Monthly State Let Construction Report For Houston District As Of Oct 14, 2014 Page 5 Of 10

Last Update: Tuesday, October 14, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHARRIS
Highway SH 249
From AT BOUDREAUX EASTBOUND & WESTBOUND
To .
CSJ 0720-03-126
Proj ID NH 2012(710)
Work Type ADD MEDIAN LNS & REBUILD SIGNALS
 
0.100 322274.27 0.00 0.00 100.0
CountyMONTGOMERY
Highway FM 2978
From CONROE HUFFSMITH ROAD
To HARRIS COUNTY LINE
CSJ 3050-02-021
Proj ID STP 2012(107)
Work Type GR, STRS, BASE AND PAVE
 
0.663 743106.43 15601.22 990166.07 100.0
Work Order 10-18-12
Work Began 04-15-13
Work Completed 09-29-14
Time Computed 02-15-13
Contract Working Days 101
Addl Days Granted 10
Working Days Charged 111
Percent Time Used 100
Contractor(s)
TRIPLE B SERVICES LLP
SUBCONTRACTOR(S) FOR CCSJ: 3050-02-021
BATTERSON,LLP(4.23%)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.( 19.45%)
HODGES BROTHERS, INC.(0.37%)
KOSSMAN CONTRACTING CO., INC.(2.67%)
ALLSTATE SIGNAL & CONSTRUCTION, LLC( 14.86%)
WILLOW CITY SIGN & RAIL, INC.(4.62%)
ENVIRONMENTAL ALLIES, L.P. (0.05%)
TEXAS HIGHWAY MAINTENANCE, LLC (3.67%)
SCMU (2.99%)
Contract # 08123244
Totals 1065380.70 15601.22 990166.07 100.0

CountyHARRIS
Highway SH 249
From AT VETERANS MEMORIAL DRIVE
To .
CSJ 0720-03-128
Proj ID STP 2014(743)HES
Work Type IMPROVE TS
 
0.404 254036.09 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-25-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 58
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0720-03-128
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143218
Totals 254036.09 0.00 0.00 0.0

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-331
Proj ID CM 2008(055)
Work Type NEW TRAFFIC SIGNALS
 
0.001 1482581.45 0.00 953292.97 64.2
Work Order 09-11-07
Work Began 04-04-08
Work Completed  
Time Computed 09-27-07
Contract Working Days 235
Addl Days Granted 0
Working Days Charged 103
Percent Time Used 43
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-331
BATTERSON, L.L.P.(1.04%)
SPRING CREEK CONSTRUCTION, INC.(4.49%)
Contract # 08073244
Totals 1482581.45 0.00 953292.97 64.2

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-336
Proj ID STP 2011(578)G
Work Type INSTALL VIVDS AND INSTALL LOOPS
 
0.003 439963.75 0.00 101681.51 23.1
Work Order 01-06-11
Work Began 04-09-12
Work Completed  
Time Computed 01-22-11
Contract Working Days 187
Addl Days Granted 0
Working Days Charged 110
Percent Time Used 58
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-336
CURB PLANET INC. (0.11%)
Contract # 12103011
Totals 439963.75 0.00 101681.51 23.1

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-350
Proj ID CM 2009(364)
Work Type NEW TRAFFIC SIGNALS
 
0.001 1289999.25 0.00 1230474.88 95.3
Work Order 06-02-09
Work Began 08-12-12
Work Completed  
Time Computed 06-18-09
Contract Working Days 225
Addl Days Granted 0
Working Days Charged 198
Percent Time Used 88
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-350
CREACOM, INC.(0.04%)
SPRING CREEK CONSTRUCTION, INC.(3.15%)
HIGHWAY TECHNOLOGIES, INC. (0.76%)
KAM CONSTRUCTION, INC. (0.86%)
WALLACE CONCRETE SAWING(0.14%)
REGIONAL TRAFFIC SERVICES LLC(0.00%)
VASQUEZ CONCRETE COMPANY (0.38%)
Contract # 04093209
Totals 1289999.25 0.00 1230474.88 95.3

