Monthly Local Let Maintenance Report For Dallas District As Of Oct 14, 2014 Page 1 Of 4

Last Update: Tuesday, October 14, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyELLIS
Highway IH0045
From VARIOUS ROADWAYS IN THE ELLIS
To COUNTY MAINTENANCE SECTION
CSJ 6201-06-001
Proj ID RMC - 620106001
Work Type REFLECTORIZED PAVEMENT MARKINGS
 
0.001 191208.00 0.00 162028.57 84.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-18-11
Work Began 05-18-11
Work Completed  
Time Computed 07-17-11
Contract Working Days 730
Addl Days Granted 80
Working Days Charged 810
Percent Time Used 100
Contractor(s)
INTERSTATE ROAD MANAGEMENT CORP.
SUBCONTRACTOR(S) FOR CCSJ: 6201-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04111801
Totals 191208.00 0.00 162028.57 84.7

CountyKAUFMAN
Highway MR0682
From VARIOUS LOCATIONS AT THE
To TERRELL STATE HOSPITAL
CSJ 6207-65-001
Proj ID RMC - 620765001
Work Type REHABILITATE ROADWAYS
 
0.001 179519.15 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 25
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6207-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07101802
Totals 179519.15 0.00 0.00 0.0

CountyCOLLIN
Highway US0075
From VARIOUS ROADWAYS IN THE COLLIN
To COUNTY MAINTENANCE SECTION
CSJ 6208-46-001
Proj ID RMC - 620846001
Work Type TREE TRIMMING AND BRUSH REMOVAL
 
88.777 50652.70 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 107
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BRAXTON TRANSPORTATION LLC
SUBCONTRACTOR(S) FOR CCSJ: 6208-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09101801
Totals 50652.70 0.00 0.00 0.0

CountyNAVARRO
Highway SH0031
From VARIOUS ROADWAYS IN THE NAVARRO COUNTY
To MAINTENANCE SECTION
CSJ 6222-60-001
Proj ID SUP - 622260001
Work Type LITTER REMOVAL
 
0.001 82247.00 0.00 71491.67 86.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-03-12
Work Began 09-01-12
Work Completed  
Time Computed 09-01-12
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 728
Percent Time Used 99
Contractor(s)
TIBH INDUSTRIES, INC.
CEN-TEX ASSOCIATION FOR RETARDED CHILDREN
SUBCONTRACTOR(S) FOR CCSJ: 6222-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09121830
Totals 82247.00 0.00 71491.67 86.9

CountyDALLAS
Highway IH0020
From VARIOUS ROADWAYS IN THE NORTHWEST DALLAS
To COUNTY MAINTENANCE SECTION
CSJ 6222-79-001
Proj ID SUP - 622279001
Work Type LITTER REMOVAL
 
0.001 140251.56 0.00 126353.80 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-03-12
Work Began 09-01-12
Work Completed 09-24-14
Time Computed 09-01-12
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 699
Percent Time Used 95
Contractor(s)
TIBH INDUSTRIES, INC.
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6222-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09121831
Totals 140251.56 0.00 126353.80 100.0

CountyDALLAS
Highway US0175
From VARIOUS ROADWAYS IN THE SOUTHEAST DALLAS
To COUNTY MAINTENANCE SECTION
CSJ 6225-47-001
Proj ID SUP - 622547001
Work Type LITTER REMOVAL
 
0.001 193189.46 0.00 173156.94 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-08-12
Work Began 09-01-12
Work Completed 09-24-14
Time Computed 09-01-12
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 729
Percent Time Used 99
Contractor(s)
TIBH INDUSTRIES, INC.
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6225-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09121832
Totals 193189.46 0.00 173156.94 100.0

CountyKAUFMAN
Highway IH0020
From VARIOUS ROADWAYS IN THE
To KAUFMAN COUNTY MAINTENANCE SECTION
CSJ 6233-96-001
Proj ID RMC - 623396001
Work Type CLEANING & SWEEPING HIGHWAYS
 
0.001 108967.00 0.00 98908.50 90.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-28-12
Work Began 09-04-12
Work Completed  
Time Computed 09-04-12
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 723
Percent Time Used 99
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6233-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03121801
Totals 108967.00 0.00 98908.50 90.7

