Monthly State Let Construction Report For Houston District As Of Feb 11, 2015 Page 5 Of 11

Last Update: Wednesday, February 11, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyWALLER
Highway FM 362
From AT FM 529
To .
CSJ 0523-02-044
Proj ID STP 2014(486)HES
Work Type INST FLASHING BEACON
 
0.001 109572.50 0.00 108248.50 100.0
Work Order 04-11-14
Work Began 10-07-14
Work Completed 02-06-15
Time Computed 10-07-14
Contract Working Days 29
Addl Days Granted 0
Working Days Charged 15
Percent Time Used 51
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0523-02-044
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03143031
Totals 109572.50 0.00 108248.50 100.0

CountyMONTGOMERY
Highway FM 1488
From FM 149
To 0.3 MI E OF COMMUNITY RD AT MOSTYN
CSJ 0523-10-034
Proj ID C 523-10-34
Work Type CONSTRUCT RR GRADE SEPARATION
 
2.779 27649979.11 154079.79 2342473.74 8.4
Work Order 10-22-13
Work Began 00-00-00
Work Completed  
Time Computed 07-19-14
Contract Working Days 478
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0523-10-034
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07133003
Totals 27649979.11 154079.79 2342473.74 8.4

CountyFORT BEND
Highway FM 1462
From BRAZORIA C/L (WEST SIDE)
To FM 762
CSJ 0543-03-070
Proj ID STP 2014(512)
Work Type BASE REP, ACP O / L, PAVE MARKS, ETC.
 
11.481 1799826.94 76.35 2273107.92 100.0
Work Order 04-22-14
Work Began 06-04-14
Work Completed 12-08-14
Time Computed 06-04-14
Contract Working Days 60
Addl Days Granted 5
Working Days Charged 68
Percent Time Used 104
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0543-03-070
BATTERSON,LLP(5.09%)
WEST TEXAS RUMBLE STRIP(0.21%)
Contract # 03143211
Totals 1799826.94 76.35 2273107.92 100.0

CountyFORT BEND
Highway FM 762
From AT FM 2977
To .
CSJ 0543-03-071
Proj ID STP 2014(927)
Work Type INSTALL TURN LANE & IMPROVE SHLDS
 
0.615 477521.30 0.00 530419.35 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-13-14
Work Began 09-04-14
Work Completed 12-18-14
Time Computed 09-04-14
Contract Working Days 55
Addl Days Granted 0
Working Days Charged 44
Percent Time Used 80
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0543-03-071
INTERSTATE BARRICADES & MARKINGS, INC. (5.36%)
WEST TEXAS RUMBLE STRIP(0.82%)
BAY CITY TRAFFIC (5.41%)
EROSION CONTROL, INC.(2.80%)
JMHP, INC. (0.91%)
R & A TRANSPORT, INC.(3.11%)
Contract # 06143052
Totals 477521.30 0.00 530419.35 100.0

CountyMONTGOMERY
Highway IH 45
From N OF CRIGHTON RD
To LEAGUE LINE ROAD
CSJ 0675-08-071
Proj ID CM 1102(305)
Work Type INST CTMS
 
6.889 1095536.50 0.00 1130502.95 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-14-11
Work Began 12-10-12
Work Completed 09-02-14
Time Computed 03-12-12
Contract Working Days 375
Addl Days Granted 0
Working Days Charged 374
Percent Time Used 99
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0675-08-071
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08113025
Totals 1095536.50 0.00 1130502.95 100.0

CountyMONTGOMERY
Highway IH 45
From NORTH OF CALVARY
To SOUTH OF FM 830
CSJ 0675-08-084
Proj ID STP 2010(629)ES
Work Type GR, STRS, BASE AND CONC PAVE
 
5.098 57435821.47 24688.38 57896192.86 99.9
CountyMONTGOMERY
Highway IH 45
From FM 830
To WALKER COUNTY LINE
CSJ 0675-08-093
Proj ID RW 675-8-93
Work Type ROW ACQ.
 
8.208 181827.00 0.00 90429.63 49.7
Work Order 05-07-10
Work Began 05-25-10
Work Completed  
Time Computed 05-23-10
Contract Working Days 1,177
Addl Days Granted 10
Working Days Charged 1,204
Percent Time Used 101
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0675-08-084
JOE VALENCIK, INC. (0.94%)
SCOTT DERR PAINTING CO (0.15%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.38%)
INDUS CONSTRUCTION, L.P. ( 14.55%)
CREATIVE LANDSCAPES OF TEXAS (1.20%)
SMITH & COMPANY( 10.78%)
L.A. UTILITIES, INC. (5.04%)
JET UNDERGROUND UTILITIES(4.78%)
INTERSTATE BARRICADES & MARKINGS, INC. (0.95%)
BORING & TUNNELING COMPANY OF AMERICA, INC.(0.17%)
VAQUERO CONSTRUCTION, INC. (0.38%)
D.L. CONDITT (0.35%)
BROOKLYN SWEEPS(0.09%)
HIGHWAY TECHNOLOGIES, INC. (0.01%)
CEN TEX HYDROSEED, INC.(0.01%)
Contract # 03103001
Totals 57617648.47 24688.38 57986622.49 99.9

