Monthly State Let Maintenance Report For Dallas District As Of Apr 12, 2024 Page 4 Of 7

Last Update: Friday, April 12, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyDENTON
HighwayIH0035
FromVARIOUS ROADWAYS IN
ToDENTON COUNTY MAINTENANCE SECTION
CSJ6425-62-001
Proj IDRMC - 642562001
Work TypePOTHOLE REPAIR
 
0.010864000.00366868.6842.4
Work Order05-10-23
Work Began05-16-23
Work Completed
Time Computed05-17-23
Contract Working Days365
Addl Days Granted0
Working Days Charged315
Percent Time Used86
Contractor(s)
PATHFIELD INVESTMENTS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6425-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03234018
Totals864000.009540.00366868.6842.4

CountyNAVARRO
HighwayUS0287
FromVARIOUS ROADWAYS IN THE
ToNAVARRO COUNTY MAINTENANCE SECTION
CSJ6426-42-001
Proj IDRMC - 642642001
Work TypeDITCH CLEANING AND RESHAPING
 
0.010421750.0087060.0020.6
Work Order05-23-23
Work Began05-29-23
Work Completed
Time Computed05-29-23
Contract Working Days730
Addl Days Granted0
Working Days Charged302
Percent Time Used41
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6426-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03234019
Totals421750.0087060.0087060.0020.6

CountyDALLAS
HighwaySL0012
FromVARIOUS ROADWAYS IN
ToWEST DALLAS COUNTY MAINTENANCE SECTIONS
CSJ6426-99-001
Proj IDRMC - 642699001
Work TypeREPAIR/REPLACE CONCRETE BARRIER
 
0.010712950.00510816.9571.6
Work Order05-04-23
Work Began05-11-23
Work Completed
Time Computed05-11-23
Contract Working Days730
Addl Days Granted0
Working Days Charged320
Percent Time Used43
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6426-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03234016
Totals712950.00226833.50510816.9571.6

CountyCOLLIN
HighwaySH0005
FromVARIOUS ROADWAYS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6428-11-001
Proj IDRMC - 642811001
Work TypeFLEXIBLE PAVEMENT STRUCTURE REPAIR
 
0.010554841.78569205.1699.9
Work Order09-11-23
Work Began09-18-23
Work Completed
Time Computed09-18-23
Contract Working Days365
Addl Days Granted0
Working Days Charged161
Percent Time Used44
Contractor(s)
PEACHTREE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6428-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04234206
Totals554841.780.00569205.1699.9

CountyDALLAS
HighwaySH0183
FromVARIOUS ROADWAYS IN
ToNORTHWEST DALLAS COUNTY MAINTENANCE
CSJ6429-60-001
Proj IDRMC - 642960001
Work TypeFLEXIBLE PAVEMENT STRUCTURE REPAIR
 
0.0101392447.001272457.2391.3
Work Order07-10-23
Work Began07-17-23
Work Completed
Time Computed07-17-23
Contract Working Days365
Addl Days Granted0
Working Days Charged253
Percent Time Used69
Contractor(s)
PEACHTREE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6429-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04234005
Totals1392447.00129656.031272457.2391.3

CountyDALLAS
HighwaySL0012
FromVARIOUS ROADWAYS IN
ToSOUTHEAST DALLAS COUNTY MAINTENANCE
CSJ6429-71-001
Proj IDRMC - 642971001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.0101490697.001100136.6473.8
Work Order05-25-23
Work Began06-15-23
Work Completed
Time Computed06-15-23
Contract Working Days730
Addl Days Granted0
Working Days Charged285
Percent Time Used39
Contractor(s)
FIREMAN EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6429-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04234006
Totals1490697.00116161.001100136.6473.8

CountyDALLAS
HighwaySL0012
FromVARIOUS ROADWAYS IN
ToSOUTHEAST DALLAS COUNTY MAINTENANCE
CSJ6429-72-001
Proj IDRMC - 642972001
Work TypeCRASH CUSHION ATTENUATOR REPAIR
 
