Monthly State Let Construction Report For Fort Worth District As Of Jul 11, 2014 Page 5 Of 5

Last Update: Friday, July 11, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyWISE
Highway FM 2123
From SH 114
To C.R. 3355
CSJ 1606-02-018
Proj ID STP 2012(736)HES
Work Type GRADING, BASE, DRAINAGE, STRUCTURE, PAV
 
12.330 4939000.01 0.00 4528881.14 91.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-03-12
Work Began 01-29-13
Work Completed  
Time Computed 12-19-12
Contract Working Days 224
Addl Days Granted 10
Working Days Charged 182
Percent Time Used 77
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1606-02-018
SIGNATURE CONTRACTING SERVICES, L.L.C. (2.47%)
BUYERS BARRICADES, INC.(0.39%)
W.S. CONSTRUCTION COMPANY( 13.29%)
PEACHTREE CONSTRUCTION, LTD. ( 20.15%)
HIGHWAY TECHNOLOGIES, INC. (2.13%)
HJC FARMS, INC.(2.96%)
STRIPING TECHNOLOGY, L.P.(2.21%)
W.O.E. CONSTRUCTION(0.03%)
Contract # 11123224
Totals 4939000.01 0.00 4528881.14 91.6

CountyTARRANT
Highway FM 1938
From SH 114
To RANDOL MILL ROAD
CSJ 1978-01-055
Proj ID STP 2012(570)
Work Type LANDSCAPE ENHANCEMENT
 
2.205 856000.00 0.00 856832.28 99.9
Work Order 07-12-12
Work Began 12-14-12
Work Completed  
Time Computed 07-28-12
Contract Working Days 128
Addl Days Granted 50
Working Days Charged 178
Percent Time Used 100
Contractor(s)
LEGENDS LANDSCAPES LLC
SUBCONTRACTOR(S) FOR CCSJ: 1978-01-055
HIGHWAY TECHNOLOGIES, INC. (0.36%)
Contract # 05123245
Totals 856000.00 0.00 856832.28 99.9

CountyTARRANT
Highway FM 1220
From EAGLE MOUNTAIN ELEM SCHOOL
To 1,100 FT. NORTH OF BAILEY BOSWELL
CSJ 2079-01-041
Proj ID STP 2013(901)
Work Type GRADING, BASE AND PAVEMENT
 
2.879 5878132.94 0.00 0.00 0.0
Work Order 12-10-13
Work Began 00-00-00
Work Completed  
Time Computed 06-09-14
Contract Working Days 160
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2079-01-041
BRENDA PRICE TRUCKING(0.72%)
DALLAS LITE AND BARRICADE INC. (0.31%)
FARR FOUNDATION, INC.(1.36%)
INDEPENDENT UTILITY CONSTRUCTION INCORPORATED(0.46%)
LAYFIELD CONSTRUCTION, INC (4.47%)
J. E. GUZMAN CONSTRUCTION, INC.(5.59%)
TEX OP CONSTRUCTION, LP(2.07%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.13%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(2.43%)
W.O.E. CONSTRUCTION(4.76%)
NORTH TEXAS CONTRACTING, INC.( 14.65%)
STRIPING TECHNOLOGY, L.P.(1.26%)
Contract # 08133064
Totals 5878132.94 0.00 0.00 0.0

CountyTARRANT
Highway SP 303
From WEST C/L (SHADY VALLEY DR)
To EAST C/L (W CORNERSTONE LN)
CSJ 2208-01-063
Proj ID NH 2013(289)
Work Type LANDSCAPE ENHANCEMENT
 
1.647 197430.50 350.00 185239.42 93.8
Work Order 07-08-13
Work Began 09-25-13
Work Completed  
Time Computed 07-24-13
Contract Working Days 81
Addl Days Granted 0
Working Days Charged 76
Percent Time Used 93
Contractor(s)
GREY CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 2208-01-063
BUYERS BARRICADES, INC.(1.41%)
UNLIMITED UTILITY CONSTRUCTION (3.62%)
L.E.D. CONCRETE, LLC (5.54%)
BOWDEN"S GUARANTEED HYDORMULCH, INC. (0.63%)
Contract # 05133037
Totals 197430.50 350.00 185239.42 93.8

