Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
County | TARRANT |
Highway | CS |
From | JACKSON DRIVE |
To | AT LITTLE BEAR CREEK |
CSJ | 0902-90-132 |
Proj ID | BR 2021(146) |
Work Type | BRIDGE REPLACEMENT |
|
| | 1754000.00 | | 329405.23 | 18.7 |
Work Order | 07-26-23 |
Work Began | 01-31-24 |
Work Completed | |
Time Computed | 10-25-23 |
Contract Working Days | 128 |
Addl Days Granted | 0 |
Working Days Charged | 14 |
Percent Time Used | 10 |
Contractor(s) |
HARPER BROTHERS CONSTRUCTION LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0902-90-132 BARRICADES UNLIMITED (2.26) REYNOLDS ASPHALT & CONSTRUCTION COMPANY (3.26) SOUTHERN CROSS CONTRACTORS, LLC (1.21) WYLIE DRILLING & DRAINAGE, INC. (6.56) TEXOP CONSTRUCTION (0.35) G J SEEDING, LLC (3.67) PRIMATE CONSTRUCTION, LP (0.34) DFW REBAR, INC. (0.17)
|
Contract # | 06233438 |
| Totals | 1754000.00 | 329289.23 | 329405.23 | 18.7 |
|
County | TARRANT |
Highway | CS |
From | AT LIVE OAK CREEK |
To | ON WHITE SETTLEMENT ROAD |
CSJ | 0902-90-134 |
Proj ID | BR 2021(124) |
Work Type | BRIDGE REPLACEMENT |
|
| 0.098 | 1644915.14 | | 890882.02 | 54.1 |
Work Order | 07-19-23 |
Work Began | 10-23-23 |
Work Completed | |
Time Computed | 08-19-23 |
Contract Working Days | 192 |
Addl Days Granted | 0 |
Working Days Charged | 95 |
Percent Time Used | 49 |
Contractor(s) |
SEMA CONSTRUCTION, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0902-90-134 WYLIE DRILLING & DRAINAGE, INC. (3.06) MASSEY CONTRACTORS, LLC (0.34) BREDA COMPANY, INC. (0.37) FC TRAFFIC CONTROL, INC. (2.18) LAUGHLEY BRIDGE & CONSTRUCTION, INC. (12.58) FORTSON CONTRACTING, INC. (0.80) TRP CONSTRUCTION GROUP, LLC (0.75) SYNERGY SIGNS & SERVICES LLC (0.18) DFW REBAR, INC. (0.13) DUSTROL, INC. (0.77) C. GREEN SCAPING, L.P. (0.41) GEOTEX ENGINEERING LLC (0.31) REYNOLDS ASPHALT & CONSTRUCTION COMPANY (0.66)
|
Contract # | 06233027 |
| Totals | 1644915.14 | 97471.78 | 890882.02 | 54.1 |
|
County | TARRANT |
Highway | VA |
From | IH 820 FROM US 377 |
To | OLD DECATUR ROAD |
CSJ | 0902-90-184 |
Proj ID | F 2021(733) |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 13.760 | 1484096.25 | | 1361949.41 | 98.2 |
Work Order | 08-12-21 |
Work Began | 02-22-23 |
Work Completed | |
Time Computed | 11-11-21 |
Contract Working Days | 128 |
Addl Days Granted | 0 |
Working Days Charged | 268 |
Percent Time Used | 209 |
Contractor(s) |
AMERICAN LIGHTING AND SIGNALIZATION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0902-90-184 COLLIER SERVICES LLC (13.87) DALLAS LITE AND BARRICADE, INC. (1.22) SNOWHILL CONTRACTING LLC (27.62) J & S DIRECTIONAL BORING INC. (0.53) LINEAR TRAFFIC MARKINGS LLC (0.37) FC TRAFFIC CONTROL, INC. (0.25)
|
Contract # | 07213030 |
| Totals | 1484096.25 | 0.00 | 1361949.41 | 98.2 |
|
County | TARRANT |
Highway | CS |
From | 0.1 E OF GARDEN SPRINGS DR |
To | 0.1 W OF GARDEN SPRINGS DR |
CSJ | 0902-90-208 |
Proj ID | STP 2023(866)HES |
Work Type | INTERSECTION & OPERATIONAL IMPRV |
|
| | 938539.00 | | 0.00 | 0.0 |
