Monthly State Let Construction Report For Fort Worth District As Of Apr 7, 2016 Page 9 Of 9

Last Update: Thursday, April 7, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyPARKER
Highway FM 3028
From FM 3028 AT ROCKY CREEK
To .
CSJ 2930-02-011
Proj ID BR 1502(336)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.100 1561559.71 61333.92 697243.40 44.6
Work Order 08-13-15
Work Began 09-22-15
Work Completed  
Time Computed 09-12-15
Contract Working Days 130
Addl Days Granted 0
Working Days Charged 92
Percent Time Used 70
Contractor(s)
PIERCE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2930-02-011
WOLFE CONSTRUCTION GROUP, INC. (0.47%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.95%)
STORM WATER MANAGEMENT, INC. (0.55%)
ALTUS TRAFFIC MANAGEMENT LLC (0.37%)
PEACHTREE CONSTRUCTION, LTD. (3.78%)
FORTSON CONTRACTING, INC.(2.02%)
TEXOP CONSTRUCTION (0.47%)
STRIPING TECHNOLOGY, L.P.(0.47%)
Contract # 06153053
Totals 1561559.71 61333.92 697243.40 44.6

CountyJOHNSON
Highway FM 2738
From TARRANT COUNTY LINE
To FM-2738 IN LILLIAN
CSJ 3010-02-013
Proj ID STP 2014(940)
Work Type SEAL COAT AND OVERLAY
 
5.196 1757389.22 0.00 1733198.02 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-13-14
Work Began 04-13-15
Work Completed 10-05-15
Time Computed 08-29-14
Contract Working Days 85
Addl Days Granted 0
Working Days Charged 88
Percent Time Used 103
Contractor(s)
PEACHTREE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 3010-02-013
DUSTROL, INC.(2.94%)
STRIPING TECHNOLOGY, L.P.(3.59%)
VANN/ELLI, INC.(3.26%)
WOLFE CONSTRUCTION GROUP, INC. (0.20%)
CROSSROADS, L.P. (0.56%)
Contract # 06143249
Totals 1757389.22 0.00 1733198.02 100.0

CountyJOHNSON
Highway FM 3136
From 5.213 MILES EAST OF FM 4
To 10.343 MILES EAST OF FM 4
CSJ 3348-01-019
Proj ID STP 1502(549)HES
Work Type GR, BS, DR, STR, & PAVT
 
5.192 6829235.17 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-28-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 384
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 3348-01-019
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01163018
Totals 6829235.17 0.00 0.00 0.0

CountyJOHNSON
Highway FM 3391
From AT STONE ROAD
To IN BURLESON
CSJ 3372-01-014
Proj ID CC 3372-1-14
Work Type TRAFFIC SIGNAL INSTALLATION
 
0.123 137750.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-16-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 3372-01-014
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10153027
Totals 137750.00 0.00 0.00 0.0

CountyPARKER
Highway FM 3325
From IH 20
To FM 1886
CSJ 3516-01-015
Proj ID STP 2013(675)
Work Type GR, BS, DR, STRUC AND PAVEMENT
 
7.160 3283284.20 0.00 3220075.53 99.9
Work Order 01-06-14
Work Began 01-28-14
Work Completed  
Time Computed 01-22-14
Contract Working Days 256
Addl Days Granted 64
Working Days Charged 381
Percent Time Used 119
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 3516-01-015
RAMBO CONTRACTING, INC.(1.36%)
INDEPENDENT UTILITY CONSTRUCTION INCORPORATED(0.40%)
SURFACE PREPARATION TECHNOLOGIES, LLC(0.29%)
NORTHEASTERN PAVERS, INC.( 37.58%)
STRIPING TECHNOLOGY, L.P.(1.71%)
JM MATERIALS, INC. (2.37%)
TEXAS ALTERNATIVE GRASSER, INC.(0.71%)
ODUM SERVICES, L.P.(0.87%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.91%)
Contract # 08133054
Totals 3283284.20 0.00 3220075.53 99.9

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9