.96%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.14%)
FORTSON CONTRACTING, INC.(0.40%)
FNH CONSTRUCTION, LLC(1.79%)
Contract # 06143001
Totals 17277016.95 338033.91 4086465.13 23.6

CountyCOLLIN
Highway US 380 ETC
From LAKE FOREST DRIVE
To SH 5
CSJ 0135-02-054
Proj ID NH 2014(392)
Work Type FULL DEPTH REPAIR
 
44.157 917408.10 0.00 974048.78 100.0
Work Order 04-25-14
Work Began 05-19-14
Work Completed 11-20-14
Time Computed 05-11-14
Contract Working Days 104
Addl Days Granted 2
Working Days Charged 106
Percent Time Used 100
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0135-02-054
W.O.E. CONSTRUCTION(3.73%)
BRENDA PRICE TRUCKING(3.77%)
ALTUS TRAFFIC MANAGEMENT LLC (0.49%)
BTA SERVICES, LTD. (0.86%)
Contract # 02143206
Totals 917408.10 0.00 974048.78 100.0

CountyCOLLIN
Highway US 380
From WEST OF CR 608 IN FARMERSVILLE
To EAST OF FLOYD RD
CSJ 0135-05-025
Proj ID C 135-5-25
Work Type GR, STRS, PVT, CUL, CURB AND GTRS
 
1.307 18186687.16 214696.30 17059896.02 93.8
Work Order 05-10-12
Work Began 11-05-12
Work Completed  
Time Computed 11-05-12
Contract Working Days 551
Addl Days Granted 156
Working Days Charged 696
Percent Time Used 98
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0135-05-025
BREDA COMPANY, INC.(0.68%)
CONCRETE CUTTING BY BOND (0.21%)
CRAIG OLDEN, INC.(1.58%)
DUSTROL, INC.(0.63%)
FORTSON CONTRACTING, INC.(0.28%)
JUST GROOVING, LTD.(0.01%)
K & S UTILITY CONTRACTORS, INC.(4.42%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(6.11%)
SCOTT DERR PAINTING CO, LLC(0.01%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.11%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.04%)
WYLIE DRILLING & DRAINAGE, INC.(7.43%)
MCL CONTRACTING, LLC (0.77%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.18%)
BRENDA PRICE TRUCKING(0.02%)
SOUTHEAST GRINDING & GROOVING, LLC (0.01%)
GIBSON & ASSOCIATES, INC.(0.24%)
Contract # 07113204
Totals 18186687.16 214696.30 17059896.02 93.8

CountyDENTON
Highway US 377
From AT FISH TRAP / MOSELEY RD
To .
CSJ 0135-10-053
Proj ID NH 2015(065)G
Work Type TRAFFIC SIGNAL INSTALLATION
 
0.001 256066.00 84549.53 199323.23 77.8
Work Order 10-28-14
Work Began 02-04-15
Work Completed  
Time Computed 02-04-15
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 28
Percent Time Used 70
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0135-10-053
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143021
Totals 256066.00 84549.53 199323.23 77.8

CountyCOLLIN
Highway US 380
From WEST OF CR 26 (DENTON COUNTY LINE)
To EAST OF SH 289 (CONTROL-SECT BREAK)
CSJ 0135-11-018
Proj ID C 135-11-18
Work Type GR, DR, STR, PAV, SIGN, PAV MRKS, CON PAV
 
2.593 57978706.51 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-22-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 772
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MARIO SINACOLA & SONS EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0135-11-018
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11143001
Totals 57978706.51 0.00 0.00 0.0

CountyCOLLIN
Highway FM 3537
From SH 289
To FM 2478
CSJ 0135-12-025
Proj ID C 135-12-25
Work Type WDN GR STRS & SURF
 
