Monthly State Let Construction Report For Houston District As Of Mar 13, 2024 Page 11 Of 13

Last Update: Wednesday, March 13, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11 | page 12 | page 13

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBRAZORIA
HighwaySH 332
FromAT BRAZOS RIVER AND FM 521
To.
CSJ1524-01-076
Proj IDBR 2022(664)
Work TypeTRANSPORTATION NON-ROADWAY
 
0.2094549092.533232651.0271.0
Work Order07-18-22
Work Began02-13-23
Work Completed
Time Computed09-16-22
Contract Working Days270
Addl Days Granted0
Working Days Charged178
Percent Time Used65
Contractor(s)
MP HEAVY CONSTRUCTION INC
SUBCONTRACTOR(S) FOR CCSJ: 1524-01-076
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.13)
MILSTEAD HIGHWAY SERVICES, LLC (0.18)
J. R. (JOE) RAMON & SONS, INC. (20.70)
BARRICADES UNLIMITED (0.08)
1 PRIORITY ENVIRONMENTAL SERVICES, LLC (0.20)
SOUTHERN CONCRETE SAWING & CORING, LLC (0.34)
STERETT CRANE AND RIGGING, LLC (6.61)
Contract #06223016
Totals4549092.5326147.003232651.0271.0

CountyBRAZORIA
HighwaySH 288
FromAT SH 332 AND AT BS 288B
To.
CSJ1524-01-082
Proj IDNH 2018(419)
Work TypeREMOV & REPL CONC PV
 
1.64013895724.7522148651.4199.9
Work Order02-14-18
Work Began07-30-18
Work Completed
Time Computed04-15-18
Contract Working Days371
Addl Days Granted546
Working Days Charged832
Percent Time Used90
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1524-01-082
MESA ROD BUSTERS, INC. (1.63)
NORWEST SERVICES, LLC (0.61)
DURWOOD GREENE CONSTRUCTION CO. (4.34)
ANTIGO CONSTRUCTION, INC. (0.71)
A-1 EROSION CONTROL, LLC (0.91)
RAY"S THREADING AND FAB SHOP (0.62)
VERNOR MATERIAL & EQUIPMENT CO., INC. (6.06)
ROMAR UNLIMITED, INC. (1.74)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.77)
HAYDEN PAVING, INC. (2.03)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.38)
TEX STAR CURBS, INC (0.06)
SORRELL CONSTRUCTION, EQUIPMENT & MATERIALS, LLC (0.40)
GMJ PAVING CO. (2.60)
EPOXY DESIGN SYSTEMS, INC. (0.18)
TOTAL HIGHWAY MAINTENANCE, LLC (0.77)
BATTERSON, LLP (1.86)
JASSO"S SAWING & SEALING (0.17)
Contract #01183204
Totals13895724.7563589.0322148651.4199.9

CountyHARRIS
HighwayFM 1960
FromSH 249
ToCUTTEN RD
CSJ1685-01-090
Proj IDCM 2021(643)
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
0.87426418938.983206796.3312.1
CountyHARRIS
HighwayFM 1960
FromSH 249
ToCUTTEN RD
CSJ1685-01-105
Proj IDROW 1685-1-105
Work TypeRIGHT OF WAY
 
0.874879802.10363639.3041.3
Work Order09-08-23
Work Began12-13-23
Work Completed
Time Computed12-07-23
Contract Working Days433
Addl Days Granted0
Working Days Charged42
Percent Time Used9
Contractor(s)
SER CONSTRUCTION PARTNERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1685-01-090
MONTALVO BRIDGE SYSTEMS, LLC (0.43)
C & C TRAFFIC CONTROL (0.02)
A. SANCHEZ TRUCKING (1.83)
D. SOLIS TRUCKING, INC. (0.54)
RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC (7.97)
SEMARCK LANDSCAPE SERVICES, INC. (0.85)
G & D DIRECCIONAL (0.10)
P&Z LOGISTICS INC. (0.06)
RANGELINE TAPPING SERVICES, INC. (0.03)
Contract #08233207
Totals27298741.081793217.883570435.6313.0