CountyDALLAS
Highway IH0030
From VARIOUS ROADWAYS IN THE SOUTHWEST DALLAS
To COUNTY MAINTENANCE SECTION
CSJ 6234-92-001
Proj ID SUP - 623492001
Work Type LITTER REMOVAL
 
0.001 125087.24 0.00 150244.25 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-03-12
Work Began 09-01-12
Work Completed 09-24-14
Time Computed 09-01-12
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 729
Percent Time Used 99
Contractor(s)
TIBH INDUSTRIES, INC.
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6234-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09121834
Totals 125087.24 0.00 150244.25 100.0

CountyKAUFMAN
Highway US0080
From VARIOUS ROADWAYS IN THE KAUFMAN
To MAINTENANCE SECTION
CSJ 6235-64-001
Proj ID SUP - 623564001
Work Type LITTER REMOVAL
 
0.001 135727.98 0.00 116975.79 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-29-12
Work Began 09-01-12
Work Completed 09-17-14
Time Computed 09-01-12
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 727
Percent Time Used 99
Contractor(s)
TIBH INDUSTRIES, INC.
PRECIOUS GEMS CHILD CARE SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6235-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09121835
Totals 135727.98 0.00 116975.79 100.0

CountyCOLLIN
Highway US0380
From VARIOUS ROADWAYS IN THE COLLIN COUNTY
To MAINTENANCE SECTION
CSJ 6236-28-001
Proj ID SUP - 623628001
Work Type LITTER REMOVAL
 
0.001 148305.70 0.00 148279.39 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-29-12
Work Began 09-01-12
Work Completed 09-24-14
Time Computed 09-01-12
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 717
Percent Time Used 98
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6236-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09121836
Totals 148305.70 0.00 148279.39 100.0

CountyDALLAS
Highway SH0066
From VARIOUS ROADWAYS IN THE NORTHEAST DALLAS
To COUNTY MAINTENANCE SECTION
CSJ 6237-04-001
Proj ID SUP - 623704001
Work Type LITTER REMOVAL
 
0.001 101631.92 0.00 86644.32 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-10-12
Work Began 09-01-12
Work Completed 09-24-14
Time Computed 09-01-12
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 729
Percent Time Used 99
Contractor(s)
TIBH INDUSTRIES, INC.
PRECIOUS GEMS CHILD CARE SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6237-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09121837
Totals 101631.92 0.00 86644.32 100.0

CountyELLIS
Highway IH0035E
From VARIOUS LOCATIONS IN THE ELLIS
To COUNTY MAINTENANCE SECTION
CSJ 6238-77-001
Proj ID SUP - 623877001
Work Type LITTER REMOVAL
 
0.001 206833.99 0.00 205737.00 100.0
Work Order 08-13-13
Work Began 09-01-13
Work Completed 09-24-14
Time Computed 09-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 365
Percent Time Used 100
Contractor(s)
TIBH INDUSTRIES, INC.
PRECIOUS GEMS CHILD CARE SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6238-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09131830
Totals 206833.99 0.00 205737.00 100.0

CountyELLIS
Highway BU0287S
From VARIOUS ROADWAYS IN THE ELLIS COUNTY
To MAINTENANCE SECTION
CSJ 6244-17-001
Proj ID SUP - 624417001
Work Type LITTER REMOVAL
 
0.001 246996.40 0.00 211756.77 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-03-12
Work Began 09-01-12
Work Completed 09-17-14
Time Computed 09-01-12
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 729
Percent Time Used 99
Contractor(s)
TIBH INDUSTRIES, INC.
CEN-TEX ASSOCIATION FOR RETARDED CHILDREN
SUBCONTRACTOR(S) FOR CCSJ: 6244-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09121838
Totals 246996.40 0.00 211756.77 100.0

CountyCOLLIN
Highway US0075
From VARIOUS LOCATIONS IN
To COLLIN COUNTY
CSJ 6251-16-001
Proj ID RMC - 625116001
Work Type POTHOLE & EDGE REPAIR
 