4.055 23788820.89 1605763.12 21248556.43 89.3
Work Order 10-21-11
Work Began 06-17-13
Work Completed  
Time Computed 04-18-12
Contract Working Days 680
Addl Days Granted 0
Working Days Charged 475
Percent Time Used 69
Contractor(s)
TEXAS STERLING CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0135-12-025
ARLINGTON PAVERS, INC. (0.43%)
CONCRETE CUTTING BY BOND (0.33%)
DALLAS LITE AND BARRICADE INC. (0.24%)
FORTSON CONTRACTING, INC.(0.39%)
INDUS CONSTRUCTION, L.P. (0.96%)
INLET STRUCTURE SPECIALTIES LTD. (5.42%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY( 17.27%)
ROADWAY SOLUTIONS, INC.(6.35%)
TEX OP CONSTRUCTION, LP(0.64%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.33%)
USA EROSION, INC.(1.69%)
W.O.E. CONSTRUCTION(0.65%)
ALLIANCE GEOTECHNICAL GROUP(0.21%)
HAYWOOD BAKER(0.53%)
TEXAS STAR TRANSPORT, LP (1.24%)
CHRISTINE"S CONCERTE SAWING & SEALING LLC(0.34%)
LAUGHLEY BRIDGE & CONSTRUCTION, INC. (0.24%)
RG PAINTING(0.00%)
Contract # 06113007
Totals 23788820.89 1605763.12 21248556.43 89.3

CountyNAVARRO
Highway SH 31
From 28TH STREET
To 15TH ST IN THE CITY OF CORSICANA
CSJ 0162-04-047
Proj ID C 162-4-47
Work Type STRM SEWERS & INLETS;REP CONC PAV;ADA
 
1.351 9138952.54 51417.65 9758269.17 99.9
Work Order 09-14-10
Work Began 07-22-11
Work Completed  
Time Computed 03-13-11
Contract Working Days 532
Addl Days Granted 105
Working Days Charged 764
Percent Time Used 119
Contractor(s)
LONE STAR CIVIL CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0162-04-047
DALLAS LITE AND BARRICADE INC. (0.51%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.98%)
ALLSTATE SIGNAL & CONSTRUCTION, LLC(0.98%)
BIG CREEK CONSTRUCTION, LTD. (8.65%)
UNDERGROUND COALITION, INC.( 12.39%)
A BROTHERS (0.97%)
RIVER CITIES SAWING, LLC (0.00%)
INDUS CONSTRUCTION, L.P. (0.49%)
W.O.E. CONSTRUCTION(0.41%)
C & C DIRECTIONAL BORING (0.07%)
INLET STRUCTURE SPECIALTIES LTD. (2.35%)
DANRIDGE CONSTRUCTION, LLC.(2.45%)
C.T. AND S. METALWORKS, INC. (0.08%)
Contract # 08103003
Totals 9138952.54 51417.65 9758269.17 99.9

CountyNAVARRO
Highway SH 31
From 34TH STREET
To 28TH STREET IN CORSICANA
CSJ 0162-04-055
Proj ID NH 2015(392)
Work Type FULL DEPTH CONC REP; OVERLAY
 
7.410 4312718.88 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-13-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 200
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0162-04-055
COWBELL TRAFFIC SERVICE, INC.(0.18%)
KENSAR LLC DBA S & S TRUCKING(0.95%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.07%)
STRIPING TECHNOLOGY, L.P.(2.14%)
PAVETEX ENGINEERING & TESTING, INC.(0.45%)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.(0.35%)
SILVER CREEK CONSTRUCTION, INC.( 27.58%)
LONE STAR HIGHWAY PRODUCTS, INC. (1.34%)
COWBOY TRUCKING(0.36%)
Contract # 12143019
Totals 4312718.88 0.00 0.00 0.0

CountyNAVARRO
Highway FM 709
From WACO ST. NEAR DAWSON
To 0.7 MILE NORTH OF FM 2555
CSJ 0162-09-035
Proj ID STP 2013(828)HES
Work Type GR, BASE, PVMT, PVMT MARKINGS
 
