Monthly Local Let Maintenance Report For Fort Worth District As Of Sep 17, 2020 Page 2 Of 5

Last Update: Monday, September 21, 2020
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountySOMERVELL
HighwayUS0067
FromVARIOUS LOCATIONS IN HOO, SOMERVELL
ToAND ERATH COUNTIES
CSJ6318-05-001
Proj IDSUP - 631805001
Work TypePICNIC AREA MAINTENANCE
 
0.010114036.34111851.3398.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-02-18
Work Began01-03-18
Work Completed
Time Computed01-03-18
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
WORKQUEST
FRESH START OF MONROE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6318-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12170232
Totals114036.340.00111851.3398.0

CountyPARKER
HighwayIH0020
FromVARIOUS LOCATION WITHIN PARKER
To& PALO PINTO COUNTIES
CSJ6318-06-001
Proj IDSUP - 631806001
Work TypePICNIC AREA MAINTENANCE
 
0.01077143.2067419.50100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-15-18
Work Began01-15-18
Work Completed12-31-18
Time Computed01-15-18
Contract Working Days358
Addl Days Granted0
Working Days Charged351
Percent Time Used98
Contractor(s)
WORKQUEST
I AM WORKS ASSOCIATION
SUBCONTRACTOR(S) FOR CCSJ: 6318-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01180231
Totals77143.200.0067419.50100.0

CountyPARKER
HighwayIH0020
FromVARIOUS ROADS IN
ToPARKER / PALO PINTO
CSJ6318-28-001
Proj IDRMC - 631828001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
116.000239500.00240170.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-09-18
Work Began03-10-18
Work Completed08-27-18
Time Computed03-10-18
Contract Working Days137
Addl Days Granted0
Working Days Charged133
Percent Time Used97
Contractor(s)
WESTGATE GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6318-28-001
DICKEY LANDSCAPE CONTRACTORS, INC. (46.34)
Contract #08170202
Totals239500.000.00240170.00100.0

CountyPARKER
HighwayIH0020
FromWEATHERFORD/MINERAL WELLS OFFICES &
ToTO GORDON LOCATION
CSJ6318-54-001
Proj IDSUP - 631854001
Work TypeJANITORIAL & GROUNDS WORK MAINTENANCE
 
0.01061457.9954978.8489.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-01-18
Work Completed
Time Computed02-01-18
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
WORKQUEST
I AM WORKS ASSOCIATION
SUBCONTRACTOR(S) FOR CCSJ: 6318-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01180232
Totals61457.990.0054978.8489.4

CountyWISE
HighwayUS0380
FromWISE AND JACK COUNTIES
ToWISE AND JACK COUNTIES
CSJ6322-27-001
Proj IDRMC - 632227001
Work TypeCALL OUT REFL PAVE MARKINGS AND MARKERS
 
0.100278580.11299806.22100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-11-18
Work Began06-18-18
Work Completed07-24-19
Time Computed06-18-18
Contract Working Days365
Addl Days Granted0
Working Days Charged355
Percent Time Used97
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6322-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03180201
Totals278580.110.00299806.22100.0

CountyWISE
HighwayUS0081
FromVARIOUS ROADWAYS WITHIN
ToJACK & WISE COUNTIES
CSJ6324-24-001
Proj IDRMC - 632424001
Work TypeDEBRIS REMOVAL
 
0.10091525.15172750.3099.9
Work Order07-02-18
Work Began07-10-18
Work Completed
Time Computed07-10-18
Contract Working Days304
Addl Days Granted365
Working Days Charged654
Percent Time Used97
Contractor(s)
TEXAS TMA RENTAL
SUBCONTRACTOR(S) FOR CCSJ: 6324-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03180202
Totals91525.156738.90172750.3099.9

CountyTARRANT
HighwayIH0820
FromLITTER REMOVAL WITHIN
ToNORTH TARRANT COUNTY
CSJ6325-46-001
Proj IDSUP - 632546001
Work TypeLITTER REMOVAL
 
