Monthly State Let Construction Report For Dallas District As Of Apr 10, 2015 Page 8 Of 9

Last Update: Friday, April 10, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyELLIS
Highway FM 879
From AT BRANCH OF MUSTANG CREEK
To .
CSJ 1159-02-031
Proj ID BR 2013(832)
Work Type REPLACE BR & APPRS
 
0.134 889807.76 0.00 682210.08 78.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-24-13
Work Began 01-15-14
Work Completed  
Time Computed 12-23-13
Contract Working Days 245
Addl Days Granted 0
Working Days Charged 275
Percent Time Used 112
Contractor(s)
RAGLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1159-02-031
FORTSON CONTRACTING, INC.(2.52%)
HOUSTON SAWING & DRILLING(0.33%)
MCL CONTRACTING, LLC (1.05%)
ALTUS TRAFFIC MANAGEMENT LLC (1.05%)
PEACHTREE CONSTRUCTION, LTD. (5.55%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.38%)
STORM WATER MANAGEMENT, INC. (1.03%)
STRIPING TECHNOLOGY, L.P.(1.46%)
W.O.E. CONSTRUCTION(0.13%)
MCL CONTRACTING, LLC (0.23%)
Contract # 07133013
Totals 889807.76 0.00 682210.08 78.7

CountyELLIS
Highway FM 984
From AT DRAW, 1.7 MI SOUTH OF SH 34
To .
CSJ 1211-01-018
Proj ID BR 2015(483)
Work Type REPL BR AND APPR
 
0.117 879623.40 0.00 0.00 0.0
CountyELLIS
Highway FM 984
From AT ONION CREEK RELIEF #1 AND #2
To .
CSJ 1211-01-019
Proj ID BR 2015(484)
Work Type REPL BR
 
0.156 1453823.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-02-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 379
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
IEA INC.
SUBCONTRACTOR(S) FOR CCSJ: 1211-01-018
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01153012
Totals 2333446.90 0.00 0.00 0.0

CountyDENTON
Highway FM 1171
From WEST OF US 377
To WEST OF SHILOH RD
CSJ 1311-01-034
Proj ID C 1311-1-34
Work Type GR, STRS, BASE, CRCP, PVMT MKGS, SIGNS
 
7.011 45721253.16 1280291.09 15712699.60 34.3
Work Order 06-05-13
Work Began 06-02-14
Work Completed  
Time Computed 03-02-14
Contract Working Days 693
Addl Days Granted 0
Working Days Charged 202
Percent Time Used 29
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1311-01-034
BREDA COMPANY, INC.(0.96%)
BUYERS BARRICADES, INC.(0.20%)
CINTEREX US, INC.(1.17%)
CLLA GROUP, LLC(9.39%)
DUSTROL, INC.(0.30%)
INTEGRATED ROADWAY SERVICES, INC.(2.34%)
JAGOE-PUBLIC COMPANY ( 14.10%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (2.74%)
THELIN RECYCLING COMPANY, L.P. (0.16%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.10%)
W.O.E. CONSTRUCTION(0.28%)
WYLIE DRILLING & DRAINAGE, INC.(0.83%)
VENUS CONSTRUCTION (7.23%)
GUIDO CONSTRUCTION, INC. DBA GUIDO"S TRUCKS(0.35%)
SLATON BROTHERS, INC.(0.58%)
CB SERVICES, INC.(0.10%)
Contract # 03133002
Totals 45721253.16 1280291.09 15712699.60 34.3

CountyDENTON
Highway FM 1385
From US 380
To APPROX. 2 MILES NORTH OF FM 428
CSJ 1315-01-025
Proj ID STP 1402(028)HES
Work Type GR, BASE, PVMT, PVMT MKGS, SIGNS
 
7.588 9063184.19 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-10-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 378
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 1315-01-025
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143208
Totals 9063184.19 0.00 0.00 0.0

CountyDENTON
Highway FM 423
From US 380
To 0.8 MI SOUTH OF FM 2934
CSJ 1315-02-009
Proj ID C 1315-2-9
Work Type WIDEN TO 6 LANE DIVIDED URBAN
 
