Monthly State Let Construction Report For Dallas District As Of Aug 10, 2015 Page 8 Of 11

Last Update: Monday, August 10, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyDALLAS
Highway VA
From VARIOUS LOCATIONS ON STATE HIGHWAYS
To IN DALLAS COUNTY
CSJ 0918-47-052
Proj ID STP 1102(553)
Work Type CONSTRUCT CURB RAMPS
 
0.001 2270944.30 154149.00 2044547.00 90.0
Work Order 07-25-14
Work Began 09-02-14
Work Completed  
Time Computed 09-02-14
Contract Working Days 244
Addl Days Granted 0
Working Days Charged 220
Percent Time Used 90
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-052
CLASSIC TEJAS CONSTRUCTION, INC. ( 17.31%)
Contract # 06143039
Totals 2270944.30 154149.00 2044547.00 90.0

CountyDALLAS
Highway VA
From VARIOUS LOCATIONS ON STATE HIGHWAYS
To IN DALLAS COUNTY
CSJ 0918-47-100
Proj ID NH 2015(653)
Work Type CONSTRUCT CURB RAMPS
 
0.001 3464886.46 146190.03 227280.63 6.5
Work Order 04-22-15
Work Began 06-22-15
Work Completed  
Time Computed 05-08-15
Contract Working Days 315
Addl Days Granted 0
Working Days Charged 39
Percent Time Used 12
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-100
CLASSIC TEJAS CONSTRUCTION, INC. ( 10.16%)
Contract # 03153224
Totals 3464886.46 146190.03 227280.63 6.5

CountyDALLAS
Highway CS
From JEFFERSON ST AT MERRIFIELD ST
To .
CSJ 0918-47-101
Proj ID STP 1502(494)HES
Work Type INSTALL TRAFFIC SIGNAL
 
0.300 802955.85 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 140
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-101
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07153012
Totals 802955.85 0.00 0.00 0.0

CountyDALLAS
Highway CS
From W TARRANT ROAD
To AT CURVE AT HAWAII DRIVE
CSJ 0918-47-102
Proj ID STP 2015(784)HES
Work Type INSTALL CHEVRONS AND OVERLAY
 
0.100 128676.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-102
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04153236
Totals 128676.50 0.00 0.00 0.0

CountyCOLLIN
Highway FM 981
From AT INDIAN CREEK AND RELIEF #2
To .
CSJ 1012-03-017
Proj ID BR 2015(067)
Work Type REPL BRIDGE
 
0.261 1828296.80 289392.07 1289414.95 70.5
Work Order 10-17-14
Work Began 02-16-15
Work Completed  
Time Computed 12-16-14
Contract Working Days 141
Addl Days Granted 0
Working Days Charged 118
Percent Time Used 83
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1012-03-017
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(2.50%)
ACTION COMMERCIAL SERVICES, L.L.C. (0.31%)
FORTSON CONTRACTING, INC.(1.72%)
MCL CONTRACTING, LLC (0.72%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(3.04%)
SCOTT DERR PAINTING CO, LLC(0.13%)
SYNERGY SIGNS & SERVICES, LLC(0.15%)
TEX OP CONSTRUCTION, LP(0.97%)
TEXAS SHAFTS, INC. (8.73%)
MCL CONTRACTING, LLC (0.28%)
USA SWPPP INSPECTIONS, INC.(2.46%)
Contract # 08143032
Totals 1828296.80 289392.07 1289414.95 70.5

CountyCOLLIN
Highway FM 546
From WEST OF THE CROSSINGS RD
To FM 982
CSJ 1013-01-028
Proj ID STP 1402(180)HES
Work Type GR, BASE, PVMT, PVMT MKGS, SIGNS
 
5.051 5997170.81 191874.90 2556881.50 42.6
Work Order 09-15-14
Work Began 12-01-14
Work Completed  
Time Computed 12-01-14
Contract Working Days 263
Addl Days Granted 3
Working Days Charged 161
Percent Time Used 60
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1013-01-028
TOTAL HIGHWAY MAINTENANCE, LLC (1.22%)
TEXAS ENVIRONMENTAL MANAGEMENT, INC(0.43%)
FARR FOUNDATION, INC.(3.02%)
EROSION CONTROL MANAGEMENT SERVICES(0.36%)
K & S UTILITY CONTRACTORS, INC.( 21.42%)
MARCOM"S MOWING SERVICE, LLC (3.13%)
ACU CONSTRUCTION LLC (0.45%)
GOLDEN TREE MAINTENANCE(0.13%)
IOWA BRIDGE & CULVERT, LC(0.51%)
Contract # 07143245
Totals 5997170.81 191874.90 2556881.50 42.6