0.010456008.80458843.8499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-30-18
Work Began09-05-18
Work Completed
Time Computed09-01-18
Contract Working Days365
Addl Days Granted0
Working Days Charged361
Percent Time Used98
Contractor(s)
WORKQUEST
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6325-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08180236
Totals456008.800.00458843.8499.9

CountyTARRANT
HighwayIH0820
FromVARIOUS ROADWAYS IN NORTH TARRANT COUNTY
ToNORTH TARRANT COUNTY
CSJ6325-80-001
Proj IDRMC - 632580001
Work TypeCALL-OUT STRPG, REFLEC PAV MRKGS & MRKS
 
0.010220889.50135854.8161.5
Work Order09-12-19
Work Began09-16-19
Work Completed
Time Computed09-16-19
Contract Working Days180
Addl Days Granted0
Working Days Charged299
Percent Time Used166
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6325-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06190201
Totals220889.500.00135854.8161.5

CountyPARKER
HighwayUS0180
FromMAINTENANCE OFFICES WITHIN
ToPARKER/PALO PINTO COUNTY
CSJ6326-83-001
Proj IDSUP - 632683001
Work TypeJANITORIAL AND GROUNDS MAINTENANCE
 
0.01065740.5055153.70100.0
Work Order00-00-00
Work Began02-01-19
Work Completed01-31-20
Time Computed02-01-19
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
WORKQUEST
I AM WORKS ASSOCIATION
SUBCONTRACTOR(S) FOR CCSJ: 6326-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01190231
Totals65740.503127.7555153.70100.0

CountyTARRANT
HighwayIH0020
FromFORT WORTH DISTRICT
ToSW LOOP 820
CSJ6327-35-001
Proj IDSUP - 632735001
Work TypeJANITORIAL MAINTENANCE
 
0.0102755080.00286987.5010.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-01-18
Work Completed
Time Computed01-01-18
Contract Working Days365
Addl Days Granted90
Working Days Charged453
Percent Time Used99
Contractor(s)
WORKQUEST
RISING STAR RESOURCE DEVELOPMENT CORP.
SUBCONTRACTOR(S) FOR CCSJ: 6327-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12170233
Totals2755080.000.00286987.5010.4

CountyTARRANT
HighwaySH0010
FromNORTH TARRANT ENGINEERS AND
ToMAINTENANCE OFFICE
CSJ6327-55-001
Proj IDSUP - 632755001
Work TypeJANITORIAL AND GROUNDS MAINTENENACE
 
0.01035320.1630776.1287.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-02-18
Work Completed
Time Computed01-02-18
Contract Working Days365
Addl Days Granted0
Working Days Charged359
Percent Time Used98
Contractor(s)
WORKQUEST
RISING STAR RESOURCE DEVELOPMENT CORP.
SUBCONTRACTOR(S) FOR CCSJ: 6327-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12170234
Totals35320.160.0030776.1287.1

CountyERATH
HighwayUS0377
FromVARIOUS LOCATIONS IN
ToERATH, HOOD AND SOMERVELL COUNTIES
CSJ6329-74-001
Proj IDRMC - 632974001
Work TypeGUARDRAIL INSTALLATION AND REPAIR
 
0.010268180.00622089.0099.9
Work Order11-26-18
Work Began11-26-18
Work Completed
Time Computed11-06-18
Contract Working Days365
Addl Days Granted365
Working Days Charged665
Percent Time Used91
Contractor(s)
VANN/ELLI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6329-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09180201
Totals268180.0058069.00622089.0099.9

CountyPARKER
HighwayIH0020
FromVARIOUS ROADSIDES WITHIN
ToPARKER AND PALO PINTO COUNTIES
CSJ6329-84-001
Proj IDSUP - 632984001
Work TypeLITTER REMOVAL
 
0.010391483.60397116.9099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-20-18
Work Began09-24-18
Work Completed
Time Computed09-01-18
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
WORKQUEST
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6329-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08180232
Totals391483.600.00397116.9099.9

