Monthly State Let Construction Report For El Paso District As Of May 11, 2015 Page 3 Of 3

Last Update: Monday, May 11, 2015
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyEL PASO
Highway IH 10
From IH 10 @ LP 375
To .
CSJ 2121-04-093
Proj ID C 2121-4-93
Work Type INTCHG IMPRV INCL CONSTR DIRECT CON
 
1.399 31027042.95 0.00 2072830.11 6.6
CountyEL PASO
Highway IH 10
From IH 10 @ LP 375
To .
CSJ 2121-04-103
Proj ID ROW 2121-4-103
Work Type UTILITY ONLY
 
1.399 462325.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-14-14
Work Began 04-15-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 519
Addl Days Granted 0
Working Days Charged 12
Percent Time Used 2
Contractor(s)
HAYDON BUILDING CORP.
SUBCONTRACTOR(S) FOR CCSJ: 2121-04-093
CHOCTAW ERECTORS, INC. ( 13.81%)
TRI STATE ELECTRIC, LTD. (8.96%)
A BROTHERS MILLING, LLC(0.18%)
HARDY HOLE DRILLING(4.67%)
ROADSAFE, INC. (0.44%)
GOMEZ TRUCKING (0.43%)
NATIONWIDE REBAR INC (0.28%)
TRAFFIC CONTROL SPECIALIST SALES & RENTALS (0.98%)
TEXAS FAR WEST CONSTRUCTION & ENGINEERING(0.99%)
PENHALL COMPANY(0.15%)
ACCURATE CORING, INC.(0.01%)
Contract # 08143054
Totals 31489367.95 0.00 2072830.11 6.5

CountyEL PASO
Highway FM 2529
From US 54
To SL 375
CSJ 2326-01-023
Proj ID NH 2015(385)
Work Type OVERLAY
 
5.875 1526309.97 0.00 0.00 0.0
Work Order 02-10-15
Work Began 00-00-00
Work Completed  
Time Computed 02-26-15
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. A. R. CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2326-01-023
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12143010
Totals 1526309.97 0.00 0.00 0.0

CountyEL PASO
Highway FM 2529
From APPROX 850 E OF US54
To BU 54A (DYER ST)
CSJ 2326-01-025
Proj ID NH 2013(866)
Work Type VEGETATIVE LANDSCAPING
 
2.400 607511.01 908.44 715442.03 99.9
Work Order 09-26-13
Work Began 06-03-14
Work Completed  
Time Computed 10-12-13
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 60
Percent Time Used 100
Contractor(s)
ACCENT LANDSCAPE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2326-01-025
HENRY TRUJILLO, INC. (8.56%)
TRI STATE ELECTRIC, LTD. (6.82%)
TRAFFIC BARRICADE SERVICE, INC.(2.96%)
BORDER DRILLING LLC(1.64%)
Contract # 07133009
Totals 607511.01 908.44 715442.03 99.9

CountyEL PASO
Highway LP 375
From 0.038 MI W OF IH 10 AT LOOP 375
To 0.479 MI E OF FRANKLIN MT STATE PRK
CSJ 2552-01-033
Proj ID C 2552-1-33
Work Type CONVERT NON - FREEWAY TO FREEWAY
 
3.624 61272749.71 7229.10 69802331.13 99.9
Work Order 10-27-11
Work Began 02-06-12
Work Completed  
Time Computed 02-06-12
Contract Working Days 696
Addl Days Granted 25
Working Days Charged 705
Percent Time Used 97
Contractor(s)
SUNDT CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2552-01-033
ROADSAFE TRAFFIC SYSTEMS, INC. (0.81%)
TRI STATE ELECTRIC, LTD. (9.99%)
HARDY HOLE DRILLING(2.23%)
TEXAS FAR WEST CONSTRUCTION & ENGINEERING(0.13%)
HOWE PRECAST (0.08%)
BOWNEN MACHINE & FABRICATING, INC. (0.68%)
CONTECH CONSTRUCTION PRODUCTS INC. (EL PASO) (0.59%)
HILL COUNTRY CULVERTS(0.10%)
CMC REBAR(2.20%)
TEXAS FAR WEST CONSTRUCTION & ENGINEERING(0.70%)
CONCRETE PLACEMENT, INC. (0.20%)
HERNANDEZ CONCRETE PUMPING (0.20%)
DUSTROL, INC.(0.14%)
HENRY TRUJILLO, INC. (0.25%)
ASPHALT PAVERS, INC. (0.09%)
COMBS CONSTRUCTION COMPANY, INC. (0.56%)
ALLEN CONCRETE, INC. (1.35%)
THREE C"S CONTRACTORS, INC.(1.84%)
HAWK CONSTRUCTION(0.03%)
CHOCTAW ERECTORS, INC. (1.43%)
STAR CITY SEALANTS (0.01%)
RNJ CONCRETE, INC. (0.11%)
GREATER EL PASO SANDBLASTING (0.54%)
TONY AVILA ROCKWALL, INC.(0.13%)
ADVANCED CONCRETE SAWING & SEALING, LLC(0.03%)
PRIMATE CONSTRUCTION, INC. (0.02%)
SOUTHWEST SURFACE BLASTING, INC. (0.12%)
BORDER DRILLING LLC(0.02%)
ALLIED PAVING CO.(0.02%)
SOUTHEAST GRINDING & GROOVING, LLC (0.02%)
TRAFFIC CONTROL SPECIALIST SALES & RENTALS (0.02%)
SOUTH PLAINS CONCRETE PRODUCTS, LP (2.76%)
QUARRY HILLS, LTD. (0.23%)
VENEGAS ENGINEERING MANAGEMENT AND CONSTRUCTION, INC.(0.17%)
Contract # 09113201
Totals 61272749.71 7229.10 69802331.13 99.9