CountyROCKWALL
Highway FM 740
From FM 549 / FM 550 INTERSECTION
To FM 1140 NORTH IN HEATH
CSJ 1014-03-049
Proj ID C 1014-3-49
Work Type GRADING, STRUCTURES, DRAINAGE, & PVMT
 
1.856 12967453.42 30848.50 219270.32 1.6
Work Order 11-14-13
Work Began 07-20-15
Work Completed  
Time Computed 08-11-14
Contract Working Days 412
Addl Days Granted 0
Working Days Charged 5
Percent Time Used 1
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1014-03-049
W.O.E. CONSTRUCTION(0.30%)
TEX OP CONSTRUCTION, LP(2.01%)
TEXAS INLETS, INC. (3.62%)
SYNERGY SIGNS & SERVICES, LLC(0.37%)
HAYWARD BAKER, INC.(0.81%)
STRIPING TECHNOLOGY, L.P.(0.99%)
USA SWPPP INSPECTIONS, INC.(1.15%)
PREMIER PAVING, LTD. (4.86%)
DURABLE SPECIALTIES, INC.(3.25%)
BREDA COMPANY, INC.(0.67%)
BUYERS BARRICADES, INC.(0.31%)
BRENDA PRICE TRUCKING(4.98%)
Contract # 08133209
Totals 12967453.42 30848.50 219270.32 1.6

CountyROCKWALL
Highway FM 3549
From SH 66
To FM 552
CSJ 1015-01-022
Proj ID STP 2015(590)
Work Type BASE REPAIR, LEVEL UP, OVERLAY
 
2.319 2576274.62 0.00 20010.00 0.7
Work Order 03-30-15
Work Began 00-00-00
Work Completed  
Time Computed 04-15-15
Contract Working Days 165
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 1015-01-022
PEACHTREE CONSTRUCTION, LTD. ( 14.69%)
K & S UTILITY CONTRACTORS, INC.(8.99%)
ALTUS TRAFFIC MANAGEMENT LLC (0.36%)
USA SWPPP INSPECTIONS, INC.(2.61%)
STRIPING TECHNOLOGY, L.P.(1.47%)
Contract # 02153221
Totals 2576274.62 0.00 20010.00 0.7

CountyROCKWALL
Highway FM 551
From NORTH OF IH 30
To SH 66
CSJ 1016-01-027
Proj ID STP 2014(766)
Work Type BASE REPAIR, LEVEL UP, OVERLAY
 
2.479 5349450.72 391869.00 713876.95 13.3
Work Order 08-07-14
Work Began 06-15-15
Work Completed  
Time Computed 02-03-15
Contract Working Days 126
Addl Days Granted 0
Working Days Charged 29
Percent Time Used 23
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1016-01-027
DUSTROL, INC.(4.85%)
PREMIER PAVING, LTD. ( 29.61%)
USA SWPPP INSPECTIONS, INC.(1.91%)
FORTSON CONTRACTING, INC.(1.26%)
STRIPING TECHNOLOGY, L.P.(0.71%)
HAYWOOD BAKER(1.24%)
SYNERGY SIGNS & SERVICES, LLC(0.86%)
BRENDA PRICE TRUCKING(1.08%)
Contract # 06143232
Totals 5349450.72 391869.00 713876.95 13.3

CountyCOLLIN
Highway FM 1138
From ROCKWALL COUNTY LINE
To FM 6 IN NEVADA
CSJ 1016-02-017
Proj ID STP 2014(006)HES
Work Type GR, BASE, PVMT, PVMT MKGS, SIGNS
 
4.216 3337173.45 0.00 2921883.05 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-04-13
Work Began 03-12-14
Work Completed 05-28-15
Time Computed 02-02-14
Contract Working Days 160
Addl Days Granted 0
Working Days Charged 195
Percent Time Used 121
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1016-02-017
FORTSON CONTRACTING, INC.(0.17%)
ENVIRONMENTAL STANDARDS, INC.(3.91%)
ALTUS TRAFFIC MANAGEMENT LLC (0.37%)
DUSTROL, INC.(2.74%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.85%)
J & M CONTRACTING, COMPANY ( 19.06%)
MARCOM"S MOWING SERVICE, LLC (1.36%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(3.49%)
Contract # 09133215
Totals 3337173.45 0.00 2921883.05 100.0