21.446 4787587.88 0.00 3915088.76 82.4
Work Order 09-26-13
Work Began 10-23-13
Work Completed  
Time Computed 10-23-13
Contract Working Days 276
Addl Days Granted 0
Working Days Charged 311
Percent Time Used 112
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0162-09-035
J & M CONTRACTING, COMPANY (6.13%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.81%)
TEXAS ALTERNATIVE GRASSER, INC.(0.46%)
SAN-ANN-CO., INC.(0.92%)
STRIPING TECHNOLOGY, L.P.(2.77%)
ALPHA EROSION PRODUCTS, LLC(0.06%)
Contract # 07133232
Totals 4787587.88 0.00 3915088.76 82.4

CountyNAVARRO
Highway SH 31
From IH 45
To FM 1393
CSJ 0163-01-061
Proj ID STP 2013(778)
Work Type OVERLAY
 
19.693 11564843.88 77000.05 11223788.44 100.0
Work Order 08-19-13
Work Began 09-24-13
Work Completed 03-19-15
Time Computed 09-24-13
Contract Working Days 317
Addl Days Granted 0
Working Days Charged 315
Percent Time Used 99
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0163-01-061
SIGNATURE CONTRACTING SERVICES, L.L.C. (0.30%)
COWBELL TRAFFIC SERVICES, INC. (0.26%)
LONE STAR BARRIER SERVICES, LLC(0.11%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.19%)
O. TREVINO CONSTRUCTION, LLC ( 13.78%)
STRIPING TECHNOLOGY, L.P.(1.88%)
Contract # 06133204
Totals 11564843.88 77000.05 11223788.44 100.0

CountyKAUFMAN
Highway SH 34 ETC
From 0.418 MI N OF ELLIS CO LINE
To 1.732 MI SW OF FM 1388
CSJ 0173-02-070
Proj ID STP 2014(647)HESG
Work Type PROFILE PAVEMENT MARKINGS
 
67.094 838275.06 187485.79 374275.92 45.5
Work Order 06-16-14
Work Began 09-22-14
Work Completed  
Time Computed 08-15-14
Contract Working Days 61
Addl Days Granted 0
Working Days Charged 73
Percent Time Used 119
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0173-02-070
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05143022
Totals 838275.06 187485.79 374275.92 45.5

CountyKAUFMAN
Highway SH 34
From US 175 INTERCHANGE
To SH 243 (MULBERRY STREET) IN KAUFMAN
CSJ 0173-03-015
Proj ID DMO 1102(478)
Work Type GR, STRS & SURF
 
1.842 23009384.99 483033.66 2848537.72 12.3
Work Order 09-12-14
Work Began 01-26-15
Work Completed  
Time Computed 01-10-15
Contract Working Days 506
Addl Days Granted 0
Working Days Charged 43
Percent Time Used 8
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0173-03-015
RUSSO CORPORATION(1.57%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.22%)
K & S UTILITY CONTRACTORS, INC.( 12.07%)
USA SWPPP INSPECTIONS, INC.(1.78%)
RONE ENGINEERING SERVICES, LTD (0.17%)
MELS ELECTRIC, L.P.(1.11%)
INDUS CONSTRUCTION, L.P. (0.59%)
HOUSTON SAWING & DRILLING(0.03%)
SCOTT DERR PAINTING CO (0.07%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.59%)
DUSTROL, INC.(0.05%)
ENCINO LANDSCAPE, INC. (1.50%)
GWG WOOD GROUP (0.30%)
FORTSON CONTRACTING, INC.(0.52%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.42%)
W.O.E. CONSTRUCTION(4.04%)
LONE STAR BARRIER SERVICES, LLC(0.44%)
MCL CONTRACTING, LLC (0.09%)
ALTUS TRAFFIC MANAGEMENT LLC (0.00%)
Contract # 03143202
Totals 23009384.99 483033.66 2848537.72 12.3

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9