Monthly State Let Construction Report For Dallas District As Of May 10, 2016 Page 8 Of 9

Last Update: Tuesday, May 10, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyDENTON
Highway FM 423
From US 380
To 0.8 MI SOUTH OF FM 2934
CSJ 1315-02-009
Proj ID C 1315-2-9
Work Type WIDEN TO 6 LANE DIVIDED URBAN
 
3.488 29826069.73 658181.23 16123926.34 54.0
Work Order 12-12-13
Work Began 10-08-14
Work Completed  
Time Computed 09-08-14
Contract Working Days 603
Addl Days Granted 0
Working Days Charged 394
Percent Time Used 65
Contractor(s)
MCM
SUBCONTRACTOR(S) FOR CCSJ: 1315-02-009
TOTAL HIGHWAY MAINTENANCE, LLC (0.96%)
STORM WATER MANAGEMENT, INC. (0.28%)
BOWMAN ENGINEERING & CONSULTING, INC.(0.84%)
FORTSON CONTRACTING, INC.(0.09%)
IEA, INC (9.39%)
JAGOE-PUBLIC COMPANY ( 10.82%)
OSCAR ORDUNO, INC. (0.23%)
ROADWAY SOLUTIONS, INC.(4.78%)
ROBERTS TRUCKING (1.98%)
RUSSO CORPORATION(0.55%)
DUSTROL, INC.(0.49%)
W.O.E. CONSTRUCTION(4.50%)
TRANSPORT TRUST(0.96%)
RICHMOND HYDROMULCH AND SEEDING, LLC (0.27%)
Contract # 09133204
Totals 29826069.73 658181.23 16123926.34 54.0

CountyCOLLIN
Highway FM 1378
From 585 SOUTH OF WHITE ROCK CREEK
To NORTH OF WHITE ROCK CREEK
CSJ 1392-01-035
Proj ID BR 2014(872)
Work Type REPL BRIDGE
 
0.526 1788995.75 71335.12 774048.50 43.2
Work Order 10-09-14
Work Began 08-10-15
Work Completed  
Time Computed 04-07-15
Contract Working Days 300
Addl Days Granted 10
Working Days Charged 177
Percent Time Used 57
Contractor(s)
ACCELERATED CRITICAL PATH, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1392-01-035
BREDA COMPANY, INC.(0.40%)
CROSSROADS, L.P. (0.90%)
D & S ENGINEERING LABS (0.45%)
DUSTROL, INC.(2.56%)
FOUNDATION DRILLERS, INC.(0.91%)
CRAIG OLDEN, INC.(1.77%)
LINDAMOOD DEMOLITION, INC. (1.39%)
MCRYAN HAULING, INC. (1.87%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.32%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.08%)
Contract # 07143231
Totals 1788995.75 71335.12 774048.50 43.2

CountyKAUFMAN
Highway FM 1836
From FM 2515
To FM 90
CSJ 1397-01-030
Proj ID STP 2016(289)
Work Type SHLDR WDN, STR EXT, REMX, SC, PAV MRKS
 
6.905 6141935.93 0.00 39032.00 0.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-29-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 218
Addl Days Granted 0
Working Days Charged 1
Percent Time Used 0
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 1397-01-030
PEACHTREE CONSTRUCTION, LTD. (1.77%)
S & S BRIDGE PAINTING, INC.(4.51%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.11%)
TRP CONSTRUCTION GROUP, LLC(1.23%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.55%)
DUSTIN ALLEN, INC. (1.46%)
FARR FOUNDATION, INC.(1.51%)
K & S UTILITY CONTRACTORS, INC.(6.21%)
WITHERS CONSTRUCTION, LLC(0.63%)
ALTUS TRAFFIC MANAGEMENT LLC (0.20%)
CAMBRIDGEMOEN LLC(2.28%)
GIBSON & ASSOCIATES, INC.(1.87%)
Contract # 11153024
Totals 6141935.93 0.00 39032.00 0.6

CountyKAUFMAN
Highway FM 1836
From SH 34
To 0.28 MI EAST OF CR 146
CSJ 1397-01-031
Proj ID C 1397-1-31
Work Type PROVIDE ADDITIONAL PAVED SURFACE
 
