Monthly Local Let Maintenance Report For Houston District As Of Jul 14, 2017 Page 4 Of 10

Last Update: Monday, July 17, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHARRIS
HighwayIH0610
FromUS 59NB CONNECTOR "D" TO IH610 NL WB
ToIH610 WL NB OVER US 59 SW
CSJ6291-94-001
Proj IDRMC - 629194001
Work TypeBRIDGE DECK AND STRUCTURE REPAIR
 
0.001121720.00442408.22100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-26-16
Work Completed02-13-17
Time Computed08-26-16
Contract Working Days45
Addl Days Granted0
Working Days Charged42
Percent Time Used93
Contractor(s)
NBG CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6291-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03161201
Totals121720.000.00442408.22100.0

CountyHARRIS
HighwaySH0249
FromVARIOUS HWYS IN N. HARRIS COUNTY
ToVARIOUS HWYS IN N. HARRIS COUNTY
CSJ6292-15-001
Proj IDSUP - 629215001
Work TypeLITTER REMOVAL
 
0.010272356.44304468.45100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-02-15
Work Began12-07-15
Work Completed12-05-16
Time Computed12-05-15
Contract Working Days366
Addl Days Granted0
Working Days Charged365
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6292-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11151230
Totals272356.440.00304468.45100.0

CountyHARRIS
HighwayIH0010
FromVARIOUS HWYS IN EAST HARRIS COUNTY
ToVARIOUS HWYS IN EAST HARRIS COUNTY
CSJ6292-39-001
Proj IDRMC - 629239001
Work TypeDITCH CLEANING AND RESHAPPING
 
0.001299400.00268566.3089.7
Work Order00-00-00
Work Began12-14-15
Work Completed
Time Computed12-14-15
Contract Working Days731
Addl Days Granted0
Working Days Charged561
Percent Time Used76
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6292-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10151201
Totals299400.002822.50268566.3089.7

CountyBRAZORIA
HighwaySH0035
FromSH35 AT CR875
ToSH35 AT CR875
CSJ6293-48-001
Proj IDRMC - 629348001
Work TypeEMBANKMENT RESTORATION-SLOPE REPAIR
 
0.001360952.00358856.91100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-08-15
Work Began12-21-15
Work Completed07-05-16
Time Computed12-21-15
Contract Working Days28
Addl Days Granted0
Working Days Charged22
Percent Time Used78
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6293-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09151208
Totals360952.000.00358856.91100.0

CountyFORT BEND
HighwayUS0059
FromVARIOUS HWYS IN FORT BEND COUNTY
ToVARIOUS HWYS IN FORT BEND COUNTY
CSJ6293-91-001
Proj IDSUP - 629391001
Work TypeLITTER REMOVAL
 
0.001171397.24143595.98100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-15
Work Completed09-01-16
Time Computed09-01-15
Contract Working Days366
Addl Days Granted0
Working Days Charged366
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
THE TEXAS HOUSE
SUBCONTRACTOR(S) FOR CCSJ: 6293-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08151232
Totals171397.240.00143595.98100.0

CountyWALLER
HighwayUS0290
FromVARIOUS ROADWAYS IN WALLER COUNTY
ToVARIOUS ROADWAYS IN WALLER COUNTY
CSJ6294-28-001
Proj IDRMC - 629428001
Work TypeGUARDRAIL REPAIR
 
0.001288775.00295329.7599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-04-16
Work Began03-01-16
Work Completed
Time Computed02-29-16
Contract Working Days366
Addl Days Granted0
Working Days Charged365
Percent Time Used99
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6294-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11151202
Totals288775.000.00295329.7599.9

CountyBRAZORIA
HighwaySH0288
FromVARIOUS ROADWAYS IN BRAZORIA COUNTY
ToVARIOUS ROADWAYS IN BRAZORIA COUNTY
CSJ6294-36-001
Proj IDSUP - 629436001
Work TypeLITTER REMOVAL
 