3.488 29826069.73 291284.53 4549089.01 15.2
Work Order 12-12-13
Work Began 10-08-14
Work Completed  
Time Computed 09-08-14
Contract Working Days 603
Addl Days Granted 0
Working Days Charged 116
Percent Time Used 19
Contractor(s)
MCM
SUBCONTRACTOR(S) FOR CCSJ: 1315-02-009
TOTAL HIGHWAY MAINTENANCE, LLC (0.96%)
STORM WATER MANAGEMENT, INC. (0.28%)
BOWMAN ENGINEERING & CONSULTING, INC.(0.84%)
FORTSON CONTRACTING, INC.(0.09%)
IEA, INC (9.39%)
JAGOE-PUBLIC COMPANY ( 10.82%)
OSCAR ORDUNO, INC. (0.23%)
ROADWAY SOLUTIONS, INC.(4.78%)
ROBERTS TRUCKING (1.98%)
RUSSO CORPORATION(0.55%)
DUSTROL, INC.(0.49%)
W.O.E. CONSTRUCTION(4.50%)
Contract # 09133204
Totals 29826069.73 291284.53 4549089.01 15.2

CountyCOLLIN
Highway FM 1378
From 585 SOUTH OF WHITE ROCK CREEK
To NORTH OF WHITE ROCK CREEK
CSJ 1392-01-035
Proj ID BR 2014(872)
Work Type REPL BRIDGE
 
0.526 1788995.75 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-09-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 300
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ACCELERATED CRITICAL PATH, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1392-01-035
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143231
Totals 1788995.75 0.00 0.00 0.0

CountyCOLLIN
Highway FM 1378
From FM 2514
To 0.2 MILE SOUTH OF FOREST GROVE RD
CSJ 1392-01-040
Proj ID STP 2015(395)
Work Type BASE REPAIR AND OVERLAY
 
6.057 2696578.78 0.00 0.00 0.0
Work Order 02-13-15
Work Began 03-30-15
Work Completed  
Time Computed 03-01-15
Contract Working Days 192
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1392-01-040
WOLFE CONSTRUCTION GROUP, INC. (0.43%)
OLDEN, INC.(1.50%)
K & S UTILITY CONTRACTORS, INC.(3.09%)
ALTUS TRAFFIC MANAGEMENT LLC (0.59%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.52%)
TRP CONSTRUCTION GROUP, LLC(2.30%)
BROCK ENVIRONMENTAL, LLC (0.92%)
TRANSPORT TRUST(0.00%)
DUSTROL, INC.(8.19%)
COWBELL TRAFFIC SERVICE, INC.(0.22%)
DURABLE SPECIALTIES, INC.(0.58%)
Contract # 12143007
Totals 2696578.78 0.00 0.00 0.0

CountyELLIS
Highway FM 1387
From WEST OF KENSINGTON DR
To EAST OF WALNUT GROVE RD
CSJ 1394-02-023
Proj ID CC 1394-2-23
Work Type GRADING, PAVING, STRUCTURES, SIGNS
 
0.925 4091255.00 25636.75 3604314.44 89.8
Work Order 08-06-13
Work Began 10-16-13
Work Completed  
Time Computed 10-05-13
Contract Working Days 309
Addl Days Granted 0
Working Days Charged 381
Percent Time Used 123
Contractor(s)
TISEO PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 1394-02-023
BROCK ENVIRONMENTAL, LLC (1.34%)
MEL"S ELECTRIC SERVICE, INC. (3.36%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY( 16.40%)
RPM XCONSTRUCTION, LLC (8.29%)
STRIPING TECHNOLOGY, L.P.(1.65%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (6.50%)
DALLAS LITE AND BARRICADE INC. (0.65%)
DUSTROL, INC.(0.91%)
CROSSROADS, L.P. (0.37%)
T-BAR FENCE, INC.(0.09%)
W.O.E. CONSTRUCTION(7.41%)
FOUR STAR EXCAVATING INC (9.19%)
INLET STRUCTURE SPECIALTIES LTD. (1.66%)
IRON CONCRETE CONSTRUCTION COMPANY, INC. (1.66%)
J.R. STEEL TIE (0.83%)
Contract # 04133010
Totals 4091255.00 25636.75 3604314.44 89.8

CountyELLIS
Highway FM 55
From 0.14 MILE SOUTH OF NASH HOWARD RD
To US 77
CSJ 1451-01-023
Proj ID STP 2015(655)HES
Work Type GR, BASE, PVMT, PVMT MKGS, SIGNS
 
5.500 4975101.65 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 215
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 1451-01-023
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03153011
Totals 4975101.65 0.00 0.00 0.0

CountyELLIS
Highway FM 55
From SH 34
To 0.14 MI S OF NASH HOWARD RD
CSJ 1451-01-024
Proj ID STP 2014(874)
Work Type GR, BASE, PVMT MKGS, SIGNS
 
