ITEMS 400 2001 TO 432 2096
Items Items Bid Code Range
0100 - 0193
0204 - 0247
0305 - 0361
0400 - 0496
0500 - 0560
0610 - 0690
0700 - 0788
1003 - 1122
2153 - 2322
3075 - 3271
4191 - 4671
5367 - 5957
6007 - 6834
7468 - 7468
8020 - 8983
9059 - 9059
400 2001 - 432 2096
434 2041 - 465 4113
465 4122 - 496 2025
Item No Description Units November 30, 2014 Twelve Month Moving Usage
Quantity Avg Bid Quantity Avg Bid
400 2001 STRUCT EXCAV CY     191.000 75.00000 1
400 2003 STRUCT EXCAV (PIPE) CY     1,247.700 9.06308 4
400 2004 STRUCT EXCAV (BRIDGE) CY     6,456.000 15.57000 1
400 2005 CEM STABIL BKFL CY     9,882.000 46.72129 4
400 2008 CUT & RESTORING PAV (ASPH) SY     700.000 45.00000 1
400 2016 CEMENT STAB BACKFILL (INLET OR MH) CY     1,110.000 62.49000 1
401 2001 FLOWABLE BACKFILL CY     818.000 81.79707 3
402 2001 TRENCH EXCAVATION PROTECTION LF     29,344.000 6.77228 8
403 2001 TEMPORARY SPL SHORING SF     215,462.000 14.84360 5
416 2001 DRILL SHAFT (18 IN) LF     6,721.000 83.60471 3
416 2002 DRILL SHAFT (24 IN) LF     3,991.000 99.80977 4
416 2003 DRILL SHAFT (30 IN) LF     118.000 145.08220 2
416 2004 DRILL SHAFT (36 IN) LF     23,877.000 152.12949 6
416 2005 DRILL SHAFT (42 IN) LF     5,806.000 197.38715 3
416 2006 DRILL SHAFT (48 IN) LF     12,575.000 227.64579 2
416 2007 DRILL SHAFT (54 IN) LF     300.000 290.00000 1
416 2008 DRILL SHAFT (60 IN) LF     4,228.000 296.49000 1
416 2016 DRILL SHAFT (SIGN MTS) (12 IN) LF     56.000 190.00000 1
416 2018 DRILL SHAFT (SIGN MTS) (24 IN) LF     160.000 210.12500 3
416 2022 DRILL SHAFT (SIGN MTS) (48 IN) LF     1,428.600 510.61164 4
416 2023 DRILL SHAFT (SIGN MTS) (54 IN) LF     666.000 640.00000 1
416 2026 DRILL SHAFT (HIGH MAST POLE) (60 IN) LF     2,039.000 650.13066 3
416 2027 DRILL SHAFT (HIGH MAST POLE) (66 IN) LF     195.000 665.96000 1
416 2029 DRILL SHAFT (RDWY ILL POLE) (30 IN) LF     410.000 290.43805 4
416 2030 DRILL SHAFT (TRF SIG POLE) (24 IN) LF     162.000 201.92444 2
416 2031 DRILL SHAFT (TRF SIG POLE) (30 IN) LF     106.700 258.41331 4
416 2032 DRILL SHAFT (TRF SIG POLE) (36 IN) LF     212.000 335.72189 4
416 2034 DRILL SHAFT (TRF SIG POLE) (48 IN) LF     110.000 512.26000 1
420 2001 CL A CONC (MISC) CY     17.000 350.00000 1
420 2002 CL B CONC (FLUME) CY     101.000 500.00000 1
420 2003 CL C CONC (ABUT) CY     63.200 716.41614 2
420 2004 CL C CONC (BENT) CY     24.700 930.00000 1
420 2006 CL C CONC (RAIL FOUNDATION) CY     1,356.800 304.76033 3
420 2013 CL C CONC (MISC) CY     63.000 450.00000 1
420 2016 CL C CONC (COLLAR) EA     36.000 1,407.82944 5
420 2018 CL C CONC (FOOTING) (MASS PLACEMENT) CY     3,095.900 501.86745 2
420 2033 CL S CONC (APPR SLAB) CY     537.700 355.25758 2
420 2035 CL S CONC (CIP SLAB SPAN) CY     88.200 609.78991 1
420 2041 CL C CONC (ABUT) (HPC) CY     1,904.700 612.90218 3
420 2042 CL C CONC (BENT) (HPC) CY     1,193.700 697.73723 3
420 2051 CL C CONC (COLUMN) CY     6.300 2,500.00000 1
420 2061 CL S CONC (HPC) BAS CY     2,954.800 472.64598 2
420 2089 CL F CONC (CAP) (MASS PLACEMENT) CY     110.300 900.00000 1
420 2092 CL C CONC (CAP) (MASS PLACEMENT) (HPC) CY     4,012.600 773.76355 2
420 2093 CL C CONC (COLUMN) (MASS PLACE) (HPC) CY     3,974.600 677.47311 2
420 2104 CL A CONC (FLUME) CY     401.000 447.48798 4
420 2223 CL C CONC (COLUMN) (HPC) CY     1,165.700 943.32370 2
420 2269 CL C CONC (CAP) (HPC) CY     1,061.400 658.69125 2