0.010944492.00218603.0023.1
Work Order05-25-23
Work Began06-15-23
Work Completed
Time Computed06-15-23
Contract Working Days730
Addl Days Granted0
Working Days Charged285
Percent Time Used39
Contractor(s)
FIREMAN EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6429-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04234207
Totals944492.002634.00218603.0023.1

CountyELLIS
HighwayBU0287R
FromVARIOUS ROADWAYS IN THE
ToELLIS COUNTY MAINTENANCE SECTION
CSJ6430-22-001
Proj IDRMC - 643022001
Work TypeREFLECTORIZED PAVEMENT MARKINGS & MARKE
 
0.010284266.91192027.8467.5
Work Order02-26-24
Work Began03-04-24
Work Completed
Time Computed03-04-24
Contract Working Days21
Addl Days Granted0
Working Days Charged5
Percent Time Used23
Contractor(s)
STRIPE-A-ZONE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6430-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12234021
Totals284266.91192027.84192027.8467.5

CountyDALLAS
HighwayIH0030
FromVARIOUS HOV LANES IN
ToDALLAS COUNTY
CSJ6431-72-001
Proj IDRMC - 643172001
Work TypePERFORMANCE BASED CONTRACT
 
0.01030767326.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days1,460
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LINDSAY CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6431-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01244218
Totals30767326.500.000.000.0

CountyROCKWALL
HighwaySH0066
FromKAUFMAN/ROCKWALL
ToMAINTENANCE SECTION
CSJ6433-50-001
Proj IDRMC - 643350001
Work TypeFLEXIBLE PAVEMENT STRUCTURE REPAIR
 
0.0102417685.742166343.0389.6
Work Order09-05-23
Work Began09-05-23
Work Completed
Time Computed09-12-23
Contract Working Days365
Addl Days Granted0
Working Days Charged203
Percent Time Used55
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6433-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05234208
Totals2417685.74187453.432166343.0389.6

CountyCOLLIN
HighwayUS0380
FromVARIOUS ROADWAYS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6433-60-001
Proj IDRMC - 643360001
Work TypeSPECIALTY MARKINGS
 
0.010329329.29418436.3499.9
Work Order08-29-23
Work Began09-05-23
Work Completed
Time Computed09-05-23
Contract Working Days365
Addl Days Granted0
Working Days Charged203
Percent Time Used55
Contractor(s)
STRIPE-A-ZONE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6433-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05234209
Totals329329.290.00418436.3499.9

CountyDENTON
HighwayIH0035
FromVARIOUS ROADWAYS IN DENTON COUNTY
ToMAINTENANCE SECTION
CSJ6435-70-001
Proj IDRMC - 643570001
Work TypeCLEANING AND SWEEPING HIGHWAYS
 
0.010572142.00200373.9035.0
Work Order09-13-23
Work Began09-20-23
Work Completed
Time Computed09-20-23
Contract Working Days365
Addl Days Granted0
Working Days Charged188
Percent Time Used51
Contractor(s)
SWEEPING CORPORATION OF AMERICA, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6435-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06234606
Totals572142.0048601.50200373.9035.0

CountyDALLAS
HighwayUS0080
FromVARIOUS ROADWAYS IN THE
ToEAST DALLAS COUNTY MAINTENANCE SECTIONS
CSJ6435-74-001
Proj IDRMC - 643574001
Work TypeMISCELLANEOUS CONCRETE REPAIR
 
0.010757170.00447208.5059.0
Work Order09-06-23
Work Began10-03-23
Work Completed
Time Computed10-03-23
Contract Working Days119
Addl Days Granted0
Working Days Charged84
Percent Time Used70
Contractor(s)
SJ&J CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6435-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06234410
Totals757170.0067281.00447208.5059.0

CountyELLIS
HighwayIH0035E
FromVARIOUS ROADWAYS IN THE
ToELLIS COUNTY MAINTENANCE SECTION
CSJ6435-87-001
Proj IDRMC - 643587001
Work TypeCLEANING AND SWEEPING HIGHWAYS
 
