ITEMS 712 6008 TO 772 2007
Items Items Bid Code Range
0104 - 0132
0400 - 0496
0500 - 0550
0610 - 0690
0712 - 0780
1002 - 1122
2144 - 2144
3281 - 3281
4100 - 4191
5009 - 5367
6001 - 6055
7022 - 7666
8852 - 8852
712 6008 - 772 2007
772 6001 - 780 2001
Item No Description Units June 30, 2015 Twelve Month Moving Usage
Quantity Avg Bid Quantity Avg Bid
712 6008 JT / CRCK SEAL (RUBBER - ASPHALT) LMI     456.500 500.00000 1
720 2003 SPALLING REPAIR (POLYMERIC) (SEMIRIGID) GAL     15.000 50.00000 1
730 2001 STRIP MOWING AC     934.000 26.00000 1
730 2002 FULL - WIDTH MOWING AC     6,713.000 25.60231 3
730 6001 STRIP MOWING AC     350.000 24.00000 2
730 6002 FULL - WIDTH MOWING AC     34,908.000 22.76223 8
734 2001 LITTER REMOVAL AC     1,730.000 15.00000 2
734 6001 LITTER REMOVAL AC 865.000 15.00000 1,165.000 46.33047 4
738 2002 CLEANING / SWEEPING (CENTER MEDIAN) MI     2,000.000 120.00000 2
738 2004 CLEANING / SWEEPING (OUTSIDE MAIN LANE) MI     2,000.000 120.00000 2
738 2006 CLEANING / SWEEPING (FRONTAGE ROAD) MI     100.000 110.00000 2
738 2008 CLEANING / SWEEPING (ENTRANCE / EXIT RAMP) MI     100.000 120.00000 2
738 2010 CLEANING / SWEEPING (SPOT) MI     40.000 130.00000 2
738 6002 CLEANING / SWEEPING (CENTER MEDIAN) MI     2,000.000 86.69000 2
738 6004 CLEANING / SWEEPING (OUTSIDE MAIN LANE MI     2,400.000 86.22000 2
738 6006 CLEANING / SWEEPING (FRONTAGE ROAD) MI     240.000 253.51000 2
738 6008 CLEANING / SWEEPING (ENTRANCE / EXIT RAMP MI     100.000 286.07000 2
738 6010 CLEANING / SWEEPING (SPOT) MI     20.000 196.22000 2
740 2005 ANTI - GRAFFITI COATING (PERMANENT) SF 10,000.000 5.70000 20,000.000 5.70000 2
740 6002 GRAFFITI REMOVAL (PAINTING) SF 500.000 4.00000 500.000 4.00000 1
745 2006 JANITORIAL MAINT (PICNIC AREAS) CYC     552.000 186.28217 4
745 2007 GROUNDS MAINT (MOWING / TRIMMING) CYC     48.000 260.88000 4
745 6061 GROUNDS MAINT (MOWING / TRIMMING) CYC 12.000 200.00000 72.000 67.00000 6
745 6154 JANITORIAL MAINT (PICNIC AREAS) CYC 120.000 300.00000 868.000 211.61290 6
745 6155 JANITORIAL MAINT (PICNIC AREAS) MO     24.000 1,350.00000 2
751 2010 VEGETATIVE WATERING (SITE A) MG     400.000 80.00000 2
751 6001 FERTILIZER APPLICATION CYC     4.000 500.00000 2
751 6002 HERBICIDE APPLICATION CYC     16.000 500.00000 2
751 6003 IRRIG SYS OPERATION AND REPAIR MO     24.000 35.00000 2
751 6004 LEAF REMOVAL CYC     14.000 35.00000 2
751 6006 LITTER PICKUP CYC     208.000 340.00000 2
751 6008 MOWING, TRIMMING, AND EDGING CYC     32.000 300.00000 2
751 6009 MULCH & RESHAPING OF PLANT BEDS CYC     8.000 250.00000 2
751 6010 PLANT BED MAINTENANCE CYC     48.000 100.00000 2
751 6011 PRUNING CYC     4.000 100.00000 2
751 6012 VEGETATIVE WATERING MG     80.000 600.00000 2
751 6094 VEGETATIVE WATERING (SITE A) MG 200.000 100.00000 200.000 100.00000 1
760 2001 DITCH CLEANING AND RESHAPING (FOOT) LF     510.000 25.00000 1
760 6002 DITCH CLEAN / RESHAPING (CU YD IN PLACE CY     12,000.000 9.00000 1
764 6001 DRAIN INLET CLEANING EA     50.000 100.00000 1
764 6007 STORM SEWER CLEANING (PIPE) (12" - 18"DIA LF     500.000 4.00000 1
764 6010 STORM SEWER CLEANING (PIPE) (31" - 36"DIA LF     4,000.000 6.75000 1
764 6012 STORM SEWER CLEANING (PIPE) (43" - 54"DIA LF     1,000.000 7.00000 1
764 6021 SLOTTED DRAIN CLEANING LF     50.000 100.00000 1
770 2001 REPAIR RAIL ELEMENT (W - BEAM) LF     22,000.000 9.76364 3
770 2002 REPAIR RAIL ELEMENT (THRIE - BEAM) LF     280.000 10.55429 3
770 2004 REM / REPL TIMBER / STL POST W / O CONC FND EA     1,050.000 32.00000 3