420 2292 CL S CONC (BRIDGE SDWLK) (HPC) CY     203.200 518.76560 2
420 2311 CL S CONC (APPR SLAB) (SPECIAL) (HPC) CY     667.300 663.20000 1
422 2001 REINF CONC SLAB SF     3,240.000 18.00000 1
422 2003 REINF CONC SLAB (HPC) (CL S) SF     758,827.000 14.97240 3
422 2008 REINF CONC SLAB (EXT SLAB) (HPC) (CL S) SF     9,653.000 17.11000 1
423 2001 RETAINING WALL (MSE) SF     176,806.000 39.96715 2
423 2007 RETAINING WALL (SPREAD FOOTING) SF     6,666.000 45.36000 1
423 2011 RETAINING WALL (DRILL SHAFT) (FACIA) SF     5,203.000 56.44000 1
423 2012 RETAINING WALL (CAST - IN - PLACE) SF     221.000 43.60000 1
423 2013 RETAINING WALL (TIEBACK) SF     21,429.000 45.36000 1
423 2014 RET WALL (SPREAD FOOTING) (SPL) SF     10,848.000 36.00179 2
423 2025 RETAINING WALL (SPECIAL) SF     31,604.000 40.00000 1
425 2016 PRESTR CONC SLAB BEAM (4SB15) LF     1,479.380 210.00000 1
425 2017 PRESTR CONC SLAB BEAM (5SB15) LF     3,064.850 190.00000 1
425 2064 PRESTR CONC GIRDER (TX28) LF     9,189.000 167.40136 2
425 2065 PRESTR CONC GIRDER (TX34) LF     3,896.630 167.13000 1
425 2066 PRESTR CONC GIRDER (TX40) LF     7,512.620 166.75000 1
425 2067 PRESTR CONC GIRDER (TX46) LF     5,295.900 166.92000 1
425 2068 PRESTR CONC GIRDER (TX54) LF     27,821.740 173.29253 3
425 2069 PRESTR CONC GIRDER (TX62) LF     24,676.620 166.47000 1
425 2070 PRESTR CONC GIRDER (TX70) LF     3,360.000 200.00000 1
425 2097 PRESTR CONC GIRDER (TX82) LF     3,105.170 167.33000 1
427 2002 CONCRETE PAINT FINISH SF     27,682.000 1.50000 1
427 2006 BLAST FINISH SF     26,910.000 1.30000 1
427 2009 CONCRETE PAINT (EXISTING CONCRETE) SF     579,119.000 .50740 2
427 2010 CONCRETE PAINT (NEW CONCRETE) SF     121,026.000 .25000 1
428 2002 CONC SURF TREAT (CLASS II) SY     10,470.000 5.00000 1
429 2007 CNC STR REP (HORIZONTAL) SF     2,573.000 26.25225 3
429 2008 CNC STR REP (VERTICAL OR OVERHEAD) SF     835.000 162.96257 2
429 2010 CNC STR REP (BRDG DECK) (FULL DEPTH) SF     3,910.000 90.00000 1
430 2088 CL C CONC FOR EXT STR (CULV) (2 - 8'X5') LF     418.000 400.00000 1
430 2126 CL C CONC FOR EXT STR (ABUT) (HPC) CY     75.800 1,154.05989 1
430 2141 CL C CONC FOR EXT STR (CULV) (2 - 10'X10' LF     42.000 1,335.48000 1
430 2181 CL C CONC FOR EXT STR (HDWL & WINGS) CY     1.000 1,612.66000 1
432 2001 RIPRAP (CONC) (4 IN) CY     6,449.600 246.13639 6
432 2002 RIPRAP (CONC) (5 IN) CY     719.000 318.56342 4
432 2005 RIPRAP (STONE TY R) (DRY) (6 IN) CY     28.000 130.00000 1
432 2015 RIPRAP (STONE COMMON) (DRY) (6 IN) CY     162.000 142.53086 3
432 2017 RIPRAP (STONE COMMON) (GROUT) (6 IN) CY     34.000 120.00000 1
432 2019 RIPRAP (STONE PROTECTION) (12 IN) CY     83.000 186.46000 1
432 2021 RIPRAP (STONE PROTECTION) (18 IN) CY     730.000 119.15522 2
432 2023 RIPRAP (STONE PROTECTION) (24 IN) CY     195.000 70.00000 1
432 2033 RIPRAP (STONE COMMON) (DRY) (12 IN) CY     19.000 140.00000 1
432 2035 RIPRAP (CONC) (6 IN) CY     18.000 420.00000 1
432 2036 RIPRAP (STONE TY R) (DRY) (12 IN) CY     470.000 60.00000 1
432 2039 RIPRAP (MOW STRIP) (4 IN) CY     415.000 457.96386 3
432 2040 RIPRAP (MOW STRIP) (5 IN) CY     8.500 500.00000 1
432 2048 RIPRAP (CONC) (FLUME) CY     568.000 385.55641 3
432 2066 RIPRAP (CONC) (CL B) CY     295.000 350.00000 1
432 2072 RIPRAP (CONC) (CL B) (RR8 & RR9) CY     3,539.900 388.05000 1
432 2084 RIPRAP (CONC) (CL B) (4") CY     90.000 428.66667 2
432 2096 RIPRAP (CONC) (CHANNEL) (6") CY     100.000 410.00000 1