Monthly State Let Maintenance Report For Dallas District As Of Aug 12, 2014 Page 2 Of 3

Last Update: Tuesday, August 12, 2014
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyDENTON
Highway IH0035E
From VARIOUS ROADWAYS IN THE DENTON
To COUNTY MAINTENANCE SECTION
CSJ 6252-21-001
Proj ID RMC - 625221001
Work Type VEGETATION MANAGEMENT
 
0.001 244816.00 27170.00 126672.00 51.7
Work Order 09-20-13
Work Began 09-23-13
Work Completed  
Time Computed 09-27-13
Contract Working Days 66
Addl Days Granted 0
Working Days Charged 18
Percent Time Used 27
Contractor(s)
ANTHONY SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6252-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04134031
Totals 244816.00 27170.00 126672.00 51.7

CountyNAVARRO
Highway SH0031
From VARIOUS ROADWAYS IN NAVARRO
To COUNTY MAINTENANCE SECTION
CSJ 6252-47-001
Proj ID RMC - 625247001
Work Type BROADCAST HERBICIDE FOR VEGETATION CONTR
 
0.001 236781.72 59909.88 79109.10 33.4
Work Order 07-18-13
Work Began 07-29-13
Work Completed  
Time Computed 07-29-13
Contract Working Days 62
Addl Days Granted 0
Working Days Charged 31
Percent Time Used 50
Contractor(s)
GANT CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6252-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01134014
Totals 236781.72 59909.88 79109.10 33.4

CountyCOLLIN
Highway US0075
From VARIOUS LOCATIONS IN THE COLLIN
To COUNTY MAINTENANCE SECTION
CSJ 6252-98-001
Proj ID RMC - 625298001
Work Type METAL BEAM GUARD FENCE & DELINEATION
 
0.001 591871.00 48227.75 570058.75 96.3
Work Order 08-23-13
Work Began 09-03-13
Work Completed  
Time Computed 09-03-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 332
Percent Time Used 90
Contractor(s)
CKORP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6252-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07134021
Totals 591871.00 48227.75 570058.75 96.3

CountyKAUFMAN
Highway IH0020
From VARIOUS LOCATIONS IN THE
To KAUFMAN MAINTENANCE SECTION
CSJ 6256-56-001
Proj ID RMC - 625656001
Work Type REFLECTORIZED PAVEMENT MARKINGS
 
0.001 1713134.00 112227.53 437617.56 25.5
Work Order 01-09-14
Work Began 01-16-14
Work Completed  
Time Computed 01-16-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 195
Percent Time Used 26
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6256-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11134019
Totals 1713134.00 112227.53 437617.56 25.5

CountyDALLAS
Highway IH0030
From VARIOUS HOV LANES IN THE DALLAS, COLLIN,
To AND TARRANT COUNTIES
CSJ 6258-16-001
Proj ID RMC - 625816001
Work Type PERFORMANCE BASE HOV LANE OPER & MAINT
 
0.001 1696777.69 79108.63 887471.52 52.3
Work Order 09-24-13
Work Began 10-01-13
Work Completed  
Time Computed 10-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 304
Percent Time Used 41
Contractor(s)
ROY JORGENSEN ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6258-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08134009
Totals 1696777.69 79108.63 887471.52 52.3

CountyDENTON
Highway IH0035W
From VARIOUS ROADWAYS IN THE DENTON
To MAINTENANCE SECTION
CSJ 6259-55-001
Proj ID RMC - 625955001
Work Type SWEEPING / DEBRIS REMOVAL
 
0.001 1190630.00 27268.50 272915.65 22.9
Work Order 10-25-13
Work Began 10-27-13
Work Completed  
Time Computed 11-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 273
Percent Time Used 37
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6259-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09134006
Totals 1190630.00 27268.50 272915.65 22.9

CountyNAVARRO
Highway FM1838
From VARIOUS LOCATIONS IN THE
To DALLAS DISTRICT
CSJ 6259-71-001
Proj ID RMC - 625971001
Work Type FOR THE CONST. OF SEAL COAT, PVMT MRKGS.
 