770 2005 REM / REPL TIMBER / STL POST W / CONC FND EA     550.000 44.54545 3
770 2006 REALIGN POSTS EA     400.000 14.50000 3
770 2007 REPAIR OF TERMINAL ANCHORS POSTS EA     12.000 13.94667 3
770 2008 REPLACE TERMINAL ANCHOR POSTS EA     12.000 111.77500 3
770 2009 REMOVE GDRAIL END TRT / REPL WITH SGT EA     3.000 1,216.51667 3
770 2010 REPL SINGLE GDRAIL TERM IMPACT HEAD EA     125.000 771.20000 3
770 2011 REPLACE SINGLE GDRAIL TERMINAL RAIL LF     4,000.000 12.00000 3
770 2012 REPLACE SINGLE GDRAIL TERMINAL POST EA     400.000 36.50000 3
770 2014 REPAIR STEEL POST WITH BASE PLATE EA     6.000 125.57667 3
770 2016 REPAIR SINGLE GUARDRAIL TERMINAL EA     10.000 900.00000 1
770 2022 REM & RESET SGT IMPACT HEAD EA     25.000 128.58400 3
770 2023 REPLACE SGT OBJECT MARKER EA     9.000 27.22222 3
770 2027 REMOVE & REPLACE BLOCKOUT EA     410.000 9.96268 3
770 2030 REPAIR RAIL ELEMENT (W - BEAM) (FURNISHED LF     10.000 9.02000 1
770 2031 INSTALL BLOCKOUT EA     20.000 17.00000 1
770 2034 REMOVE AND RESET SGT IMPACT HEAD EA     4.000 112.31500 3
770 2035 REPAIR RAIL ELEMENT (CURVED RAIL) LF     1,400.000 14.16714 3
770 2037 REM / REPL TIM POST W / O CONC FND (FURN) EA     20.000 10.25000 1
770 2040 RAISE RAIL ELEMENT LF     14.000 8.35714 3
770 6001 REPAIR RAIL ELEMENT (W - BEAM) LF     12,100.000 8.78264 3
770 6002 REPAIR RAIL ELEMENT (THRIE - BEAM) LF     161.000 24.96273 3
770 6004 REPAIR RAIL ELEMENT (CURVED RAIL) LF     500.000 18.70000 3
770 6006 RAISE RAIL ELEMENT LF     1.000 10.00000 1
770 6010 REM / REPL TIMBER / STL POST W / O CONC FN EA     780.000 27.92308 3
770 6011 REM / REPL TIMBER / STL POST W / CONC FN EA     250.000 38.80000 3
770 6017 REALIGN POSTS EA     475.000 14.36842 3
770 6018 INSTALL BLOCKOUT (TYPE SPECIFIED) EA     40.000 6.58000 2
770 6019 REMOVE & REPLACE BLOCKOUT EA     100.000 9.00000 1
770 6021 REPLACE SINGLE GDRAIL TERMINAL RAIL LF     4,200.000 10.14286 3
770 6022 REPLACE SINGLE GDRAIL TERMINAL POST EA     500.000 29.80000 3
770 6023 REPAIR OF TERMINAL ANCHORS POSTS EA     22.000 228.09091 3
770 6024 REPLACE TERMINAL ANCHOR POSTS EA     22.000 148.00000 3
770 6027 REMOVE GDRAIL END TRT / REPL WITH SGT EA     24.000 2,350.00000 1
770 6028 REPL SINGLE GDRAIL TERM IMPACT HEAD EA     90.000 282.33333 3
770 6029 REM & RESET SGT IMPACT HEAD EA     1.000 100.00000 1
770 6033 REPLACE SGT OBJECT MARKER EA     31.000 29.90323 3
770 6052 REPAIR STEEL POST WITH BASE PLATE EA     1.000 186.00000 1
771 6001 REPLACE POSTS (TL - 3) EA     120.000 38.00000 1
771 6002 REPLACE POSTS (TL - 4) EA     900.000 46.66667 3
771 6003 CABLE SPLICE / TURNBUCKLE (TL - 3) EA     1.000 105.00000 1
771 6004 CABLE SPLICE / TURNBUCKLE (TL - 4) EA     5.000 105.00000 1
771 6005 REPAIR CONCRETE FOUNDATION (TL - 3) EA     1.000 20.00000 1
771 6006 REPAIR CONCRETE FOUNDATION (TL - 4) EA     11.000 42.72727 3
771 6007 REPR OR REPLC CABLE BARR TERM SEC (TL - 3 EA     1.000 45.00000 1
771 6008 REPR OR REPLC CABLE BARR TERM SEC (TL - 4 EA     29.000 151.17241 3
771 6009 REPLACE CABLE (TL - 3) LF     90.000 2.50000 1
771 6010 REPLACE CABLE (TL - 4) LF     400.000 2.75000 3
772 2001 POST AND CABLE FENCE (REMOVAL) LF     30.000 4.34667 3
772 2002 POST AND CABLE FENCE (REMV CONC ANCHOR) EA     6.000 57.33333 3
772 2003 POST AND CABLE FENCE (NEW INSTALLATION) LF     60.000 34.16667 3
772 2004 POST AND CABLE FENCE (NEW CONC ANCHOR) EA     5.000 47.00000 3
772 2005 POST AND CABLE FENCE (REMV / REPL POSTS) EA     70.000 39.64286 3
772 2007 POST AND CABLE FENCE (REMV / REPL CABLE) LF     300.000 3.50333 3