Monthly State Let Construction Report For Fort Worth District As Of Oct 14, 2014 Page 5 Of 6

Last Update: Tuesday, October 14, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyTARRANT
Highway SS 341
From SH-183/IH-30 INTERCHANGE
To N WHITE SETTLEMENT RD INTERCHANGE
CSJ 1068-03-021
Proj ID STP 2013(288)
Work Type LANDSCAPE ENHANCEMENT
 
1.905 124997.55 1469.50 113687.98 90.9
Work Order 09-17-13
Work Began 10-17-13
Work Completed  
Time Computed 10-03-13
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 26
Percent Time Used 86
Contractor(s)
LANDSCAPE CONTRACTING AND IRRIGATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1068-03-021
ALTUS TRAFFIC MANAGEMENT LLC (2.08%)
Contract # 08133024
Totals 124997.55 1469.50 113687.98 90.9

CountyPARKER
Highway IH 30
From IH 20, AT WALSH RANCH PARKWAY
To TARRANT COUNTY LINE
CSJ 1068-05-009
Proj ID IM 0304(092)
Work Type GRADING, DRAINAGE, STRUCTURE & PAVE
 
1.541 14593117.40 909456.25 7698645.97 52.7
Work Order 09-03-13
Work Began 10-01-13
Work Completed  
Time Computed 09-19-13
Contract Working Days 225
Addl Days Granted 95
Working Days Charged 243
Percent Time Used 75
Contractor(s)
HAYDON BUILDING CORP.
SUBCONTRACTOR(S) FOR CCSJ: 1068-05-009
DALLAS LITE AND BARRICADE INC. (0.22%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (2.80%)
SCOTT DERR PAINTING CO (0.23%)
COWBOY TRUCKING(3.09%)
W.O.E. CONSTRUCTION(0.41%)
INDEPENDENT UTILITY CONSTRUCTION INCORPORATED(5.28%)
T-BAR FENCE, INC.(0.04%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.55%)
PEACHTREE CONSTRUCTION, LTD. (9.14%)
BUYERS BARRICADES, INC.(0.33%)
DUSTROL, INC.(0.53%)
HJC FARMS, INC.(1.45%)
ATS DRILLING, INC. (0.60%)
BREDA COMPANY, INC.(1.31%)
FORTSON CONTRACTING, INC.(0.05%)
LINDAMOOD DEMOLITION, INC. (0.01%)
Contract # 04133201
Totals 14593117.40 909456.25 7698645.97 52.7

CountyWISE
Highway FM 718
From SH 114
To NORTH END OF DERRETT CREEK BRIDGE
CSJ 1098-01-020
Proj ID STP 2011(599)
Work Type GRADING, DRAINAGE AND PAVEMENT
 
5.649 4598915.86 121916.02 3084499.92 67.0
Work Order 12-03-13
Work Began 02-18-14
Work Completed  
Time Computed 02-02-14
Contract Working Days 225
Addl Days Granted 0
Working Days Charged 165
Percent Time Used 73
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1098-01-020
LANCO TURF & SEEDING, INC. (0.64%)
PEACHTREE CONSTRUCTION, LTD. (4.20%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.86%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.41%)
TEX OP CONSTRUCTION, LP(0.21%)
ALTUS TRAFFIC MANAGEMENT LLC (0.51%)
TRANSPORT TRUST(0.54%)
NORTH TEXAS CONTRACTING, INC.( 10.34%)
STORM WATER MANAGEMENT, INC. (0.51%)
STRIPING TECHNOLOGY, L.P.(1.70%)
CEN CONCRETE CONSTRUCTION COMPANY, INC.(2.93%)
Contract # 08133272
Totals 4598915.86 121916.02 3084499.92 67.0

CountyPALO PINTO
Highway FM 919
From AT PANTHER CREEK RELIEF BRIDGE
To .
CSJ 1178-01-026
Proj ID BR 2007(290)
Work Type REPLACE BRIDGE
 
0.104 391234.00 1996.50 354873.72 90.7
Work Order 05-29-14
Work Began 06-25-14
Work Completed  
Time Computed 06-14-14
Contract Working Days 46
Addl Days Granted 0
Working Days Charged 46
Percent Time Used 100
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1178-01-026
BICK"S CONSTRUCTION, INC.( 22.02%)
FORTSON CONTRACTING, INC.(3.43%)
TRP CONSTRUCTION GROUP, LLC(0.00%)
Contract # 04143015
Totals 391234.00 1996.50 354873.72 90.7

CountyWISE
Highway FM 920
From TRINITY RIVER
To 3.174 MI N OF SH 199
CSJ 1179-01-039
Proj ID STP 2013(900)
Work Type GR, BS AND PAVEMENT
 