0.001193584.63193067.63100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-15
Work Completed08-31-16
Time Computed09-01-15
Contract Working Days366
Addl Days Granted0
Working Days Charged366
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
DAVID & IVORY MINISTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6294-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08151233
Totals193584.630.00193067.63100.0

CountyFORT BEND
HighwayUS0059
FromVARIOUS HWYS IN FORT BEND COUNTY
ToVARIOUS HWYS IN FORT BEND COUNTY
CSJ6295-29-001
Proj IDRMC - 629529001
Work TypeGUARDRAIL REPAIR
 
0.001236430.00252948.95100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-01-16
Work Completed03-01-17
Time Computed03-01-16
Contract Working Days366
Addl Days Granted0
Working Days Charged359
Percent Time Used98
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6295-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12151201
Totals236430.000.00252948.95100.0

CountyGALVESTON
HighwaySH0087
FromGALVESTON FERRY LANDING
ToPORT BOLIVAR FERRY LANDING
CSJ6295-35-001
Proj IDRMC - 629535001
Work TypeLANDSCAPE MAINTENANCE SERVICES
 
0.01046428.0046328.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-27-16
Work Began04-29-16
Work Completed04-28-17
Time Computed04-29-16
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
BEACH TOWN LAWN SERVICE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6295-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03161202
Totals46428.000.0046328.00100.0

CountyHARRIS
HighwayIH0010
FromEAST HARRIS MAINT. GROUNDS
ToEAST HARRIS_MAINT. GROUNDS
CSJ6295-52-001
Proj IDSUP - 629552001
Work TypeLANDSCAPE MAINTENANCE
 
0.00115300.2814274.28100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-01-16
Work Completed02-01-17
Time Computed02-01-16
Contract Working Days366
Addl Days Granted0
Working Days Charged366
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
DAVID & IVORY MINISTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6295-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01161230
Totals15300.280.0014274.28100.0

CountyWALLER
HighwayUS0290
FromVARIOUS HWYS IN WALLER COUNTY
ToVARIOUS HWYS IN WALLER COUNTY
CSJ6295-56-001
Proj IDRMC - 629556001
Work TypePUMP STATION AND DRAINAGE SYSTEM CLEANIN
 
0.001179550.0079604.0044.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-02-16
Work Began02-15-16
Work Completed
Time Computed02-15-16
Contract Working Days366
Addl Days Granted0
Working Days Charged355
Percent Time Used96
Contractor(s)
CLEAN SERVE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6295-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12151202
Totals179550.000.0079604.0044.3

CountyGALVESTON
HighwayFM0517
FromVARIOUS HWYS IN GALVESTON COUNTY
ToVARIOUS HWYS IN GALVESTON COUNTY
CSJ6295-67-001
Proj IDRMC - 629567001
Work TypeDITCH CLEANING & RESHAPING
 
0.001152250.00205872.52100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-02-16
Work Began03-02-16
Work Completed02-09-17
Time Computed02-08-16
Contract Working Days366
Addl Days Granted0
Working Days Charged366
Percent Time Used100
Contractor(s)
RELIANT SAND AND CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6295-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12151203
Totals152250.000.00205872.52100.0

CountyFORT BEND
HighwayUS0059
FromVARIOUS HWYS IN FORT BEND COUNTY
ToVARIOUS HWYS IN FORT BEND COUNTY
CSJ6295-96-001
Proj IDRMC - 629596001
Work TypeCONCRETE SPALL REPAIR
 
0.001108260.00114426.12100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-01-16
Work Completed03-01-17
Time Computed03-01-16
Contract Working Days366
Addl Days Granted0
Working Days Charged365
Percent Time Used99
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6295-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12151204
Totals108260.000.00114426.12100.0

