Monthly Local Let Maintenance Report For Fort Worth District As Of Jul 12, 2019 Page 2 Of 4

Last Update: Friday, July 12, 2019
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyPARKER
HighwayIH0020
FromVARIOUS ROADWAYS IN PARKER AND
ToPALO PINTO COUNTIES
CSJ6315-68-001
Proj IDSUP - 631568001
Work TypeLITTER REMOVAL
 
0.010293917.44286342.94100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-15-17
Work Began09-22-17
Work Completed08-31-18
Time Computed09-15-17
Contract Working Days365
Addl Days Granted0
Working Days Charged350
Percent Time Used95
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6315-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08170235
Totals293917.440.00286342.94100.0

CountyTARRANT
HighwayIH0820
FromVARIOUS ROADWAYS IN
ToNORTH TARRANT COUNTY
CSJ6315-69-001
Proj IDSUP - 631569001
Work TypeLITTER REMOVAL
 
0.010391997.62360136.2691.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-14-17
Work Began09-15-17
Work Completed
Time Computed09-15-17
Contract Working Days365
Addl Days Granted0
Working Days Charged348
Percent Time Used95
Contractor(s)
TIBH INDUSTRIES, INC.
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6315-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08170236
Totals391997.620.00360136.2691.8

CountyJOHNSON
HighwayUS0067
FromJOHNSON COUNTY
ToWITHIN CITY LIMITS
CSJ6315-82-001
Proj IDSUP - 631582001
Work TypeLANDSCAPING MAINTENANCE
 
0.01017700.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-01-17
Work Began00-00-00
Work Completed
Time Computed12-07-17
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6315-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05170231
Totals17700.000.000.000.0

CountyJOHNSON
HighwayFM2280
FromKEENE MAINTENANCE
ToOFFICE
CSJ6315-86-001
Proj IDSUP - 631586001
Work TypeJANITORIAL AND GROUNDS MAINTENANCE
 
0.01025095.0019545.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-04-17
Work Completed11-30-18
Time Computed12-01-18
Contract Working Days365
Addl Days Granted0
Working Days Charged360
Percent Time Used98
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6315-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11170231
Totals25095.000.0019545.00100.0

CountyWISE
HighwayUS0081
FromUS DECATUR,OFFICE JACKSBORO OFFICE, OLD
ToAREA OFFICE, JACKSBORO MAINTENANCE YARD
CSJ6315-87-001
Proj IDSUP - 631587001
Work TypeJANITORIAL AND GROUNDS MAINTENANCE
 
0.01062450.0052360.0083.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-03-17
Work Began11-03-17
Work Completed
Time Computed11-09-17
Contract Working Days365
Addl Days Granted0
Working Days Charged362
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6315-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10170231
Totals62450.000.0052360.0083.8

CountyJOHNSON
HighwayIH0035W
FromVARIOUS ROADWAYS WITHIN JOHNSON
ToCOUNTY
CSJ6316-02-001
Proj IDRMC - 631602001
Work TypeCLEANING AND SEALING JOINTS & CRACKS
 
0.010205978.00183928.4089.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-30-17
Work Began11-14-17
Work Completed
Time Computed11-06-17
Contract Working Days43
Addl Days Granted0
Working Days Charged17
Percent Time Used39
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6316-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07170201
Totals205978.000.00183928.4089.2

CountyPARKER
HighwayIH0020
FromVARIOUS LOCATIONS IN
ToPARKER AND PALO PINTO
CSJ6316-03-001
Proj IDRMC - 631603001
Work TypeSWEEPING AND DEBRIS
 
0.010286745.33411667.8099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-04-17
Work Began10-04-17
Work Completed
Time Computed10-04-17
Contract Working Days365
Addl Days Granted120
Working Days Charged485
Percent Time Used100
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6316-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07170203
Totals286745.330.00411667.8099.9

