Monthly State Let Construction Report For Houston District As Of Apr 12, 2024 Page 2 Of 13

Last Update: Friday, April 12, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11 | page 12 | page 13

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHARRIS
HighwayBU 290H
From0.25 MI NW OF KICKAPOO RD
To0.25 MI SE OF KICKAPOO RD
CSJ0050-06-094
Proj IDSTP 2021(331)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.50078734.4073839.5093.7
Work Order06-17-21
Work Began06-06-22
Work Completed
Time Computed07-17-21
Contract Working Days90
Addl Days Granted0
Working Days Charged38
Percent Time Used42
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0050-06-094
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05213236
Totals78734.400.0073839.5093.7

CountyHARRIS
HighwaySH 3
FromSOUTH RICHEY STREET
ToGALVESTON COUNTY LINE
CSJ0051-02-108
Proj IDSTP 2022(405)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
14.5865450259.593512547.8469.2
Work Order04-19-22
Work Began08-03-22
Work Completed
Time Computed05-19-22
Contract Working Days223
Addl Days Granted0
Working Days Charged458
Percent Time Used205
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0051-02-108
GMJ PAVING CO. (17.46)
TRAFFIC SIGNS & LINES, LLC (14.02)
SOUTHERN EROSION, LLC (2.54)
CURB PLANET INC. (2.03)
PROFESSIONAL TRAFFIC CONTROL LLC (0.13)
Contract #03223204
Totals5450259.593097.703512547.8469.2

CountyGALVESTON
HighwaySH 3
FromN OF FM 1765
ToSH 146
CSJ0051-03-117
Proj IDC 51-3-117
Work TypeOVERLAY
 
2.9804384915.813854817.6387.9
Work Order03-24-22
Work Began05-14-22
Work Completed
Time Computed05-14-22
Contract Working Days150
Addl Days Granted0
Working Days Charged135
Percent Time Used90
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0051-03-117
QUALITY TURF FARMS, L.C. (0.26)
STRIPE LINES, INC. (4.27)
TRAF-TEX, INC. (11.28)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. (0.87)
Contract #02223210
Totals4384915.810.003854817.6387.9

CountyGALVESTON
HighwaySH 3
FromHARRIS C/L
ToFM 646
CSJ0051-03-119
Proj IDSTP 2022(919)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3.7001131153.801058646.3893.5
Work Order09-20-22
Work Began03-23-23
Work Completed
Time Computed10-20-22
Contract Working Days357
Addl Days Granted0
Working Days Charged122
Percent Time Used34
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0051-03-119
REPUBLIC TRAFFIC SAFETY, INC. (4.06)
LONESTAR TRAFFIC SAFETY, LLC (1.22)
TEXAS REEXCAVATION (1.87)
J.KRU LAND SERVICES, LLC (4.87)
TEXAS DRAINAGE INC. (7.48)
Contract #08223023
Totals1131153.8019624.251058646.3893.5

CountyGALVESTON
HighwaySS 342
FromAT HEARDS LANE
To.
CSJ0051-08-019
Proj IDSTP 2021(260)HES
Work TypeTRAFFIC CONTROL DEVICES
 
2.000243649.85117830.0048.3
CountyBRAZORIA
HighwaySH 35
FromAT FM 524
To.
CSJ0179-11-004
Proj IDSTP 2021(260)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.200145343.20266200.9099.9
CountyBRAZORIA
HighwaySH 332
FromAT FM 523
To.
CSJ0586-01-068
Proj IDSTP 2021(260)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.20019680.000.000.0
CountyGALVESTON
HighwayFM 2004
From0.5 MI N OF TACQUARD RANCH ROAD
To0.5 MI S OF TACQUARD RANCH ROAD
CSJ2523-01-027
Proj IDSTP 2021(260)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.00049795.000.000.0
Work Order03-01-21
Work Began03-18-22
Work Completed
Time Computed06-29-21
Contract Working Days61
Addl Days Granted0
Working Days Charged26
Percent Time Used42
Contractor(s)
CITYLYNX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0051-08-019
SPECIALTY DRILLING (5.58)
H & N CONTRACTOR MANAGEMENT SERVICES LLC (0.00)
Contract #01213222
Totals458468.058170.00384030.9083.7

CountyGALVESTON
HighwayFM 3005
FromSAN LUIS PASS
ToWEST END OF GALVESTON SEAWALL
CSJ0051-09-024
Proj IDNH 2019(988)
Work TypeOVERLAY
 
