Monthly Local Let Maintenance Report For Fort Worth District As Of Nov 13, 2018 Page 2 Of 3

Last Update: Tuesday, November 13, 2018
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyTARRANT
HighwayIH0820
FromVARIOUS LOCATIONS WITHIN
ToNORTH TARRANT COUNTY
CSJ6315-35-001
Proj IDRMC - 631535001
Work TypeCALL-OUT STRIPING & PREFAB HANDWORK
 
0.010218354.4491305.8041.8
Work Order03-27-18
Work Began04-16-18
Work Completed
Time Computed04-16-18
Contract Working Days365
Addl Days Granted0
Working Days Charged208
Percent Time Used56
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6315-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02180201
Totals218354.447798.1091305.8041.8

CountyJOHNSON
HighwayUS0067
FromVARIOUS ROADWAYS WITHIN
ToJOHNSON COUNTY
CSJ6315-64-001
Proj IDSUP - 631564001
Work TypeLITTER REMOVAL
 
0.010193333.86243508.90100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-15-17
Work Began09-25-17
Work Completed08-24-18
Time Computed09-22-17
Contract Working Days365
Addl Days Granted0
Working Days Charged357
Percent Time Used97
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6315-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08170231
Totals193333.860.00243508.90100.0

CountyWISE
HighwayUS0081
FromLITTER REMOVAL WITHIN
ToWISE & JACK COUNTIES
CSJ6315-65-001
Proj IDSUP - 631565001
Work TypeLITTER REMOVAL
 
0.010221679.54200985.3090.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-12-17
Work Began09-13-17
Work Completed
Time Computed09-13-17
Contract Working Days365
Addl Days Granted0
Working Days Charged348
Percent Time Used95
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6315-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08170232
Totals221679.540.00200985.3090.6

CountyTARRANT
HighwayIH0020
FromVARIOUS LOCATIONS WITHIN
ToSOUTH TARRANT COUNTY
CSJ6315-66-001
Proj IDSUP - 631566001
Work TypeLITTER REMOVAL
 
0.010482216.16475289.0598.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-05-17
Work Completed
Time Computed09-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6315-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08170233
Totals482216.160.00475289.0598.5

CountySOMERVELL
HighwayUS0067
FromVARIOUS ROADWAYS IN HOOD, SOMERVELL &
ToERATH COUNTIES
CSJ6315-67-001
Proj IDSUP - 631567001
Work TypeLITTER REMOVAL
 
0.010143861.00141461.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-19-17
Work Began09-26-17
Work Completed08-28-18
Time Computed09-26-17
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6315-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08170234
Totals143861.000.00141461.00100.0

CountyPARKER
HighwayIH0020
FromVARIOUS ROADWAYS IN PARKER AND
ToPALO PINTO COUNTIES
CSJ6315-68-001
Proj IDSUP - 631568001
Work TypeLITTER REMOVAL
 
0.010293917.44286342.94100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-15-17
Work Began09-22-17
Work Completed08-31-18
Time Computed09-15-17
Contract Working Days365
Addl Days Granted0
Working Days Charged350
Percent Time Used95
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6315-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08170235
Totals293917.440.00286342.94100.0

CountyTARRANT
HighwayIH0820
FromVARIOUS ROADWAYS IN
ToNORTH TARRANT COUNTY
CSJ6315-69-001
Proj IDSUP - 631569001
Work TypeLITTER REMOVAL
 
0.010391997.62360136.2691.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-14-17
Work Began09-15-17
Work Completed
Time Computed09-15-17
Contract Working Days365
Addl Days Granted0
Working Days Charged348
Percent Time Used95
Contractor(s)
TIBH INDUSTRIES, INC.
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6315-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08170236
Totals391997.620.00360136.2691.8

CountyJOHNSON
HighwayUS0067
FromJOHNSON COUNTY
ToWITHIN CITY LIMITS
CSJ6315-82-001
Proj IDSUP - 631582001
Work TypeLANDSCAPING MAINTENANCE
 
0.01017700.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-01-17
Work Began00-00-00
Work Completed
Time Computed12-07-17
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6315-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05170231
Totals17700.000.000.000.0

CountyJOHNSON
HighwayFM2280
FromKEENE MAINTENANCE
ToOFFICE
CSJ6315-86-001
Proj IDSUP - 631586001
Work TypeJANITORIAL AND GROUNDS MAINTENANCE
 
0.01025095.0018160.0072.3
Work Order00-00-00
Work Began12-04-17
Work Completed
Time Computed12-01-18
Contract Working Days365
Addl Days Granted0
Working Days Charged329
Percent Time Used90
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6315-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11170231
Totals25095.001385.0018160.0072.3

CountyWISE
HighwayUS0081
FromUS DECATUR,OFFICE JACKSBORO OFFICE, OLD
ToAREA OFFICE, JACKSBORO MAINTENANCE YARD
CSJ6315-87-001
Proj IDSUP - 631587001
Work TypeJANITORIAL AND GROUNDS MAINTENANCE
 
0.01062450.0052360.0083.8
Work Order11-03-17
Work Began11-03-17
Work Completed
Time Computed11-09-17
Contract Working Days365
Addl Days Granted0
Working Days Charged362
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6315-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10170231
Totals62450.006045.0052360.0083.8

CountyJOHNSON
HighwayIH0035W
FromVARIOUS ROADWAYS WITHIN JOHNSON
ToCOUNTY
CSJ6316-02-001
Proj IDRMC - 631602001
Work TypeCLEANING AND SEALING JOINTS & CRACKS
 
0.010205978.00183928.4089.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-30-17
Work Began11-14-17
Work Completed
Time Computed11-06-17
Contract Working Days43
Addl Days Granted0
Working Days Charged17
Percent Time Used39
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6316-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07170201
Totals205978.000.00183928.4089.2