0.001 2107144.98 0.00 1909683.79 90.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-22-14
Work Began 06-02-14
Work Completed  
Time Computed 06-02-14
Contract Working Days 123
Addl Days Granted 0
Working Days Charged 41
Percent Time Used 33
Contractor(s)
F. N. PLOCH CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6259-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10134006
Totals 2107144.98 0.00 1909683.79 90.6

CountyCOLLIN
Highway FM2478
From VARIOUS LOCATIONS
To IN COLLIN COUNTY
CSJ 6260-02-001
Proj ID BPM - 626002001
Work Type VARIOUS CULVERT REPAIRS
 
0.001 445075.23 67355.56 347508.57 78.0
Work Order 01-28-14
Work Began 02-17-14
Work Completed  
Time Computed 02-17-14
Contract Working Days 54
Addl Days Granted 90
Working Days Charged 115
Percent Time Used 79
Contractor(s)
AUSTIN FILTER SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6260-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11134012
Totals 445075.23 67355.56 347508.57 78.0

CountyDALLAS
Highway US0080
From IH 635/US 80 CONNECTORS "B","C", & "D"
To IH 635 SBML,US 80 EBML, AND US 80 WBML
CSJ 6260-70-001
Proj ID BPM - 626070001
Work Type BPM BRIDGE APPROACH & PART DEPTH REPAIR
 
0.001 346416.00 0.00 291003.18 84.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-27-14
Work Began 06-02-14
Work Completed  
Time Computed 06-03-14
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 25
Percent Time Used 62
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6260-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11134011
Totals 346416.00 0.00 291003.18 84.0

CountyROCKWALL
Highway IH0030
From VARIOUS ROADWAYS IN ROCKWALL
To & COLLIN COUNTIES
CSJ 6260-71-001
Proj ID RMC - 626071001
Work Type VEGETATION MANAGEMENT
 
0.001 222490.00 0.00 53618.00 24.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-16-14
Work Began 04-09-14
Work Completed  
Time Computed 07-23-14
Contract Working Days 66
Addl Days Granted 0
Working Days Charged 11
Percent Time Used 16
Contractor(s)
LONESTAR HAWK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6260-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01144017
Totals 222490.00 0.00 53618.00 24.0

CountyKAUFMAN
Highway FM3094
From FM 148
To FM 148
CSJ 6260-98-001
Proj ID RMC - 626098001
Work Type REHABILITATION AND WIDENING PAVEMENT
 
0.001 2041457.81 396805.93 1092466.80 53.5
Work Order 03-28-14
Work Began 04-04-14
Work Completed  
Time Computed 04-04-14
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 72
Percent Time Used 60
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6260-98-001
TOTAL HIGHWAY MAINTENANCE, LLC (1.02%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.84%)
Contract # 01144016
Totals 2041457.81 396805.93 1092466.80 53.5

CountyKAUFMAN
Highway SH0034
From VARIOUS LOCATIONS IN THE KAUFMAN
To MAINTENANCE SECTION
CSJ 6261-26-001
Proj ID RMC - 626126001
Work Type MILL & INLAY
 
6.000 744881.95 789423.71 1335227.19 99.9
Work Order 05-12-14
Work Began 05-19-14
Work Completed  
Time Computed 05-19-14
Contract Working Days 55
Addl Days Granted 10
Working Days Charged 33
Percent Time Used 50
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6261-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03144012
Totals 744881.95 789423.71 1335227.19 99.9

CountyDALLAS
Highway SH0114
From SL0012
To SS0482
CSJ 6261-81-001
Proj ID RMC - 626181001
Work Type REMVL OF 2 PED BRDGS OVER SH114 & RAMP
 
0.100 511165.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SJ&J CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6261-81-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07144210
Totals 511165.00 0.00 0.00 0.0