12.795 5559330.74 893997.49 4398337.08 79.1
Work Order 11-14-13
Work Began 02-14-14
Work Completed  
Time Computed 11-30-13
Contract Working Days 205
Addl Days Granted 0
Working Days Charged 182
Percent Time Used 88
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1179-01-039
FORTSON CONTRACTING, INC.(0.88%)
NORTHEASTERN PAVERS, INC.( 15.58%)
CROSSROADS, L.P. (0.97%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (4.82%)
STRIPING TECHNOLOGY, L.P.(2.57%)
BRENDA PRICE TRUCKING(0.00%)
J.V. CONCRETE CONSTRUCTION ( 12.23%)
SYNERGY SIGNS & SERVICES (0.47%)
Contract # 08133251
Totals 5559330.74 893997.49 4398337.08 79.1

CountyJOHNSON
Highway FM 917
From SH 171 IN GODLEY
To SH 174 IN JOSHUA
CSJ 1181-02-035
Proj ID STP 2014(394)
Work Type HMAC OVERLAY
 
8.950 2080434.45 200243.69 1374053.97 66.0
Work Order 04-11-14
Work Began 08-11-14
Work Completed  
Time Computed 04-27-14
Contract Working Days 86
Addl Days Granted 0
Working Days Charged 45
Percent Time Used 52
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1181-02-035
ALTUS TRAFFIC MANAGEMENT LLC (0.30%)
VANN/ELLI, INC.(7.79%)
STRIPING TECHNOLOGY, L.P.(3.33%)
Contract # 02143214
Totals 2080434.45 200243.69 1374053.97 66.0

CountyJACK
Highway FM 1156
From FM 1156 OVER BEANS CREEK
To .
CSJ 1309-01-029
Proj ID BR 2014(771)
Work Type REPL BRIDGE AND APPROACHES
 
0.174 930482.24 0.00 0.00 0.0
Work Order 08-27-14
Work Began 00-00-00
Work Completed  
Time Computed 09-12-14
Contract Working Days 171
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1309-01-029
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143022
Totals 930482.24 0.00 0.00 0.0

CountyWISE
Highway FM 2264
From CR 4431 N
To FM 407
CSJ 1310-03-025
Proj ID STP 2014(578)HES
Work Type GRADING, BASE, DRAINAGE, STRUCTURE, PAV
 
5.617 3983917.91 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 200
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 1310-03-025
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143040
Totals 3983917.91 0.00 0.00 0.0

CountyTARRANT
Highway FM 1187
From NEWT PATTERSON
To BU 287P
CSJ 1330-02-034
Proj ID STP 2010(399)ES
Work Type GRADING, DRAINAGE, STRUCTURES & PAV
 
1.503 6895052.12 6467.78 12778422.79 99.9
Work Order 05-05-10
Work Began 06-17-11
Work Completed  
Time Computed 11-01-10
Contract Working Days 427
Addl Days Granted 325
Working Days Charged 751
Percent Time Used 99
Contractor(s)
LONE STAR CIVIL CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1330-02-034
UNDERGROUND COALITION, INC.(2.92%)
INLET STRUCTURE SPECIALTIES LTD. (2.88%)
DURABLE SPECIALTIES, INC.(2.04%)
BANDA TRUCKING COMPANY (0.10%)
STORM WATER MANAGEMENT, INC. (0.31%)
INDUS CONSTRUCTION, L.P. (8.05%)
AUSTIN BRIDGE & ROAD, LP ( 16.96%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.34%)
DUSTROL, INC.(0.53%)
JM MATERIALS, INC. (0.32%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.83%)
Contract # 03103004
Totals 6895052.12 6467.78 12778422.79 99.9

CountyJACK
Highway FM 1191
From US 380
To YOUNG COUNTY LINE
CSJ 1333-03-018
Proj ID STP 2014(664)HRR
Work Type GRADING, BASE, DRAINAGE, STRUCTURE, PAV
 
6.980 5404940.22 0.00 0.00 0.0
Work Order 06-18-14
Work Began 00-00-00
Work Completed  
Time Computed 07-04-14
Contract Working Days 230
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1333-03-018
EROSION CONTROL MANAGEMENT SERVICES(1.96%)
NORTH EASTERN PAVERS ( 34.25%)
Contract # 05143217
Totals 5404940.22 0.00 0.00 0.0

CountyPARKER
Highway FM 1189
From YOUNG BEND ROAD
To HOOD COUNTY LINE
CSJ 1468-01-024
Proj ID STP 1402(036)
Work Type GR, STR, FLX BS, SC, MBGF, SIGN, PVT MK
 
