Monthly Local Let Maintenance Report For Houston District As Of Jan 13, 2015 Page 5 Of 6

Last Update: Tuesday, January 13, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHARRIS
Highway FM1959
From 702 FM 1959
To 702 FM 1959
CSJ 6270-33-001
Proj ID SUP - 627033001
Work Type LANDSCAPE MAINTENANCE
 
0.001 24285.00 2025.00 11232.50 46.2
Work Order 05-30-14
Work Began 06-01-14
Work Completed  
Time Computed 06-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 201
Percent Time Used 55
Contractor(s)
TIBH INDUSTRIES, INC.
THE TEXAS HOUSE
SUBCONTRACTOR(S) FOR CCSJ: 6270-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141231
Totals 24285.00 2025.00 11232.50 46.2

CountyFORT BEND
Highway US0059
From VARIOUS HWYS IN FORT BEND COUNTY
To VARIOUS HWYS IN FORT BEND COUNTY
CSJ 6270-42-001
Proj ID RMC - 627042001
Work Type REFLECTIVE PAVEMENT MARKINGS (LONG LINE)
 
0.001 229536.00 0.00 178818.83 77.9
Work Order 08-01-14
Work Began 08-01-14
Work Completed  
Time Computed 08-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 141
Percent Time Used 38
Contractor(s)
PROFESSIONAL TRAFFIC CONTROL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6270-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141204
Totals 229536.00 0.00 178818.83 77.9

CountyFORT BEND
Highway US0059
From VARIOUS HWYS IN FORT BEND COUNTY
To VARIOUS HWYS IN FORT BEND COUNTY
CSJ 6271-15-001
Proj ID RMC - 627115001
Work Type ASPHALT PAVEMENT REPAIR
 
0.001 284928.00 0.00 341616.28 100.0
Work Order 06-23-14
Work Began 06-23-14
Work Completed 12-22-14
Time Computed 06-23-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 182
Percent Time Used 49
Contractor(s)
FORDE CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6271-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141205
Totals 284928.00 0.00 341616.28 100.0

CountyMONTGOMERY
Highway FM3083
From MONTGOMERY AREA/MAINTENANCE OFFICE
To MONTGOMERY AREA/MAINTENANCE OFFICE
CSJ 6271-23-001
Proj ID SUP - 627123001
Work Type LANDSCAPE MAINTENANCE
 
0.001 17709.98 1478.00 9629.00 54.3
Work Order 06-01-14
Work Began 06-01-14
Work Completed  
Time Computed 06-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 203
Percent Time Used 55
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6271-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141233
Totals 17709.98 1478.00 9629.00 54.3

CountyHARRIS
Highway IH0010
From VARIOUS HWYS IN EAST HARRIS COUNTY
To VARIOUS HWYS IN EAST HARRIS COUNTY
CSJ 6271-40-001
Proj ID RMC - 627140001
Work Type SIGN REPLACEMENT
 
0.001 59872.00 3150.00 63816.00 100.0
Work Order 00-00-00
Work Began 09-01-14
Work Completed 10-28-14
Time Computed 09-01-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 57
Percent Time Used 95
Contractor(s)
L&S CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6271-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06141205
Totals 59872.00 3150.00 63816.00 100.0

CountyHARRIS
Highway US0059
From NORTH HARRIS AREA OFFICE
To NORTH HARRIS AREA OFFICE
CSJ 6271-46-001
Proj ID SUP - 627146001
Work Type LANDSCAPE MAINTENANCE
 
0.001 22335.00 1635.00 8635.00 38.6
Work Order 08-01-14
Work Began 08-01-14
Work Completed  
Time Computed 08-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 153
Percent Time Used 41
Contractor(s)
TIBH INDUSTRIES, INC.
THE TEXAS HOUSE
SUBCONTRACTOR(S) FOR CCSJ: 6271-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07141231
Totals 22335.00 1635.00 8635.00 38.6

CountyBRAZORIA
Highway SH0288
From VARIOUS ROADWAYS IN BRAZORIA COUNTY
To VARIOUS ROADWAYS IN BRAZORIA COUNTY
CSJ 6271-61-001
Proj ID RMC - 627161001
Work Type SIGN REPLACEMENT
 
0.001 195739.86 42238.88 172542.73 91.7
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 10-02-14
Contract Working Days 44
Addl Days Granted 0
Working Days Charged 56
Percent Time Used 127
Contractor(s)
LONESTAR TRAFFIC SAFETY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6271-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07141202
Totals 195739.86 42238.88 172542.73 91.7

