Monthly Local Let Maintenance Report For El Paso District As Of Jul 14, 2017 Page 3 Of 4

Last Update: Monday, July 17, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyEL PASO
HighwayIH0010
FromEL PASO DISTRICT COMPLEX
ToEL PASO DISTRICT COMPLEX
CSJ6293-50-001
Proj IDSUP - 629350001
Work TypeJANITORIAL DHQ
 
1.000336378.00294330.7587.5
Work Order10-01-15
Work Began00-00-00
Work Completed
Time Computed10-01-15
Contract Working Days730
Addl Days Granted0
Working Days Charged639
Percent Time Used87
Contractor(s)
TIBH INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6293-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09152431
Totals336378.0014015.75294330.7587.5

CountyHUDSPETH
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6293-96-001
Proj IDRMC - 629396001
Work TypeROADWAY LEVEL UP
 
1.800421150.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
INTERNATIONAL EAGLE ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6293-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01162406
Totals421150.000.000.000.0

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6294-03-001
Proj IDRMC - 629403001
Work TypeMOWING HIGHWAY RIGHT-OF-WAY
 
100.00068635.0041172.8559.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged29
Percent Time Used48
Contractor(s)
E. G. L. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6294-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10152403
Totals68635.000.0041172.8559.9

CountyEL PASO
HighwayUS0062
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6295-55-001
Proj IDRMC - 629555001
Work TypePICNIC AREA MAINTENANCE
 
5.00024239.6737389.8999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-01-16
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted92
Working Days Charged395
Percent Time Used86
Contractor(s)
A CUT ABOVE LAWN MAINTENANCE & SPRINKLER CO.
SUBCONTRACTOR(S) FOR CCSJ: 6295-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12152404
Totals24239.672735.4437389.8999.9

CountyJEFF DAVIS
HighwaySH0017
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6295-62-001
Proj IDRMC - 629562001
Work TypeLITTER BARREL MAINTENANCE
 
210.00040160.0032500.0080.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-01-16
Work Began04-01-16
Work Completed
Time Computed04-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
CM COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6295-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01162402
Totals40160.000.0032500.0080.9

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6295-65-001
Proj IDRMC - 629565001
Work TypeJANITORIAL GROUND MAINTENANCE
 
200.00050072.0061432.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-02-16
Work Began03-02-16
Work Completed
Time Computed03-02-16
Contract Working Days365
Addl Days Granted68
Working Days Charged433
Percent Time Used100
Contractor(s)
CM COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6295-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12152408
Totals50072.000.0061432.0099.9

CountyBREWSTER
HighwayUS0067
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6295-66-001
Proj IDRMC - 629566001
Work TypeLANDSCAPE MAINTENANCE
 
11.00072660.0077367.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-05-16
Work Began00-00-00
Work Completed
Time Computed05-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
CM COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6295-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03162403
Totals72660.000.0077367.0099.9

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6298-14-001
Proj IDSUP - 629814001
Work TypeHIGHWAY LANDSCAPE MAINTENANCE
 
30.0001659870.201095064.5065.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-01-16
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged487
Percent Time Used66
Contractor(s)
TIBH INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6298-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02162402
Totals1659870.2092251.061095064.5065.9

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6300-11-001
Proj IDRMC - 630011001
Work TypeCLEANING & SWEEPING HIGHWAYS
 
600.000312795.00260423.3383.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-19-16
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted120
Working Days Charged377
Percent Time Used77
Contractor(s)
E. G. L. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6300-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05162402
Totals312795.008170.00260423.3383.2

CountyPRESIDIO
HighwayUS0067
FromPRESIDIO COUNTY
ToBREWSTER COUNTY
CSJ6300-29-001
Proj IDRMC - 630029001
Work TypePICNIC AREA LITTER BARREL
 
271.00057360.0065743.4199.9
Work Order05-25-16
Work Began07-01-16
Work Completed
Time Computed07-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
CM COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6300-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04162411
Totals57360.005982.5065743.4199.9