4.269 5943147.30 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-01-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 166
Addl Days Granted 0
Working Days Charged 1
Percent Time Used 0
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1397-01-031
ALTUS TRAFFIC MANAGEMENT LLC (0.17%)
ODUM SERVICES, L.P.(1.02%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.55%)
J & M CONTRACTING, COMPANY ( 20.60%)
Contract # 01163240
Totals 5943147.30 0.00 0.00 0.0

CountyELLIS
Highway FM 55
From AT LITTLE ONION CREEK
To .
CSJ 1451-01-020
Proj ID BR 2005(274)
Work Type REPLACE BRIDGES AND APPROACHES
 
0.312 2010620.16 135790.00 278519.91 13.8
Work Order 07-24-15
Work Began 02-18-16
Work Completed  
Time Computed 11-21-15
Contract Working Days 340
Addl Days Granted 0
Working Days Charged 49
Percent Time Used 14
Contractor(s)
IEA INC.
SUBCONTRACTOR(S) FOR CCSJ: 1451-01-020
TEXOP CONSTRUCTION (1.10%)
FORTSON CONTRACTING, INC.(2.27%)
SAN-ANN-CO., INC.(0.96%)
USA EROSION, INC.(4.31%)
STRIPING TECHNOLOGY, L.P.(1.50%)
Contract # 05153220
Totals 2010620.16 135790.00 278519.91 13.8

CountyELLIS
Highway FM 55
From 0.14 MILE SOUTH OF NASH HOWARD RD
To US 77
CSJ 1451-01-023
Proj ID STP 2015(655)HES
Work Type GR, BASE, PVMT, PVMT MKGS, SIGNS
 
5.500 4975101.65 553679.74 3791317.01 76.2
Work Order 05-15-15
Work Began 06-29-15
Work Completed  
Time Computed 06-15-15
Contract Working Days 215
Addl Days Granted 0
Working Days Charged 214
Percent Time Used 99
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 1451-01-023
ALTUS TRAFFIC MANAGEMENT LLC (0.31%)
RAMBO CONTRACTING, INC.(4.29%)
BEAR CREEK CONSTRUCTION, LLC ( 14.22%)
TEXAS ALTERNATIVE GRASSER, INC.(0.62%)
STRIPING TECHNOLOGY, L.P.(0.91%)
SAN-ANN-CO., INC.(0.99%)
FORTSON CONTRACTING, INC.(1.01%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.65%)
SOUTHWEST MAINTENANCE, LTD (0.01%)
Contract # 03153011
Totals 4975101.65 553679.74 3791317.01 76.2

CountyELLIS
Highway FM 55
From SH 34
To 0.14 MI S OF NASH HOWARD RD
CSJ 1451-01-024
Proj ID STP 2014(874)
Work Type GR, BASE, PVMT MKGS, SIGNS
 
5.052 5538628.87 6614.45 4632730.13 85.7
Work Order 10-02-14
Work Began 12-01-14
Work Completed  
Time Computed 10-18-14
Contract Working Days 263
Addl Days Granted 0
Working Days Charged 366
Percent Time Used 139
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1451-01-024
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(3.86%)
STRIPING TECHNOLOGY, L.P.(0.83%)
SAN-ANN-CO., INC.(1.01%)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.(0.25%)
FORTSON CONTRACTING, INC.(3.25%)
OLDEN, INC.(5.14%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.49%)
Contract # 07143018
Totals 5538628.87 6614.45 4632730.13 85.7

CountyELLIS
Highway FM 55
From AT BIG ONION CREEK
To .
CSJ 1451-01-025
Proj ID BR 1502(533)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.135 1530409.40 0.00 4560.51 0.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-28-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 183
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
IEA INC.
SUBCONTRACTOR(S) FOR CCSJ: 1451-01-025
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08153020
Totals 1530409.40 0.00 4560.51 0.2