0.001 208749.00 22260.60 298546.83 99.9
Work Order 10-24-13
Work Began 12-16-13
Work Completed  
Time Computed 11-11-13
Contract Working Days 268
Addl Days Granted 179
Working Days Charged 311
Percent Time Used 69
Contractor(s)
BRYDL CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6251-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09131801
Totals 208749.00 22260.60 298546.83 99.9

CountyCOLLIN
Highway SH0078
From COLLIN
To COUNTY
CSJ 6252-44-001
Proj ID SUP - 625244001
Work Type PICNIC AREA AND LANDSCAPE MAINTENANCE
 
0.001 21271.52 793.99 15350.23 72.1
Work Order 11-15-12
Work Began 12-01-12
Work Completed  
Time Computed 12-01-12
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 656
Percent Time Used 89
Contractor(s)
TIBH INDUSTRIES, INC.
LIFENET COMMUNITY BEHAVIORAL HEALTHCARE
SUBCONTRACTOR(S) FOR CCSJ: 6252-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12121830
Totals 21271.52 793.99 15350.23 72.1

CountyDENTON
Highway IH0035E
From DENTON COUNTY AREA OFFICE
To AND MAINTENANCE FACILITIES
CSJ 6253-45-001
Proj ID SUP - 625345001
Work Type JANITORIAL AND GROUNDS MAINTENANCE
 
0.001 36315.30 1341.86 30879.06 85.0
Work Order 12-18-12
Work Began 01-01-13
Work Completed  
Time Computed 01-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 624
Percent Time Used 85
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6253-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01131830
Totals 36315.30 1341.86 30879.06 85.0

CountyDALLAS
Highway IH0045
From SOUTHEAST DALLAS COUNTY AREA OFFICE
To AND MAINTENANCE FACILITIES
CSJ 6254-17-001
Proj ID SUP - 625417001
Work Type JANITORIAL AND GROUNDS MAINTENANCE
 
0.001 48763.60 1019.46 33548.87 68.7
Work Order 02-07-13
Work Began 03-01-13
Work Completed  
Time Computed 03-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 565
Percent Time Used 77
Contractor(s)
TIBH INDUSTRIES, INC.
LIFENET COMMUNITY BEHAVIORAL HEALTHCARE
SUBCONTRACTOR(S) FOR CCSJ: 6254-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03131830
Totals 48763.60 1019.46 33548.87 68.7

CountyCOLLIN
Highway SH0005
From COLLIN COUNTY AREA OFFICE AND
To MAINTENANCE FACILITY
CSJ 6254-18-001
Proj ID SUP - 625418001
Work Type JANITORIAL AND GROUNDS MAINTENANCE
 
0.001 48936.24 1555.26 36867.44 75.3
Work Order 02-22-13
Work Began 03-01-13
Work Completed  
Time Computed 03-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 566
Percent Time Used 77
Contractor(s)
TIBH INDUSTRIES, INC.
LIFENET COMMUNITY BEHAVIORAL HEALTHCARE
SUBCONTRACTOR(S) FOR CCSJ: 6254-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03131831
Totals 48936.24 1555.26 36867.44 75.3

CountyDALLAS
Highway US0080
From DALLAS DISTRICT
To COMPLEX FACILITIES
CSJ 6254-42-001
Proj ID SUP - 625442001
Work Type JANITORIAL MAINTENANCE
 
0.001 225341.12 18032.85 62131.51 27.5
Work Order 05-30-14
Work Began 07-01-14
Work Completed  
Time Computed 07-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 79
Percent Time Used 21
Contractor(s)
TIBH INDUSTRIES, INC.
LIFENET COMMUNITY BEHAVIORAL HEALTHCARE
SUBCONTRACTOR(S) FOR CCSJ: 6254-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07141830
Totals 225341.12 18032.85 62131.51 27.5

CountyDALLAS
Highway SL0012
From OLD IRVING BLVD. BRIDGE
To OVER LOOP 12
CSJ 6256-34-001
Proj ID RMC - 625634001
Work Type BRIDGE BEAM REPAIR
 
0.001 106550.00 106550.00 106550.00 99.9
Work Order 08-04-14
Work Began 08-11-14
Work Completed  
Time Computed 08-11-14
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 26
Percent Time Used 86
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6256-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141801
Totals 106550.00 106550.00 106550.00 99.9

page 1 | page 2 | page 3 | page 4