CountyHARRIS
HighwayFM 1960
FromAT ELDRIDGE PARKWAY
To.
CSJ1685-01-092
Proj IDCM 2020(884)
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
0.61014685047.588807371.9160.0
Work Order05-03-22
Work Began08-01-22
Work Completed
Time Computed08-01-22
Contract Working Days337
Addl Days Granted0
Working Days Charged348
Percent Time Used103
Contractor(s)
BRIZO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1685-01-092
ALLSTATE SIGNAL & CONSTRUCTION, LLC (3.16)
TRAFFIC SIGNS & LINES, LLC (1.29)
DORAN STEEL, INC. (0.57)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.68)
MARTIN MARIETTA MATERIALS, INC. (1.66)
DNA TRUCKING (0.60)
CURB PLANET INC. (0.07)
GALVESTON PILING, LLC (0.30)
GMJ PAVING COMPANY LLC (6.30)
JB PINNACLE GROUP, LLC (4.54)
TSTAR DRILLING & SAWING INC (0.15)
YELLOWSTONE LANDSCAPE - CENTRAL, INC. (0.42)
SK CONCRETE SERVICES LLC (0.00)
Contract #03223004
Totals14685047.58314769.998807371.9160.0

CountyHARRIS
HighwayFM 1960
FromMILLS RD
ToSH 249
CSJ1685-01-107
Proj IDSTP 2023(752)TP
Work TypeBICYCLE INFRASTRUCTURE IMPROVEMENTS
 
0.4901450429.421088548.4775.0
Work Order06-19-23
Work Began07-19-23
Work Completed
Time Computed08-03-23
Contract Working Days187
Addl Days Granted0
Working Days Charged151
Percent Time Used80
Contractor(s)
TEXAS WALL & LANDSCAPE
SUBCONTRACTOR(S) FOR CCSJ: 1685-01-107
HOUSTON SAWING & DRILLING (0.77)
R. ORTIZ TRUCKING (0.87)
CONARMET LLC (4.16)
K4 ENVIRONMENTAL LLC (0.15)
Contract #05233041
Totals1450429.42152806.981088548.4775.0

CountyHARRIS
HighwayFM 1960
FromAT WUNDERLICH ROAD
To.
CSJ1685-01-113
Proj IDSTP 2020(416)HES
Work TypeTRAFFIC CONTROL DEVICES
 
0.724729130.11401937.3555.1
Work Order01-06-20
Work Began08-17-20
Work Completed
Time Computed05-05-20
Contract Working Days125
Addl Days Granted0
Working Days Charged89
Percent Time Used71
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1685-01-113
BADGER DAYLIGHTING CORP. (0.46)
Contract #12193224
Totals729130.1173698.57401937.3555.1

CountyHARRIS
HighwayFM 1960
FromAT ALDINE WESTFIELD ROAD
To.
CSJ1685-02-055
Proj IDSTP 2023(594)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.010377740.8377220.0020.4
CountyHARRIS
HighwayFM 1960
From0.369 MI E OF IH 45
To0.179 MI W OF LEE RD
CSJ1685-02-056
Proj IDSTP 2023(594)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
6.9403726088.221332563.9635.7
CountyHARRIS
HighwayFM 1960
FromAT KENSWICK DRIVE
To.
CSJ1685-03-109
Proj IDSTP 2023(594)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.010286666.060.000.0
CountyHARRIS
HighwayFM 1960
From0.179 MILES WEST OF LEE ROAD
ToWHITAKER DRIVE
CSJ1685-03-110
Proj IDSTP 2023(594)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2.142737157.3113520.001.8
Work Order06-28-23
Work Began11-27-23
Work Completed
Time Computed10-26-23
Contract Working Days145
Addl Days Granted0
Working Days Charged56
Percent Time Used38
Contractor(s)
BRIZO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1685-02-055
GALVESTON PILING, LLC (26.63)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (11.08)
TRAFFIC SIGNS & LINES, LLC (7.00)
CURB PLANET INC. (6.28)
Contract #05233214
Totals5127652.42706473.671423303.9627.7

CountyHARRIS
HighwayFM 1960
FromBF 1960A
ToE. OF TWIGSWORTH LN
CSJ1685-03-058
Proj IDC 1685-3-58
Work TypeWIDEN NON-FREEWAY
 