CountyJOHNSON
Highway FM 2331
From SH 171
To FM 4 (NORTH)
CSJ 2213-01-013
Proj ID STP 2014(007)HES
Work Type ADDITIONAL PAVED SURFACE WIDTH
 
10.092 4289114.81 164672.71 1138429.58 26.5
Work Order 11-22-13
Work Began 01-08-14
Work Completed  
Time Computed 12-08-13
Contract Working Days 214
Addl Days Granted 5
Working Days Charged 127
Percent Time Used 57
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 2213-01-013
RAMBO CONTRACTING, INC.(9.51%)
TEXAS ALTERNATIVE GRASSER, INC.(0.48%)
NORTHEASTERN PAVERS, INC.( 62.69%)
FORTSON CONTRACTING, INC.(2.11%)
D. I. J. CONSTRUCTION, INC.(1.25%)
BUYER BARRICADES (0.44%)
Contract # 09133023
Totals 4289114.81 164672.71 1138429.58 26.5

CountyTARRANT
Highway SH 360
From AT SH 180 (DIVISION STREET)
To AND UPRR; IN ARLINGTON
CSJ 2266-02-127
Proj ID NH 2007(806)
Work Type GR, STRS & PAVEMENT
 
0.854 55975100.62 0.00 58949145.19 99.9
Work Order 04-07-08
Work Began 03-07-09
Work Completed  
Time Computed 10-05-08
Contract Working Days 555
Addl Days Granted 509
Working Days Charged 1,064
Percent Time Used 100
Contractor(s)
W.W. WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2266-02-127
COWTOWN TRAFFIC CONTROL, INC.(0.20%)
EVANS ENVIRONMENTAL CONTRACTING, LLC.(0.43%)
CAPROCK SPECIALITY CONTRACTORS (0.01%)
CRAIG OLDEN, INC.(1.53%)
FOUNDATION DRILLERS, INC.(1.00%)
HAYWARD BAKER, INC.(1.52%)
HIGHWAY TECHNOLOGIES, INC. (0.68%)
MAGNUM TUNNELING, LLC(0.32%)
MICA CORPORATION (3.87%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(7.49%)
TEX OP CONSTRUCTION, LP(0.33%)
DURABLE SPECIALTIES, INC.(0.67%)
LAYFIELD CONSTRUCTION, INC (0.07%)
BRENDA PRICE TRUCKING(4.11%)
SCOTT DERR PAINTING CO (0.06%)
INDUS CONSTRUCTION, L.P. (2.51%)
GREAT WESTERN ERECTORS (0.05%)
RAILWORKS TRACK SYSTEMS TEXAS, INC.( 11.20%)
SOUTHWEST CONSTRUCTION SERVICES(0.11%)
ERWIN STEEL WORKS, LLC (0.29%)
MOBILE ENTERPRISES, INC. (0.39%)
STOMPER DEMOLITION COMPANY, INC. (0.27%)
RIVER CITIES SAWING LLC(0.01%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.41%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.00%)
Contract # 02083001
Totals 55975100.62 0.00 58949145.19 99.9

CountyPARKER
Highway FM 1187
From FM 5
To TARRANT COUNTY LINE
CSJ 2291-01-013
Proj ID STP 2014(772)
Work Type GR, BS, STR, SURFACE, SIGNING & MARKING
 
5.731 5524918.83 0.00 0.00 0.0
CountyTARRANT
Highway FM 1187
From PARKER COUNTY LINE
To US 377
CSJ 2291-02-008
Proj ID STP 2014(772)
Work Type GR, BS, STR, SURFACE, SIGNING & MARKING
 
1.473 1260929.75 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 374
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 2291-01-013
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143231
Totals 6785848.58 0.00 0.00 0.0

CountyJOHNSON
Highway FM 2415
From FM 4
To C.R. 401
CSJ 2464-01-014
Proj ID STP 2014(665)HES
Work Type GRADING, BASE AND PAVEMENT
 
6.253 2913097.88 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2464-01-014
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05143019
Totals 2913097.88 0.00 0.00 0.0

