AVERAGE LOW BID UNIT PRICE - CONSTRUCTION - HOUSTON DISTRICT

Last Update: Friday, September 28, 2018
ITEMS 560 2001 TO 585 6001
ItemsItemsBid Code Range
0100 - 0193
0216 - 0292
0305 - 0361
0400 - 0496
0500 - 0585
0610 - 0690
0721 - 0788
1000 - 1009
3000 - 3040
4000 - 4196
5001 - 5387
6000 - 6507
7017 - 7058
500 2001 - 531 2005
531 2006 - 556 6008
560 2001 - 585 6001
Item NoDescriptionUnitsSept 30, 2018Twelve-Month-MovingUsage
QuantityAvg BidQuantityAvg Bid
560 2001MAILBOX INSTALLATION (SINGLE)EA  83.000175.277112
560 2002MAILBOX INSTALLATION (DOUBLE)EA  7.000230.000001
560 2003MAILBOX INSTALLATION (MULTIPLE)EA  4.000400.000001
560 6001MAILBOX INSTALL-S (TWG-POST) TY 1EA  44.000263.272735
560 6002MAILBOX INSTALL-D (TWG-POST) TY 1EA  3.000351.666672
560 6003MAILBOX INSTALL-M (TWG-POST) TY 1EA  4.000411.250002
560 6004MAILBOX INSTALL-S (TWG-POST) TY 2EA  2.000370.000001
560 6007MAILBOX INSTALL-S (WC-POST) TY 3EA  11.000295.000001
560 6011MAILBOX INSTALL-S (TWW-POST) TY 4EA  30.000344.833334
560 6012MAILBOX INSTALL-D (TWW-POST) TY 4EA  6.000258.333333
560 6013MAILBOX INSTALL-M (TWW-POST) TY 4EA  8.000543.750003
585 6001RIDE PAYMENT ADJUSTMENT (ITEM 340)DOL  1.0001.000001