3.97656096943.4444473727.2479.2
CountyHARRIS
HighwayFM 1960
FromBF 1960A
ToE. OF TWIGSWORTH LN
CSJ1685-03-097
Proj IDROW 1685-3-97
Work TypeRIGHT OF WAY
 
3.9762102357.102254126.4399.9
Work Order08-20-20
Work Began06-21-21
Work Completed
Time Computed11-18-20
Contract Working Days1,126
Addl Days Granted0
Working Days Charged425
Percent Time Used37
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1685-03-058
CPAVE, INC. (0.20)
HIGHWAY 1 LLC (0.79)
JMHP, INC. (0.10)
CEN TEX HYDROSEED, INC. (1.52)
THIRD COAST SERVICES LLC (3.81)
THOMAS TRACTOR WORKS, INC. (0.44)
NEW MASADA ENVIRONMENTAL, LLC (0.12)
R & A ROAD BORING LLC (0.07)
MESA ROD BUSTERS, INC. (1.04)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.27)
MESA ROD BUSTERS, INC. (0.01)
TNT CRANE & RIGGING, INC. (0.01)
TEXAS REEXCAVATION (0.03)
AGGREGATE TECHNOLOGIES, INC. (0.02)
ONCALL STAFFING INCORPORATED (1.02)
LEOS STEEL (1.90)
Contract #07203003
Totals58199300.541961119.2946727853.6780.2

CountyHARRIS
HighwayFM 1960
FromE OF TWIGSWORTH LN
ToW OF SAN JACINTO RIVER BRIDGE
CSJ1685-03-098
Proj IDC 1685-3-98
Work TypeWIDEN NON-FREEWAY
 
2.84167186566.6370403299.2199.9
CountyHARRIS
HighwayFM 1960
FromE OF TWIGSWORTH LN
ToW OF SAN JACINTO RIVER BRIDGE
CSJ1685-03-101
Proj IDROW 1685-3-101
Work TypeRIGHT OF WAY
 
2.8412856159.743267054.4799.9
Work Order10-21-20
Work Began01-18-21
Work Completed
Time Computed01-19-21
Contract Working Days1,050
Addl Days Granted0
Working Days Charged746
Percent Time Used71
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1685-03-098
TRAF-TEX, INC. (4.71)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.67)
BUYERS BARRICADES, INC. (0.17)
WEBER-BALKE FOUNDATION COMPANY, INC (5.12)
C&M PRECAST CONCRETE COMPANY (1.38)
ROSALES LAND CLEARING (0.15)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. (4.56)
SCOTT DERR PAINTING CO, LLC (0.15)
MESA ROD BUSTERS, INC. (1.24)
JOSLIN CONSTRUCTION TEXAS, LLC (6.77)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.14)
WILLOW CITY SIGN & RAIL, INC. (0.20)
PROFESSIONAL TRAFFIC CONTROL LLC (0.86)
AVILES CONSTRUCTION SERVICE, INC (2.22)
E & R WELDING (0.43)
HYDROMAX, LLC (0.03)
BUYERS BARRICADES HOUSTON, LLC (0.17)
ALPHA TESTING, INC. (0.32)
MICKIE SERVICE, INC. (0.02)
SOUTHERN CRUSHED CONCRETE, LLC (1.26)
MARTIN MARIETTA MATERIALS, INC. (1.26)
GMJ PAVING COMPANY LLC (0.36)
GMJ PAVING CO. (0.36)
SWEEPING CORPORATION OF AMERICA, INC. (0.01)
DORAN STEEL, INC. (4.95)
SK CONCRETE SERVICES LLC (0.12)
LONG LEGACY ENTERPRISES, LLC (0.24)
DTSG CONSTRUCTION (0.09)
Contract #09203201
Totals70042726.37871496.2473670353.6899.9

CountyHARRIS
HighwaySH 6
FromAT BRIAR HILLS PKWY
To.
CSJ1685-05-123
Proj IDSTP 2020(697)HES
Work TypeTRAFFIC CONTROL DEVICES
 