CountyELLIS
Highway US0287
From VARIOUS ROADWAYS IN THE ELLIS
To COUNTY MAINTENANCE SECTION
CSJ 6262-32-001
Proj ID RMC - 626232001
Work Type FLEX PAVEMENT STRUCTURE REPAIR & OVERLAY
 
0.001 3099160.00 854594.87 2846998.68 91.8
Work Order 04-28-14
Work Began 05-03-14
Work Completed  
Time Computed 05-05-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 88
Percent Time Used 24
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6262-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03144028
Totals 3099160.00 854594.87 2846998.68 91.8

CountyDALLAS
Highway IH0345
From IH 345 SOUTHBOUND COLLECTOR RAMP D-C IN
To THE EAST DALLAS COUNTY MAINTENANCE SECT
CSJ 6262-36-001
Proj ID RMC - 626236001
Work Type IH345 ROADWAY AND RETAINING WALL REPAIR
 
0.001 745894.42 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-07-14
Work Began 00-00-00
Work Completed  
Time Computed 09-01-14
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
REBCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6262-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06144208
Totals 745894.42 0.00 0.00 0.0

CountyNAVARRO
Highway FM1946
From HILL CO. LINE
To FM 744
CSJ 6262-54-001
Proj ID RMC - 626254001
Work Type REHABILITATION AND WIDENING OF PAVEMENT
 
0.001 1345389.15 239580.49 622159.09 46.2
Work Order 05-15-14
Work Began 05-20-14
Work Completed  
Time Computed 05-27-14
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 38
Percent Time Used 31
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 6262-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03144011
Totals 1345389.15 239580.49 622159.09 46.2

CountyCOLLIN
Highway FM0075
From MONTE CARLO BLVD. (OLD HIGHWAY 24)
To E. MCKINNEY AVE.
CSJ 6262-89-001
Proj ID RMC - 626289001
Work Type FLEX PVMT STRUCTURE REPAIR AND OVERLAY
 
1.215 364618.10 0.00 341637.12 93.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-28-14
Work Began 04-21-14
Work Completed  
Time Computed 04-21-14
Contract Working Days 42
Addl Days Granted 0
Working Days Charged 38
Percent Time Used 90
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6262-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02144012
Totals 364618.10 0.00 341637.12 93.6

CountyNAVARRO
Highway SH0031
From VARIOUS ROADWAYS IN NAVARRO COUNTY
To MAINTENANCE SECTION EXCEPT IH45
CSJ 6262-99-001
Proj ID RMC - 626299001
Work Type GUARD FENCE
 
0.001 337535.00 0.00 25015.00 7.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-27-14
Work Began 06-01-14
Work Completed  
Time Computed 06-02-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 56
Percent Time Used 7
Contractor(s)
FIREMAN EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6262-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02144027
Totals 337535.00 0.00 25015.00 7.4

CountyELLIS
Highway US0287
From VARIOUS ROADWAYS IN THE ELLIS
To COUNTY MAINTENANCE SECTION EXCEPT IH45
CSJ 6263-94-001
Proj ID RMC - 626394001
Work Type GUARDRAIL REPAIR
 
0.001 325835.35 8165.50 39434.40 12.1
Work Order 04-28-14
Work Began 05-01-14
Work Completed  
Time Computed 05-05-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 88
Percent Time Used 12
Contractor(s)
FORTSON CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6263-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03144013
Totals 325835.35 8165.50 39434.40 12.1

CountyDENTON
Highway IH0035
From VARIOUS ROADWAYS IN THE DENTON
To COUNTY MAINTENANCE SECTION
CSJ 6264-18-001
Proj ID RMC - 626418001
Work Type GENERAL PAVEMENT REPAIR
 
0.010 6473250.00 94584.36 428976.41 6.6
Work Order 05-12-14
Work Began 05-19-14
Work Completed  
Time Computed 05-19-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 74
Percent Time Used 10
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6264-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03144029
Totals 6473250.00 94584.36 428976.41 6.6