9.058 6481549.55 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-07-14
Work Began 00-00-00
Work Completed  
Time Computed 10-23-14
Contract Working Days 253
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1468-01-024
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143043
Totals 6481549.55 0.00 0.00 0.0

CountyHOOD
Highway FM 167
From FM-51
To FM-3450
CSJ 1598-01-020
Proj ID STP 2014(976)
Work Type GR, BS, DR STRUCTURE & HMAC PAVEMENT
 
2.928 2079661.57 360283.55 360283.55 17.3
Work Order 08-27-14
Work Began 09-15-14
Work Completed  
Time Computed 09-12-14
Contract Working Days 61
Addl Days Granted 0
Working Days Charged 10
Percent Time Used 16
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1598-01-020
NORTHEASTERN PAVERS, INC.( 26.76%)
HJC FARMS, INC.(1.73%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.85%)
CROSSROADS, L.P. (0.47%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. ( 11.09%)
Contract # 06143056
Totals 2079661.57 360283.55 360283.55 17.3

CountyJOHNSON
Highway FM 916
From SH 171
To FM 4
CSJ 1599-02-014
Proj ID STP 1402(037)HES
Work Type GRADING, BASE AND PAVEMENT
 
12.842 6925133.46 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-30-14
Work Began 00-00-00
Work Completed  
Time Computed 10-16-14
Contract Working Days 201
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1599-02-014
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143036
Totals 6925133.46 0.00 0.00 0.0

CountyPARKER
Highway FM 1884
From B.B. FIELDER ROAD
To TO END OF FM 1884
CSJ 1601-02-023
Proj ID STP 2012(685)
Work Type GR, DRAINAGE, STRUCTURES, & PAVEMEN
 
6.305 6349600.35 2348.24 6359488.45 99.9
Work Order 11-01-12
Work Began 01-21-13
Work Completed  
Time Computed 11-17-12
Contract Working Days 299
Addl Days Granted 15
Working Days Charged 312
Percent Time Used 99
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1601-02-023
COWTOWN TRAFFIC CONTROL, INC.(0.23%)
DUSTROL, INC.(0.30%)
FORTSON CONTRACTING, INC.(1.36%)
MCL CONTRACTING, LLC (0.11%)
NORTHEASTERN PAVERS, INC.( 36.29%)
SCOTT DERR PAINTING CO (0.04%)
STRIPING TECHNOLOGY, L.P.(0.90%)
SOUTHEAST GRINDING & GROOVING, LLC (0.04%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.33%)
TEXAS SHAFTS, INC. (0.78%)
USA EROSION, INC.(1.18%)
INLET STRUCTURE SPECIALTIES LTD. (3.54%)
BRENDA PRICE TRUCKING(1.23%)
Contract # 08123234
Totals 6349600.35 2348.24 6359488.45 99.9

CountyTARRANT
Highway FM 1709
From UP RAILROAD, WEST OF US 377
To ELM STREET; IN KELLER
CSJ 1603-03-033
Proj ID CM 2011(928)
Work Type GR, DR, STRUCT AND PAVEMENT
 
0.226 879231.70 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-02-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 49
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MASSANA CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 1603-03-033
A & A CONSTRUCTION (2.36%)
CLEMONS TRUCKING (3.55%)
ENVIRONMENTAL STANDARDS, INC.(1.31%)
INTEGRATED ROADWAY SERVICES, INC.( 18.42%)
PEACHTREE CONSTRUCTION, LTD. (9.54%)
STRIPE-A-ZONE, INC.(4.10%)
COWTOWN TRAFFIC CONTROL, INC.(0.82%)
Contract # 01143210
Totals 879231.70 0.00 0.00 0.0

CountyTARRANT
Highway FM 1709
From PEARSON LANE; WEST CITY LIMITS
To SH 114; EAST CITY LIMITS
CSJ 1603-03-034
Proj ID STP 2011(228)TE
Work Type GRADING, DRAINAGE, INSTALL SIDEWALKS
 
6.100 1320757.45 0.00 1446798.88 99.9
Work Order 12-03-12
Work Began 01-28-13
Work Completed  
Time Computed 12-19-12
Contract Working Days 149
Addl Days Granted 46
Working Days Charged 198
Percent Time Used 101
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1603-03-034
ENVIRONMENTAL STANDARDS, INC.(3.97%)
CONCRETE PAVER SYSTEMS, INC. (0.26%)
CROSSROADS, L.P. (0.71%)
HIGHWAY TECHNOLOGIES, INC. (0.52%)
MIKE ALBERT, INC.( 34.12%)
WOODLAKE OUTDOOR, INC. (2.37%)
BUYERS BARRICADES, INC.(0.28%)
BUZZ SERVICES, L.L.C.(3.76%)
Contract # 11123021
Totals 1320757.45 0.00 1446798.88 99.9

