Monthly Local Let Maintenance Report For Houston District As Of Apr 10, 2015 Page 4 Of 6

Last Update: Friday, April 10, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHARRIS
Highway FM1959
From 702 FM 1959
To 702 FM 1959
CSJ 6270-33-001
Proj ID SUP - 627033001
Work Type LANDSCAPE MAINTENANCE
 
0.001 24285.00 2025.00 19520.00 80.3
Work Order 05-30-14
Work Began 06-01-14
Work Completed  
Time Computed 06-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 298
Percent Time Used 81
Contractor(s)
TIBH INDUSTRIES, INC.
THE TEXAS HOUSE
SUBCONTRACTOR(S) FOR CCSJ: 6270-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141231
Totals 24285.00 2025.00 19520.00 80.3

CountyFORT BEND
Highway US0059
From VARIOUS HWYS IN FORT BEND COUNTY
To VARIOUS HWYS IN FORT BEND COUNTY
CSJ 6270-42-001
Proj ID RMC - 627042001
Work Type REFLECTIVE PAVEMENT MARKINGS (LONG LINE)
 
0.001 229536.00 0.00 178818.83 77.9
Work Order 08-01-14
Work Began 08-01-14
Work Completed  
Time Computed 08-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 238
Percent Time Used 65
Contractor(s)
PROFESSIONAL TRAFFIC CONTROL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6270-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141204
Totals 229536.00 0.00 178818.83 77.9

CountyMONTGOMERY
Highway FM3083
From MONTGOMERY AREA/MAINTENANCE OFFICE
To MONTGOMERY AREA/MAINTENANCE OFFICE
CSJ 6271-23-001
Proj ID SUP - 627123001
Work Type LANDSCAPE MAINTENANCE
 
0.001 17709.98 1390.00 12497.00 70.5
Work Order 06-01-14
Work Began 06-01-14
Work Completed  
Time Computed 06-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 297
Percent Time Used 81
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6271-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141233
Totals 17709.98 1390.00 12497.00 70.5

CountyHARRIS
Highway US0059
From NORTH HARRIS AREA OFFICE
To NORTH HARRIS AREA OFFICE
CSJ 6271-46-001
Proj ID SUP - 627146001
Work Type LANDSCAPE MAINTENANCE
 
0.001 22335.00 1635.00 14725.00 65.9
Work Order 08-01-14
Work Began 08-01-14
Work Completed  
Time Computed 08-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 232
Percent Time Used 63
Contractor(s)
TIBH INDUSTRIES, INC.
THE TEXAS HOUSE
SUBCONTRACTOR(S) FOR CCSJ: 6271-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07141231
Totals 22335.00 1635.00 14725.00 65.9

CountyBRAZORIA
Highway SH0288
From VARIOUS ROADWAYS IN BRAZORIA COUNTY
To VARIOUS ROADWAYS IN BRAZORIA COUNTY
CSJ 6271-61-001
Proj ID RMC - 627161001
Work Type SIGN REPLACEMENT
 
0.001 195739.86 0.00 172542.73 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 10-02-14
Work Completed 03-03-15
Time Computed 10-02-14
Contract Working Days 44
Addl Days Granted 0
Working Days Charged 56
Percent Time Used 127
Contractor(s)
LONESTAR TRAFFIC SAFETY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6271-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07141202
Totals 195739.86 0.00 172542.73 100.0

CountyGALVESTON
Highway SH0087
From GALVESTON-PORT BOLIVAR FERRY OPERATION
To GALVESTON-PORT BOLIVAR FERRY OPERATION
CSJ 6271-92-001
Proj ID SUP - 627192001
Work Type JANITORIAL MAINTENANCE
 
0.010 140840.00 11150.00 78834.00 55.9
Work Order 00-00-00
Work Began 09-01-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 204
Percent Time Used 55
Contractor(s)
TIBH INDUSTRIES, INC.
SOUTHEAST KELLER CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6271-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08141233
Totals 140840.00 11150.00 78834.00 55.9