5.052 5538628.87 239726.38 1091239.58 19.7
Work Order 10-02-14
Work Began 12-01-14
Work Completed  
Time Computed 10-18-14
Contract Working Days 263
Addl Days Granted 0
Working Days Charged 82
Percent Time Used 31
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1451-01-024
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(3.86%)
STRIPING TECHNOLOGY, L.P.(0.83%)
SAN-ANN-CO., INC.(1.01%)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.(0.25%)
FORTSON CONTRACTING, INC.(3.25%)
OLDEN, INC.(5.14%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.49%)
Contract # 07143018
Totals 5538628.87 239726.38 1091239.58 19.7

CountyKAUFMAN
Highway FM 1565
From FM 986
To HUNT COUNTY LINE
CSJ 1494-02-008
Proj ID STP 2015(485)
Work Type GR, BASE, ACP OVERLAY, PVMT MKGS
 
1.623 1652146.23 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-02-15
Work Began 04-09-15
Work Completed  
Time Computed 03-18-15
Contract Working Days 159
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1494-02-008
J & M CONTRACTING, COMPANY ( 15.62%)
STRIPING TECHNOLOGY, L.P.(1.25%)
GJ SEEDING, LLC(4.19%)
LONE STAR BARRIER SERVICES, LLC(1.14%)
ALTUS TRAFFIC MANAGEMENT LLC (0.56%)
Contract # 01153215
Totals 1652146.23 0.00 0.00 0.0

CountyDENTON
Highway FM 720
From AT HARTS BRANCH
To .
CSJ 1567-01-021
Proj ID BR 2010(983)
Work Type REPL BR & APPRS
 
0.080 1726268.66 22695.08 1594725.05 92.3
CountyDENTON
Highway FM 720
From AT LITTLE ELM CREEK BRANCH OF LAKE
To LEWISVILLE
CSJ 1567-01-022
Proj ID BR 2010(983)
Work Type REPL BR & APPRS
 
0.484 15758790.61 42816.58 15709577.45 99.6
CountyDENTON
Highway FM 720
From 0.2 MI W OF GARZA LANE (W OF LAKE L
To 0.1 MI WEST OF FM 423
CSJ 1567-01-029
Proj ID STP 2010(982)MM
Work Type GRADING, STR, PVMT, SIGNS
 
4.493 33538923.64 506812.16 30926435.18 92.2
CountyDENTON
Highway FM 720
From 0.2 MILE WEST OF GARZA LANE
To 0.1 MILE WEST OF FM 423
CSJ 1567-01-032
Proj ID RW 1567-1-32
Work Type ROW ACQ. AND UTIL. ADJUST.
 
0.001 3297279.80 0.00 460852.58 13.9
Work Order 09-13-10
Work Began 07-14-11
Work Completed  
Time Computed 03-12-11
Contract Working Days 577
Addl Days Granted 185
Working Days Charged 724
Percent Time Used 95
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 1567-01-029
ATS DRILLING, L.P. (5.77%)
BRENDA PRICE TRUCKING(0.22%)
CRAIG OLDEN, INC.(0.61%)
DALLAS LITE AND BARRICADE INC. (0.11%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.21%)
HIGHWAY TECHNOLOGIES, INC. (0.31%)
L & E HART ENTERPRISES, INC. (2.09%)
MICA CORPORATION (4.78%)
NORTH TEXAS REBAR, LLC (5.54%)
PENHALL COMPANY(0.05%)
RAMBO CONTRACTING, INC.(2.62%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(6.26%)
S & V CONSTRUCTION LLC (0.05%)
SOUTH TEXAS PAINTING COMPANY (0.15%)
STORM WATER MANAGEMENT, INC. (0.10%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.28%)
TEX OP CONSTRUCTION, LP(0.99%)
WEIR BROS.,INC.(5.19%)
GREAT WESTERN ERECTORS (0.12%)
DURABLE SPECIALTIES, INC.(1.39%)
LAYFIELD CONSTRUCTION, INC (0.01%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.36%)
GREAT WESTERN ERECTORS (0.49%)
Contract # 07103001
Totals 54321262.71 572323.82 48691590.26 89.6

CountyDENTON
Highway FM 720
From ELDORADO PKWY (FM 720)
To SOUTH OF MARTOP
CSJ 1567-01-025
Proj ID C 1567-1-25
Work Type GR, STRS & PVT
 
2.565 15597320.25 0.00 81200.00 0.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-11-14
Work Began 00-00-00
Work Completed  
Time Computed 01-06-15
Contract Working Days 420
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HAYDON BUILDING CORP.
SUBCONTRACTOR(S) FOR CCSJ: 1567-01-025
S & S BRIDGE PAINTING, INC.(0.02%)
C.T. AND S. METALWORKS, INC. (0.11%)
ACU CONSTRUCTION LLC (0.69%)
W.O.E. CONSTRUCTION(1.22%)
Contract # 02143001
Totals 15597320.25 0.00 81200.00 0.5

