Monthly Local Let Maintenance Report For Fort Worth District As Of Sep 10, 2018 Page 2 Of 4

Last Update: Monday, September 10, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyPARKER
HighwayIH0020
FromVARIOUS ROADWAYS WITHIN PARKER
ToAND PALO PINTO COUNTIES
CSJ6301-31-001
Proj IDRMC - 630131001
Work TypeCALL OUT REFLEC PAV MRKGS PARKER
 
0.010255737.50418898.40100.0
Work Order07-11-16
Work Began07-17-16
Work Completed08-31-18
Time Computed07-14-16
Contract Working Days89
Addl Days Granted36
Working Days Charged99
Percent Time Used79
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6301-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05160206
Totals255737.5041147.80418898.40100.0

CountyJOHNSON
HighwayIH0035W
FromJOHNSON COUNTY
To.
CSJ6301-97-001
Proj IDRMC - 630197001
Work TypeSWEEPING AND DEBRIS REMOVAL
 
0.010136860.80123788.90100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-29-16
Work Began12-06-16
Work Completed01-25-18
Time Computed12-06-16
Contract Working Days365
Addl Days Granted31
Working Days Charged387
Percent Time Used97
Contractor(s)
TEXAS TMA RENTAL
SUBCONTRACTOR(S) FOR CCSJ: 6301-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07160205
Totals136860.800.00123788.90100.0

CountyTARRANT
HighwayIH0030
FromVARIOUS LOCATIONS WITHIN
ToSOUTH TARRANT COUNTY
CSJ6302-93-001
Proj IDRMC - 630293001
Work TypeCLEANING & SEALING JOINTS & CRACKS
 
0.010347656.40395102.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-14-16
Work Began00-00-00
Work Completed
Time Computed11-21-16
Contract Working Days45
Addl Days Granted0
Working Days Charged12
Percent Time Used26
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6302-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07160204
Totals347656.400.00395102.0099.9

CountySOMERVELL
HighwayUS0067
FromVARIOUS ROADWAYS IN HOOD, SOMERVELL, &
ToERATH COUNTIES
CSJ6303-13-001
Proj IDSUP - 630313001
Work TypeLITTER REMOVAL
 
0.010137244.12141571.24100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-20-16
Work Began09-20-16
Work Completed12-01-17
Time Computed09-27-16
Contract Working Days365
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6303-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160236
Totals137244.120.00141571.24100.0

CountyTARRANT
HighwayIH0820
FromVARIOUS LOCATION WITHIN
ToNORTH TARRANT COUNTY
CSJ6303-66-001
Proj IDRMC - 630366001
Work TypeCALL-OUT STRIPING & PREFAB HANDWORK
 
0.010252480.00245344.0097.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-05-16
Work Began12-05-16
Work Completed
Time Computed12-05-16
Contract Working Days120
Addl Days Granted0
Working Days Charged51
Percent Time Used42
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6303-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07160210
Totals252480.000.00245344.0097.1

CountyJOHNSON
HighwayIH0035W
FromVARIOUS LOCATIONS WITHIN
ToJOHNSON COUNTY
CSJ6304-39-001
Proj IDRMC - 630439001
Work TypeTREE & BRUSH TRIMMING / REMOVAL
 
0.010326665.00334378.6099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-01-17
Work Began04-05-17
Work Completed
Time Computed04-12-17
Contract Working Days150
Addl Days Granted0
Working Days Charged110
Percent Time Used73
Contractor(s)
CEN-TEX IRRIGATION SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6304-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160202
Totals326665.000.00334378.6099.9

CountyPARKER
HighwaySH0199
FromVARIOUS LOCATIONS IN
ToPARKER/PALO PINTO
CSJ6304-93-001
Proj IDRMC - 630493001
Work TypeTREE TRIMMING
 
0.010177000.00422100.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-17-16
Work Began10-17-16
Work Completed
Time Computed10-24-16
Contract Working Days86
Addl Days Granted42
Working Days Charged111
Percent Time Used86
Contractor(s)
KASPARIAN UNDERGROUND, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6304-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160204
Totals177000.000.00422100.0099.9

CountyWISE
HighwaySH0114
FromVARIOUS LOCATIONS IN WISE & JACK COUNTY
ToMAINTENANCE AREAS
CSJ6305-38-001
Proj IDRMC - 630538001
Work TypeRAISED PAVEMENT MARKERS
 
0.100196340.78171932.0487.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-18-17
Work Began09-25-17
Work Completed
Time Computed09-25-17
Contract Working Days19
Addl Days Granted5
Working Days Charged24
Percent Time Used100
Contractor(s)
BRYDL CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6305-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06170201
Totals196340.780.00171932.0487.5

CountyTARRANT
HighwayIH0020
FromFORT WORTH
ToDISTRICT COMPLEX
CSJ6307-94-001
Proj IDSUP - 630794001
Work TypeGROUNDS MAINTENANCE
 
0.01083829.3165105.8177.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged306
Percent Time Used83
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6307-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160237
Totals83829.310.0065105.8177.6

CountyTARRANT
HighwayUS0287
FromVARIOUS LOCATIONS WITHIN
ToSOUTH TARRANT COUNTY
CSJ6311-71-001
Proj IDRMC - 631171001
Work TypeFULL DEPTH REPAIR OF EXISTING CONCRETE
 
0.010243481.00389189.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-09-18
Work Completed07-13-18
Time Computed04-09-18
Contract Working Days26
Addl Days Granted21
Working Days Charged47
Percent Time Used100
Contractor(s)
IIPL USA LLC
SUBCONTRACTOR(S) FOR CCSJ: 6311-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07170202
Totals243481.000.00389189.00100.0