CountyPRESIDIO
HighwayUS0067
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6300-30-001
Proj IDRMC - 630030001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
270.60092800.00164739.0099.9
Work Order06-14-16
Work Began07-05-16
Work Completed
Time Computed06-20-16
Contract Working Days55
Addl Days Granted150
Working Days Charged108
Percent Time Used52
Contractor(s)
MARKO CONTRACTING & MAINTENANCE LLC
SUBCONTRACTOR(S) FOR CCSJ: 6300-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03162404
Totals92800.000.00164739.0099.9

CountyHUDSPETH
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6300-31-001
Proj IDRMC - 630031001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
270.000126745.00107518.4086.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-11-16
Work Completed
Time Computed00-00-00
Contract Working Days66
Addl Days Granted0
Working Days Charged70
Percent Time Used106
Contractor(s)
MESA D CORP.
SUBCONTRACTOR(S) FOR CCSJ: 6300-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04162413
Totals126745.000.00107518.4086.6

CountyHUDSPETH
HighwayUS0062
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6300-32-001
Proj IDRMC - 630032001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
231.00081718.0039692.7249.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-23-16
Work Began06-07-16
Work Completed
Time Computed06-07-16
Contract Working Days66
Addl Days Granted6
Working Days Charged73
Percent Time Used101
Contractor(s)
MESA D CORP.
SUBCONTRACTOR(S) FOR CCSJ: 6300-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04162410
Totals81718.000.0039692.7249.2

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6300-89-001
Proj IDRMC - 630089001
Work TypeCULVERT CLEANING
 
200.000140275.0079086.4256.3
Work Order06-09-16
Work Began06-27-16
Work Completed
Time Computed06-27-16
Contract Working Days365
Addl Days Granted95
Working Days Charged369
Percent Time Used80
Contractor(s)
E. G. L. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6300-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04162415
Totals140275.0020333.3179086.4256.3

CountyEL PASO
HighwaySL0375
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6300-90-001
Proj IDRMC - 630090001
Work TypeCHAIN LINK FENCE REPAIR
 
100.00054126.0088529.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-20-16
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted102
Working Days Charged376
Percent Time Used80
Contractor(s)
E. G. L. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6300-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05162403
Totals54126.00891.0088529.0099.9

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6301-35-001
Proj IDRMC - 630135001
Work TypeCULVERT CLEANING
 
200.000201425.00146538.8972.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-08-16
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged327
Percent Time Used89
Contractor(s)
E. G. L. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6301-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04162420
Totals201425.004133.33146538.8972.7

CountyPRESIDIO
HighwayRM0169
From467
To467
CSJ6301-58-001
Proj IDRMC - 630158001
Work TypeCONTAINMENT FENCE
 
1.00035122.5035122.5099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-10-16
Work Completed
Time Computed00-00-00
Contract Working Days40
Addl Days Granted0
Working Days Charged16
Percent Time Used40
Contractor(s)
CM COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6301-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08162401
Totals35122.500.0035122.5099.9

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6304-05-001
Proj IDRMC - 630405001
Work TypeCLEANING & SWEEPING HIGHWAYS
 
600.000391600.00245848.0062.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-07-16
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged328
Percent Time Used89
Contractor(s)
E. G. L. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6304-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06162401
Totals391600.0027572.00245848.0062.7

CountyEL PASO
HighwaySL0375
FromSL 0375 TRANSMOUNTAIN
ToSL 0375 TRANSMOUNTAIN
CSJ6304-06-001
Proj IDRMC - 630406001
Work TypePICNIC AREA MAINTENANCE
 
1.00030375.0022500.0074.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-16
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged303
Percent Time Used83
Contractor(s)
EL ROI CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6304-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06162402
Totals30375.002250.0022500.0074.0

CountyBREWSTER
HighwayUS0067
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6307-76-001
Proj IDRMC - 630776001
Work TypePICNIC AREA LITTER BARREL MAINTENANCE
 
300.00080975.0053674.4066.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-03-16
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged273
Percent Time Used74
Contractor(s)
CM COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6307-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09162405
Totals80975.004414.4053674.4066.2

page 1 | page 2 | page 3 | page 4