CountyKAUFMAN
Highway FM 1565
From FM 986
To HUNT COUNTY LINE
CSJ 1494-02-008
Proj ID STP 2015(485)
Work Type GR, BASE, ACP OVERLAY, PVMT MKGS
 
1.623 1652146.23 58631.66 745258.06 45.1
Work Order 03-02-15
Work Began 04-09-15
Work Completed  
Time Computed 03-18-15
Contract Working Days 159
Addl Days Granted 6
Working Days Charged 118
Percent Time Used 71
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1494-02-008
J & M CONTRACTING, COMPANY ( 15.62%)
STRIPING TECHNOLOGY, L.P.(1.25%)
GJ SEEDING, LLC(4.19%)
LONE STAR BARRIER SERVICES, LLC(1.14%)
ALTUS TRAFFIC MANAGEMENT LLC (0.56%)
C & J TREE SERVICE (0.18%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.63%)
Contract # 01153215
Totals 1652146.23 58631.66 745258.06 45.1

CountyKAUFMAN
Highway FM 3486
From FM 986
To SH 34
CSJ 1494-03-001
Proj ID C 1494-3-1
Work Type GR, STRS, BASE & SURF
 
2.490 4849821.37 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 168
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1494-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04163222
Totals 4849821.37 0.00 0.00 0.0

CountyDENTON
Highway FM 720
From AT HARTS BRANCH
To .
CSJ 1567-01-021
Proj ID BR 2010(983)
Work Type REPL BR & APPRS
 
0.080 1726268.66 0.00 1650996.63 95.6
CountyDENTON
Highway FM 720
From AT LITTLE ELM CREEK BRANCH OF LAKE
To LEWISVILLE
CSJ 1567-01-022
Proj ID BR 2010(983)
Work Type REPL BR & APPRS
 
0.484 15758790.61 0.00 15876178.12 99.9
CountyDENTON
Highway FM 720
From 0.2 MI W OF GARZA LANE (W OF LAKE L
To 0.1 MI WEST OF FM 423
CSJ 1567-01-029
Proj ID STP 2010(982)MM
Work Type GRADING, STR, PVMT, SIGNS
 
4.493 33538923.64 38389.35 36944080.43 99.9
CountyDENTON
Highway FM 720
From 0.2 MILE WEST OF GARZA LANE
To 0.1 MILE WEST OF FM 423
CSJ 1567-01-032
Proj ID RW 1567-1-32
Work Type ROW ACQ. AND UTIL. ADJUST.
 
0.001 3297279.80 0.00 460852.58 13.9
Work Order 09-13-10
Work Began 07-14-11
Work Completed  
Time Computed 03-12-11
Contract Working Days 577
Addl Days Granted 197
Working Days Charged 774
Percent Time Used 100
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 1567-01-029
ATS DRILLING, L.P. (5.77%)
BRENDA PRICE TRUCKING(0.22%)
CRAIG OLDEN, INC.(0.61%)
DALLAS LITE AND BARRICADE INC. (0.11%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.21%)
HIGHWAY TECHNOLOGIES, INC. (0.31%)
L & E HART ENTERPRISES, INC. (2.09%)
MICA CORPORATION (4.78%)
NORTH TEXAS REBAR, LLC (5.54%)
PENHALL COMPANY(0.05%)
RAMBO CONTRACTING, INC.(2.62%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(6.26%)
S & V CONSTRUCTION LLC (0.05%)
SOUTH TEXAS PAINTING COMPANY (0.15%)
STORM WATER MANAGEMENT, INC. (0.10%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.28%)
TEX OP CONSTRUCTION, LP(0.99%)
WEIR BROS.,INC.(5.19%)
GREAT WESTERN ERECTORS (0.12%)
DURABLE SPECIALTIES, INC.(1.39%)
LAYFIELD CONSTRUCTION, INC (0.01%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.36%)
GREAT WESTERN ERECTORS (0.49%)
HAVEN LANDSCAPING & IRRIGATION, INC. (0.50%)
Contract # 07103001
Totals 54321262.71 38389.35 54932107.76 99.9