CountyTARRANT
HighwayIH0820
FromNORTH TARRANT ENGINEERS AND
ToMAINTENANCE OFFICES
CSJ6311-89-001
Proj IDSUP - 631189001
Work TypeJANITORIAL & GROUNDS MAINTENANCE
 
0.01013081.6811850.9190.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-01-17
Work Began07-11-17
Work Completed
Time Computed07-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged297
Percent Time Used81
Contractor(s)
TIBH INDUSTRIES, INC.
I AM WORKS ASSOCIATION
SUBCONTRACTOR(S) FOR CCSJ: 6311-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05170232
Totals13081.680.0011850.9190.5

CountySOMERVELL
HighwayUS0067
FromVARIOUS LOCATIONS IN HOOD, SOMERVELL
ToAND ERATH COUNTIES
CSJ6311-93-001
Proj IDSUP - 631193001
Work TypePICNIC
 
0.010108113.02105293.74100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-02-17
Work Began01-02-17
Work Completed01-01-18
Time Computed01-09-17
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
FRESH START OF MONROE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12160231
Totals108113.020.00105293.74100.0

CountyPARKER
HighwayIH0020
FromVARIOUS LOCATIONS WITHIN PARKER
To& PALO PINTO
CSJ6311-94-001
Proj IDSUP - 631194001
Work TypePICNIC AREA MAINTENANCE
 
0.01074176.1862230.23100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-01-17
Work Completed01-01-18
Time Computed01-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
I AM WORKS ASSOCIATION
SUBCONTRACTOR(S) FOR CCSJ: 6311-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12160232
Totals74176.180.0062230.23100.0

CountyTARRANT
HighwayIH0035W
FromVARIOUS LOCATIONS
ToWITHIN SOUTH TARRANT COUNTY
CSJ6312-88-001
Proj IDRMC - 631288001
Work TypeCALLOUT REFLECTORIZED PAVEMENT MARKINGS
 
0.010273472.50187077.4168.4
Work Order00-00-00
Work Began12-04-17
Work Completed
Time Computed12-04-17
Contract Working Days96
Addl Days Granted0
Working Days Charged42
Percent Time Used43
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6312-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07170204
Totals273472.5065532.07187077.4168.4

CountyPARKER
HighwayIH0020
FromWEATHERFOR/MINERAL WELLS OFFICES &
ToGORDON LOCATION
CSJ6313-03-001
Proj IDSUP - 631303001
Work TypeJANITORIAL & GROUNDS WORK MAINTNENACE
 
0.01074537.0069676.40100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-01-17
Work Completed02-01-18
Time Computed02-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
I AM WORKS ASSOCIATION
SUBCONTRACTOR(S) FOR CCSJ: 6313-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01170231
Totals74537.000.0069676.40100.0

CountyTARRANT
HighwayIH0035W
FromSPECIAL MAINTENANCE
ToWAGGOMAN STREET
CSJ6315-33-001
Proj IDSUP - 631533001
Work TypeJANITORIAL MAINTENCANCE
 
0.0108526.608526.6099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-01-17
Work Completed
Time Computed05-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged389
Percent Time Used106
Contractor(s)
TIBH INDUSTRIES, INC.
I AM WORKS ASSOCIATION
SUBCONTRACTOR(S) FOR CCSJ: 6315-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04170231
Totals8526.600.008526.6099.9

CountyTARRANT
HighwayIH0820
FromVARIOUS LOCATIONS WITHIN
ToNORTH TARRANT COUNTY
CSJ6315-35-001
Proj IDRMC - 631535001
Work TypeCALL-OUT STRIPING & PREFAB HANDWORK
 
0.010218354.4463946.2529.2
Work Order03-27-18
Work Began04-16-18
Work Completed
Time Computed04-16-18
Contract Working Days365
Addl Days Granted0
Working Days Charged153
Percent Time Used41
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6315-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02180201
Totals218354.4412325.0363946.2529.2

CountyJOHNSON
HighwayUS0067
FromVARIOUS ROADWAYS WITHIN
ToJOHNSON COUNTY
CSJ6315-64-001
Proj IDSUP - 631564001
Work TypeLITTER REMOVAL
 
0.010193333.86243508.90100.0
Work Order09-15-17
Work Began09-25-17
Work Completed08-24-18
Time Computed09-22-17
Contract Working Days365
Addl Days Granted0
Working Days Charged357
Percent Time Used97
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6315-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08170231
Totals193333.8626068.72243508.90100.0

CountyWISE
HighwayUS0081
FromLITTER REMOVAL WITHIN
ToWISE & JACK COUNTIES
CSJ6315-65-001
Proj IDSUP - 631565001
Work TypeLITTER REMOVAL
 
0.010221679.54200985.3090.6
Work Order09-12-17
Work Began09-13-17
Work Completed
Time Computed09-13-17
Contract Working Days365
Addl Days Granted0
Working Days Charged348
Percent Time Used95
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6315-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08170232
Totals221679.5418972.58200985.3090.6

CountyTARRANT
HighwayIH0020
FromVARIOUS LOCATIONS WITHIN
ToSOUTH TARRANT COUNTY
CSJ6315-66-001
Proj IDSUP - 631566001
Work TypeLITTER REMOVAL
 
0.010482216.16475289.0598.5
Work Order00-00-00
Work Began09-05-17
Work Completed
Time Computed09-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6315-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08170233
Totals482216.1633242.99475289.0598.5

page 1 | page 2 | page 3 | page 4