CountyHARRIS
Highway US0090
From 5OO FT. SOUTH OF NEW ROAD
To CEDAR BAYOU
CSJ 6272-82-001
Proj ID SUP - 627282001
Work Type TREE AND BRUSH REMOVAL (CHANNELS)
 
0.001 50400.00 0.00 16800.00 33.3
Work Order 10-09-14
Work Began 10-10-14
Work Completed  
Time Computed 10-10-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 168
Percent Time Used 46
Contractor(s)
TIBH INDUSTRIES, INC.
D & D HELPING OTHERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6272-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09141230
Totals 50400.00 0.00 16800.00 33.3

CountyFORT BEND
Highway SH0036
From FORT BEND AREA OFFICE
To FORT BEND AREA OFFICE
CSJ 6273-10-001
Proj ID SUP - 627310001
Work Type LANDSCAPE MAINTENANCE
 
0.001 17463.50 1865.00 9417.00 53.9
Work Order 09-01-14
Work Began 09-01-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 207
Percent Time Used 56
Contractor(s)
TIBH INDUSTRIES, INC.
DAVID & IVORY MINISTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6273-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08141232
Totals 17463.50 1865.00 9417.00 53.9

CountyHARRIS
Highway SL0008
From VARIOUS HWYS IN SOUTH HARRIS COUNTY
To VARIOUS HWYS IN SOUTH HARRIS COUNTY
CSJ 6274-00-001
Proj ID RMC - 627400001
Work Type ROADSIDE MOWING
 
0.001 227772.73 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 102
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RELIANT SAND AND CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6274-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03151202
Totals 227772.73 0.00 0.00 0.0

CountyWALLER
Highway US0290
From VARIOUS HWYS IN WALLER COUNTY
To VARIOUS HWYS IN WALLER COUNTY
CSJ 6274-20-001
Proj ID RMC - 627420001
Work Type DITCH CLEANING AND RESHAPING
 
0.001 138050.00 19144.69 55543.75 40.2
Work Order 11-18-14
Work Began 02-12-15
Work Completed  
Time Computed 01-05-15
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 82
Percent Time Used 22
Contractor(s)
RELIANT SAND AND CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6274-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09141201
Totals 138050.00 19144.69 55543.75 40.2

CountyWALLER
Highway IH0010
From VARIOUS HWYS IN WALLER COUNTY
To VARIOUS HWYS IN WALLER COUNTY
CSJ 6274-27-001
Proj ID SUP - 627427001
Work Type LITTER REMOVAL
 
0.001 121334.76 9096.26 79037.50 65.1
Work Order 00-00-00
Work Began 06-02-14
Work Completed  
Time Computed 06-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 298
Percent Time Used 81
Contractor(s)
TIBH INDUSTRIES, INC.
DAVID & IVORY MINISTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6274-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141232
Totals 121334.76 9096.26 79037.50 65.1

CountyFORT BEND
Highway SH0006
From 12015 SH 6 SUGAR LAND
To .
CSJ 6274-70-001
Proj ID SUP - 627470001
Work Type LANDSCAPE MAINTENANCE
 
0.010 9030.00 752.50 6772.50 75.0
Work Order 07-01-14
Work Began 07-01-14
Work Completed  
Time Computed 07-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 273
Percent Time Used 74
Contractor(s)
TIBH INDUSTRIES, INC.
DAVID & IVORY MINISTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6274-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06141230
Totals 9030.00 752.50 6772.50 75.0

CountyWALLER
Highway FM1488
From WALLER MAINTENANCE OFFICE
To WALLER MAINTENANCE OFFICE
CSJ 6274-73-001
Proj ID SUP - 627473001
Work Type LANDSCAPE MAINTENANCE
 
0.001 37840.10 1950.00 12798.00 33.8
Work Order 00-00-00
Work Began 07-01-14
Work Completed  
Time Computed 07-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 270
Percent Time Used 36
Contractor(s)
TIBH INDUSTRIES, INC.
DAVID & IVORY MINISTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6274-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06141231
Totals 37840.10 1950.00 12798.00 33.8