CountyDALLAS
Highway FM 1382
From NEW CLARK ROAD
To WEST OF STRAUS RD IN CEDAR HILL
CSJ 1047-03-063
Proj ID C 1047-3-63
Work Type INTERSECTION IMPROVEMENTS
 
0.493 1893193.60 119.00 1432118.51 75.6
Work Order 01-06-14
Work Began 02-26-14
Work Completed  
Time Computed 01-22-14
Contract Working Days 300
Addl Days Granted 8
Working Days Charged 299
Percent Time Used 97
Contractor(s)
CD BUILDERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1047-03-063
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(7.09%)
ODUM SERVICES, L.P.(0.39%)
SIEMENS INDUSTRY, INC. (2.95%)
USA EROSION, INC.(1.02%)
TOTAL HIGHWAY MAINTENANCE, LLC (2.17%)
MELS ELECTRIC, L.P.(2.98%)
ALLIANCE GEOTECHNICAL GROUP(0.20%)
GLL CORPORATION DBA MG TRUCKING(3.30%)
W.O.E. CONSTRUCTION(0.82%)
Contract # 11133021
Totals 1893193.60 119.00 1432118.51 75.6

CountyELLIS
Highway FM 664
From NORTH OF US 287
To SOUTH OF RED OAK CREEK IN OVILLA
CSJ 1051-01-042
Proj ID STP 2015(654)
Work Type ADD 3 - FOOT PAVED SHOULDERS
 
7.303 11142221.20 0.00 75000.00 0.6
Work Order 04-20-15
Work Began 06-22-15
Work Completed  
Time Computed 05-21-15
Contract Working Days 293
Addl Days Granted 0
Working Days Charged 4
Percent Time Used 1
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1051-01-042
BROCK ENVIRONMENTAL SERVICES, LLC(0.31%)
CROSSROADS, L.P. (0.48%)
DUSTROL, INC.(1.95%)
STRIPING TECHNOLOGY, L.P.(0.63%)
PEACHTREE CONSTRUCTION, LTD. ( 33.79%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.89%)
JE CASEY, LLC(1.56%)
SYNERGY SIGNS & SERVICES (0.72%)
OSCAR ORDUNO, INC. (2.36%)
BRENDA PRICE TRUCKING(1.09%)
AAA DRILLING FOUNDATION CO., INC.(0.32%)
FORTSON CONTRACTING, INC.(0.58%)
Contract # 03153213
Totals 11142221.20 0.00 75000.00 0.6

CountyELLIS
Highway FM 876
From AT BIG ONION CREEK
To .
CSJ 1051-02-017
Proj ID BR 2015(591)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.255 1721378.55 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-03-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 360
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MASSANA CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 1051-02-017
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02153207
Totals 1721378.55 0.00 0.00 0.0

CountyTARRANT
Highway IH 30
From 0.5 MILES WEST OF N. FIELDER ROAD
To DALLAS/TARRANT COUNTY LINE
CSJ 1068-02-135
Proj ID C 1068-2-135
Work Type ITS, ETC, SIGNS
 
6.091 6960302.24 39983.54 5238426.42 75.2
CountyDALLAS
Highway IH 30
From TARRANT/DALLAS COUNTY LINE
To SYLVAN AVE.
CSJ 1068-04-147
Proj ID IM 0305(082)
Work Type STR, GR, PVMT, PVMT MKGS, SIGNS, ITS
 