18.71235347635.3334767918.7698.3
Work Order06-13-19
Work Began08-20-19
Work Completed
Time Computed09-11-19
Contract Working Days450
Addl Days Granted89
Working Days Charged539
Percent Time Used100
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0051-09-024
PROFESSIONAL TRAFFIC CONTROL LLC (3.21)
CEN TEX HYDROSEED, INC. (1.83)
JMHP, INC. (0.70)
MURRAY CONSTRUCTION (0.74)
KMA CONTRACTORS SERVICES INC. (1.82)
THIRD COAST SERVICES LLC (1.33)
CURB PLANET INC. (0.07)
TRAFFIC SIGNS & LINES, LLC (0.02)
Contract #05193003
Totals35347635.33230510.0034767918.7698.3

CountyGALVESTON
HighwayFM 3005
FromAT 89TH ST
To.
CSJ0051-09-126
Proj IDSTP 2022(920)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.600848580.69322335.7537.9
Work Order09-15-22
Work Began00-00-00
Work Completed
Time Computed01-13-23
Contract Working Days86
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ALLSTATE SIGNAL & CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0051-09-126
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08223242
Totals848580.690.00322335.7537.9

CountyFORT BEND
HighwayUS 59
FromWEST OF HAMLINK ROAD
ToWEST OF SPUR 10
CSJ0089-09-058
Proj IDC 89-9-58
Work TypeGR, STRS, BS & SURF
 
8.004100144090.32100052760.4099.9
Work Order01-06-16
Work Began01-18-16
Work Completed
Time Computed01-18-16
Contract Working Days919
Addl Days Granted201
Working Days Charged1,120
Percent Time Used100
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0089-09-058
BASE CONSTRUCTION (9.99)
CPAVE, INC. (0.24)
CREACOM, INC. (3.26)
ESSARY, HART & MACWILIAM,INC. (6.93)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.01)
INTERSTATE BARRICADES & MARKINGS, INC. (0.96)
QUALITY TURF FARMS, LC (2.08)
SCOTT DERR PAINTING CO, LLC (0.01)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (1.13)
BORTUNCO (0.23)
WASTE PARTNERS OF TEXAS, INC (0.07)
ANTIGO CONSTRUCTION, INC. (0.03)
RAY"S THREADING AND FAB SHOP (0.72)
STEEL EFFECTS (0.08)
WEST TEXAS ROCK RESOURCES, LLC (0.10)
CURB PLANET INC. (0.02)
PINNACLE GRINDING AND GROOVING LLC (0.00)
Contract #12153001
Totals100144090.320.00100052760.4099.9

CountyMONTGOMERY ETC
HighwayIH 45 ETC
FromSL 336 SOUTH
ToHARRIS COUNTY LINE
CSJ0110-04-219
Proj IDC 110-4-219
Work TypeLANDSCAPE & SCENIC ENHANCEMENT
 
54.1032579831.801666610.6864.6
Work Order02-14-23
Work Began03-16-23
Work Completed
Time Computed03-16-23
Contract Working Days135
Addl Days Granted0
Working Days Charged136
Percent Time Used100
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0110-04-219
R & A DIRECTIONAL BORING (0.15)
SCOTT DERR PAINTING CO, LLC (0.17)
Contract #01233219
Totals2579831.80215219.191666610.6864.6

CountyHARRIS
HighwayIH 45
FromCYPRESS STA. DRIVE
ToCYPRESS OAK DRIVE
CSJ0110-05-126
Proj IDC 110-5-126
Work TypeBRIDGE REPLACEMENT
 
1.5566683533.8011754370.5899.9
Work Order02-23-22
Work Began03-25-22
Work Completed
Time Computed03-25-22
Contract Working Days591
Addl Days Granted0
Working Days Charged591
Percent Time Used100
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0110-05-126
STRIPE LINES, INC. (0.29)
RDI FOUNDATION DRILLING (4.41)
MARTIN MARIETTA MATERIALS, INC. (1.57)
SER CONSTRUCTION PARTNERS, LLC (91.11)
STRIPE LINES, INC. (0.37)
A. SANCHEZ TRUCKING (0.74)
PRV SERVICES, INC. (0.74)
HOUSTON SAWING & DRILLING (0.66)
MARTIN MARIETTA MATERIALS, INC. (1.57)
RDI FOUNDATION DRILLING (6.29)
MONTALVO BRIDGE SYSTEMS, LLC (0.63)
TNT CRANE & RIGGING, INC. (0.54)
HI-TECH CONCREE PUMPING SERVICES (0.00)
WILLOW CITY SIGN & RAIL, INC. (0.29)
SCOTT DERR PAINTING CO, LLC (0.16)
CURB PLANET INC. (0.03)
BRUNDAGE-BONE (0.07)
SEAMARCK LANDSCAPE SERVICES, INC (0.00)
SEMARCK LANDSCAPE SERVICES, INC. (0.29)
Contract #12213014
Totals6683533.80542037.4911754370.5899.9