Work Order | 07-19-23 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 08-19-23 |
Contract Working Days | 107 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
FNH CONSTRUCTION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0902-90-208 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 06233038 |
| Totals | 938539.00 | 0.00 | 0.00 | 0.0 |
|
County | TARRANT |
Highway | CS |
From | 0.1 MI N OF S BEACH ST |
To | 0.1 MI S OF S BEACH ST |
CSJ | 0902-90-210 |
Proj ID | STP 2B23(139)HESG |
Work Type | INTERSECTION & OPERATIONAL IMPRV |
|
| | 734812.40 | | 21540.01 | 2.9 |
Work Order | 09-06-23 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 10-06-23 |
Contract Working Days | 200 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
YUNEX LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0902-90-210 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 08233058 |
| Totals | 734812.40 | 21540.01 | 21540.01 | 2.9 |
|
County | TARRANT |
Highway | CS |
From | 0.1 MI E OF STALCUP RD |
To | 0.1 MI W OF STALCUP RD |
CSJ | 0902-90-211 |
Proj ID | STP 2023(867)HES |
Work Type | INTERSECTION & OPERATIONAL IMPRV |
|
| | 565876.00 | | 0.00 | 0.0 |
Work Order | 09-07-23 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 10-08-23 |
Contract Working Days | 200 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
DURABLE SPECIALTIES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0902-90-211 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 08233068 |
| Totals | 565876.00 | 0.00 | 0.00 | 0.0 |
|
County | TARRANT |
Highway | CS |
From | MUSTANG DR |
To | SH 114 WB FRONTAGE RD |
CSJ | 0902-90-217 |
Proj ID | STP 2022(871)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 0.350 | 509265.25 | | 387879.56 | 76.1 |
Work Order | 03-08-23 |
Work Began | 05-31-23 |
Work Completed | |
Time Computed | 05-26-23 |
Contract Working Days | 128 |
Addl Days Granted | 0 |
Working Days Charged | 122 |
Percent Time Used | 95 |
Contractor(s) |
WESSON CONSTRUCTION SERVICES, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0902-90-217 DUSTROL, INC. (1.61) BARRICADES UNLIMITED (0.85) PRO PAVERS, LLC (20.90) ROAD SOLUTIONS L.L.C. (19.44) AWP SAFETY (2.82) TRP CONSTRUCTION GROUP, LLC (5.66)
|
Contract # | 10223221 |
| Totals | 509265.25 | 0.00 | 387879.56 | 76.1 |
|
County | TARRANT |
Highway | VA |
From | ON SYSTEM SIGNALS |
To | IN ARLINGTON CITY LIMITS |
CSJ | 0902-90-244 |
Proj ID | STP 2B23(145)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 1328101.25 | | 141055.00 | 10.6 |
County | TARRANT |
Highway | VA |
From | ON SYSTEM SIGNALS |
To | IN ARLINGTON CITY LIMITS |
CSJ | 0902-90-245 |
Proj ID | STP 2B23(145)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 167652.40 | | 0.00 | 0.0 |
Work Order | 09-07-23 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 10-08-23 |
Contract Working Days | 207 |
Addl Days Granted | 0 |
Working Days Charged | 4 |
Percent Time Used | 1 |
Contractor(s) |
YUNEX LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0902-90-244 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 08233262 |