0.010541558.25174713.0932.2
Work Order08-02-23
Work Began08-09-23
Work Completed
Time Computed08-09-23
Contract Working Days365
Addl Days Granted0
Working Days Charged230
Percent Time Used63
Contractor(s)
SWEEPING CORPORATION OF AMERICA, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6435-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06234607
Totals541558.2540543.45174713.0932.2

CountyELLIS
HighwayIH0045
FromVARIOUS ROADWAYS IN THE
ToELLIS COUNTY MAINTENANCE SECTION
CSJ6436-17-001
Proj IDRMC - 643617001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010798843.00413262.2551.7
Work Order08-07-23
Work Began08-14-23
Work Completed
Time Computed08-14-23
Contract Working Days365
Addl Days Granted0
Working Days Charged225
Percent Time Used61
Contractor(s)
FIREMAN EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6436-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06234203
Totals798843.0022549.00413262.2551.7

CountyELLIS
HighwayIH0045
FromVARIOUS ROADWAYS IN THE
ToELLIS COUNTY MAINTENANCE SECTION
CSJ6436-49-001
Proj IDRMC - 643649001
Work TypeCRASH CUSHION ATTENUATOR REPAIR
 
0.010427230.00286543.0067.0
Work Order08-07-23
Work Began09-05-23
Work Completed
Time Computed09-05-23
Contract Working Days365
Addl Days Granted0
Working Days Charged203
Percent Time Used55
Contractor(s)
FIREMAN EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6436-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06234204
Totals427230.00108484.00286543.0067.0

CountyKAUFMAN
HighwayIH0020
FromVARIOUS ROADWAYS IN KAUFMAN/ROCKWALL
ToMAINTENANCE SECTION
CSJ6436-90-001
Proj IDRMC - 643690001
Work TypeTRAFFIC CONTROL SERVICES
 
0.010861750.00237600.5027.5
Work Order09-22-23
Work Began09-22-23
Work Completed
Time Computed09-29-23
Contract Working Days365
Addl Days Granted0
Working Days Charged186
Percent Time Used50
Contractor(s)
AWP SAFETY
SUBCONTRACTOR(S) FOR CCSJ: 6436-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08234214
Totals861750.0039102.00237600.5027.5

CountyDALLAS
HighwayIH0035E
FromVARIOUS ROADWAYS IN
ToTHE DALLAS DISTRICT
CSJ6437-25-001
Proj IDRMC - 643725001
Work TypeTRAFFIC SIGNAL MAINTENANCE
 
0.0101722550.10597201.1934.6
Work Order08-17-23
Work Began09-05-23
Work Completed
Time Computed09-05-23
Contract Working Days365
Addl Days Granted0
Working Days Charged203
Percent Time Used55
Contractor(s)
YUNEX LLC
SUBCONTRACTOR(S) FOR CCSJ: 6437-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06234023
Totals1722550.1060227.22597201.1934.6

CountyELLIS
HighwayIH0045
FromVARIOUS ROADWAYS IN THE
ToELLIS COUNTY MAINTENANCE SECTION
CSJ6437-31-001
Proj IDRMC - 643731001
Work TypeREPAIR/REPLACE CONCRETE BARRIER
 
0.010451100.00152520.0033.8
Work Order08-31-23
Work Began09-07-23
Work Completed
Time Computed09-07-23
Contract Working Days365
Addl Days Granted0
Working Days Charged201
Percent Time Used55
Contractor(s)
IBCTX, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6437-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06234411
Totals451100.0063990.00152520.0033.8

CountyELLIS
HighwayIH0045
FromVARIOUS ROADWAYS IN THE
ToELLIS COUNTY MAINTENANCE SECTION
CSJ6437-55-001
Proj IDRMC - 643755001
Work TypeSPECIALTY MARKINGS
 
0.010275264.050.000.0
Work Order03-13-24
Work Began00-00-00
Work Completed
Time Computed04-01-24
Contract Working Days102
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STRIPE-A-ZONE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6437-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12234206
Totals275264.050.000.000.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7