AVERAGE LOW BID UNIT PRICE - MAINTENANCE - EL PASO DISTRICT
ITEMS 7148 6014 TO 7148 6020 |
Items | Items | Bid Code Range |
---|---|---|
0000 - 0000 0104 - 0104 0361 - 0361 0401 - 0480 0500 - 0550 0666 - 0672 0712 - 0785 | 5009 - 5009 6001 - 6185 7022 - 7148 | 7148 6001 - 7148 6013 7148 6014 - 7148 6020 |
Item No | Description | Units | March 31, 2019 | Twelve-Month-Moving | Usage | ||
---|---|---|---|---|---|---|---|
Quantity | Avg Bid | Quantity | Avg Bid | ||||
7148 6014 | ONE LANE CONNECTING RAMP CLOSURE | HR | 26.000 | 37.30769 | 3 | ||
7148 6015 | TWO LANE CONNECTING RAMP CLOSURE | HR | 26.000 | 37.30769 | 3 | ||
7148 6016 | WORK AREA ON SHOULDER | HR | 1,200.000 | 20.83333 | 4 | ||
7148 6017 | TURN AROUND CLOSURE | HR | 40.000 | 30.25000 | 3 | ||
7148 6019 | FURNISH ADDITIONAL FLAGGER | HR | 80.000 | 35.00000 | 2 | ||
7148 6020 | PILOT VEHICLE AND OPERATOR | HR | 80.000 | 45.00000 | 2 | ||
7148 6021 | FURNISH ADDITIONAL ARROW BOARD | HR | 80.000 | 3.00000 | 2 | ||
7052 6075 | LANE CLOSURE (MAINTENANCE) (TY 17) | HR | 18.000 | 0.01000 | 1 | ||
7148 6001 | 1 LN CLOSURE 2 LN RD NO SHOULDERS | HR | 1,000.000 | 52.25000 | 4 | ||
7148 6002 | 1 LN CLOSURE 2 LN RD PAVED SHOULDERS | HR | 1,600.000 | 51.56250 | 4 | ||
7148 6003 | 1 LN CLOSURE 4 LN RD | HR | 110.000 | 42.72727 | 3 | ||
7148 6004 | 2 LN CLOSURE 4 LN RD | HR | 100.000 | 38.80000 | 3 | ||
7148 6005 | FREEWAY 1 LANE CLOSURE | HR | 350.000 | 75.71429 | 2 | ||
7148 6006 | FREEWAY 2 LANE CLOSURE | HR | 40.000 | 33.00000 | 2 | ||
7148 6007 | FREEWAY 3 LANE CLOSURE | HR | 10.000 | 75.00000 | 1 | ||
7148 6008 | FREEWAY 4 LANE CLOSURE | HR | 10.000 | 80.00000 | 1 | ||
7148 6009 | EXIT OR ENTRANCE RAMP CLOSURE | HR | 250.000 | 29.56000 | 3 | ||
7148 6010 | FREEWAY CLOSURE SEQUENCE DAYTIME ONLY | HR | 20.000 | 75.50000 | 2 | ||
7148 6011 | COMPLETE FREEWAY CLOSURE | HR | 170.000 | 110.41176 | 3 | ||
7148 6012 | ONE LANE FRONTAGE ROAD CLOSURE | HR | 270.000 | 46.66667 | 3 | ||
7148 6013 | TWO LANE FRONTAGE ROAD CLOSURE | HR | 160.000 | 38.12500 | 3 | ||
7148 6014 | ONE LANE CONNECTING RAMP CLOSURE | HR | 26.000 | 37.30769 | 3 | ||
7148 6015 | TWO LANE CONNECTING RAMP CLOSURE | HR | 26.000 | 37.30769 | 3 | ||
7148 6016 | WORK AREA ON SHOULDER | HR | 1,200.000 | 20.83333 | 4 | ||