CountyDENTON
Highway FM 720
From ELDORADO PKWY (FM 720)
To SOUTH OF MARTOP
CSJ 1567-01-025
Proj ID C 1567-1-25
Work Type GR, STRS & PVT
 
2.565 15597320.25 351726.14 2450374.11 15.7
Work Order 04-11-14
Work Began 10-26-15
Work Completed  
Time Computed 01-06-15
Contract Working Days 420
Addl Days Granted 0
Working Days Charged 111
Percent Time Used 26
Contractor(s)
HAYDON BUILDING CORP.
SUBCONTRACTOR(S) FOR CCSJ: 1567-01-025
S & S BRIDGE PAINTING, INC.(0.02%)
C.T. AND S. METALWORKS, INC. (0.11%)
ACU CONSTRUCTION LLC (0.69%)
W.O.E. CONSTRUCTION(1.22%)
BREDA COMPANY, INC.(0.99%)
USA SWPPP INSPECTIONS, INC.(1.99%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.04%)
FORTSON CONTRACTING, INC.(0.02%)
DURABLE SPECIALTIES, INC.(1.69%)
MARCOM"S MOWING SERVICE, LLC (0.10%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY( 15.66%)
DALLAS LITE AND BARRICADE INC. (0.66%)
THELIN RECYCLING COMPANY, L.P. (0.21%)
A.E.A. TRANSPORTATION(0.21%)
Contract # 02143001
Totals 15597320.25 351726.14 2450374.11 15.7

CountyDENTON
Highway FM 423
From STEWARTS CREEK ROAD
To SH 121
CSJ 1567-02-032
Proj ID C 1567-2-32
Work Type WIDEN TO 6 LANE DIVIDED URBAN
 
3.761 49691109.92 738638.14 20748725.60 41.7
CountyDENTON
Highway FM 423
From STEWARTS CREEK ROAD
To SH 121
CSJ 1567-02-033
Proj ID RW 1567-2-33
Work Type ADJUSTMENT OF UTILITIES
 
3.761 8252384.38 185249.82 5858619.02 70.9
Work Order 08-27-14
Work Began 10-20-14
Work Completed  
Time Computed 09-12-14
Contract Working Days 756
Addl Days Granted 0
Working Days Charged 401
Percent Time Used 53
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1567-02-032
ATS DRILLING, INC. (1.12%)
C.T. AND S. METALWORKS, INC. (0.32%)
DUSTROL, INC.(0.52%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.08%)
HOUSTON SAWING & DRILLING(0.00%)
LANDSCAPE CONTRACTING AND IRRIGATION, INC. (0.31%)
MEL"S ELECTRIC SERVICE, INC. (6.02%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(8.40%)
DALLAS LITE AND BARRICADE INC. (0.14%)
SCOTT DERR PAINTING CO, LLC(0.66%)
STORM WATER MANAGEMENT, INC. (0.14%)
STRIPING TECHNOLOGY, L.P.(0.73%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.13%)
WEST TEXAS REBAR PLACERS INC.(0.35%)
W.O.E. CONSTRUCTION(4.60%)
MCL CONTRACTING, LLC (0.06%)
BORE COMPANY (2.11%)
GUIDO CONSTRUCTION, INC. DBA GUIDO"S TRUCKS(0.19%)
TEXAS STAR TRANSPORT, LP (0.69%)
INDUS CONSTRUCTION, L.P. (4.75%)
FORTSON CONTRACTING, INC.(0.09%)
ACTION CONSTRUCTORS(0.54%)
SYNERGY SIGNS & SERVICES, LLC(0.11%)
RICE TUNNELING & BORING, INC.(0.15%)
HIGH QUALITY ELECTRIC(0.04%)
ALLIED DRILLING COMPANY(0.08%)
TOMAS REYES TRUCKING, INC. (0.68%)
ROAD MAKER CONTRACTORS (0.44%)
PANIOLO CONSTRUCTION SERVICES, LLC (0.40%)
DALE BROWN, INC. (0.15%)
URBAN INFRACONSTRUCTION, LLC (0.14%)
Contract # 05143001
Totals 57943494.30 923887.96 26607344.62 45.9