| Totals | 1495753.65 | 141055.00 | 141055.00 | 9.4 |
|
County | TARRANT |
Highway | VA |
From | JOHNSON COUNTY |
To | TARRANT COUNTY |
CSJ | 0902-90-300 |
Proj ID | F 2024(110) |
Work Type | BRIDGE MAINTENANCE |
|
| | 473301.00 | | 0.00 | 0.0 |
Work Order | 11-08-23 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 12-09-23 |
Contract Working Days | 150 |
Addl Days Granted | 0 |
Working Days Charged | 10 |
Percent Time Used | 6 |
Contractor(s) |
GIBSON & ASSOCIATES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0902-90-300 S & S BRIDGE PAINTING, INC. (0.00) DALLAS LITE AND BARRICADE, INC. (0.00)
|
Contract # | 10233221 |
| Totals | 473301.00 | 0.00 | 0.00 | 0.0 |
|
County | TARRANT |
Highway | IH 30 |
From | 1.0 MI W OF SH 360 |
To | GREAT SOUTHWEST PKWY |
CSJ | 1068-02-076 |
Proj ID | NH 2016(183) |
Work Type | GR STRS & SURF |
|
| 2.933 | 228440784.53 | | 300928438.89 | 99.9 |
County | TARRANT |
Highway | IH 30 |
From | 1.0 MI W OF SH 360 |
To | GREAT SOUTHWEST PKWY |
CSJ | 1068-02-123 |
Proj ID | NH 2007(893) |
Work Type | ROW ACQ, RELOC & UTILITIES |
|
| 0.001 | 4741104.00 | | 5723869.11 | 99.9 |
Work Order | 12-09-15 |
Work Began | 01-19-16 |
Work Completed | |
Time Computed | 01-19-16 |
Contract Working Days | 1,150 |
Addl Days Granted | 1,324 |
Working Days Charged | 2,460 |
Percent Time Used | 99 |
Contractor(s) |
WILLIAMS BROTHERS CONSTRUCTION CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 1068-02-076 USA SWPPP INSPECTIONS, INC. (0.99) THELIN RECYCLING COMPANY, L.P. (0.06) HIGHWAY PAVEMENT SPECIALTIES, INC. (0.06) SCOTT DERR PAINTING CO, LLC (0.21) BROOKLYN SWEEPS (0.35) F A BROWN"S CONSTRUCTION, LLC (0.67) REYNOLDS ASPHALT & CONSTRUCTION COMPANY (5.72) W.O.E. CONSTRUCTION (3.34) BUYERS BARRICADES, INC. (0.00) ROYAL REBAR (5.43) ARK CONTRACTING SERVICES, LLC (2.31) INTEGRATED ROADWAY SERVICES, INC. (4.41) TOTAL HIGHWAY MAINTENANCE, LLC (0.59) NORTH TEXAS CONTRACTING, INC. (7.30) MIKE ALBERT, INC. (0.13) 1 PRIORITY ENVIRONMENTAL SERVICES, INC. (0.40) AR DANIEL CONSTRUCTION SERVICES, INC. (0.07) BORE COMPANY, LLC (0.29) EXCEL 4 CONSTRUCTION, LLC (0.09) JAGOE-PUBLIC COMPANY (0.13) UNDER CONSTRUCTION INC. (0.07) FOUNDATION DRILLERS, INC. (0.03) MORNING STAR TREE SERVICE (0.00) ROADWAY CONSTRUCTION, LLC (0.01) N.L. SCHUTTE FOUNDATION DRILLING, INC. (0.04) MEX DRILLING (0.06) IMT CONSTRUCTION (0.01) RELIABLE CONCRETE CUTTING LLC (0.00) PRIME UTILITY CONSTRUCTION, L.L.C. (0.01) DALLAS FOUNDATION DRILLING CO., INC. (0.02) A R DANIEL CONSTRUCTION SERVICES, INCORPORATED (0.02) STEEL EFFECTS (0.00) RAY"S THREADING AND FAB SHOP (0.20) CIRCLE H CONTRACTORS, L.P. (0.01) SWEEPING SERVICES OF TEXAS - OPERATING, L.P. (0.09) LIBERTY PROCLAIMED MINISTRY (0.01) A-CORE CONCRETE CUTTING OF TEXAS, INC. (0.00) NORTEX CONCRETE LIFT & STABILIZATION, INC. (0.01) HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, LLC (0.01) SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. (0.32) TEXAS BOMANITE (0.42) NORTH TEXAS INTELLIGENT TRANSPORTATION SYSTEMS LLC (0.05) CELL-CRETE CORPORATION (0.10)