7148 6017 | TURN AROUND CLOSURE | HR | 40.000 | 30.25000 | 3 | ||
7148 6019 | FURNISH ADDITIONAL FLAGGER | HR | 80.000 | 35.00000 | 2 | ||
7148 6020 | PILOT VEHICLE AND OPERATOR | HR | 80.000 | 45.00000 | 2 | ||
7148 6021 | FURNISH ADDITIONAL ARROW BOARD | HR | 80.000 | 3.00000 | 2 | ||
7052 6070 | LANE CLOSURE (MAINTENANCE) (TY 12) | HR | 1,582.000 | 34.77561 | 9 | ||
7052 6071 | LANE CLOSURE (MAINTENANCE) (TY 13) | HR | 285.000 | 35.73684 | 2 | ||
7052 6072 | LANE CLOSURE (MAINTENANCE) (TY 14) | HR | 102.000 | 372.64412 | 4 | ||
7052 6073 | LANE CLOSURE (MAINTENANCE) (TY 15) | HR | 12.000 | 23.00000 | 2 | ||
7052 6074 | LANE CLOSURE (MAINTENANCE) (TY 16) | HR | 2,605.000 | 99.00438 | 6 | ||
7052 6075 | LANE CLOSURE (MAINTENANCE) (TY 17) | HR | 30.000 | 9.20600 | 3 | ||
7052 6076 | MOBILE OPERATIONS | HR | 2,850.000 | 46.49123 | 2 | ||
7148 6001 | 1 LN CLOSURE 2 LN RD NO SHOULDERS | HR | 1,000.000 | 52.25000 | 4 | ||
7148 6002 | 1 LN CLOSURE 2 LN RD PAVED SHOULDERS | HR | 1,600.000 | 51.56250 | 4 | ||
7148 6003 | 1 LN CLOSURE 4 LN RD | HR | 110.000 | 42.72727 | 3 | ||
7148 6004 | 2 LN CLOSURE 4 LN RD | HR | 100.000 | 38.80000 | 3 | ||
7148 6005 | FREEWAY 1 LANE CLOSURE | HR | 350.000 | 75.71429 | 2 | ||
7148 6006 | FREEWAY 2 LANE CLOSURE | HR | 40.000 | 33.00000 | 2 | ||
7148 6007 | FREEWAY 3 LANE CLOSURE | HR | 10.000 | 75.00000 | 1 | ||
7148 6008 | FREEWAY 4 LANE CLOSURE | HR | 10.000 | 80.00000 | 1 | ||
7148 6009 | EXIT OR ENTRANCE RAMP CLOSURE | HR | 250.000 | 29.56000 | 3 | ||
7148 6010 | FREEWAY CLOSURE SEQUENCE DAYTIME ONLY | HR | 20.000 | 75.50000 | 2 | ||
7148 6011 | COMPLETE FREEWAY CLOSURE | HR | 170.000 | 110.41176 | 3 | ||
7148 6012 | ONE LANE FRONTAGE ROAD CLOSURE | HR | 270.000 | 46.66667 | 3 | ||
7148 6013 | TWO LANE FRONTAGE ROAD CLOSURE | HR | 160.000 | 38.12500 | 3 | ||
7148 6014 | ONE LANE CONNECTING RAMP CLOSURE | HR | 26.000 | 37.30769 | 3 | ||
7148 6015 | TWO LANE CONNECTING RAMP CLOSURE | HR | 26.000 | 37.30769 | 3 | ||
7148 6016 | WORK AREA ON SHOULDER | HR | 1,200.000 | 20.83333 | 4 | ||
7148 6017 | TURN AROUND CLOSURE | HR | 40.000 | 30.25000 | 3 | ||
7148 6019 | FURNISH ADDITIONAL FLAGGER | HR | 80.000 | 35.00000 | 2 | ||
7148 6020 | PILOT VEHICLE AND OPERATOR | HR | 80.000 | 45.00000 | 2 |