CountyDENTON
Highway FM 423
From STEWARTS CREEK ROAD
To SH 121
CSJ 1567-02-032
Proj ID C 1567-2-32
Work Type WIDEN TO 6 LANE DIVIDED URBAN
 
3.761 49691109.92 349677.27 9306690.37 18.7
CountyDENTON
Highway FM 423
From STEWARTS CREEK ROAD
To SH 121
CSJ 1567-02-033
Proj ID RW 1567-2-33
Work Type ADJUSTMENT OF UTILITIES
 
3.761 8252384.38 420709.99 3693500.52 44.7
Work Order 08-27-14
Work Began 10-20-14
Work Completed  
Time Computed 09-12-14
Contract Working Days 756
Addl Days Granted 0
Working Days Charged 116
Percent Time Used 15
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1567-02-032
ATS DRILLING, INC. (1.12%)
C.T. AND S. METALWORKS, INC. (0.32%)
DUSTROL, INC.(0.52%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.08%)
HOUSTON SAWING & DRILLING(0.00%)
LANDSCAPE CONTRACTING AND IRRIGATION, INC. (0.31%)
MEL"S ELECTRIC SERVICE, INC. (6.02%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(8.40%)
DALLAS LITE AND BARRICADE INC. (0.14%)
SCOTT DERR PAINTING CO, LLC(0.66%)
STORM WATER MANAGEMENT, INC. (0.14%)
STRIPING TECHNOLOGY, L.P.(0.73%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.13%)
WEST TEXAS REBAR PLACERS INC.(0.35%)
W.O.E. CONSTRUCTION(4.60%)
MCL CONTRACTING, LLC (0.06%)
BORE COMPANY (2.11%)
GUIDO CONSTRUCTION, INC. DBA GUIDO"S TRUCKS(0.19%)
TEXAS STAR TRANSPORT, LP (0.69%)
INDUS CONSTRUCTION, L.P. (4.75%)
FORTSON CONTRACTING, INC.(0.09%)
ACTION CONSTRUCTORS(0.39%)
Contract # 05143001
Totals 57943494.30 770387.26 13000190.89 22.4

CountyDENTON
Highway FM 407
From FM 1830
To WEST OF LANTANA TRAIL
CSJ 1785-01-028
Proj ID C 1785-1-28
Work Type GR, STRS & PVT.
 
6.126 12873212.87 2148.60 14308687.03 99.9
Work Order 09-16-11
Work Began 03-01-12
Work Completed  
Time Computed 03-01-12
Contract Working Days 497
Addl Days Granted 195
Working Days Charged 692
Percent Time Used 100
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 1785-01-028
BREDA COMPANY, INC.(1.11%)
BRENDA PRICE TRUCKING(0.00%)
CONCRETE CUTTING BY BOND (0.50%)
FARR FOUNDATION, INC.(0.24%)
FORTSON CONTRACTING, INC.(0.13%)
HIGHWAY TECHNOLOGIES, INC. (0.00%)
IOWA BRIDGE & CULVERT, LC(1.16%)
MICA CORPORATION (2.69%)
MIKE ALBERT, INC.(4.47%)
TEXAS CURB CUT, LP (0.05%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.82%)
THELIN RECYCLING CO., LLC(0.23%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.45%)
C.T. AND S. METALWORKS, INC. (0.00%)
CEN CONCRETE CONSTRUCTION COMPANY, INC.(2.03%)
PENHALL COMPANY(0.00%)
STRIPING TECHNOLOGY, L.P.(0.99%)
DURABLE SPECIALTIES, INC.(2.56%)
Contract # 07113205
Totals 12873212.87 2148.60 14308687.03 99.9

CountyDENTON
Highway FM 407
From W. OF CHIN CHAPEL
To W. OF BRIARHILL BLVD.
CSJ 1950-01-026
Proj ID C 1950-1-26
Work Type GRADING, STRUCTURES, BAND AND SURF
 