0.200207829.21248220.8099.9
Work Order06-09-20
Work Began06-30-21
Work Completed
Time Computed10-07-20
Contract Working Days35
Addl Days Granted0
Working Days Charged31
Percent Time Used88
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1685-05-123
HIGHWAY 1 LLC (9.45)
Contract #04203021
Totals207829.210.00248220.8099.9

CountyHARRIS ETC
HighwaySH 6 ETC
FromAT YORKTOWN CROSSING PKWY
To.
CSJ1685-05-126
Proj IDSTP 2021(261)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.471882567.27910951.0399.9
Work Order03-01-21
Work Began10-18-21
Work Completed
Time Computed06-29-21
Contract Working Days180
Addl Days Granted0
Working Days Charged144
Percent Time Used80
Contractor(s)
CITYLYNX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1685-05-126
ALLY GENERAL SOLUTIONS, LLC (8.29)
MLH CONCRETE (2.03)
H&N CONTRACTORS (3.96)
SEMPER STRIPING LLC (1.54)
Contract #01213219
Totals882567.273716.56910951.0399.9

CountyHARRIS
HighwaySH 6
FromWESTPARK ROAD
ToHARRIS COUNTY LINE
CSJ1685-05-127
Proj IDSTP 2021(330)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.7231010336.873326.400.3
CountyFORT BEND
HighwaySH 6
FromHARRIS COUNTY LINE
ToVOSS ROAD
CSJ1685-06-036
Proj IDSTP 2021(330)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3.606969485.252823512.3599.9
Work Order03-12-21
Work Began12-01-21
Work Completed
Time Computed07-19-21
Contract Working Days273
Addl Days Granted0
Working Days Charged184
Percent Time Used67
Contractor(s)
ALLSTATE SIGNAL & CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1685-05-127
LONESTAR TRAFFIC SAFETY, LLC (0.84)
WILLOW CITY SIGN & RAIL, INC. (29.30)
Contract #02213216
Totals1979822.120.002826838.7599.9

CountyHARRIS
HighwaySH 6
FromIH 10 WEST
ToN OF WESTPARK TOLLWAY
CSJ1685-05-132
Proj IDF 2023(057)
Work TypeTRAFFIC CONTROL DEVICES
 
4.365289671.240.000.0
Work Order01-06-23
Work Began00-00-00
Work Completed
Time Computed02-05-23
Contract Working Days44
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 1685-05-132
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12223228
Totals289671.240.000.000.0

CountyFORT BEND
HighwaySH 6
FromVOSS ROAD
ToUS 90A
CSJ1685-06-045
Proj IDC 1685-6-45
Work TypeLANDSCAPE & SCENIC ENHANCEMENT
 
9.3731459342.88105236.827.2
Work Order07-26-23
Work Began01-09-24
Work Completed
Time Computed08-25-23
Contract Working Days105
Addl Days Granted0
Working Days Charged24
Percent Time Used22
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1685-06-045
R & A DIRECTIONAL BORING (1.74)
ALL ACCESS TRAFFIX LIMITED LIABILITY COMPANY (6.78)
Contract #06233444
Totals1459342.88105236.82105236.827.2

CountyMONTGOMERY
HighwayFM 1791
FromWALKER C/L
ToFM 149
CSJ1706-02-008
Proj IDF 2023(021)
Work TypeOVERLAY
 
3.0341006888.631073193.6899.9
Work Order09-07-23
Work Began10-09-23
Work Completed
Time Computed10-09-23
Contract Working Days38
Addl Days Granted0
Working Days Charged27
Percent Time Used71
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1706-02-008
LONESTAR TRAFFIC SAFETY, LLC (0.31)
TRAFFIC SIGNS & LINES, LLC (5.78)
WILLOW CITY SIGN & RAIL, INC. (1.89)
Contract #08233037
Totals1006888.630.001073193.6899.9

CountyMONTGOMERY
HighwayFM 2090
FromFM 3083
ToIH 69
CSJ1912-01-022
Proj IDC 1912-1-22
Work TypeOVERLAY
 