CountyMONTGOMERY
Highway IH 45
From SH 336 SOUTH LOOP
To NORTH LEAGUE LINE ROAD
CSJ 0675-08-107
Proj ID HP 2013(692)
Work Type LANDSCAPE DEVELOPMENT
 
6.300 745136.01 4266.34 600188.28 80.5
Work Order 08-26-13
Work Began 10-14-13
Work Completed  
Time Computed 10-14-13
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 90
Percent Time Used 100
Contractor(s)
BIO LANDSCAPE & MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0675-08-107
CC TREE FARMS, L.L.C.(1.89%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.96%)
Contract # 05133027
Totals 745136.01 4266.34 600188.28 80.5

CountyGALVESTON
Highway FM 1765
From AT 33RD STREET S
To .
CSJ 0686-01-046
Proj ID STP 2015(315)HES
Work Type FLASHING BEACON AND TURN LANE
 
0.186 481773.82 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-02-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FORDE CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0686-01-046
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11143208
Totals 481773.82 0.00 0.00 0.0

CountyMONTGOMERY
Highway FM 149
From FM 1488
To SS 149
CSJ 0720-02-083
Proj ID STP 2014(741)
Work Type INST LT TN LNS
 
2.466 3762255.55 48965.17 1399918.27 37.2
Work Order 08-29-14
Work Began 10-27-14
Work Completed  
Time Computed 10-27-14
Contract Working Days 220
Addl Days Granted 0
Working Days Charged 38
Percent Time Used 17
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0720-02-083
THIRD COAST SERVICES LLC (3.68%)
COWBELL TRAFFIC SERVICES, INC. (0.24%)
WILLOW CITY SIGN & RAIL, INC.(5.82%)
J & M CONTRACTING, COMPANY ( 11.50%)
EROSION CONTROL, INC.(3.95%)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.06%)
Contract # 06143030
Totals 3762255.55 48965.17 1399918.27 37.2

CountyHARRIS
Highway SH 249
From AT BOUDREAUX EASTBOUND & WESTBOUND
To .
CSJ 0720-03-126
Proj ID NH 2012(710)
Work Type ADD MEDIAN LNS & REBUILD SIGNALS
 
0.100 322274.27 0.00 0.00 100.0
CountyMONTGOMERY
Highway FM 2978
From CONROE HUFFSMITH ROAD
To HARRIS COUNTY LINE
CSJ 3050-02-021
Proj ID STP 2012(107)
Work Type GR, STRS, BASE AND PAVE
 
0.663 743106.43 0.00 997166.07 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-18-12
Work Began 04-15-13
Work Completed 09-29-14
Time Computed 02-15-13
Contract Working Days 101
Addl Days Granted 10
Working Days Charged 111
Percent Time Used 100
Contractor(s)
TRIPLE B SERVICES LLP
SUBCONTRACTOR(S) FOR CCSJ: 3050-02-021
BATTERSON,LLP(4.23%)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.( 19.45%)
HODGES BROTHERS, INC.(0.37%)
KOSSMAN CONTRACTING CO., INC.(2.67%)
ALLSTATE SIGNAL & CONSTRUCTION, LLC( 14.86%)
WILLOW CITY SIGN & RAIL, INC.(4.62%)
ENVIRONMENTAL ALLIES, L.P. (0.05%)
TEXAS HIGHWAY MAINTENANCE, LLC (3.67%)
SCMU (2.99%)
Contract # 08123244
Totals 1065380.70 0.00 997166.07 100.0

CountyHARRIS
Highway SH 249
From AT VETERANS MEMORIAL DRIVE
To .
CSJ 0720-03-128
Proj ID STP 2014(743)HES
Work Type IMPROVE TS
 
0.404 254036.09 0.00 0.00 0.0
Work Order 07-25-14
Work Began 00-00-00
Work Completed  
Time Computed 01-21-15
Contract Working Days 58
Addl Days Granted 0
Working Days Charged 6
Percent Time Used 10
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0720-03-128
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143218
Totals 254036.09 0.00 0.00 0.0

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-331
Proj ID CM 2008(055)
Work Type NEW TRAFFIC SIGNALS
 
0.001 1482581.45 0.00 953292.97 64.2
Work Order 09-11-07
Work Began 04-04-08
Work Completed  
Time Computed 09-27-07
Contract Working Days 235
Addl Days Granted 0
Working Days Charged 103
Percent Time Used 43
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-331
BATTERSON, L.L.P.(1.04%)
SPRING CREEK CONSTRUCTION, INC.(4.49%)
Contract # 08073244
Totals 1482581.45 0.00 953292.97 64.2

