Contract Identification and Information |
Length |
Contract Amount |
Amount This Estimate |
Total Estimate To Date |
% Comp |
|
County | BRAZORIA |
Highway |
FM 2004 |
From |
AT CHOCOLATE BAYOU |
To |
. |
CSJ |
2523-02-067 |
Proj ID |
STP 2015(417) |
Work Type |
BR JT REP |
|
|
0.409 |
262610.50 |
0.00 |
311487.88 |
100.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order |
01-13-15 |
Work Began |
02-26-15 |
Work Completed |
07-01-15 |
Time Computed |
02-26-15 |
Contract Working Days |
35 |
Addl Days Granted |
0 |
Working Days Charged |
31 |
Percent Time Used |
88 |
Contractor(s) |
SCR CONSTRUCTION CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 2523-02-067 LONESTAR TRAFFIC SAFETY, LLC (0.74%)
|
Contract # |
12143207 |
|
Totals |
262610.50 |
0.00 |
311487.88 |
100.0 |
|
County | MONTGOMERY |
Highway |
FM 2854 |
From |
AT O'GRADY |
To |
. |
CSJ |
2744-01-030 |
Proj ID |
STP 1402(104) |
Work Type |
INST LT TN LN |
|
|
0.183 |
298966.25 |
0.00 |
295189.20 |
100.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order |
09-09-14 |
Work Began |
11-10-14 |
Work Completed |
02-11-15 |
Time Computed |
11-08-14 |
Contract Working Days |
29 |
Addl Days Granted |
0 |
Working Days Charged |
28 |
Percent Time Used |
96 |
Contractor(s) |
FORDE CONSTRUCTION COMPANY, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 2744-01-030 BIO LANDSCAPE & MAINTENANCE, INC.(4.50%) LONESTAR TRAFFIC SAFETY, LLC (0.59%) AQUALAWN HYDROMULCH & EROSION CONTROL(6.41%) STRIPE-A-LINE, INC.(1.33%) WILLOW CITY SIGN & RAIL, INC.(2.80%)
|
Contract # |
08143235 |
|
Totals |
298966.25 |
0.00 |
295189.20 |
100.0 |
|
County | HARRIS |
Highway |
FM 2920 |
From |
AT ROBERTS CEMETERY, LOBLOLLY, |
To |
BINFORD & MUESCHKE |
CSJ |
2941-01-021 |
Proj ID |
STP 2013(462) |
Work Type |
INTERSECTION IMPROVEMENTS |
|
|
10.795 |
3074858.55 |
240.00 |
3166657.68 |
99.9 |
Work Order |
08-30-13 |
Work Began |
11-11-13 |
Work Completed |
|
Time Computed |
10-29-13 |
Contract Working Days |
167 |
Addl Days Granted |
0 |
Working Days Charged |
166 |
Percent Time Used |
99 |
Contractor(s) |
DURWOOD GREENE CONSTRUCTION CO. |
SUBCONTRACTOR(S) FOR CCSJ: 2941-01-021 BATTERSON,LLP(0.95%) EROSION CONTROL, INC.(3.00%) INTERSTATE BARRICADES & MARKINGS, INC. (2.07%) JMHP, INC. (3.79%) THIRD COAST SERVICES LLC (6.87%)
|
Contract # |
07133021 |
|
Totals |
3074858.55 |
240.00 |
3166657.68 |
99.9 |
|
County | HARRIS |
Highway |
FM 2920 |
From |
BUS 249 |
To |
HOWARD ST |
CSJ |
2941-02-050 |
Proj ID |
STP 1502(020) |
Work Type |
BS REP, MILL, CR SL, TOM, RADAR, ETC |
|
|
3.188 |
2999793.89 |
0.00 |
0.00 |
0.0 |
Work Order |
08-24-15 |
Work Began |
00-00-00 |
Work Completed |
|
Time Computed |
10-23-15 |
Contract Working Days |
75 |
Addl Days Granted |
0 |
Working Days Charged |
0 |
Percent Time Used |
0 |
Contractor(s) |