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-380
Proj ID STP 2012(020)
Work Type NEW TRAFFIC SIGNALS
 
0.001 1515998.78 80264.10 1497720.84 98.7
Work Order 11-16-11
Work Began 02-13-12
Work Completed  
Time Computed 12-02-11
Contract Working Days 437
Addl Days Granted 0
Working Days Charged 270
Percent Time Used 61
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-380
BATTERSON,LLP(5.72%)
ISI CONTRACTING, INC.(6.40%)
VASQUEZ CONCRETE COMPANY (0.32%)
Contract # 09113211
Totals 1515998.78 80264.10 1497720.84 98.7

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-381
Proj ID STP 2012(021)
Work Type UPGRADE / RECONSTRUCT TRAFFIC SIGNALS
 
0.001 1787199.58 119250.00 707304.38 39.5
Work Order 07-19-13
Work Began 00-00-00
Work Completed  
Time Computed 08-04-13
Contract Working Days 432
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-381
AAA ASPHALT PAVING, INC. (3.02%)
PROFESSIONAL TRAFFIC CONTROL, LLC(2.54%)
Contract # 03133016
Totals 1787199.58 119250.00 707304.38 39.5

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-385
Proj ID STP 2011(714)G
Work Type UPGRADE / RECONSTRUCT TRAFFIC SIGNALS
 
0.001 911168.15 0.00 1161441.48 99.9
Work Order 02-10-11
Work Began 11-01-11
Work Completed  
Time Computed 02-26-11
Contract Working Days 270
Addl Days Granted 0
Working Days Charged 182
Percent Time Used 67
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-385
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12103230
Totals 911168.15 0.00 1161441.48 99.9

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-413
Proj ID STP 2013(542)
Work Type NEW TRAFFIC SIGNALS
 
0.001 1456616.50 0.00 582641.90 39.9
Work Order 07-08-13
Work Began 11-06-13
Work Completed  
Time Computed 11-06-13
Contract Working Days 417
Addl Days Granted 0
Working Days Charged 59
Percent Time Used 14
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-413
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04133222
Totals 1456616.50 0.00 582641.90 39.9

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-417
Proj ID STP 2012(462)
Work Type NEW / UPGRADE TO LED LIGHT ASSEMBLIES
 
0.001 859065.05 0.00 872721.60 99.9
Work Order 05-09-12
Work Began 12-04-12
Work Completed  
Time Computed 05-25-12
Contract Working Days 220
Addl Days Granted 0
Working Days Charged 187
Percent Time Used 85
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-417
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04123026
Totals 859065.05 0.00 872721.60 99.9

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-418
Proj ID STP 2013(321)
Work Type NEW SATELLITE BUILDING POWER SYS
 
0.001 598106.25 447.03 541667.67 90.5
Work Order 03-22-13
Work Began 02-24-14
Work Completed  
Time Computed 04-07-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 181
Percent Time Used 49
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-418
GENERATORS OF HOUSTON, LP( 69.74%)
BEVCO COMPANY, INC.(3.17%)
Contract # 01133028
Totals 598106.25 447.03 541667.67 90.5

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-420
Proj ID STP 2013(322)
Work Type NEW TRAFFIC SIGNALS
 
0.001 1899903.95 0.00 0.00 0.0
Work Order 03-20-13
Work Began 00-00-00
Work Completed  
Time Computed 09-16-13
Contract Working Days 525
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-420
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01133213
Totals 1899903.95 0.00 0.00 0.0

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS IN HARRIS COUNTY
To .
CSJ 0912-00-424
Proj ID CM 1102(560)
Work Type PED & SIG IMPRVMTS IN AIRLINE DIST
 