12.664 56121468.07 2401189.01 47409594.16 84.4
Work Order 02-28-13
Work Began 03-25-13
Work Completed  
Time Computed 03-16-13
Contract Working Days 728
Addl Days Granted 16
Working Days Charged 684
Percent Time Used 91
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 1068-04-147
COWTOWN TRAFFIC CONTROL, INC.(0.04%)
THE ANCHOR GROUP, INC. (0.02%)
ANTIGO CONSTRUCTION, INC.(0.02%)
DUSTROL, INC.(0.33%)
DUSTIN ALLEN, INC. (0.41%)
HOUSTON SAWING & DRILLING(0.02%)
GUIDO CONSTRUCTION, INC. DBA GUIDO"S TRUCKS(0.09%)
PENHALL COMPANY(0.06%)
STORM WATER MANAGEMENT, INC. (0.13%)
VSTRUCTURAL LLC(0.42%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.12%)
W.O.E. CONSTRUCTION(0.64%)
STRIPING TECHNOLOGY, L.P.(2.08%)
MICA CORPORATION ( 19.67%)
W. W. FOUNDATION DRILLING, LTD.(2.65%)
K & S UTILITY CONTRACTORS, INC.(4.66%)
INDUS CONSTRUCTION, L.P. (0.56%)
PRESSURE CLEANING SERVICE, INC. DBA WATERBLASTING.COM(0.06%)
RAMBO CONTRACTING, INC.(1.19%)
NORTH TEXAS REBAR, LLC (0.00%)
HERDEZ TRUCKING, INC.(0.09%)
J.H. PAINTING COMPANY(0.41%)
MCL CONTRACTING, LLC (0.09%)
CB SERVICES, INC.(0.06%)
Contract # 12123201
Totals 63081770.31 2441172.55 52648020.58 83.4

CountyDALLAS
Highway IH 30
From BELT LINE RD. IN GRAND PRAIRIE
To N.E. 15TH ST.
CSJ 1068-04-142
Proj ID STP 2011(706)MM
Work Type GR, STR, PVMT, SIGNS, BUILDING
 
0.767 7282375.53 0.00 9620575.01 100.0
CountyDALLAS
Highway IH 30
From BELT LINE RD.
To MACARTHUR BLVD.
CSJ 1068-04-145
Proj ID C 1068-4-145
Work Type GR, STR, PVMT, SIGNS
 
2.060 7497722.23 0.00 7581597.40 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-15-11
Work Began 04-22-11
Work Completed 12-22-14
Time Computed 04-16-11
Contract Working Days 491
Addl Days Granted 219
Working Days Charged 686
Percent Time Used 96
Contractor(s)
HAYDON BUILDING CORP.
SUBCONTRACTOR(S) FOR CCSJ: 1068-04-142
DUSTROL, INC. (ROANOKE)(0.09%)
FORTSON CONTRACTING, INC.(0.81%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(5.65%)
BUYERS BARRICADES, INC.(0.04%)
THE ANCHOR GROUP, INC. (0.38%)
CONCRETE CUTTING BY BOND (0.06%)
COWTOWN TRAFFIC CONTROL, INC.(0.19%)
FARR FOUNDATION, INC.(6.20%)
GK CONSTRUCTION, LLC (0.66%)
C.T. AND S. METALWORKS, INC. (1.72%)
CENTRAL NORTH CONSTRUCTION, LLC(2.17%)
STAR OPERATIONS, INC.(3.43%)
MCMAHON CONTRACTING, L.P.( 20.81%)
STRIPE-A-ZONE, INC.(0.61%)
ALLIANCE GEOTECHNICAL GROUP(0.15%)
PIBURN & CARSON, LLC (0.50%)
FOUNDATION DRILLERS, INC.(0.15%)
COWBOY TRUCKING(0.13%)
RMI WORLDWIDE, LLC (0.05%)
LONE STAR HIGHWAY PRODUCTS, INC. (2.50%)
USA SWPPP INSPECTIONS, INC.(0.45%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.02%)
SUPREME SAWING AND SEALING (0.24%)
J.L. STEEL REINFORCING, LLC(0.09%)
W.O.E. CONSTRUCTION(0.05%)
L & E HART ENTERPRISES, INC. (2.20%)
STORM WATER MANAGEMENT, INC. (0.03%)
SCOTT DERR PAINTING CO, LLC(0.12%)
STRAIGHT LINE SAWING & SEALING (0.14%)
UTILITY AND ENVIRONMENTAL SERVICES, INCORPORATED (0.10%)
Contract # 12103201
Totals 14780097.76 0.00 17202172.41 100.0

CountyDALLAS
Highway IH 30
From COCKRELL HILL ROAD
To WESTMORELAND RD IN DALLAS
CSJ 1068-04-154
Proj ID C 1068-4-154
Work Type GRADING, PAVEMENT, SIGNS, PVMT MKGS
 
2.704 9814841.51 89035.45 2590283.51 26.3
Work Order 09-09-14
Work Began 11-11-14
Work Completed  
Time Computed 09-25-14
Contract Working Days 321
Addl Days Granted 0
Working Days Charged 196
Percent Time Used 61
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 1068-04-154
K & S UTILITY CONTRACTORS, INC.(9.08%)
OSCAR ORDUNO, INC. (4.26%)
STORM WATER MANAGEMENT, INC. (0.29%)
SLATON BROTHERS, INC.(4.57%)
Contract # 07143214
Totals 9814841.51 89035.45 2590283.51 26.3