CountyDENTON
Highway FM 407
From FM 1830
To JETER RD
CSJ 1785-01-035
Proj ID STP 1502(498)
Work Type LANDSCAPE DEVELOPMENT
 
9.160 498172.50 43704.90 80904.90 16.2
Work Order 11-02-15
Work Began 12-07-15
Work Completed  
Time Computed 12-07-15
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 93
Percent Time Used 62
Contractor(s)
C. GREEN SCAPING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 1785-01-035
RICE TUNNELING & BORING, INC.(2.10%)
Contract # 07153027
Totals 498172.50 43704.90 80904.90 16.2

CountyCOLLIN
Highway FM 2551
From FM 544
To FM 2514 (PARKER ROAD)
CSJ 2056-01-048
Proj ID STP 2015(223)
Work Type LANDSCAPE DEVELOPMENT
 
3.090 373099.80 77658.52 401338.08 99.9
Work Order 11-18-14
Work Began 10-14-15
Work Completed  
Time Computed 12-04-14
Contract Working Days 91
Addl Days Granted 0
Working Days Charged 91
Percent Time Used 100
Contractor(s)
LANDSCAPE CONTRACTING AND IRRIGATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2056-01-048
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC(1.66%)
AQUA BORE(6.22%)
MCBRIDE ELECTRIC, INC. (1.59%)
Contract # 10143017
Totals 373099.80 77658.52 401338.08 99.9

CountyDENTON
Highway LP 288
From IH 35
To US 377 / US 380
CSJ 2250-02-016
Proj ID STP 2014(661)
Work Type FULL DEPTH CONCRETE PAVEMENT REPAIR
 
6.722 3653118.00 190900.89 3486417.24 96.2
Work Order 06-30-14
Work Began 10-06-14
Work Completed  
Time Computed 08-29-14
Contract Working Days 210
Addl Days Granted 26
Working Days Charged 266
Percent Time Used 112
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2250-02-016
ALTUS TRAFFIC MANAGEMENT LLC (0.47%)
BRENDA PRICE TRUCKING(6.28%)
PEACHTREE CONSTRUCTION, LTD. (3.78%)
STRAIGHT LINE SAWING & SEALING (5.96%)
STRIPING TECHNOLOGY, L.P.(1.01%)
ACU CONSTRUCTION LLC (0.44%)
USA EROSION, INC.(0.36%)
Contract # 05143209
Totals 3653118.00 190900.89 3486417.24 96.2

CountyDALLAS
Highway IH 635
From WEST OF IH 35E
To IH 35E
CSJ 2374-01-172
Proj ID CM 2015(849)
Work Type ITS INSTALLATION
 
8.634 3126590.32 302090.91 2809664.36 89.8
Work Order 05-14-15
Work Began 08-24-15
Work Completed  
Time Computed 08-13-15
Contract Working Days 162
Addl Days Granted 0
Working Days Charged 145
Percent Time Used 89
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2374-01-172
ALTUS TRAFFIC MANAGEMENT LLC (0.29%)
INTEGRATED ROADWAY SERVICES, INC.( 37.74%)
NETWORK CABLING SERVICES, INC. (7.18%)
N.L. SCHUTTE FOUNDATION DRILLING, INC. (0.14%)
TX DOWN UNDER CONSTRUCTION LLC (2.57%)
QUAD `A` CONSTRUCTION(1.48%)
Contract # 04153042
Totals 3126590.32 302090.91 2809664.36 89.8

CountyDALLAS
Highway IH 635
From WEST OF US 75
To KCS RR
CSJ 2374-01-176
Proj ID CM 2015(593)
Work Type TOLL GANTRIES; SIGNS
 
8.901 3115183.14 280071.70 2600332.98 83.4
CountyDALLAS
Highway IH 635
From CENTERVILLE RD
To LA PRADA
CSJ 2374-02-139
Proj ID STP 2015(594)
Work Type NOISE WALL
 