SMITH & COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 2941-02-050 REPUBLIC TRAFFIC SAFETY, INC.(6.09%) DUSTROL, INC.(6.38%) SOUTHWEST SIGNAL SUPPLY, INC.( 12.48%)
|
Contract # |
07153040 |
|
Totals |
2999793.89 |
0.00 |
0.00 |
0.0 |
|
County | GALVESTON |
Highway |
FM 646 |
From |
IH 45 |
To |
SH 3 |
CSJ |
3049-01-027 |
Proj ID |
STP 1102(316) |
Work Type |
GR, BASE, SURF, STRS |
|
|
1.434 |
9777012.33 |
0.00 |
9733056.28 |
100.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order |
09-30-11 |
Work Began |
10-17-11 |
Work Completed |
09-04-14 |
Time Computed |
10-16-11 |
Contract Working Days |
270 |
Addl Days Granted |
0 |
Working Days Charged |
314 |
Percent Time Used |
116 |
Contractor(s) |
HASSELL CONSTRUCTION COMPANY, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 3049-01-027 TRAFFIC SYSTEMS CONSTRUCTION, INC. (4.48%) BATTERSON,LLP(1.20%) GULF COAST PAVERS, INC.(1.06%) H & H CURB COMPANY (0.13%) HIGHWAY PAVEMENT SPECIALTIES, INC. (0.37%) GMJ PAVING CO. (5.39%) JMHP, INC. (0.15%) CHAMPIONS HYDRO-LAWN (0.64%) BREDA COMPANY, INC.(6.20%) NBG CONSTRUCTORS, INC. ( 12.51%) TOM-MAC, INC.(0.68%) DIXIE DRILLING COMPANY, INC. (0.34%) HOUSTON SAWING & DRILLING(0.02%) SCOTT DERR PAINTING CO (0.01%)
|
Contract # |
08113210 |
|
Totals |
9777012.33 |
0.00 |
9733056.28 |
100.0 |
|
County | MONTGOMERY |
Highway |
FM 2978 |
From |
FM 1488 |
To |
S OF DRY CREEK |
CSJ |
3050-02-024 |
Proj ID |
STP 2016(119)MM |
Work Type |
GR, STRS, BASE AND PAVE |
|
|
4.070 |
15788778.29 |
0.00 |
0.00 |
0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order |
00-00-00 |
Work Began |
00-00-00 |
Work Completed |
|
Time Computed |
00-00-00 |
Contract Working Days |
457 |
Addl Days Granted |
0 |
Working Days Charged |
0 |
Percent Time Used |
0 |
Contractor(s) |
J.D. ABRAMS, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 3050-02-024 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # |
02163202 |
|
Totals |
15788778.29 |
0.00 |
0.00 |
0.0 |
|
County | MONTGOMERY |
Highway |
FM 2978 |
From |
S OF DRY CREEK |
To |
CONROE HUFFSMITH |
CSJ |
3050-02-025 |
Proj ID |
C 3050-2-25 |
Work Type |
GR, STRS, BASE AND PAVE |
|
|
2.462 |
8195982.09 |
544548.62 |
544548.62 |
6.6 |
Work Order |
01-29-16 |
Work Began |
03-15-16 |
Work Completed |
|
Time Computed |
02-29-16 |
Contract Working Days |
276 |
Addl Days Granted |
0 |
Working Days Charged |
6 |
Percent Time Used |
2 |
Contractor(s) |
FORDE CONSTRUCTION COMPANY, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 3050-02-025 THIRD COAST SERVICES LLC (2.84%) K4 ENVIRONMENTAL LLC (3.19%) LONESTAR TRAFFIC SAFETY, LLC (0.50%) ROADSAFE TRAFFIC SYSTEMS, INC. (0.97%)
|
Contract # |
12153035 |
|
Totals |
8195982.09 |
544548.62 |
544548.62 |
6.6 |
|
County | HARRIS |
Highway |
FM 2978 |
From |
0.065 MILES SOUTH OF BOGS RD |
To |
0.145 MILES SOUTH OF BOGS RD |
CSJ |
3050-03-015 |
Proj ID |
STP 2012(376) |
Work Type |