|
Contract # | 11153231 |
| Totals | 233181888.53 | 1127945.44 | 306652308.00 | 99.9 |
|
County | TARRANT |
Highway | FM 731 |
From | S HAMPTON RD |
To | DEER CREEK DR |
CSJ | 1094-02-017 |
Proj ID | F 2B23(174) |
Work Type | LANDSCAPE & SCENIC ENHANCEMENT |
|
| | 434716.00 | | 248586.25 | 57.1 |
Work Order | 09-07-23 |
Work Began | 01-29-24 |
Work Completed | |
Time Computed | 12-07-23 |
Contract Working Days | 60 |
Addl Days Granted | 0 |
Working Days Charged | 20 |
Percent Time Used | 33 |
Contractor(s) |
CENTRAL NORTH CONSTRUCTION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 1094-02-017 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 08233253 |
| Totals | 434716.00 | 248586.25 | 248586.25 | 57.1 |
|
County | TARRANT |
Highway | FM 718 |
From | WISE COUNTY LINE |
To | BU 287P |
CSJ | 1098-02-015 |
Proj ID | F 2023(864) |
Work Type | OVERLAY |
|
| 3.265 | 2852725.75 | | 2854869.09 | 99.9 |
Work Order | 07-19-23 |
Work Began | 09-11-23 |
Work Completed | |
Time Computed | 08-19-23 |
Contract Working Days | 128 |
Addl Days Granted | 0 |
Working Days Charged | 107 |
Percent Time Used | 83 |
Contractor(s) |
AUSTIN BRIDGE & ROAD SERVICES, LP |
SUBCONTRACTOR(S) FOR CCSJ: 1098-02-015 ODUM SERVICES, LLC (8.95) SYNERGY SIGNS & SERVICES LLC (1.94) TEXAS TRAFFIC AND BARRICADE, LLC (0.92) G J SEEDING, LLC (2.02) HILBASH INVESTMENT LLC (6.10) LINEAR TRAFFIC MARKINGS LLC (2.79)
|
Contract # | 06233234 |
| Totals | 2852725.75 | 267253.74 | 2854869.09 | 99.9 |
|
County | WISE |
Highway | FM 920 |
From | PARKER COUNTY LINE |
To | SH 199 |
CSJ | 1179-01-045 |
Proj ID | STP 2B20(201) |
Work Type | OVERLAY |
|
| 0.001 | 243658.05 | | 359674.86 | 99.9 |
County | PARKER |
Highway | FM 920 |
From | RIC WILLIAMSON MEMORIAL HIGHWAY |
To | WISE COUNTY LINE |
CSJ | 1179-02-039 |
Proj ID | STP 2B20(201) |
Work Type | OVERLAY |
|
| | 4943592.15 | | 5416726.50 | 99.9 |
Work Order | 10-21-20 |
Work Began | 12-10-20 |
Work Completed | |
Time Computed | 11-21-20 |
Contract Working Days | 126 |
Addl Days Granted | 56 |
Working Days Charged | 449 |
Percent Time Used | 246 |
Contractor(s) |
VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 1179-01-045 STATEWIDE SAFETY SYSTEMS (0.25) STRIPE-A-ZONE, INC. (4.00) J & M CONTRACTING, COMPANY (3.85) SYNERGY SIGNS & SERVICES LLC (2.04) R & A TRANSPORT, INC. (2.23) PROTEX EROSION CONTROL, LLC (0.60) SOUTHERN CROSS CONTRACTORS, LLC (3.30) THIRD COAST SERVICES LLC (0.24) PRIMATE CONSTRUCTION, LP (0.12) HDZ CONSTRUCTION (0.37)
|
Contract # | 09203007 |
| Totals | 5187250.20 | 16258.03 | 5776401.36 | 99.9 |
|
County | JOHNSON |
Highway | FM 917 |
From | FM 1902 |
To | MANSON ST. |
CSJ | 1181-02-038 |
Proj ID | F 2024(057) |
Work Type | OVERLAY |
|
| 1.704 | 6838229.11 | | 821501.68 | 12.0 |
Work Order | 10-23-23 |
Work Began | 01-02-24 |
Work Completed | |
Time Computed | 11-23-23 |
Contract Working Days | 256 |
Addl Days Granted | 0 |
Working Days Charged | 41 |