CountyJOHNSON
Highway FM 2738
From FM 2738 AT MOUNTAIN CREEK
To .
CSJ 2762-01-014
Proj ID BR 2012(572)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.307 1319000.00 6444.83 1313218.01 99.9
Work Order 07-16-12
Work Began 04-29-13
Work Completed  
Time Computed 08-01-12
Contract Working Days 192
Addl Days Granted 13
Working Days Charged 234
Percent Time Used 114
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 2762-01-014
T-BAR FENCE, INC.(0.73%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(6.71%)
HIGHWAY TECHNOLOGIES, INC. (1.21%)
FORTSON CONTRACTING, INC.(1.49%)
ATS DRILLING, L.P. (2.91%)
GJ SEEDING, LLC(1.43%)
MCL CONTRACTING, LLC (0.49%)
TEX OP CONSTRUCTION, LP(1.27%)
HOUSTON SAWING & DRILLING(0.31%)
SCOTT DERR PAINTING CO (0.21%)
ROAD MASTER STRIPING LLC (0.79%)
SOUTHEAST GRINDING & GROOVING, LLC (0.15%)
BRENDA PRICE TRUCKING(0.89%)
Contract # 05123231
Totals 1319000.00 6444.83 1313218.01 99.9

CountyTARRANT
Highway RM 2871
From RM 2871 OVER MARY'S CREEK
To .
CSJ 2855-01-016
Proj ID BR 1102(208)
Work Type REHABILITATE BRIDGE AND APPROACHES
 
0.291 1796479.01 0.00 1882045.97 99.9
Work Order 09-06-11
Work Began 04-02-12
Work Completed  
Time Computed 03-15-12
Contract Working Days 299
Addl Days Granted 27
Working Days Charged 326
Percent Time Used 100
Contractor(s)
IOWA BRIDGE & CULVERT, LC
SUBCONTRACTOR(S) FOR CCSJ: 2855-01-016
STRIPING TECHNOLOGY, L.P.(1.61%)
USA SWPPP INSPECTIONS, INC.(1.79%)
PEACHTREE CONSTRUCTION, LTD. (8.58%)
A.M.S. COMPANY, INC. ( 12.08%)
RICE ENVIRONMENTAL SERVICES(6.83%)
FOUNDATION DRILLERS, INC.(1.50%)
DUSTROL, INC.(0.78%)
HIGHWAY TECHNOLOGIES, INC. (0.59%)
M-CO CONSTRUCTION, INC.(0.38%)
T & R EXCAVATION, INC. (0.51%)
Contract # 08113066
Totals 1796479.01 0.00 1882045.97 99.9

CountyTARRANT
Highway RM 2871
From SOUTH OF RR CROSSING
To US-377
CSJ 2855-01-021
Proj ID STP 2014(319)
Work Type OVERLAY
 
1.387 2072283.33 238627.03 416776.99 20.1
Work Order 02-19-14
Work Began 04-28-14
Work Completed  
Time Computed 03-07-14
Contract Working Days 167
Addl Days Granted 0
Working Days Charged 42
Percent Time Used 25
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 2855-01-021
PEACHTREE CONSTRUCTION, LTD. ( 38.67%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.53%)
FORTSON CONTRACTING, INC.(1.20%)
ENVIRONMENTAL STANDARDS(1.13%)
DURABLE SPECIALTIES, INC.(0.48%)
Contract # 01143023
Totals 2072283.33 238627.03 416776.99 20.1

CountyPARKER
Highway FM 3325
From IH 20
To FM 1886
CSJ 3516-01-015
Proj ID STP 2013(675)
Work Type GR, BS, DR, STRUC AND PAVEMENT
 
7.160 3283284.20 26682.00 685416.75 20.8
Work Order 01-06-14
Work Began 01-28-14
Work Completed  
Time Computed 01-22-14
Contract Working Days 256
Addl Days Granted 0
Working Days Charged 108
Percent Time Used 42
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 3516-01-015
RAMBO CONTRACTING, INC.(1.36%)
INDEPENDENT UTILITY CONSTRUCTION INCORPORATED(0.40%)
SURFACE PREPARATION TECHNOLOGIES, LLC(0.29%)
NORTHEASTERN PAVERS, INC.( 37.58%)
STRIPING TECHNOLOGY, L.P.(1.71%)
JM MATERIALS, INC. (2.37%)
TEXAS ALTERNATIVE GRASSER, INC.(0.71%)
ODUM SERVICES, L.P.(0.87%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.91%)
Contract # 08133054
Totals 3283284.20 26682.00 685416.75 20.8

page 1 | page 2 | page 3 | page 4 | page 5