CountyPARKER
HighwayIH0020
FromVARIOUS LOCATIONS IN
ToPARKER AND PALO PINTO
CSJ6316-03-001
Proj IDRMC - 631603001
Work TypeSWEEPING AND DEBRIS
 
0.010286745.33382447.6099.9
Work Order10-04-17
Work Began10-04-17
Work Completed
Time Computed10-04-17
Contract Working Days365
Addl Days Granted120
Working Days Charged389
Percent Time Used80
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6316-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07170203
Totals286745.333570.75382447.6099.9

CountyJOHNSON
HighwayIH0035W
FromVARIOUS ROADWAYS WITHIN
ToJOHNSON COUNTY
CSJ6316-15-001
Proj IDRMC - 631615001
Work TypeCALL OUT REFLEC PVMT MRKGS & MRKRS
 
0.010256350.00225766.4588.0
Work Order02-27-18
Work Began03-08-18
Work Completed
Time Computed03-05-18
Contract Working Days88
Addl Days Granted72
Working Days Charged21
Percent Time Used13
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6316-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10170201
Totals256350.0028252.00225766.4588.0

CountyJOHNSON
HighwayIH0035W
FromJOHNSON COUNTY
To.
CSJ6316-30-001
Proj IDRMC - 631630001
Work TypeSWEEPING AND DEBRIS REMOVAL JOHNSON CO
 
0.010138385.4083942.5060.6
Work Order02-16-18
Work Began03-05-18
Work Completed
Time Computed02-22-18
Contract Working Days365
Addl Days Granted0
Working Days Charged246
Percent Time Used67
Contractor(s)
DEMENT ENTERPRISES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6316-30-001
TEXAS TMA RENTAL (70.00)
Contract #12170201
Totals138385.4010614.0083942.5060.6

CountyWISE
HighwayUS0380
FromVARIOUS LOCATIONS IN WISE & JACK COUNTY
ToMAINTENANCE AREAS
CSJ6316-56-001
Proj IDRMC - 631656001
Work TypeTREE & BRUSH TRIMMING AND REMOVAL
 
0.100350500.00244828.5069.8
Work Order10-25-17
Work Began11-02-17
Work Completed
Time Computed11-02-17
Contract Working Days110
Addl Days Granted25
Working Days Charged110
Percent Time Used81
Contractor(s)
BOEN LANDSCAPING & IRRIGATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6316-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08170201
Totals350500.000.00244828.5069.8

CountyWISE
HighwayUS0081
FromVARIOUS LOCATIONS WITHIN WISE
ToAND JACK CONTIES
CSJ6318-04-001
Proj IDSUP - 631804001
Work TypePICNIC AREA MAINTENANCE
 
0.01056810.0041985.0073.9
Work Order01-04-18
Work Began01-05-18
Work Completed
Time Computed01-05-18
Contract Working Days365
Addl Days Granted0
Working Days Charged294
Percent Time Used80
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6318-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12170231
Totals56810.003240.0041985.0073.9

CountySOMERVELL
HighwayUS0067
FromVARIOUS LOCATIONS IN HOO, SOMERVELL
ToAND ERATH COUNTIES
CSJ6318-05-001
Proj IDSUP - 631805001
Work TypePICNIC AREA MAINTENANCE
 
0.010114036.3487324.4176.5
Work Order01-02-18
Work Began01-03-18
Work Completed
Time Computed01-03-18
Contract Working Days365
Addl Days Granted0
Working Days Charged298
Percent Time Used81
Contractor(s)
TIBH INDUSTRIES, INC.
FRESH START OF MONROE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6318-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12170232
Totals114036.348880.4687324.4176.5

CountyPARKER
HighwayIH0020
FromVARIOUS LOCATION WITHIN PARKER
To& PALO PINTO COUNTIES
CSJ6318-06-001
Proj IDSUP - 631806001
Work TypePICNIC AREA MAINTENANCE
 
0.01077143.2056886.1673.7
Work Order01-15-18
Work Began01-15-18
Work Completed
Time Computed01-15-18
Contract Working Days358
Addl Days Granted0
Working Days Charged284
Percent Time Used79
Contractor(s)
TIBH INDUSTRIES, INC.
I AM WORKS ASSOCIATION
SUBCONTRACTOR(S) FOR CCSJ: 6318-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01180231
Totals77143.206313.0356886.1673.7

CountyPARKER
HighwayIH0020
FromVARIOUS ROADS IN
ToPARKER / PALO PINTO
CSJ6318-28-001
Proj IDRMC - 631828001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
116.000239500.00240170.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-09-18
Work Began03-10-18
Work Completed08-27-18
Time Computed03-10-18
Contract Working Days137
Addl Days Granted0
Working Days Charged133
Percent Time Used97
Contractor(s)
WESTGATE GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6318-28-001
DICKEY LANDSCAPE CONTRACTORS, INC. (46.34)
Contract #08170202
Totals239500.000.00240170.00100.0

CountyPARKER
HighwayIH0020
FromWEATHERFORD/MINERAL WELLS OFFICES &
ToTO GORDON LOCATION
CSJ6318-54-001
Proj IDSUP - 631854001
Work TypeJANITORIAL & GROUNDS WORK MAINTENANCE
 
0.01061457.9943163.7970.2
Work Order00-00-00
Work Began02-01-18
Work Completed
Time Computed02-01-18
Contract Working Days365
Addl Days Granted0
Working Days Charged267
Percent Time Used73
Contractor(s)
TIBH INDUSTRIES, INC.
I AM WORKS ASSOCIATION
SUBCONTRACTOR(S) FOR CCSJ: 6318-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01180232
Totals61457.993938.3543163.7970.2

page 1 | page 2 | page 3