DETENTION POND & STORM SEWER OUTFAL |
|
|
0.080 |
848935.94 |
0.00 |
824956.78 |
100.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order |
05-22-12 |
Work Began |
08-16-12 |
Work Completed |
02-24-15 |
Time Computed |
08-16-12 |
Contract Working Days |
63 |
Addl Days Granted |
0 |
Working Days Charged |
96 |
Percent Time Used |
152 |
Contractor(s) |
TRIPLE B SERVICES LLP |
SUBCONTRACTOR(S) FOR CCSJ: 3050-03-015 WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(2.12%) STRIPES & STOPS COMPANY, INC.(0.08%) LANDSCAPING CONTRACTING & IRRIGATION ( 19.81%) ENVIRONMENTAL ALLIES, L.P. (0.42%) HASARA LAND SERVICES (1.00%) CANALES TRUCKING INC.( 15.80%)
|
Contract # |
03123216 |
|
Totals |
848935.94 |
0.00 |
824956.78 |
100.0 |
|
County | MONTGOMERY |
Highway |
FM 3083 |
From |
AT UPRR |
To |
. |
CSJ |
3158-01-031 |
Proj ID |
C 3158-1-31 |
Work Type |
CONSTRUCT GRADE SEPARATION |
|
|
0.705 |
13080676.41 |
0.00 |
0.00 |
0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order |
09-11-15 |
Work Began |
00-00-00 |
Work Completed |
|
Time Computed |
00-00-00 |
Contract Working Days |
378 |
Addl Days Granted |
0 |
Working Days Charged |
0 |
Percent Time Used |
0 |
Contractor(s) |
SMITH & COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 3158-01-031 ROADSAFE TRAFFIC SYSTEMS, INC. (0.33%) J & M CONTRACTING, COMPANY (6.16%) WILLOW CITY SIGN & RAIL, INC.(0.94%) CENTEX HYDROSEED (1.70%) EROSION PREVENTION PRODUCTS(0.48%) M & D FOUNDATION DRILLING INDUSTRIES, INC. (7.51%)
|
Contract # |
07143209 |
|
Totals |
13080676.41 |
0.00 |
0.00 |
0.0 |
|
County | MONTGOMERY |
Highway |
FM 3083 |
From |
IH 45 |
To |
0.4 MI EAST OF SH 75 |
CSJ |
3158-01-035 |
Proj ID |
C 3158-1-35 |
Work Type |
WIDEN ROADWAY |
|
|
1.040 |
3065561.19 |
0.00 |
3420815.71 |
100.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order |
10-15-13 |
Work Began |
12-16-13 |
Work Completed |
02-11-15 |
Time Computed |
12-14-13 |
Contract Working Days |
181 |
Addl Days Granted |
1 |
Working Days Charged |
178 |
Percent Time Used |
97 |
Contractor(s) |
SMITH & COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 3158-01-035 CEN TEX HYDROSEED, INC.(3.49%) J & M CONTRACTING, COMPANY ( 10.40%) N-LINE TRAFFIC MAINTENANCE, L.P. (0.25%) ROADSAFE TRAFFIC SYSTEMS, INC. (1.02%) SIEMENS INDUSTRY, INC. (6.31%) WEST TEXAS RUMBLE STRIP(0.14%) WILLOW CITY SIGN & RAIL, INC.(0.34%) THIRD COAST SERVICES LLC (6.31%)
|
Contract # |
07133227 |
|
Totals |
3065561.19 |
0.00 |
3420815.71 |
100.0 |
|
County | MONTGOMERY |
Highway |
FM 3083 |
From |
LP 336 NORTH |
To |
0.208 MI N OF FM 1485 |
CSJ |
3158-01-037 |
Proj ID |
NH 1502(021) |
Work Type |
BASE REPAIR AND ACP O / L |
|
|
10.519 |
4452712.16 |
12595.08 |
3924042.04 |
100.0 |
Work Order |
06-04-15 |
Work Began |
08-24-15 |
Work Completed |
02-22-16 |
Time Computed |
08-04-15 |
Contract Working Days |
81 |
Addl Days Granted |