CountyHARRIS
HighwayIH 45
FromAT FM 1960
To.
CSJ0110-05-130
Proj IDSTP 2021(259)HES
Work TypeTRAFFIC CONTROL DEVICES
 
0.200474658.72540429.4899.9
Work Order03-05-21
Work Began06-30-23
Work Completed
Time Computed07-03-21
Contract Working Days93
Addl Days Granted0
Working Days Charged84
Percent Time Used90
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0110-05-130
STRIPE LINES, INC. (4.29)
Contract #01213024
Totals474658.7251229.99540429.4899.9

CountyHARRIS
HighwayIH 45
FromKUYKENDAHL
ToFM 1960
CSJ0110-05-140
Proj IDC 110-5-140
Work TypeTRAFFIC CONTROL DEVICES
 
5.677423534.75455503.3099.9
Work Order02-27-23
Work Began04-27-23
Work Completed
Time Computed03-29-23
Contract Working Days69
Addl Days Granted0
Working Days Charged47
Percent Time Used68
Contractor(s)
PROFESSIONAL TRAFFIC CONTROL LLC
SUBCONTRACTOR(S) FOR CCSJ: 0110-05-140
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01233232
Totals423534.7511446.70455503.3099.9

CountyHARRIS
HighwayIH 45
FromAT WEST ROAD
To.
CSJ0110-06-143
Proj IDSTP 2020(204)HES
Work TypeTRAFFIC CONTROL DEVICES
 
0.200485208.48678963.1199.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-19-19
Work Began04-17-20
Work Completed
Time Computed00-00-00
Contract Working Days59
Addl Days Granted0
Working Days Charged56
Percent Time Used94
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0110-06-143
MENADE, INC. (13.63)
SEMPER STRIPING LLC (5.35)
Contract #11193021
Totals485208.480.00678963.1199.9

CountyHARRIS
HighwayIH 45
FromAT GREENS ROAD
To.
CSJ0110-06-144
Proj IDSTP 2021(187)HES
Work TypeTRAFFIC CONTROL DEVICES
 
0.4001115889.751869663.4499.9
Work Order01-14-21
Work Began08-16-22
Work Completed
Time Computed05-14-21
Contract Working Days137
Addl Days Granted99
Working Days Charged222
Percent Time Used94
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0110-06-144
PROFESSIONAL TRAFFIC CONTROL LLC (2.93)
REDLINE CONSTRUCTION SERVICES LLC (6.05)
Contract #12203214
Totals1115889.7514248.531869663.4499.9

CountyHARRIS
HighwaySS 261
From0.1 MILES NORTH OF W. TIDWELL RD.
To0.1 MILES SOUTH OF W. TIDWELL RD.
CSJ0110-06-154
Proj IDSTP 2023(749)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.200507603.45410572.0080.8
CountyHARRIS
HighwayIH 610
FromAT UA 90
To.
CSJ0271-14-243
Proj IDSTP 2023(749)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.200649660.750.000.0
CountyHARRIS
HighwayIH 10
FromAT WADE RD
To.
CSJ0508-01-384
Proj IDSTP 2023(749)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.10012174.000.000.0
Work Order06-14-23
Work Began00-00-00
Work Completed
Time Computed10-12-23
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0110-06-154
HIGHWAY 1 LLC (1.76)
REDLINE SERVICES, INC. (10.24)
Contract #05233043
Totals1169438.204930.00410572.0035.1

CountyHARRIS
HighwayFM 521
FromAT FUQUA STREET
To.
CSJ0111-01-096
Proj IDSTP 2020(055)HES
Work TypeTRAFFIC CONTROL DEVICES
 
0.200226988.26348368.6999.9
Work Order03-12-20
Work Began11-02-20
Work Completed
Time Computed07-10-20
Contract Working Days31
Addl Days Granted0
Working Days Charged24
Percent Time Used77
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0111-01-096
STRIPE LINES, INC. (9.26)
REDLINE CONSTRUCTION SERVICES LLC (5.90)
Contract #10193223
Totals226988.2632621.19348368.6999.9

CountyFORT BEND
HighwayFM 521
FromSH 6
ToFM 2234
CSJ0111-03-059
Proj IDF 2023(494)
Work TypeWIDEN NON-FREEWAY
 