CountyHARRIS
Highway IH0010
From VARIOUS HIGHWAYS IN WEST HARRIS CO.
To .
CSJ 6274-89-001
Proj ID RMC - 627489001
Work Type BRIDGE DECK REPAIR
 
0.001 143500.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6274-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01151201
Totals 143500.00 0.00 0.00 0.0

CountyHARRIS
Highway SH0225
From EAST HARRIS MAINTENANCE OFFICE
To EAST HARRIS MAINTENANCE OFFICE
CSJ 6274-90-001
Proj ID SUP - 627490001
Work Type JANITORIAL MAINTENANCE
 
0.001 16889.08 1229.34 6146.70 36.3
Work Order 00-00-00
Work Began 11-01-14
Work Completed  
Time Computed 11-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 146
Percent Time Used 40
Contractor(s)
TIBH INDUSTRIES, INC.
DAVID & IVORY MINISTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6274-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10141230
Totals 16889.08 1229.34 6146.70 36.3

CountyGALVESTON
Highway 0087
From GALVESTON FERRY LANDING
To PORT BOLIVAR FERRY LANDING
CSJ 6274-91-001
Proj ID RMC - 627491001
Work Type LANDSCAPE MAINTENANCE SERVICES
 
0.010 48000.00 4650.00 12150.00 25.3
Work Order 12-10-14
Work Began 01-02-15
Work Completed  
Time Computed 01-02-15
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 83
Percent Time Used 22
Contractor(s)
BEACH TOWN LAWN SERVICE
SUBCONTRACTOR(S) FOR CCSJ: 6274-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10141201
Totals 48000.00 4650.00 12150.00 25.3

CountyHARRIS
Highway IH0010
From VARIOUS HWYS IN EAST HARRIS COUNTY
To VARIOUS HWYS IN EAST HARRIS COUNTY
CSJ 6275-12-001
Proj ID RMC - 627512001
Work Type REFLECTIVE PAVEMENT MARKINGS (GRAPHICS)
 
0.001 236547.20 4775.24 21081.88 8.9
Work Order 00-00-00
Work Began 01-20-15
Work Completed  
Time Computed 01-20-15
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 66
Percent Time Used 9
Contractor(s)
ROADSAFE TRAFFIC SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6275-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12141201
Totals 236547.20 4775.24 21081.88 8.9

CountyHARRIS
Highway SH0249
From VARIOUS HIGHWAYS IN N. HARRIS COUNTY
To VARIOUS HIGHWAYS IN N. HARRIS COUNTY
CSJ 6275-29-001
Proj ID RMC - 627529001
Work Type GUARDRAIL REPAIR
 
0.001 294025.00 15424.65 19781.40 6.7
Work Order 01-15-15
Work Began 01-30-15
Work Completed  
Time Computed 01-22-15
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 58
Percent Time Used 15
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6275-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10141202
Totals 294025.00 15424.65 19781.40 6.7

CountyGALVESTON
Highway SH0146
From VARIOUS HWYS IN GALVESTON COUNTY
To VARIOUS HWYS IN GALVESTON COUNTY
CSJ 6275-70-001
Proj ID RMC - 627570001
Work Type PUMP STATION & DRAINAGE SYSTEM CLEANING
 
0.001 296950.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-19-15
Work Began 00-00-00
Work Completed  
Time Computed 04-06-15
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CLEAN SERVE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6275-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01151202
Totals 296950.00 0.00 0.00 0.0

CountyHARRIS
Highway US0059
From SAN JACINTO RIVER AT US 59
To SAN JACINTO RIVER_AT US 59
CSJ 6276-17-001
Proj ID RMC - 627617001
Work Type REML & DISPL DRIFTWOOD & DEBRIS
 
0.001 142500.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AFTERMATH DISASTER RECOVERY INC
SUBCONTRACTOR(S) FOR CCSJ: 6276-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02151201
Totals 142500.00 0.00 0.00 0.0