CountyJOHNSON
HighwayIH0035W
FromVARIOUS ROADWAYS WITHIN
ToJOHNSON COUNTY
CSJ6316-15-001
Proj IDRMC - 631615001
Work TypeCALL OUT REFLEC PVMT MRKGS & MRKRS
 
0.010256350.00361994.3099.9
Work Order02-27-18
Work Began03-08-18
Work Completed
Time Computed03-05-18
Contract Working Days88
Addl Days Granted72
Working Days Charged41
Percent Time Used25
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6316-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10170201
Totals256350.000.00361994.3099.9

CountyJOHNSON
HighwayIH0035W
FromJOHNSON COUNTY
To.
CSJ6316-30-001
Proj IDRMC - 631630001
Work TypeSWEEPING AND DEBRIS REMOVAL JOHNSON CO
 
0.010138385.4099771.50100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-16-18
Work Began03-05-18
Work Completed01-27-19
Time Computed02-22-18
Contract Working Days365
Addl Days Granted0
Working Days Charged340
Percent Time Used93
Contractor(s)
DEMENT ENTERPRISES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6316-30-001
TEXAS TMA RENTAL (70.00)
Contract #12170201
Totals138385.400.0099771.50100.0

CountyWISE
HighwayUS0380
FromVARIOUS LOCATIONS IN WISE & JACK COUNTY
ToMAINTENANCE AREAS
CSJ6316-56-001
Proj IDRMC - 631656001
Work TypeTREE & BRUSH TRIMMING AND REMOVAL
 
0.100350500.00328371.0093.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-25-17
Work Began11-02-17
Work Completed
Time Computed11-02-17
Contract Working Days110
Addl Days Granted25
Working Days Charged134
Percent Time Used99
Contractor(s)
BOEN LANDSCAPING & IRRIGATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6316-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08170201
Totals350500.000.00328371.0093.6

CountyWISE
HighwayUS0081
FromVARIOUS LOCATIONS WITHIN WISE
ToAND JACK CONTIES
CSJ6318-04-001
Proj IDSUP - 631804001
Work TypePICNIC AREA MAINTENANCE
 
0.01056810.0051330.0090.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-04-18
Work Began01-05-18
Work Completed
Time Computed01-05-18
Contract Working Days365
Addl Days Granted0
Working Days Charged360
Percent Time Used98
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6318-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12170231
Totals56810.000.0051330.0090.3

CountySOMERVELL
HighwayUS0067
FromVARIOUS LOCATIONS IN HOO, SOMERVELL
ToAND ERATH COUNTIES
CSJ6318-05-001
Proj IDSUP - 631805001
Work TypePICNIC AREA MAINTENANCE
 
0.010114036.34111851.3398.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-02-18
Work Began01-03-18
Work Completed
Time Computed01-03-18
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
FRESH START OF MONROE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6318-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12170232
Totals114036.340.00111851.3398.0

CountyPARKER
HighwayIH0020
FromVARIOUS LOCATION WITHIN PARKER
To& PALO PINTO COUNTIES
CSJ6318-06-001
Proj IDSUP - 631806001
Work TypePICNIC AREA MAINTENANCE
 
0.01077143.2067419.50100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-15-18
Work Began01-15-18
Work Completed12-31-18
Time Computed01-15-18
Contract Working Days358
Addl Days Granted0
Working Days Charged351
Percent Time Used98
Contractor(s)
TIBH INDUSTRIES, INC.
I AM WORKS ASSOCIATION
SUBCONTRACTOR(S) FOR CCSJ: 6318-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01180231
Totals77143.200.0067419.50100.0

CountyPARKER
HighwayIH0020
FromVARIOUS ROADS IN
ToPARKER / PALO PINTO
CSJ6318-28-001
Proj IDRMC - 631828001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
116.000239500.00240170.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-09-18
Work Began03-10-18
Work Completed08-27-18
Time Computed03-10-18
Contract Working Days137
Addl Days Granted0
Working Days Charged133
Percent Time Used97
Contractor(s)
WESTGATE GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6318-28-001
DICKEY LANDSCAPE CONTRACTORS, INC. (46.34)
Contract #08170202
Totals239500.000.00240170.00100.0

