Monthly Local Let Maintenance Report For El Paso District As Of Sep 21, 2017 Page 3 Of 4

Last Update: Friday, September 22, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6298-14-001
Proj IDSUP - 629814001
Work TypeHIGHWAY LANDSCAPE MAINTENANCE
 
30.0001659870.201207829.8672.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-01-16
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged549
Percent Time Used75
Contractor(s)
TIBH INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6298-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02162402
Totals1659870.2046639.061207829.8672.7

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6300-11-001
Proj IDRMC - 630011001
Work TypeCLEANING & SWEEPING HIGHWAYS
 
600.000312795.00279293.3389.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-19-16
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted120
Working Days Charged439
Percent Time Used90
Contractor(s)
E. G. L. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6300-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05162402
Totals312795.0014300.00279293.3389.2

CountyPRESIDIO
HighwayUS0067
FromPRESIDIO COUNTY
ToBREWSTER COUNTY
CSJ6300-29-001
Proj IDRMC - 630029001
Work TypePICNIC AREA LITTER BARREL
 
271.00057360.0076298.4199.9
Work Order05-25-16
Work Began07-01-16
Work Completed
Time Computed07-01-16
Contract Working Days365
Addl Days Granted92
Working Days Charged427
Percent Time Used93
Contractor(s)
CM COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6300-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04162411
Totals57360.007145.0076298.4199.9

CountyPRESIDIO
HighwayUS0067
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6300-30-001
Proj IDRMC - 630030001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
270.60092800.00170017.0099.9
Work Order06-14-16
Work Began07-05-16
Work Completed
Time Computed06-20-16
Contract Working Days55
Addl Days Granted150
Working Days Charged138
Percent Time Used67
Contractor(s)
MARKO CONTRACTING & MAINTENANCE LLC
SUBCONTRACTOR(S) FOR CCSJ: 6300-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03162404
Totals92800.005278.00170017.0099.9

CountyHUDSPETH
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6300-31-001
Proj IDRMC - 630031001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
270.000126745.00107518.4086.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-11-16
Work Completed
Time Computed00-00-00
Contract Working Days66
Addl Days Granted0
Working Days Charged70
Percent Time Used106
Contractor(s)
MESA D CORP.
SUBCONTRACTOR(S) FOR CCSJ: 6300-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04162413
Totals126745.000.00107518.4086.6

CountyHUDSPETH
HighwayUS0062
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6300-32-001
Proj IDRMC - 630032001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
231.00081718.0039692.7249.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-23-16
Work Began06-07-16
Work Completed
Time Computed06-07-16
Contract Working Days66
Addl Days Granted6
Working Days Charged73
Percent Time Used101
Contractor(s)
MESA D CORP.
SUBCONTRACTOR(S) FOR CCSJ: 6300-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04162410
Totals81718.000.0039692.7249.2

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6300-89-001
Proj IDRMC - 630089001
Work TypeCULVERT CLEANING
 
200.000140275.00110363.3978.6
Work Order06-09-16
Work Began06-27-16
Work Completed
Time Computed06-27-16
Contract Working Days365
Addl Days Granted95
Working Days Charged431
Percent Time Used93
Contractor(s)
E. G. L. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6300-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04162415
Totals140275.0031152.65110363.3978.6

CountyEL PASO
HighwaySL0375
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6300-90-001
Proj IDRMC - 630090001
Work TypeCHAIN LINK FENCE REPAIR
 
100.00054126.00100424.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-20-16
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted102
Working Days Charged438
Percent Time Used93
Contractor(s)
E. G. L. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6300-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05162403
Totals54126.005578.00100424.0099.9

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6301-35-001
Proj IDRMC - 630135001
Work TypeCULVERT CLEANING
 
200.000201425.00155130.3177.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-08-16
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted85
Working Days Charged389
Percent Time Used86
Contractor(s)
E. G. L. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6301-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04162420
Totals201425.006981.35155130.3177.0

CountyPRESIDIO
HighwayRM0169
From467
To467
CSJ6301-58-001
Proj IDRMC - 630158001
Work TypeCONTAINMENT FENCE
 
1.00035122.5035122.50100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-10-16
Work Completed10-29-16
Time Computed00-00-00
Contract Working Days40
Addl Days Granted0
Working Days Charged16
Percent Time Used40
Contractor(s)
CM COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6301-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08162401
Totals35122.500.0035122.50100.0