2 |
Working Days Charged |
81 |
Percent Time Used |
97 |
Contractor(s) |
ANGEL BROTHERS ENTERPRISES, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 3158-01-037 J & M CONTRACTING, COMPANY (2.07%) STRIPE A LINE(3.10%) WILLOW CITY SIGN & RAIL, INC.(2.30%)
|
Contract # |
04153029 |
|
Totals |
4452712.16 |
12595.08 |
3924042.04 |
100.0 |
|
County | HARRIS |
Highway |
SH 99 |
From |
BS 146 EAST (SEGMENT 1-2) |
To |
CHAMBERS COUNTY LINE |
CSJ |
3187-01-005 |
Proj ID |
C 3187-1-5 |
Work Type |
CONSTRUCT TWO 2 - LN FRONTAGE ROADS |
|
|
3.101 |
35161387.54 |
3093194.00 |
11167694.17 |
31.7 |
Work Order |
10-17-14 |
Work Began |
08-31-15 |
Work Completed |
|
Time Computed |
11-02-14 |
Contract Working Days |
486 |
Addl Days Granted |
0 |
Working Days Charged |
162 |
Percent Time Used |
33 |
Contractor(s) |
WEBBER, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 3187-01-005 WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.38%) TEXAS ENVIRONMENTAL MANAGEMENT, INC(2.19%) SOUTHERN CRUSHED CONCRETE LLC(1.13%) WILLOW CITY SIGN & RAIL, INC.(1.28%) PRIMATE CONSTRUCTION, INC. (0.19%) WEBBER BARRIER SERVICES, LLC.(0.28%) ALLSTATE SIGNAL & CONSTRUCTION, LLC(0.87%) CHOCTAW ERECTORS, INC. (2.04%) MESA ROD BUSTERS, INC. (0.78%) MBN ENTERPRISES LLC(1.64%) SCOTT DERR PAINTING CO, LLC(0.20%) GMJ PAVING CO. (2.80%)
|
Contract # |
07143003 |
|
Totals |
35161387.54 |
3093194.00 |
11167694.17 |
31.7 |
|
County | HARRIS |
Highway |
BW 8 |
From |
AT WHITE OAK BAYOU |
To |
. |
CSJ |
3256-01-096 |
Proj ID |
NH 2014(955) |
Work Type |
CHANNEL IMPROVEMENTS |
|
|
0.034 |
275178.00 |
0.00 |
401171.34 |
100.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order |
08-20-14 |
Work Began |
09-05-14 |
Work Completed |
02-02-15 |
Time Computed |
09-05-14 |
Contract Working Days |
40 |
Addl Days Granted |
0 |
Working Days Charged |
40 |
Percent Time Used |
100 |
Contractor(s) |
SJ&J CONSTRUCTION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 3256-01-096 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # |
07143034 |
|
Totals |
275178.00 |
0.00 |
401171.34 |
100.0 |
|
County | HARRIS |
Highway |
SL 8 |
From |
AT HAMMERLY BLVD |
To |
. |
CSJ |
3256-01-102 |
Proj ID |
STP 2015(616)HES |
Work Type |
IMPROVE TS |
|
|
0.404 |
611048.35 |
1500.00 |
657922.74 |
99.9 |
Work Order |
03-20-15 |
Work Began |
05-18-15 |
Work Completed |
|
Time Computed |
05-18-15 |
Contract Working Days |
134 |
Addl Days Granted |
0 |
Working Days Charged |
102 |
Percent Time Used |
76 |
Contractor(s) |
ALLSTATE SIGNAL & CONSTRUCTION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 3256-01-102 REPUBLIC TRAFFIC SAFETY, INC.(3.71%) THOMPSON"S CONSTRUCTION STR DESIGNS(8.86%) SCMU ( 17.36%)
|
Contract # |
02153216 |
|
Totals |
611048.35 |
1500.00 |
657922.74 |
99.9 |
|
County | HARRIS |
Highway |
SL 8 |
From |
WEST AIRPORT BLVD |
To |
WESTPARK |
CSJ |
