Monthly Local Let Maintenance Report For Fort Worth District As Of Mar 10, 2023 Page 2 Of 3

Last Update: Friday, March 10, 2023
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyJOHNSON
HighwayIH0035W
FromVARIOUS LOCATIONS WITHIN
ToJOHNSON COUNTY
CSJ6391-41-001
Proj IDRMC - 639141001
Work TypeCLEANING AND SEALING CRACKS
 
0.010145407.05210866.0499.9
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed01-25-23
Contract Working Days21
Addl Days Granted0
Working Days Charged12
Percent Time Used57
Contractor(s)
NATIONAL INDUSTRIAL MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6391-41-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07220201
Totals145407.05210866.04210866.0499.9

CountyWISE
HighwayUS0380
FromVARIOUS LOCATIONS IN
ToWISE AND JACK COUNTIES
CSJ6391-48-001
Proj IDRMC - 639148001
Work TypeTHERMOPLASTIC PAVEMENT MARKINGS
 
0.010190415.00155177.7581.4
Work Order00-00-00
Work Began07-18-22
Work Completed
Time Computed07-18-22
Contract Working Days365
Addl Days Granted0
Working Days Charged223
Percent Time Used61
Contractor(s)
BARRICADES UNLIMITED
SUBCONTRACTOR(S) FOR CCSJ: 6391-48-001
TRP CONSTRUCTION GROUP, LLC (0.00)
Contract #01220201
Totals190415.0030383.70155177.7581.4

CountyJOHNSON
HighwayFM2280
FromKEENE MAINTENANCE
ToOFFICE
CSJ6392-53-001
Proj IDSUP - 639253001
Work TypeDAY LABOR
 
0.01030379.7721157.2169.6
Work Order00-00-00
Work Began12-01-21
Work Completed
Time Computed12-01-21
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
WORKQUEST
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6392-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11210231
Totals30379.771908.1221157.2169.6

CountyTARRANT
HighwayIH0035W
FromFORT WORTH DISTRICT COMPLEX
ToSW LOOP 820
CSJ6392-54-001
Proj IDSUP - 639254001
Work TypeJANITORIAL MAINTENANCE
 
0.010288220.12262405.1191.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-04-22
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged304
Percent Time Used83
Contractor(s)
WORKQUEST
RISING STAR RESOURCE DEVELOPMENT CORP.
SUBCONTRACTOR(S) FOR CCSJ: 6392-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04220231
Totals288220.1223855.01262405.1191.0

CountyERATH
HighwayUS0377
FromVARIOUS LOCATIONS WITHIN
ToERATH, HOOD AND SOMERVELL COUNTIES
CSJ6393-28-001
Proj IDRMC - 639328001
Work TypeCRACK SEAL
 
0.010216370.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days42
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6393-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07220203
Totals216370.000.000.000.0

CountyERATH
HighwayUS0377
FromVARIOUS LOCATIONS WITHIN
ToERATH, HOOD AND SOMERVELL COUNTIES
CSJ6393-29-001
Proj IDRMC - 639329001
Work TypeSWEEPING AND DEBRIS REMOVAL
 
0.010112202.0032619.0029.0
Work Order00-00-00
Work Began10-18-22
Work Completed
Time Computed10-18-22
Contract Working Days730
Addl Days Granted0
Working Days Charged148
Percent Time Used20
Contractor(s)
TEXAS TMA RENTAL
SUBCONTRACTOR(S) FOR CCSJ: 6393-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05220201
Totals112202.008220.0032619.0029.0

CountyERATH
HighwayUS0377
FromSTEPHENVILLE AREA OFFICE
ToSTEPHENVILLE AREA OFFICE
CSJ6393-64-001
Proj IDSUP - 639364001
Work TypeJANITORIAL MAINTENANCE
 
0.01047396.1416278.8234.3
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed01-01-22
Contract Working Days365
Addl Days Granted0
Working Days Charged181
Percent Time Used49
Contractor(s)
WORKQUEST
RISING STAR RESOURCE DEVELOPMENT CORP.
SUBCONTRACTOR(S) FOR CCSJ: 6393-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12210201
Totals47396.143639.4716278.8234.3

CountyWISE
HighwayUS0081
FromVARIOUS LOCATIONS WITHIN
ToWISE & JACK COUNTIES
CSJ6399-13-001
Proj IDRMC - 639913001
Work TypeCLEANING AND SEALING CRACKS
 
0.010136110.0073048.5053.6
Work Order00-00-00
Work Began02-20-23
Work Completed
Time Computed02-20-23
Contract Working Days26
Addl Days Granted0
Working Days Charged4
Percent Time Used15
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6399-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07220202
Totals136110.0073048.5073048.5053.6

CountyTARRANT
HighwayIH0020
FromSOUTH TARRANT AREA OFFICE
To.
CSJ6400-06-001
Proj IDSUP - 640006001
Work TypeJANITORIAL MAINTENANCE
 
0.01043925.8437423.3285.1
Work Order00-00-00
Work Began04-01-22
Work Completed
Time Computed04-01-22
Contract Working Days365
Addl Days Granted0
Working Days Charged305
Percent Time Used83
Contractor(s)
WORKQUEST
RISING STAR RESOURCE DEVELOPMENT CORP.
SUBCONTRACTOR(S) FOR CCSJ: 6400-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06220231
Totals43925.843402.1237423.3285.1

CountyPARKER
HighwayIH0020
FromVARIOUS LOCATIONS WITHIN
ToPARKER AND PALO PINTO COUNTIES
CSJ6400-96-001
Proj IDRMC - 640096001
Work TypeCLEANING AND SEALING CRACKS
 