CountyFORT BEND
HighwayUS0059
FromVARIOUS HWYS IN FORT BEND COUNTY
ToVARIOUS HWYS IN FORT BEND COUNTY
CSJ6295-97-001
Proj IDRMC - 629597001
Work TypePUMP STATION AND DRAINAGE SYSM CLEANING
 
0.001190483.00179972.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-01-16
Work Completed03-01-17
Time Computed03-01-16
Contract Working Days366
Addl Days Granted0
Working Days Charged359
Percent Time Used98
Contractor(s)
CLEAN SERVE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6295-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12151205
Totals190483.000.00179972.00100.0

CountyHARRIS
HighwaySH0099
FromVARIOUS HIGHWAYS IN WEST HARRIS CO.
To.
CSJ6295-98-001
Proj IDSUP - 629598001
Work TypeLITTER REMOVAL
 
0.001328430.05463772.62100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-06-15
Work Completed10-06-16
Time Computed10-06-15
Contract Working Days366
Addl Days Granted0
Working Days Charged366
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6295-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09151231
Totals328430.050.00463772.62100.0

CountyHARRIS
HighwaySL0008
FromVARIOUS HWYS IN SOUTH HARRIS COUNTY
ToVARIOUS HWYS IN SOUTH HARRIS COUNTY
CSJ6296-26-001
Proj IDRMC - 629626001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
0.00169900.0065690.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-12-16
Work Completed10-10-16
Time Computed04-11-16
Contract Working Days182
Addl Days Granted0
Working Days Charged182
Percent Time Used100
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6296-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02161201
Totals69900.000.0065690.00100.0

CountyFORT BEND
HighwayUS0059
FromVARIOUS HWYS IN FORT BEND COUNTY
ToVARIOUS HWYS IN FORT BEND COUNTY
CSJ6296-71-001
Proj IDRMC - 629671001
Work TypeREFLECTIVE PAVEMENT MARKINGS (GRAPHICS)
 
0.001209603.00219460.09100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-24-16
Work Completed04-24-17
Time Computed03-24-16
Contract Working Days366
Addl Days Granted30
Working Days Charged396
Percent Time Used100
Contractor(s)
ROADSAFE TRAFFIC SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6296-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01161204
Totals209603.000.00219460.09100.0

CountyGALVESTON
HighwayFM0518
FromVARIOUS HWYS IN GALVESTON COUNTY
ToVARIOUS HWYS IN GALVESTON COUNTY
CSJ6297-07-001
Proj IDRMC - 629707001
Work TypeFULL DEPTH CONCRETE REPAIR
 
0.001133050.00166526.13100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-01-16
Work Began03-10-16
Work Completed09-02-16
Time Computed03-01-16
Contract Working Days366
Addl Days Granted0
Working Days Charged185
Percent Time Used50
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6297-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01161205
Totals133050.000.00166526.13100.0

CountyMONTGOMERY
HighwayIH0069
FromVARIOUS HWYS IN MONTGOMERY COUNTY
ToVARIOUS HWYS IN MONTGOMERY COUNTY
CSJ6297-24-001
Proj IDRMC - 629724001
Work TypePUMP STATION & DRAINAGE SYSTEM CLEANING
 
0.00192360.0084928.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-07-16
Work Began04-07-16
Work Completed04-06-17
Time Computed04-07-16
Contract Working Days365
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
CLEAN SERVE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6297-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02161202
Totals92360.000.0084928.00100.0

CountyMONTGOMERY
HighwayIH0069
FromVARIOUS HWYS IN MONTGOMERY COUNTY
ToVARIOUS HWYS IN MONTGOMERY COUNTY
CSJ6297-47-001
Proj IDRMC - 629747001
Work TypeTREES AND BRUSH REMOVAL
 
0.001130962.00130965.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-26-16
Work Began06-01-16
Work Completed03-31-17
Time Computed06-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged327
Percent Time Used89
Contractor(s)
BOEN LANDSCAPING & IRRIGATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6297-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03161203
Totals130962.000.00130965.00100.0