1.369 5419912.44 25532.32 6259052.37 100.0
Work Order 02-16-10
Work Began 09-21-10
Work Completed 12-18-14
Time Computed 05-17-10
Contract Working Days 300
Addl Days Granted 209
Working Days Charged 485
Percent Time Used 95
Contractor(s)
TISEO PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 1950-01-026
AXIS CONTRACTING, INC. (1.90%)
BROCK ENVIRONMENTAL, LLC (0.38%)
BUYERS BARRICADES, INC.(0.52%)
DURABLE SPECIALTIES, INC.(1.95%)
FORTSON CONTRACTING, INC.(0.02%)
IOWA BRIDGE & CULVERT, LC(1.45%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY( 17.25%)
STRIPE-A-ZONE, INC.(1.19%)
T & R EXCAVATION, INC. ( 21.56%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.21%)
TOMAS REYES TRUCKING, INC. (2.93%)
W.O.E. CONSTRUCTION(0.14%)
TEXAS INLETS, INC. (3.48%)
DUSTROL, INC.(3.03%)
Contract # 01103007
Totals 5419912.44 25532.32 6259052.37 100.0

CountyDENTON
Highway FM 407
From 0.25 MILE WEST OF BRIARHILL
To IH 35E
CSJ 1950-01-036
Proj ID STP 2015(646)
Work Type FULL - DEPTH CONCRETE REPAIR
 
4.892 1063700.86 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-13-15
Work Began 00-00-00
Work Completed  
Time Computed 04-13-15
Contract Working Days 122
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1950-01-036
ALTUS TRAFFIC MANAGEMENT LLC (1.28%)
BRENDA PRICE TRUCKING(4.08%)
STRAIGHT LINE SAWING & SEALING (3.20%)
TOTAL HIGHWAY MAINTENANCE, LLC ( 11.08%)
Contract # 02153233
Totals 1063700.86 0.00 0.00 0.0

CountyCOLLIN
Highway FM 2551
From FM 544
To FM 2514
CSJ 2056-01-045
Proj ID C 2056-1-45
Work Type GR., STR., BASE AND PAVEMENT
 
2.953 15783469.03 251934.26 15863953.48 99.9
Work Order 12-07-11
Work Began 11-26-12
Work Completed  
Time Computed 06-25-12
Contract Working Days 480
Addl Days Granted 37
Working Days Charged 530
Percent Time Used 102
Contractor(s)
LONE STAR CIVIL CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2056-01-045
ARTEX ELECTRIC, INC. (3.54%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY( 14.01%)
DALLAS LITE AND BARRICADE INC. (0.25%)
DUSTIN ALLEN, INC. (0.30%)
SOUTHWEST CONSTRUCTION SERVICES(0.46%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.90%)
WYLIE DRILLING & DRAINAGE, INC.(0.19%)
BROCK ENVIRONMENTAL, LLC (0.15%)
THELIN RECYCLING COMPANY, L.P. (0.16%)
DUSTROL, INC.(0.35%)
JM MATERIALS, INC. (4.40%)
PANTHER CREEK TRANSPORTATION, INC. (0.57%)
USA SWPPP INSPECTIONS, INC.(0.01%)
MCL CONTRACTING, LLC (0.01%)
BREDA COMPANY, INC.(0.00%)
CTBX, INC. (0.52%)
HERDEZ TRUCKING, INC.(0.00%)
A BROTHERS MILLING, LLC(0.41%)
Contract # 06113239
Totals 15783469.03 251934.26 15863953.48 99.9

CountyCOLLIN
Highway FM 2551
From FM 544
To FM 2514 (PARKER ROAD)
CSJ 2056-01-048
Proj ID STP 2015(223)
Work Type LANDSCAPE DEVELOPMENT
 
3.090 373099.80 0.00 0.00 0.0
Work Order 11-18-14
Work Began 00-00-00
Work Completed  
Time Computed 12-04-14
Contract Working Days 91
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LANDSCAPE CONTRACTING AND IRRIGATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2056-01-048
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10143017
Totals 373099.80 0.00 0.00 0.0

CountyDENTON
Highway LP 288
From IH 35
To US 377 / US 380
CSJ 2250-02-016
Proj ID STP 2014(661)
Work Type FULL DEPTH CONCRETE PAVEMENT REPAIR
 
6.722 3653118.00 105185.40 1203279.04 32.9
Work Order 06-30-14
Work Began 10-06-14
Work Completed  
Time Computed 08-29-14
Contract Working Days 210
Addl Days Granted 0
Working Days Charged 116
Percent Time Used 55
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2250-02-016
ALTUS TRAFFIC MANAGEMENT LLC (0.47%)
BRENDA PRICE TRUCKING(6.28%)
PEACHTREE CONSTRUCTION, LTD. (3.78%)
STRAIGHT LINE SAWING & SEALING (5.96%)
STRIPING TECHNOLOGY, L.P.(1.01%)
ACU CONSTRUCTION LLC (0.44%)
USA EROSION, INC.(0.36%)
Contract # 05143209
Totals 3653118.00 105185.40 1203279.04 32.9