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6304-05-001
Proj IDRMC - 630405001
Work TypeCLEANING & SWEEPING HIGHWAYS
 
600.000391600.00284985.0072.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-07-16
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted85
Working Days Charged390
Percent Time Used86
Contractor(s)
E. G. L. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6304-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06162401
Totals391600.0023040.00284985.0072.7

CountyEL PASO
HighwaySL0375
FromSL 0375 TRANSMOUNTAIN
ToSL 0375 TRANSMOUNTAIN
CSJ6304-06-001
Proj IDRMC - 630406001
Work TypePICNIC AREA MAINTENANCE
 
1.00030375.0027000.0088.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-16
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
EL ROI CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6304-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06162402
Totals30375.002250.0027000.0088.8

CountyBREWSTER
HighwayUS0067
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6307-76-001
Proj IDRMC - 630776001
Work TypePICNIC AREA LITTER BARREL MAINTENANCE
 
300.00080975.0068214.4084.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-03-16
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged335
Percent Time Used91
Contractor(s)
CM COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6307-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09162405
Totals80975.005920.0068214.4084.2

CountyEL PASO
HighwayIH0010
FromVARIOUS
To.
CSJ6308-25-001
Proj IDSUP - 630825001
Work TypeJANITORIAL AND GROUNDS
 
0.001261055.30130527.6550.0
Work Order08-25-16
Work Began00-00-00
Work Completed
Time Computed09-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged365
Percent Time Used50
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6308-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08162406
Totals261055.3011085.91130527.6550.0

CountyEL PASO
HighwaySL0375
FromEAST AREA OFFICE
ToWEST AREA OFFICE
CSJ6309-28-001
Proj IDSUP - 630928001
Work TypeSTATE USE CONTRACT
 
1.00078123.0435973.0646.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-01-16
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged335
Percent Time Used45
Contractor(s)
TIBH INDUSTRIES, INC.
BORDER TM INDUSTRIES, INC
SUBCONTRACTOR(S) FOR CCSJ: 6309-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09162431
Totals78123.043088.4635973.0646.0

CountyEL PASO
HighwaySH0020
From0.5 MI SOUTH SH0020_ON DELTA DR.
To0.25 MI SOUTH SH0020
CSJ6309-41-001
Proj IDRMC - 630941001
Work TypeCONSTRUCTION OF ADDITIONAL PARKING LOT
 
1.00083876.21343386.5299.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-03-17
Work Completed
Time Computed00-00-00
Contract Working Days30
Addl Days Granted30
Working Days Charged43
Percent Time Used71
Contractor(s)
ALLIED PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 6309-41-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02172404
Totals83876.21243208.79343386.5299.9

CountyEL PASO
HighwayIH0010
FromEAST AREA OFFICE
ToWEST AREA OFFICE
CSJ6310-78-001
Proj IDSUP - 631078001
Work TypeJANITORIAL MAINTENANCE SERVICES
 
1.00065716.8029629.1045.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-01-16
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged335
Percent Time Used45
Contractor(s)
TIBH INDUSTRIES, INC.
BORDER TM INDUSTRIES, INC
SUBCONTRACTOR(S) FOR CCSJ: 6310-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09162432
Totals65716.802728.9429629.1045.0

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6313-78-001
Proj IDSUP - 631378001
Work TypeLITTER PICK UP & DISPOSAL
 
100.000527040.00173732.5032.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-01-17
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged184
Percent Time Used25
Contractor(s)
TIBH INDUSTRIES, INC.
BORDER TM INDUSTRIES, INC
SUBCONTRACTOR(S) FOR CCSJ: 6313-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02172431
Totals527040.0032525.00173732.5032.9

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6313-79-001
Proj IDSUP - 631379001
Work TypeLITTER PICK UP & DISPOSAL
 
200.000673720.00216475.0032.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-01-17
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged184
Percent Time Used25
Contractor(s)
TIBH INDUSTRIES, INC.
BORDER TM INDUSTRIES, INC
SUBCONTRACTOR(S) FOR CCSJ: 6313-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02172432
Totals673720.0037910.00216475.0032.1

CountyBREWSTER
HighwayUS0067
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6313-95-001
Proj IDRMC - 631395001
Work TypeLANDSCAPE MAINTENANCE
 
11.00069802.0025781.0036.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-01-17
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged123
Percent Time Used33
Contractor(s)
CM COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6313-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03172402
Totals69802.007178.0025781.0036.9

page 1 | page 2 | page 3 | page 4