3256-01-106 |
Proj ID |
HP 1502(450) |
Work Type |
LANDSCAPE DEVELOPMENT |
|
|
5.660 |
875730.77 |
0.00 |
0.00 |
0.0 |
Work Order |
11-02-15 |
Work Began |
00-00-00 |
Work Completed |
|
Time Computed |
01-31-16 |
Contract Working Days |
90 |
Addl Days Granted |
0 |
Working Days Charged |
0 |
Percent Time Used |
0 |
Contractor(s) |
BOYER, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 3256-01-106 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # |
07153020 |
|
Totals |
875730.77 |
0.00 |
0.00 |
0.0 |
|
County | HARRIS |
Highway |
BW 8 |
From |
0.8 MI W OF US 59(N) |
To |
0.3 MI E OF OLD HUMBLE RD (PHASE 2) |
CSJ |
3256-02-040 |
Proj ID |
C 3256-2-40 |
Work Type |
GR, STRS, BASE & CONC PAVT |
|
|
0.341 |
8671033.70 |
0.00 |
9412235.09 |
100.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order |
10-09-12 |
Work Began |
11-05-12 |
Work Completed |
02-24-15 |
Time Computed |
10-25-12 |
Contract Working Days |
365 |
Addl Days Granted |
34 |
Working Days Charged |
379 |
Percent Time Used |
94 |
Contractor(s) |
LONE STAR ROAD CONSTRUCTION, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 3256-02-040 HIGHWAY TECHNOLOGIES, INC. (1.20%) HOUSTON SAWING & DRILLING(0.16%) CREACOM, INC.(5.72%) REGIONAL TRAFFIC SERVICES LLC(0.21%) W. W. FOUNDATION DRILLING, LTD.(2.53%) WEBBER-BALKE FOUNDATION COMPANY, INC.(1.95%) SCOTT DERR PAINTING CO, LLC(0.39%) ENVIRONMENTAL ALLIES, L.P. (0.23%) MESA ROD BUSTERS, INC. (1.81%) BREDA COMPANY, INC.(0.14%) REGIONAL TRAFFIC SERVICES LLC(1.44%) SPECIALTY DRILLING, LTD. (1.03%) J. T. B. SERVICES, INC.(0.05%) A-1 EROSION CONTROL, LLC (0.14%) CURB PLANET INC. (0.00%) BUYERS BARRICADES, INC.(0.17%)
|
Contract # |
08123024 |
|
Totals |
8671033.70 |
0.00 |
9412235.09 |
100.0 |
|
County | HARRIS |
Highway |
BW 8 |
From |
WEST OF GREENSPOINT DR. |
To |
WEST HARDY ROAD |
CSJ |
3256-02-061 |
Proj ID |
CM 2008(838) |
Work Type |
GR, STRS, BASE AND PAVE |
|
|
2.451 |
15013244.15 |
107800.00 |
17114259.82 |
100.0 |
County | HARRIS |
Highway |
BW 8 |
From |
IH 45N |
To |
HARDY TOLL ROAD |
CSJ |
3256-02-070 |
Proj ID |
CM 2006(382) |
Work Type |
ACQUISITION, UTILITIES AND RELOCATI |
|
|
1.553 |
390857.00 |
0.00 |
568669.54 |
100.0 |
Work Order |
05-22-09 |
Work Began |
09-05-09 |
Work Completed |
02-10-16 |
Time Computed |
09-05-09 |
Contract Working Days |
575 |
Addl Days Granted |
647 |
Working Days Charged |
1,219 |
Percent Time Used |
99 |
Contractor(s) |
LIBERTY MUTUAL INSURANCE COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 3256-02-061 COASTAL CRUSHED CONCRETE, LLC(2.59%) ROADSAFE TRAFFIC SYSTEMS, INC. (0.26%) SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (1.14%) DIAMOND J DRILLING (1.75%) KENNETH LAMB CONSTRUCTION( 12.42%) JOE VALENCIK, INC. (0.88%) STRIPES & STOPS COMPANY, INC.(0.06%) CHERRY DEMOLITION(0.11%) JET UNDERGROUND UTILITIES, INC.