10.5947041940.218618199.4999.9
Work Order12-07-22
Work Began02-13-23
Work Completed
Time Computed02-05-23
Contract Working Days124
Addl Days Granted0
Working Days Charged118
Percent Time Used95
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1912-01-022
LONESTAR TRAFFIC SAFETY, LLC (0.16)
WEST TEXAS ROCK RESOURCES, LLC (0.07)
HIGHWAY DATA SERVICES (4.38)
WILLOW CITY SIGN & RAIL, INC. (1.14)
THE TRUESDELL CORPORATION (10.93)
THIRD COAST SERVICES LLC (0.29)
Contract #11223210
Totals7041940.2129250.598618199.4999.9

CountyMONTGOMERY
HighwayFM 1314
FromN OF FATHEREE DR
ToSL 494
CSJ1986-01-067
Proj IDF 2022(725)
Work TypeOVERLAY
 
2.5304740080.604779195.2999.9
Work Order07-27-22
Work Began10-02-22
Work Completed
Time Computed09-25-22
Contract Working Days98
Addl Days Granted0
Working Days Charged88
Percent Time Used89
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1986-01-067
HIGHWAY 1 LLC (0.45)
JMHP, INC. (0.38)
STRIPE LINES, INC. (4.26)
A.J.J.A . TRUCKING, INC. (2.51)
TRAFFIC SIGNS & LINES, LLC (0.56)
THIRD COAST SERVICES LLC (0.36)
Contract #06223644
Totals4740080.600.004779195.2999.9

CountyMONTGOMERY
HighwayFM 1314
FromSH 99
ToSL 494
CSJ1986-01-070
Proj IDSTP 2B23(073)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
4.6272022486.20417855.0020.6
Work Order09-06-23
Work Began00-00-00
Work Completed
Time Computed12-05-23
Contract Working Days258
Addl Days Granted0
Working Days Charged4
Percent Time Used1
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 1986-01-070
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08233017
Totals2022486.20383630.00417855.0020.6

CountyFORT BEND
HighwayFM 2218
FromSH 36
ToIH 69
CSJ2093-01-010
Proj IDSTP 2020(303)
Work TypeWIDEN NON-FREEWAY
 
3.61936717603.3733169800.6790.3
Work Order08-10-20
Work Began11-30-20
Work Completed
Time Computed11-09-20
Contract Working Days820
Addl Days Granted0
Working Days Charged623
Percent Time Used75
Contractor(s)
JAMES CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2093-01-010
ADCOCK 4 INVESTMENTS, LLC (3.13)
RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC (2.22)
A BROTHERS MILLING, LLC (0.41)
MESA ROD BUSTERS, INC. (3.86)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.04)
BATTERSON, LLP (0.79)
B & D MAINTENANCE (4.40)
AVILES CONSTRUCTION SERVICE, INC (1.35)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.18)
CURB PLANET INC. (0.03)
FARR FOUNDATION, INC. (0.90)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P. (0.10)
PROSCAPE DEVELOPMENT LLC (0.02)
SPEEDY PAVING (0.73)
DOUBLE OAK EROSION, INC. (0.06)
CGC LOGISTICS (0.75)
DNA TRUCKING (1.37)
TEXAS REEXCAVATION (0.03)
MAIN LANE INDUSTRIES LTD. (0.07)
CPAVE, INC. (0.27)
VERA INDUSTRIES, LLC (1.38)
CHERRY CRUSHED CONCRETE (0.15)
ASHTON SAWING AND DRILLING LLC (0.01)
Contract #06203010
Totals36717603.37658002.5433169800.6790.3

CountyGALVESTON
HighwayFM 2004
FromSH 6
ToBRAZORIA C/L
CSJ2523-01-026
Proj IDC 2523-1-26
Work TypeOVERLAY
 
6.9827147856.637947420.1699.9
Work Order01-20-22
Work Began03-09-22
Work Completed
Time Computed03-21-22
Contract Working Days201
Addl Days Granted0
Working Days Charged201
Percent Time Used100
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2523-01-026
HIGHWAY 1 LLC (0.16)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (6.27)
STRIPE LINES, INC. (2.09)
TRAFFIC SIGNS & LINES, LLC (1.14)
WEST TEXAS ROCK RESOURCES, LLC (0.15)
RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC (0.06)
Contract #08213018
Totals7147856.630.007947420.1699.9