0.010109823.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days22
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6400-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08220202
Totals109823.000.000.000.0

CountyPALO PINTO
HighwayIH0020
FromVARIOUS LOCATIONS WITHIN
ToPALO PINTO COUNTY
CSJ6401-26-001
Proj IDMMC - 640126001
Work TypeDENSE GRADED HOT MIX
 
0.010314000.0020601.786.5
Work Order00-00-00
Work Began09-27-22
Work Completed
Time Computed09-27-22
Contract Working Days120
Addl Days Granted0
Working Days Charged153
Percent Time Used127
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6401-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05220203
Totals314000.000.0020601.786.5

CountyTARRANT
HighwayIH0035W
FromIH35W
ToIH35W
CSJ6403-80-001
Proj IDSUP - 640380001
Work TypeJANITORIAL, GROUNDS AND/OR LANDSCAPE SE
 
0.01029803.7020819.8469.8
Work Order00-00-00
Work Began06-03-22
Work Completed
Time Computed06-01-22
Contract Working Days365
Addl Days Granted0
Working Days Charged273
Percent Time Used74
Contractor(s)
WORKQUEST
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6403-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05220231
Totals29803.70834.4220819.8469.8

CountyPARKER
HighwayIH0020
From1427 W. BANKHEAD
To1427 W BANKHEAD
CSJ6405-22-001
Proj IDSUP - 640522001
Work TypeJANITORIAL, GROUNDS AND/OR LANDSCAPE SE
 
0.01097114.4643668.5144.9
Work Order00-00-00
Work Began06-01-22
Work Completed
Time Computed06-01-22
Contract Working Days365
Addl Days Granted0
Working Days Charged273
Percent Time Used74
Contractor(s)
WORKQUEST
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6405-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05220232
Totals97114.463969.9643668.5144.9

CountyTARRANT
HighwayIH0020
FromVARIOUS LOCATIONS WITHIN
ToSOUTH TARRANT COUNTY
CSJ6406-24-001
Proj IDRMC - 640624001
Work TypeCLEANING AND SEALING CRACKS
 
0.010239921.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6406-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11220202
Totals239921.000.000.000.0

CountyTARRANT
HighwayFM1938
FromVARIOUS LOCATIONS WITHIN
ToNORTH TARRANT COUNTY
CSJ6410-17-001
Proj IDRMC - 641017001
Work TypeCRACK SEAL
 
0.010124855.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days19
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6410-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08220203
Totals124855.000.000.000.0

CountyJOHNSON
HighwayUS0067
FromVARIOUS LOCATIONS WITHIN
ToJOHNSON COUNTY
CSJ6411-25-001
Proj IDSUP - 641125001
Work TypeLITTER REMOVAL
 
0.010393574.22156384.7139.7
Work Order00-00-00
Work Began10-20-22
Work Completed
Time Computed10-01-22
Contract Working Days365
Addl Days Granted0
Working Days Charged133
Percent Time Used36
Contractor(s)
WORKQUEST
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6411-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10220230
Totals393574.2225404.00156384.7139.7

CountyTARRANT
HighwayIH0020
FromVARIOUS LOCATIONS WITHIN
ToSOUTH TARRANT COUNTY
CSJ6411-27-001
Proj IDSUP - 641127001
Work TypeLITTER REMOVAL
 
0.0101502151.46520943.8834.6
Work Order00-00-00
Work Began10-01-22
Work Completed
Time Computed10-01-22
Contract Working Days365
Addl Days Granted0
Working Days Charged132
Percent Time Used36
Contractor(s)
WORKQUEST
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6411-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10220232
Totals1502151.4693617.42520943.8834.6

CountyJACK
HighwayUS0380
FromVARIOUS LOCATIONS WITHIN
ToWISE & JACK COUNTIES
CSJ6411-29-001
Proj IDSUP - 641129001
Work TypeLITTER REMOVAL
 
0.010222192.00102586.5046.1
Work Order00-00-00
Work Began09-27-22
Work Completed
Time Computed09-27-22
Contract Working Days365
Addl Days Granted0
Working Days Charged155
Percent Time Used42
Contractor(s)
WORKQUEST
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6411-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09220230
Totals222192.0010833.75102586.5046.1

CountyPARKER
HighwayIH0020
FromVARIOUS LOCATIONS WITHIN
ToPALO PINTO AND PARKER COUNTIES
CSJ6411-31-001
Proj IDSUP - 641131001
Work TypeLITTER REMOVAL
 
0.010396286.22166916.5242.1
Work Order00-00-00
Work Began10-19-22
Work Completed
Time Computed10-01-22
Contract Working Days365
Addl Days Granted0
Working Days Charged133
Percent Time Used36
Contractor(s)
WORKQUEST
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6411-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10220231
Totals396286.2223129.80166916.5242.1

CountyTARRANT
HighwayIH0035W
FromVARIOUS LOCATIONS WITHIN
ToNORTH TARRANT COUNTY
CSJ6411-33-001
Proj IDSUP - 641133001
Work TypeLITTER REMOVAL
 
0.010584435.00220034.5037.6
Work Order00-00-00
Work Began10-01-22
Work Completed
Time Computed10-01-22
Contract Working Days365
Addl Days Granted0
Working Days Charged133
Percent Time Used36
Contractor(s)
WORKQUEST
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6411-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10220233
Totals584435.0049774.00220034.5037.6

page 1 | page 2 | page 3