5.31299699464.9019392560.7919.4
Work Order08-03-23
Work Began11-06-23
Work Completed
Time Computed11-01-23
Contract Working Days767
Addl Days Granted0
Working Days Charged115
Percent Time Used14
Contractor(s)
GRANITE CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0111-03-059
KAY SERVICES, INC. (0.04)
QUALITY TURF FARMS, L.C. (1.15)
ALLSTATE SIGNAL & CONSTRUCTION, LLC (5.55)
REPUBLIC TRAFFIC SAFETY, INC. (1.13)
SAFETEX,INC. (0.09)
RDI FOUNDATION DRILLING (1.97)
DURWOOD GREENE CONSTRUCTION CO. (3.28)
ANTIGO CONSTRUCTION, INC. (0.10)
VALLEY PLACERS, LLC (0.10)
FLOVERA CONSTRUCTION SERVICES, LLC (1.07)
ROADWAY SPECIALTIES, INC. (0.10)
A BROTHERS MILLING, LLC (0.37)
ROYAL REBAR (5.55)
B & D MAINTENANCE (0.04)
AARON CONCRETE CONTRACTORS, LLC (0.44)
COMPRA IMPORT&EXPORT.JR LLC (0.30)
LINA T. RAMEY & ASSOCIATES, INC. (0.03)
CURB PLANET INC. (0.03)
PRIMATE CONSTRUCTION, LP (0.13)
PRECISION CONCRETE PUMPING LLC (0.04)
Contract #04233201
Totals99699464.901218703.9219392560.7919.4

CountyBRAZORIA
HighwaySH 36
From0.5 MI S OF THE BRAZOS RIVER
ToFM 1495 (SEG. 15)
CSJ0111-08-100
Proj IDC 111-8-100
Work TypeWIDEN NON-FREEWAY
 
1.2468923164.9010616413.2599.9
Work Order09-16-21
Work Began11-15-21
Work Completed
Time Computed11-15-21
Contract Working Days522
Addl Days Granted5
Working Days Charged524
Percent Time Used99
Contractor(s)
COPASA INC
SUBCONTRACTOR(S) FOR CCSJ: 0111-08-100
GMJ PAVING COMPANY LLC (5.80)
PROFESSIONAL TRAFFIC CONTROL LLC (1.13)
THIRD COAST SERVICES LLC (3.27)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. (3.26)
ANTIGO CONSTRUCTION, INC. (0.26)
TEXOP CONSTRUCTION (0.29)
(INACTIVE)SORRELL CONSTRUCTION, EQUIPMENT & MATERIALS, LLC (0.00)
QUALITY TURF FARMS, L.C. (2.07)
HERMANOS STEEL, LLC (1.47)
CPAVE, INC. (0.51)
PENHALL COMPANY (0.78)
SMYRNA READY MIX CONCRETE, LLC (14.82)
CRANE MASTERS, INC. (0.17)
Contract #08213016
Totals8923164.90102082.3010616413.2599.9

CountyBRAZORIA
HighwaySH 288
From2ND STREET
ToSH 36
CSJ0111-08-124
Proj IDC 111-8-124
Work TypeOVERLAY
 
1.4102068826.464379332.9299.9
Work Order03-15-23
Work Began06-05-23
Work Completed
Time Computed04-14-23
Contract Working Days51
Addl Days Granted16
Working Days Charged58
Percent Time Used86
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0111-08-124
LONESTAR TRAFFIC SAFETY, LLC (0.17)
PENHALL COMPANY (23.55)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (8.45)
WILLOW CITY SIGN & RAIL, INC. (2.65)
BATTERSON, LLP (5.95)
HIGHWAY 1 LLC (0.35)
AGGREGATE TECHNOLOGIES, INC. (0.97)
CPAVE, INC. (1.08)
QUALITY TURF FARMS, L.C. (0.18)
Contract #02233234
Totals2068826.460.004379332.9299.9

CountyBRAZORIA
HighwayBS 288B
FromFM 2004
ToJOHNSON COOK ROAD
CSJ0111-08-126
Proj IDSTP 2023(348)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
8.6001319307.50899720.8368.1
Work Order04-12-23
Work Began00-00-00
Work Completed
Time Computed05-12-23
Contract Working Days82
Addl Days Granted0
Working Days Charged12
Percent Time Used14
Contractor(s)
VACA UNDERGROUND UTILITIES INC
SUBCONTRACTOR(S) FOR CCSJ: 0111-08-126
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01233020
Totals1319307.500.00899720.8368.1

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11 | page 12 | page 13