CountyPARKER
Highway FM 1886
From FM 730
To TARRANT COUNTY LINE
CSJ 1605-01-014
Proj ID STP 2014(478)
Work Type GR.BS, DR, STRUC AND PAVEMENT
 
5.748 4834822.79 71922.00 369058.96 7.6
Work Order 05-07-14
Work Began 06-12-14
Work Completed  
Time Computed 05-23-14
Contract Working Days 256
Addl Days Granted 0
Working Days Charged 66
Percent Time Used 25
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1605-01-014
RAMBO CONTRACTING, INC.(4.85%)
BICK"S CONSTRUCTION, INC.( 16.34%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.93%)
MARCOM"S MOWING SERVICE, LLC (0.53%)
WEST TEXAS RUMBLE STRIP(0.08%)
AAA DRILLING FOUNDATION CO., INC.(0.36%)
LIRA ELECTRIC(1.57%)
ENVIRONMENTAL SAFETY SERVICES, INC.(1.81%)
TEXAS ALTERNATIVE GRASSER, INC.(0.79%)
Contract # 03143221
Totals 4834822.79 71922.00 369058.96 7.6

CountyWISE
Highway FM 2123
From AT SALT CREEK
To AND AT COTTONWOOD CREEK
CSJ 1606-02-013
Proj ID BR 1102(297)
Work Type REPL BRIDGES
 
0.099 1968338.24 0.00 1872436.82 99.9
Work Order 09-14-11
Work Began 12-08-11
Work Completed  
Time Computed 09-30-11
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 380
Percent Time Used 253
Contractor(s)
DOUGHTIE CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1606-02-013
COWTOWN TRAFFIC CONTROL, INC.(0.36%)
BROCK ENVIRONMENTAL, LLC (0.39%)
DUSTIN ALLEN, INC. (1.70%)
GORRONDONA & ASSOCIATES, INC.(0.50%)
HIGHWAY TECHNOLOGIES, INC. (1.28%)
RG PAINTING(0.19%)
TEXAS ALTERNATIVE GRASSER, INC.(0.20%)
PRIMATE CONSTRUCTION, INC. (0.54%)
TEX OP CONSTRUCTION, LP(0.78%)
PEACHTREE CONSTRUCTION, LTD. (8.23%)
EW WELLS GROUP LLC (2.13%)
W. W. FOUNDATION DRILLING, LTD.(8.30%)
J.L. STEEL REINFORCING, LLC(0.33%)
ENVIRONMENTAL SAFETY SERVICES, INC.(8.95%)
JUST GROOVING, LTD.(0.29%)
JTM MATERIALS, INC.(0.17%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.42%)
KYLE ERWIN CONSTRUCTION, LLC (0.13%)
Contract # 08113260
Totals 1968338.24 0.00 1872436.82 99.9

CountyWISE
Highway FM 2123
From SH 114
To C.R. 3355
CSJ 1606-02-018
Proj ID STP 2012(736)HES
Work Type GRADING, BASE, DRAINAGE, STRUCTURE, PAV
 
12.330 4939000.01 283554.18 4913344.12 99.6
Work Order 12-03-12
Work Began 01-29-13
Work Completed  
Time Computed 12-19-12
Contract Working Days 224
Addl Days Granted 10
Working Days Charged 241
Percent Time Used 102
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1606-02-018
SIGNATURE CONTRACTING SERVICES, L.L.C. (2.47%)
BUYERS BARRICADES, INC.(0.39%)
W.S. CONSTRUCTION COMPANY( 13.29%)
PEACHTREE CONSTRUCTION, LTD. ( 20.15%)
HIGHWAY TECHNOLOGIES, INC. (2.13%)
HJC FARMS, INC.(2.96%)
STRIPING TECHNOLOGY, L.P.(2.21%)
W.O.E. CONSTRUCTION(0.03%)
Contract # 11123224
Totals 4939000.01 283554.18 4913344.12 99.6

CountyTARRANT
Highway FM 1938
From 0.2 MILE SOUTH OF FM 1709
To RANDOL MILL RD/WESTLAKE C/L
CSJ 1978-01-050
Proj ID STP 1402(039)MM
Work Type GR, BS, DR, STRUCTURES & PAVEMENT
 
1.743 20575236.87 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 554
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AUSTIN BRIDGE & ROAD, LP
SUBCONTRACTOR(S) FOR CCSJ: 1978-01-050
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143005
Totals 20575236.87 0.00 0.00 0.0