CountyPARKER
HighwayIH0020
FromWEATHERFORD/MINERAL WELLS OFFICES &
ToTO GORDON LOCATION
CSJ6318-54-001
Proj IDSUP - 631854001
Work TypeJANITORIAL & GROUNDS WORK MAINTENANCE
 
0.01061457.9954978.8489.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-01-18
Work Completed
Time Computed02-01-18
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
I AM WORKS ASSOCIATION
SUBCONTRACTOR(S) FOR CCSJ: 6318-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01180232
Totals61457.990.0054978.8489.4

CountyERATH
HighwaySH0006
FromFM 847
ToFM 914
CSJ6319-09-001
Proj IDRMC - 631909001
Work TypeEMERGENCY WORK ON SH 6 IN ERATH COUNTY
 
8.1941755117.003798424.58100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-16-17
Work Completed09-20-17
Time Computed06-16-17
Contract Working Days47
Addl Days Granted7
Working Days Charged54
Percent Time Used100
Contractor(s)
PEACHTREE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6319-09-001
DUSTROL, INC. (1.18)
TRP CONSTRUCTION GROUP, LLC (4.41)
CROSS ROADS, L.P. (0.74)
Contract #06170240
Totals1755117.000.003798424.58100.0

CountyWISE
HighwayUS0380
FromWISE AND JACK COUNTIES
ToWISE AND JACK COUNTIES
CSJ6322-27-001
Proj IDRMC - 632227001
Work TypeCALL OUT REFL PAVE MARKINGS AND MARKERS
 
0.100278580.11299806.2299.9
Work Order06-11-18
Work Began06-18-18
Work Completed
Time Computed06-18-18
Contract Working Days365
Addl Days Granted0
Working Days Charged355
Percent Time Used97
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6322-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03180201
Totals278580.1119994.52299806.2299.9

CountyWISE
HighwayUS0081
FromVARIOUS ROADWAYS WITHIN
ToJACK & WISE COUNTIES
CSJ6324-24-001
Proj IDRMC - 632424001
Work TypeDEBRIS REMOVAL
 
0.10091525.1596564.0599.9
Work Order07-02-18
Work Began07-10-18
Work Completed
Time Computed07-10-18
Contract Working Days304
Addl Days Granted365
Working Days Charged351
Percent Time Used52
Contractor(s)
TEXAS TMA RENTAL
SUBCONTRACTOR(S) FOR CCSJ: 6324-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03180202
Totals91525.159058.3596564.0599.9

CountyWISE
HighwayUS0380
FromMAINTENANCE OFFICES WITHIN
ToWISE AND JACK COUNTY
CSJ6325-40-001
Proj IDSUP - 632540001
Work TypeJANITORIAL AND GROUNDS MAINTENANCE
 
0.01063547.0034076.0053.6
Work Order11-01-18
Work Began11-02-18
Work Completed
Time Computed11-02-18
Contract Working Days365
Addl Days Granted0
Working Days Charged236
Percent Time Used64
Contractor(s)
WORKQUEST
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6325-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10180231
Totals63547.005161.0034076.0053.6

CountyWISE
HighwayUS0081
FromLITTER REMOVAL WITHIN
ToWISE AND JACK COUNTY
CSJ6325-42-001
Proj IDSUP - 632542001
Work TypeLITTER REMOVAL
 
0.010221190.33155176.6870.1
Work Order09-07-18
Work Began09-19-18
Work Completed
Time Computed09-10-18
Contract Working Days365
Addl Days Granted0
Working Days Charged289
Percent Time Used79
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6325-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08180235
Totals221190.3330763.20155176.6870.1

page 1 | page 2 | page 3 | page 4