CountyJOHNSON
HighwayIH0035W
FromJOHNSON COUNTY
To.
CSJ6331-44-001
Proj IDRMC - 633144001
Work TypeSWEEPING AND DEBRIS REMOVAL
 
0.010154567.00215549.5099.9
Work Order02-01-19
Work Began02-01-19
Work Completed
Time Computed02-01-19
Contract Working Days365
Addl Days Granted182
Working Days Charged541
Percent Time Used98
Contractor(s)
TEXAS TMA RENTAL
SUBCONTRACTOR(S) FOR CCSJ: 6331-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11180203
Totals154567.0011946.00215549.5099.9

CountyHOOD
HighwayUS0377
FromVARIOUS ROADSIDES WITHIN
ToHOOD, SOMERVELL AND ERATH COUNTIES
CSJ6332-67-001
Proj IDSUP - 633267001
Work TypeLITTER REMOVAL
 
0.010147732.00143492.0097.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-18
Work Began10-05-18
Work Completed
Time Computed09-01-18
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
WORKQUEST
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6332-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08180231
Totals147732.000.00143492.0097.1

CountyTARRANT
HighwayIH0020
FromVARIOUS ROADSIDES WITHIN
ToSOUTH TARRANT COUNTY
CSJ6332-79-001
Proj IDSUP - 633279001
Work TypeLITTER REMOVAL
 
0.010757757.60732396.2896.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-18
Work Began09-05-18
Work Completed
Time Computed09-01-18
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
WORKQUEST
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6332-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08180233
Totals757757.600.00732396.2896.6

CountyERATH
HighwayUS0377
FromVARIOUS LOCATIONS
ToERATH,HOOD AND SOMERVELL COUNTY
CSJ6333-27-001
Proj IDRMC - 633327001
Work TypeCALLOUT REFL PAV MRKING,MRKR,RUMBLE STIP
 
0.010297190.00215546.5572.5
Work Order01-31-19
Work Began02-01-19
Work Completed
Time Computed02-01-19
Contract Working Days365
Addl Days Granted365
Working Days Charged578
Percent Time Used79
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6333-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11180202
Totals297190.0058685.30215546.5572.5

CountyERATH
HighwayUS0377
FromVARIOUS LOCATIONS
ToERATH, HOOD AND SOMERVELL COUNTY
CSJ6334-39-001
Proj IDRMC - 633439001
Work TypeREFLECTORIZED PAVEMENT MARKINGS AND MRKS
 
0.010221553.46192450.8987.1
Work Order05-13-19
Work Began05-13-19
Work Completed
Time Computed05-13-19
Contract Working Days34
Addl Days Granted6
Working Days Charged41
Percent Time Used102
Contractor(s)
REPUBLIC TRAFFIC SAFETY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6334-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02190201
Totals221553.4632275.09192450.8987.1

CountyERATH
HighwayUS0377
FromVARIOUS LOCATIONS
ToERATH,HOOD AND SOMERVELL COUNTY
CSJ6334-40-001
Proj IDRMC - 633440001
Work TypeCLEANING AND SWEEPNG HIGHWAYS
 
0.010125815.00211500.0099.9
Work Order02-28-19
Work Began01-30-19
Work Completed
Time Computed01-29-19
Contract Working Days365
Addl Days Granted212
Working Days Charged574
Percent Time Used99
Contractor(s)
CEN-TEX IRRIGATION SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6334-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11180201
Totals125815.0010600.00211500.0099.9

CountyERATH
HighwayUS0377
FromVARIOUS LOCATIONS IN
ToERATH,HOOD AND SOMERVELL
CSJ6334-41-001
Proj IDRMC - 633441001
Work TypeCLEANING AND SEALING JOINTS AND CRACKS
 
0.010174906.77180940.3699.9
Work Order11-22-19
Work Began11-23-19
Work Completed
Time Computed11-22-19
Contract Working Days30
Addl Days Granted0
Working Days Charged26
Percent Time Used86
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6334-41-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09190203
Totals174906.77151120.90180940.3699.9

page 1 | page 2 | page 3 | page 4 | page 5