CountyEL PASO
Highway LP 375
From 1.36 MI N OF SS 601
To 0.24 MI N OF US 62/180
CSJ 2552-02-025
Proj ID NH 2013(867)
Work Type REHABILITATION
 
5.634 2083068.70 0.00 2321254.59 99.9
CountyEL PASO
Highway LP 375
From SPUR 601
To IRON MEDICS INTERCHANGE
CSJ 2552-02-027
Proj ID STP 2013(868)MM
Work Type CONSTRUCT AUXILIARY LANES
 
0.992 2346556.41 0.00 3200357.19 99.9
CountyEL PASO
Highway LP 375
From 0.27 MI N OF US 62/180
To 0.17 MI S OF US 62/180
CSJ 2552-03-051
Proj ID NH 2013(867)
Work Type REHABILITATION
 
0.496 183452.00 0.00 304441.71 99.9
Work Order 01-17-14
Work Began 03-24-14
Work Completed  
Time Computed 02-02-14
Contract Working Days 160
Addl Days Granted 57
Working Days Charged 194
Percent Time Used 89
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 2552-02-027
DUSTROL, INC.(3.02%)
TRI STATE ELECTRIC, LTD. ( 11.42%)
HAWK CONSTRUCTION( 13.92%)
HENRY TRUJILLO, INC. (0.48%)
PAVEMENT MARKINGS INC. (3.85%)
HARDY HOLE DRILLING(0.22%)
STAR CITY SEALANTS (0.30%)
GREATER EL PASO SANDBLASTING (0.04%)
Contract # 12133209
Totals 4613077.11 0.00 5826053.49 99.9

CountyEL PASO
Highway SS 1966
From US 85 (PAISANO DR)
To SCHUSTER AVE
CSJ 3628-01-001
Proj ID C 3628-1-1
Work Type CONSTRUCTION OF SPUR
 
0.650 29259577.28 672364.97 32704901.71 99.9
CountyEL PASO
Highway SS 1966
From US 85 (PAISANO DR)
To SCHUSTER AVE
CSJ 3628-01-002
Proj ID RW 3628-1-2
Work Type ACQ, RELOC, ASST, & UTIL ADJ
 
0.650 1699305.05 0.00 2216691.31 99.9
Work Order 05-13-13
Work Began 05-20-13
Work Completed  
Time Computed 05-20-13
Contract Working Days 518
Addl Days Granted 25
Working Days Charged 518
Percent Time Used 95
Contractor(s)
HAYDON BUILDING CORP.
SUBCONTRACTOR(S) FOR CCSJ: 3628-01-001
C & C ROAD CONSTRUCTION, INC.(6.30%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (0.12%)
A BROTHERS MILLING, LLC(0.12%)
SCOTT DERR PAINTING CO, LLC(0.29%)
ADAMS FENCE, LLC (0.25%)
TRI STATE ELECTRIC, LTD. (3.13%)
TRAFFIC CONTROL SPECIALIST SALES & RENTALS (0.02%)
PRIMATE CONSTRUCTION, INC. (0.13%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.30%)
TEXAS FAR WEST CONSTRUCTION & ENGINEERING(1.38%)
MONRREAL TRUCKING, INC.(0.30%)
HARDY HOLE DRILLING( 13.25%)
INTERNATIONAL EAGLE ENTERPRISES, INC.(3.33%)
HORIZONTAL BORING, INC.(1.47%)
SANCHEZ CONSTRUCTION & LANDSCAPING (0.07%)
FORET COMPANIES(0.22%)
GORMAN MOISTURE PROTECTION (0.06%)
APACHE BARRICADE & SIGN(0.00%)
ALLIED PAVING CO.(0.00%)
QANNEX CORP. (0.04%)
ER HAWKINS, LLC(0.60%)
Contract # 02133001
Totals 30958882.33 672364.97 34921593.02 99.9

page 1 | page 2 | page 3