(2.80%) CPAV SPECIALTIES, LP (0.42%) TRIUMPH PARKING LOT MAINTENANCE, INC.(0.04%) NORTHWEST MATERIALS(0.01%) BAHENA STEEL (0.12%) MESA ROD BUSTERS, INC. (1.17%) GROUND HOG FOUNDATION DRILLING (0.06%) VICK OPERATING COMPANY, LLC(0.96%) HUBCO, INC.(0.96%) JTB SERVICES (0.32%) PEREZ CONSTRUCTION (0.12%) TEXAS STERLING CONSTRUCTION CO.( 65.72%) MAGNUM TUNNELING, LLC(0.70%) SCOTT DERR PAINTING CO (0.07%) PRIMATE CONSTRUCTION, INC. (0.38%) ROADSAFE TRAFFIC SYSTEMS, INC. (0.17%) BATTERSON,LLP(1.24%) TRAFFIC SYSTEMS CONSTRUCTION, INC. (2.39%) SOUTHERN CRUSHED CONCRETE LLC(1.64%) EL DORADO PAVING COMPANY, INC. (0.61%) A A CONSTRUCTION (0.61%) WILLOW CITY SIGN & RAIL, INC.(0.16%) ENVIRONMENTAL ALLIES, L.P. (0.31%) MESA ROD BUSTERS, INC. (0.97%) EROSION CONTROL, INC.(0.56%)
|
Contract # |
03093228 |
|
Totals |
15404101.15 |
107800.00 |
17682929.36 |
100.0 |
|
County | HARRIS |
Highway |
BW 8 |
From |
AT JOHN F KENNEDY BLVD |
To |
. |
CSJ |
3256-02-086 |
Proj ID |
STP 1102(317)HESG |
Work Type |
TRAFFIC SIGNAL |
|
|
0.002 |
380585.05 |
0.00 |
468911.83 |
100.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order |
09-14-11 |
Work Began |
10-10-11 |
Work Completed |
02-10-15 |
Time Computed |
09-30-11 |
Contract Working Days |
122 |
Addl Days Granted |
0 |
Working Days Charged |
78 |
Percent Time Used |
63 |
Contractor(s) |
TRAF-TEX, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 3256-02-086 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # |
08113272 |
|
Totals |
380585.05 |
0.00 |
468911.83 |
100.0 |
|
County | HARRIS |
Highway |
SL 8 |
From |
IH 45 NORTH |
To |
US 59 NORTH |
CSJ |
3256-02-089 |
Proj ID |
NH 2016(448) |
Work Type |
TRANSPORTATION MANAGEMENT SYSTEM |
|
|
3.087 |
26822716.09 |
0.00 |
0.00 |
0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order |
03-24-16 |
Work Began |
00-00-00 |
Work Completed |
|
Time Computed |
00-00-00 |
Contract Working Days |
536 |
Addl Days Granted |
0 |
Working Days Charged |
0 |
Percent Time Used |
0 |
Contractor(s) |
WEBBER, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 3256-02-089 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # |
11153003 |
|
Totals |
26822716.09 |
0.00 |
0.00 |
0.0 |
|
County | HARRIS |
Highway |
SL 8 |
From |
RDWY APP TO BW 8 WB/IH 45 SB DC |
To |
RDWY DEP FROM IH 45 NB/BW 8 EB DC |
CSJ |
3256-02-091 |
Proj ID |
NH 2016(728) |
Work Type |
CONSTR CR ATTENUATING MIX W / O / L |
|
|
0.560 |
596804.70 |
0.00 |
0.00 |
0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order |
03-16-16 |
Work Began |
00-00-00 |
Work Completed |
|
Time Computed |
00-00-00 |
Contract Working Days |
15 |
Addl Days Granted |
0 |
Working Days Charged |
0 |
Percent Time Used |
0 |
Contractor(s) |
DURWOOD GREENE CONSTRUCTION CO. |
SUBCONTRACTOR(S) FOR CCSJ: 3256-02-091 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # |
02163032 |
|
Totals |
596804.70 |
0.00 |
0.00 |
0.0 |
|