1.104 3648098.25 152328.20 1866451.38 51.1
Work Order 04-24-15
Work Began 06-01-15
Work Completed  
Time Computed 05-10-15
Contract Working Days 267
Addl Days Granted 0
Working Days Charged 238
Percent Time Used 89
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 2374-01-176
BUYERS BARRICADES, INC.(0.42%)
WYLIE DRILLING & DRAINAGE, INC.(6.09%)
LAYFIELD CONSTRUCTION, INC (0.25%)
USA SWPPP INSPECTIONS, INC.(2.74%)
RG PAINTING(0.56%)
STRIPE-A-ZONE, INC.(0.25%)
HERDEZ TRUCKING, INC.(0.12%)
UNDER CONSTRUCTION INC.(0.17%)
MCL CONTRACTING, LLC (3.04%)
HIGHWAY INTELLIGENT TRAFFIC SYSTEMS, INC ( 20.98%)
DALLAS LIGHT & BARRICADES(1.37%)
THE RIOS GROUP, INC. (0.21%)
PENHALL COMPANY(0.01%)
UNION ELECTRICAL CONTRACTOR, INC.(2.04%)
G & B COMMUNICATIONS, INC. (1.97%)
TX DOWN UNDER CONSTRUCTION LLC (0.39%)
CARRASCO TRUCKING(0.02%)
PANIOLO CONSTRUCTION SERVICES, LLC (3.74%)
HICKS LIGHTNING PROTECTION (0.41%)
SHERON STONE DBA DOUBLE-S CONSTRUCTION (0.03%)
Contract # 02153202
Totals 6763281.39 432399.90 4466784.36 66.0

CountyDALLAS
Highway IH 635
From IH 20
To IH 30
CSJ 2374-02-136
Proj ID CM 1402(030)
Work Type FULL ITS
 
14.781 6594770.84 82643.60 5417966.74 82.1
Work Order 01-02-15
Work Began 04-07-15
Work Completed  
Time Computed 04-02-15
Contract Working Days 240
Addl Days Granted 0
Working Days Charged 195
Percent Time Used 81
Contractor(s)
MICA CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 2374-02-136
LAYFIELD CONSTRUCTION, INC (0.23%)
KLP COMMERCIAL, LLC(3.94%)
DYNAMIC VISION CO., INC. (0.09%)
BUYERS BARRICADES, INC.(1.42%)
BOWMAN ENGINEERING & CONSTRUCTION, INC.(0.07%)
Contract # 08143229
Totals 6594770.84 82643.60 5417966.74 82.1

CountyDALLAS
Highway IH 20
From AT IH 45 RAMP FROM EB IH 20
To NB IH 45
CSJ 2374-03-057
Proj ID IM 0205(151)
Work Type ADD LANE TO DIRECT CONNECTION RAMP
 
1.418 5699998.00 62087.80 7905058.67 99.9
Work Order 10-07-11
Work Began 01-12-12
Work Completed  
Time Computed 12-06-11
Contract Working Days 471
Addl Days Granted 142
Working Days Charged 650
Percent Time Used 106
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 2374-03-057
ALLIANCE GEOTECHNICAL GROUP(0.86%)
AXIS CONTRACTING, INC. (1.14%)
BREDA COMPANY, INC.(0.96%)
BROCK ENVIRONMENTAL, LLC (0.71%)
CONCRETE CUTTING BY BOND (0.26%)
DUSTIN ALLEN, INC. (1.41%)
DUSTROL, INC.(0.87%)
FOUNDATION DRILLERS, INC.(1.05%)
HIGHWAY TECHNOLOGIES, INC. (0.55%)
LANDSCAPE CONTRACTING AND IRRIGATION, INC. (1.12%)
MELS ELECTRIC, L.P.(0.34%)
STRIPING TECHNOLOGY, L.P.(0.93%)
GREAT WESTERN ERECTORS (0.06%)
ERWIN STEEL WORKS, LLC (0.11%)
RG PAINTING(0.39%)
MAGNUM SAWING(0.34%)
D & D STUD WELDING (0.17%)
GIBSON & ASSOCIATES, INC.( 12.15%)
INDUS CONSTRUCTION, L.P. (0.39%)
Contract # 08113245
Totals 5699998.00 62087.80 7905058.67 99.9