1.367 2697458.33 25078.34 571304.32 21.1
Work Order 01-23-14
Work Began 04-14-14
Work Completed  
Time Computed 04-14-14
Contract Working Days 228
Addl Days Granted 0
Working Days Charged 106
Percent Time Used 46
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-424
GEORGE MEEKS LANDPRO, INC. (7.03%)
ODUM SERVICES, L.P.(0.35%)
TRAFFIC SYSTEMS CONSTRUCTION, INC. ( 11.47%)
REGIONAL TRAFFIC SERVICES LLC(2.15%)
AGGREGATE TECHNOLOGIES, INC. (5.02%)
SPEEDY PAVING(1.31%)
Contract # 10133027
Totals 2697458.33 25078.34 571304.32 21.1

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-441
Proj ID NH 2014(297)
Work Type UPGRADE / RECONSTRUCT TRAFFIC SIGNALS
 
0.001 1210347.90 785.00 854337.56 70.5
Work Order 03-03-14
Work Began 06-02-14
Work Completed  
Time Computed 06-02-14
Contract Working Days 500
Addl Days Granted 0
Working Days Charged 75
Percent Time Used 15
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-441
REGIONAL TRAFFIC SERVICES LLC(1.78%)
Contract # 12133223
Totals 1210347.90 785.00 854337.56 70.5

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS
To .
CSJ 0912-00-443
Proj ID STP 2014(298)
Work Type INSTALL CCTV
 
0.001 243957.34 2421.12 247982.50 99.9
Work Order 01-17-14
Work Began 03-11-14
Work Completed  
Time Computed 03-11-14
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 147
Percent Time Used 98
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-443
AMERICAN CABLE SERVICES, INC.(2.55%)
Contract # 12133020
Totals 243957.34 2421.12 247982.50 99.9

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS ON IH 45
To .
CSJ 0912-00-468
Proj ID IM 0451(341)
Work Type LANDSCAPE DEVELOPMENT
 
52.668 1130845.26 20634.48 952565.69 84.2
Work Order 05-15-12
Work Began 06-15-12
Work Completed  
Time Computed 07-15-12
Contract Working Days 105
Addl Days Granted 45
Working Days Charged 130
Percent Time Used 86
Contractor(s)
BIO LANDSCAPE & MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-468
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04123018
Totals 1130845.26 20634.48 952565.69 84.2

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To ALL LOCATIONS ON US 59 & IH 610
CSJ 0912-00-469
Proj ID NH 2012(513)
Work Type LANDSCAPE DEVELOPMENT
 
0.001 778293.17 8518.79 665905.15 85.5
Work Order 06-11-12
Work Began 06-15-12
Work Completed  
Time Computed 06-27-12
Contract Working Days 90
Addl Days Granted 75
Working Days Charged 139
Percent Time Used 84
Contractor(s)
BIO LANDSCAPE & MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-469
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05123222
Totals 778293.17 8518.79 665905.15 85.5

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-484
Proj ID STP 2013(993)
Work Type UPGRADE & MODERNIZE SIGNALS
 
0.001 557849.99 1687.78 592298.35 99.9
Work Order 10-30-13
Work Began 05-12-14
Work Completed  
Time Computed 04-28-14
Contract Working Days 94
Addl Days Granted 0
Working Days Charged 100
Percent Time Used 106
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-484
PROFESSIONAL TRAFFIC CONTROL, LLC(3.36%)
Contract # 08133263
Totals 557849.99 1687.78 592298.35 99.9

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS WITHIN DISTRICT
To .
CSJ 0912-00-489
Proj ID NH 2014(744)
Work Type LANDSCAPE DEVELOPMENT
 
0.001 887550.77 55861.00 55861.00 6.2
Work Order 08-13-14
Work Began 09-22-14
Work Completed  
Time Computed 09-22-14
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 5
Percent Time Used 11
Contractor(s)
BOYER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-489
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143020
Totals 887550.77 55861.00 55861.00 6.2

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-509
Proj ID STP 2015(161)
Work Type REP BR APPROACH SLABS
 
0.001 3708936.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
NORTEX CONCRETE LIFT & STABILIZATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-509
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143233
Totals 3708936.00 0.00 0.00 0.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10