Percent Time Used | 16 |
Contractor(s) |
ED BELL CONSTRUCTION COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 1181-02-038 BEAN ELECTRICAL, INC. (3.39) BRENDA PRICE TRUCKING (0.73) DUSTROL, INC. (1.94) NORTHEASTERN PAVERS, LLC (27.48) SYNERGY SIGNS & SERVICES LLC (0.45) T-BAR FENCE, INC. (0.60) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (3.54) TEXAS SWPPP SERVICES (0.58) TRAFFIC HIGHWAY MAINTENANCE, LLC (2.30) AWP SAFETY (0.63)
|
Contract # | 09233015 |
| Totals | 6838229.11 | 768813.58 | 821501.68 | 12.0 |
|
County | JOHNSON |
Highway | FM 917 |
From | CR 806 |
To | IH 35W |
CSJ | 1181-03-040 |
Proj ID | STP 2022(873)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 2.226 | 4410629.30 | | 1577000.20 | 35.7 |
Work Order | 09-28-22 |
Work Began | 08-08-23 |
Work Completed | |
Time Computed | 12-28-22 |
Contract Working Days | 278 |
Addl Days Granted | 0 |
Working Days Charged | 162 |
Percent Time Used | 58 |
Contractor(s) |
JAY MILLS CONTRACTING, INCORPORATED |
SUBCONTRACTOR(S) FOR CCSJ: 1181-03-040 WEST TEXAS ROCK RESOURCES, LLC (0.09) SYNERGY SIGNS & SERVICES LLC (0.55) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (7.59) NORTHEASTERN PAVERS, LLC (27.95) RAMBO CONTRACTING, INC. (3.27) FARR FOUNDATION, INC. (1.24) TRP CONSTRUCTION GROUP, LLC (2.46)
|
Contract # | 08223013 |
| Totals | 4410629.30 | 75211.17 | 1577000.20 | 35.7 |
|
County | TARRANT |
Highway | FM 1187 |
From | WEST OF IH 35W NB FRONTAGE ROAD |
To | WEST OF HUNTERS FIELD BLVD |
CSJ | 1330-02-049 |
Proj ID | C 1330-2-49 |
Work Type | OVERLAY |
|
| 0.991 | 2305368.40 | | 2019390.39 | 87.5 |
Work Order | 02-14-23 |
Work Began | 05-01-23 |
Work Completed | |
Time Computed | 03-17-23 |
Contract Working Days | 160 |
Addl Days Granted | 0 |
Working Days Charged | 128 |
Percent Time Used | 80 |
Contractor(s) |
FOUTSCO PAVING COMPANY, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 1330-02-049 FORTSON CONTRACTING, INC. (0.78) STRAIGHT LINE (5.53) SYNERGY SIGNS & SERVICES LLC (0.45) TIERRA X EXCAVATION LLC (9.45) VENUS CONSTRUCTION COMPANY (16.77) TRAFFIC HIGHWAY MAINTENANCE, LLC (2.01)
|
Contract # | 01233014 |
| Totals | 2305368.40 | 196487.42 | 2019390.39 | 87.5 |
|
County | JOHNSON |
Highway | FM 2258 |
From | CR 205 |
To | ELLIS COUNTY LINE |
CSJ | 1599-03-016 |
Proj ID | F 2023(038) |
Work Type | OVERLAY |
|
| | 13791080.43 | | 1083793.50 | 7.8 |
Work Order | 04-19-23 |
Work Began | 11-16-23 |
Work Completed | |
Time Computed | 05-20-23 |
Contract Working Days | 278 |
Addl Days Granted | 0 |
Working Days Charged | 159 |
Percent Time Used | 57 |
Contractor(s) |
JAY MILLS CONTRACTING, INCORPORATED |
SUBCONTRACTOR(S) FOR CCSJ: 1599-03-016 NORTHEASTERN PAVERS, LLC (17.80) WEST TEXAS ROCK RESOURCES, LLC (0.05) MARCOMS CONSTRUCTION LLC (0.36) TRP CONSTRUCTION GROUP, LLC (0.45) RAMBO CONTRACTING, INC. (2.75) DIIBS SPECIALISTS, LLC (1.74) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (6.54) FARR FOUNDATION, INC. (1.82)
|
Contract # | 03233209 |
| Totals | 13791080.43 | 143948.50 | 1083793.50 | 7.8 |