CountyKAUFMAN
Highway FM 740
From RANCH ROAD IN FORNEY
To ROCKWALL COUNTY LINE
CSJ 1091-01-019
Proj ID STP 2013(318)
Work Type GR, BASE, PVMT, HMAC, PVMT MKGS, SI
 
6.023 5599999.92 198101.97 6582135.97 99.9
Work Order 06-20-13
Work Began 07-25-13
Work Completed  
Time Computed 07-06-13
Contract Working Days 210
Addl Days Granted 89
Working Days Charged 298
Percent Time Used 99
Contractor(s)
WESTFIELD INSURANCE GROUP
SUBCONTRACTOR(S) FOR CCSJ: 1091-01-019
PEACHTREE CONSTRUCTION, LTD. ( 39.38%)
HIGHWAY 19 CONSTRUCTION, LLC (8.06%)
TEXAS HIGHWAY MAINTENANCE, LLC (1.20%)
USA SWPPP INSPECTIONS, INC.(2.50%)
DUSTROL, INC.(3.13%)
INTEGRATED ROADWAY SERVICES, INC.(2.53%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.40%)
PEACHTREE CONSTRUCTION, LTD. ( 39.68%)
TOTAL HIGHWAY MAINTENANCE, LLC (2.69%)
USA SWPPP INSPECTIONS, INC.(1.15%)
DUSTROL, INC.(1.91%)
FORTSON CONTRACTING, INC.(0.97%)
BRENDA PRICE TRUCKING(2.54%)
FANNIN TREE FARM, LTD(0.64%)
MIDWAY STRIPING & SEALCOATING(0.07%)
Contract # 04133223
Totals 5599999.92 198101.97 6582135.97 99.9

CountyROCKWALL
Highway FM 740 ETC
From AT AMY PARKS ELEMENTARY SCHOOL
To IN CITY OF HEATH
CSJ 1091-04-019
Proj ID STP 1102(212)SRS
Work Type PEDESTRIAN WALKWAY IMPROVEMENTS#2
 
0.982 1049080.05 11268.50 802512.23 100.0
Work Order 12-03-13
Work Began 05-19-14
Work Completed 05-15-15
Time Computed 02-01-14
Contract Working Days 76
Addl Days Granted 0
Working Days Charged 70
Percent Time Used 92
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1091-04-019
BRENDA PRICE TRUCKING(1.20%)
DUSTROL, INC.(0.68%)
LONE STAR MANHOLE & STRUCTURES, LLC(1.79%)
ROAD MASTER STRIPING LLC (0.32%)
USA SWPPP INSPECTIONS, INC.(3.66%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.55%)
Contract # 08133057
Totals 1049080.05 11268.50 802512.23 100.0

CountyKAUFMAN
Highway FM 741
From US 175
To EAST OF FM 548
CSJ 1092-01-017
Proj ID STP 2015(778)
Work Type GR, BASE, ACP OVERLAY, PVMT MKGS
 
7.726 4550316.19 226501.31 1301200.19 28.5
Work Order 03-23-15
Work Began 06-03-15
Work Completed  
Time Computed 04-23-15
Contract Working Days 187
Addl Days Granted 0
Working Days Charged 45
Percent Time Used 24
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1092-01-017
ALTUS TRAFFIC MANAGEMENT LLC (0.26%)
TEXAS ENVIRONMENTAL MANAGEMENT SA, INC.(4.68%)
DUSTROL, INC.(4.57%)
MARCOM"S MOWING SERVICE, LLC (1.16%)
J & M CONTRACTING, COMPANY (7.65%)
STRIPING TECHNOLOGY, L.P.(1.43%)
FORTSON CONTRACTING, INC.(0.60%)
C & J TREE SERVICE (0.03%)
Contract # 02153235
Totals 4550316.19 226501.31 1301200.19 28.5

CountyELLIS
Highway FM 875
From AT WAXAHACHIE CREEK
To .
CSJ 1159-01-022
Proj ID BR 2013(604)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.471 3724841.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 467
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MASSANA CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 1159-01-022
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153025
Totals 3724841.00 0.00 0.00 0.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11