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-336
Proj ID STP 2011(578)G
Work Type INSTALL VIVDS AND INSTALL LOOPS
 
0.003 439963.75 0.00 101681.51 23.1
Work Order 01-06-11
Work Began 04-09-12
Work Completed  
Time Computed 01-22-11
Contract Working Days 187
Addl Days Granted 0
Working Days Charged 110
Percent Time Used 58
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-336
CURB PLANET INC. (0.11%)
Contract # 12103011
Totals 439963.75 0.00 101681.51 23.1

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-350
Proj ID CM 2009(364)
Work Type NEW TRAFFIC SIGNALS
 
0.001 1289999.25 0.00 1232112.93 95.5
Work Order 06-02-09
Work Began 08-12-12
Work Completed  
Time Computed 06-18-09
Contract Working Days 225
Addl Days Granted 0
Working Days Charged 198
Percent Time Used 88
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-350
CREACOM, INC.(0.04%)
SPRING CREEK CONSTRUCTION, INC.(3.15%)
HIGHWAY TECHNOLOGIES, INC. (0.76%)
KAM CONSTRUCTION, INC. (0.86%)
WALLACE CONCRETE SAWING(0.14%)
REGIONAL TRAFFIC SERVICES LLC(0.00%)
VASQUEZ CONCRETE COMPANY (0.38%)
Contract # 04093209
Totals 1289999.25 0.00 1232112.93 95.5

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-380
Proj ID STP 2012(020)
Work Type NEW TRAFFIC SIGNALS
 
0.001 1515998.78 300.00 1564776.90 99.9
Work Order 11-16-11
Work Began 02-13-12
Work Completed  
Time Computed 12-02-11
Contract Working Days 437
Addl Days Granted 0
Working Days Charged 274
Percent Time Used 62
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-380
BATTERSON,LLP(5.72%)
ISI CONTRACTING, INC.(6.40%)
VASQUEZ CONCRETE COMPANY (0.32%)
Contract # 09113211
Totals 1515998.78 300.00 1564776.90 99.9

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-381
Proj ID STP 2012(021)
Work Type UPGRADE / RECONSTRUCT TRAFFIC SIGNALS
 
0.001 1787199.58 14033.50 1010031.82 56.5
Work Order 07-19-13
Work Began 10-14-14
Work Completed  
Time Computed 08-04-13
Contract Working Days 432
Addl Days Granted 0
Working Days Charged 66
Percent Time Used 15
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-381
AAA ASPHALT PAVING, INC. (3.02%)
PROFESSIONAL TRAFFIC CONTROL, LLC(2.54%)
Contract # 03133016
Totals 1787199.58 14033.50 1010031.82 56.5

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-385
Proj ID STP 2011(714)G
Work Type UPGRADE / RECONSTRUCT TRAFFIC SIGNALS
 
0.001 911168.15 19960.00 1181401.48 99.9
Work Order 02-10-11
Work Began 11-01-11
Work Completed  
Time Computed 02-26-11
Contract Working Days 270
Addl Days Granted 0
Working Days Charged 182
Percent Time Used 67
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-385
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12103230
Totals 911168.15 19960.00 1181401.48 99.9

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-413
Proj ID STP 2013(542)
Work Type NEW TRAFFIC SIGNALS
 
0.001 1456616.50 51731.20 649331.10 44.5
Work Order 07-08-13
Work Began 11-06-13
Work Completed  
Time Computed 11-06-13
Contract Working Days 417
Addl Days Granted 0
Working Days Charged 67
Percent Time Used 16
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-413
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04133222
Totals 1456616.50 51731.20 649331.10 44.5

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-417
Proj ID STP 2012(462)
Work Type NEW / UPGRADE TO LED LIGHT ASSEMBLIES
 
0.001 859065.05 1445.43 910199.63 99.9
Work Order 05-09-12
Work Began 12-04-12
Work Completed  
Time Computed 05-25-12
Contract Working Days 220
Addl Days Granted 24
Working Days Charged 187
Percent Time Used 76
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-417
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04123026
Totals 859065.05 1445.43 910199.63 99.9

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-418
Proj ID STP 2013(321)
Work Type NEW SATELLITE BUILDING POWER SYS
 
0.001 598106.25 6244.07 549252.83 91.8
Work Order 03-22-13
Work Began 02-24-14
Work Completed  
Time Computed 04-07-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 288
Percent Time Used 78
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-418
GENERATORS OF HOUSTON, LP( 69.74%)
BEVCO COMPANY, INC.(3.17%)
Contract # 01133028
Totals 598106.25 6244.07 549252.83 91.8

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11