|
County | JOHNSON ETC |
Highway | FM 1807 ETC |
From | FM 1706 |
To | ELLIS COUNTY LINE |
CSJ | 1600-02-019 |
Proj ID | C 1600-2-19 |
Work Type | SEAL COAT |
|
| 29.091 | 3153376.15 | | 0.00 | 0.0 |
Work Order | 01-10-24 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 02-10-24 |
Contract Working Days | 64 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
NORTHEASTERN PAVERS, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 1600-02-019 COX PAVING OF TEXAS, INC. (45.93) BARRICADES PLUS, LLC (1.71) STRIPE-A-ZONE, LLC (8.22)
|
Contract # | 12233215 |
| Totals | 3153376.15 | 0.00 | 0.00 | 0.0 |
|
County | JOHNSON |
Highway | FM 1434 |
From | FS 1434 |
To | S OF FM 200 |
CSJ | 1853-01-046 |
Proj ID | STP 2021(079) |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 14.174 | 17922672.36 | | 13072225.92 | 72.9 |
County | JOHNSON |
Highway | FM 1434 |
From | FS 1434 |
To | S OF FM 200 |
CSJ | 1853-01-048 |
Proj ID | C 1853-1-48 |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 14.174 | 2969620.67 | | 1533821.37 | 51.6 |
Work Order | 10-21-20 |
Work Began | 06-07-21 |
Work Completed | |
Time Computed | 11-21-20 |
Contract Working Days | 790 |
Addl Days Granted | 31 |
Working Days Charged | 683 |
Percent Time Used | 83 |
Contractor(s) |
JAY MILLS CONTRACTING, INCORPORATED |
SUBCONTRACTOR(S) FOR CCSJ: 1853-01-046 RAMBO CONTRACTING, INC. (9.53) SOUTHERN CROSS CONTRACTORS, LLC (0.63) TEXAS ALTERNATIVE GRASSER INCORPORATED (1.73) DUSTIN ALLEN, INC. (0.68) WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (4.41) JR WEST TEXAS CONCRETE LLC (2.90) FARR FOUNDATION, INC. (2.33) TOTAL HIGHWAY MAINTENANCE, LLC (2.64) NORTHEASTERN PAVERS, LLC (18.45) WEST TEXAS ROCK RESOURCES, LLC (0.10)
|
Contract # | 09203001 |
| Totals | 20892293.03 | 213609.38 | 14606047.29 | 69.9 |
|
County | TARRANT |
Highway | SS 303 |
From | COLLINS ST. |
To | SH 360 |
CSJ | 2208-01-070 |
Proj ID | CM 2B20(202) |
Work Type | PEDESTRIAN, SIDEWALKS & CURB RAMPS |
|
| 1.937 | 3172002.50 | | 3171102.56 | 99.9 |
Work Order | 10-21-20 |
Work Began | 01-18-21 |
Work Completed | |
Time Computed | 11-20-20 |
Contract Working Days | 192 |
Addl Days Granted | 122 |
Working Days Charged | 328 |
Percent Time Used | 104 |
Contractor(s) |
TEXAS-REYES GROUP LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 2208-01-070 STATEWIDE SAFETY SYSTEMS (0.96) SPOONER & ASSOCIATES, INC. (1.16) C.T. AND S. METALWORKS, INC. (0.61) BIG D CONCRETE, INC. (8.49) ELITE STRIPING, LLC (0.10) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (3.71) COWBOY TRUCKING (3.08) TEXAS STAR SAWING & SEALING, LLC (0.83) ALPHA TESTING, INC. (0.99) INTEGRATED ROADWAY SERVICES, INC. (18.47) C. GREEN SCAPING, L.P. (0.31) TEAM CONSULTANTS INC. (0.67) DFW AGGREGATES, LLC (2.52) MOLINA TRUCKING (0.31) RELIABLE CONCRETE CUTTING LLC (0.00) ACT SAW CUTTING & REMOVAL (0.99) C T & S METAL FABRICATORS INC. (0.00) BEAN ELECTRICAL, INC. (1.95)
|
Contract # | 09203011 |
| Totals | 3172002.50 | 37079.52 | 3171102.56 | 99.9 |
|