CountyGALVESTON
Highway SH0087
From GALVESTON-PORT BOLIVAR FERRY OPERATION
To GALVESTON-PORT BOLIVAR FERRY OPERATION
CSJ 6271-92-001
Proj ID SUP - 627192001
Work Type JANITORIAL MAINTENANCE
 
0.010 140840.00 11150.00 44600.00 31.6
Work Order 00-00-00
Work Began 09-01-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 119
Percent Time Used 32
Contractor(s)
TIBH INDUSTRIES, INC.
SOUTHEAST KELLER CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6271-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08141233
Totals 140840.00 11150.00 44600.00 31.6

CountyHARRIS
Highway US0090
From 5OO FT. SOUTH OF NEW ROAD
To CEDAR BAYOU
CSJ 6272-82-001
Proj ID SUP - 627282001
Work Type TREE AND BRUSH REMOVAL (CHANNELS)
 
0.001 50400.00 0.00 16800.00 33.3
Work Order 10-09-14
Work Began 10-10-14
Work Completed  
Time Computed 10-10-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 70
Percent Time Used 19
Contractor(s)
TIBH INDUSTRIES, INC.
D & D HELPING OTHERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6272-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09141230
Totals 50400.00 0.00 16800.00 33.3

CountyFORT BEND
Highway SH0036
From FORT BEND AREA OFFICE
To FORT BEND AREA OFFICE
CSJ 6273-10-001
Proj ID SUP - 627310001
Work Type LANDSCAPE MAINTENANCE
 
0.001 17463.50 1110.00 5207.00 29.8
Work Order 09-01-14
Work Began 09-01-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 113
Percent Time Used 30
Contractor(s)
TIBH INDUSTRIES, INC.
DAVID & IVORY MINISTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6273-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08141232
Totals 17463.50 1110.00 5207.00 29.8

CountyWALLER
Highway US0290
From VARIOUS HWYS IN WALLER COUNTY
To VARIOUS HWYS IN WALLER COUNTY
CSJ 6274-20-001
Proj ID RMC - 627420001
Work Type DITCH CLEANING AND RESHAPING
 
0.001 138050.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-18-14
Work Began 00-00-00
Work Completed  
Time Computed 01-05-15
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RELIANT SAND AND CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6274-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09141201
Totals 138050.00 0.00 0.00 0.0

CountyWALLER
Highway IH0010
From VARIOUS HWYS IN WALLER COUNTY
To VARIOUS HWYS IN WALLER COUNTY
CSJ 6274-27-001
Proj ID SUP - 627427001
Work Type LITTER REMOVAL
 
0.001 121334.76 16924.08 57268.16 47.1
Work Order 00-00-00
Work Began 06-02-14
Work Completed  
Time Computed 06-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 212
Percent Time Used 58
Contractor(s)
TIBH INDUSTRIES, INC.
DAVID & IVORY MINISTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6274-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141232
Totals 121334.76 16924.08 57268.16 47.1

CountyFORT BEND
Highway SH0006
From 12015 SH 6 SUGAR LAND
To .
CSJ 6274-70-001
Proj ID SUP - 627470001
Work Type LANDSCAPE MAINTENANCE
 
0.010 9030.00 752.50 4515.00 50.0
Work Order 07-01-14
Work Began 07-01-14
Work Completed  
Time Computed 07-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 183
Percent Time Used 50
Contractor(s)
TIBH INDUSTRIES, INC.
DAVID & IVORY MINISTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6274-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06141230
Totals 9030.00 752.50 4515.00 50.0

CountyWALLER
Highway FM1488
From WALLER MAINTENANCE OFFICE
To WALLER MAINTENANCE OFFICE
CSJ 6274-73-001
Proj ID SUP - 627473001
Work Type LANDSCAPE MAINTENANCE
 
0.001 37840.10 1299.00 8185.00 21.6
Work Order 00-00-00
Work Began 07-01-14
Work Completed  
Time Computed 07-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 182
Percent Time Used 24
Contractor(s)
TIBH INDUSTRIES, INC.
DAVID & IVORY MINISTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6274-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06141231
Totals 37840.10 1299.00 8185.00 21.6

CountyHARRIS
Highway SH0225
From EAST HARRIS MAINTENANCE OFFICE
To EAST HARRIS MAINTENANCE OFFICE
CSJ 6274-90-001
Proj ID SUP - 627490001
Work Type JANITORIAL MAINTENANCE
 
0.001 16889.08 1229.34 2458.68 14.5
Work Order 00-00-00
Work Began 11-01-14
Work Completed  
Time Computed 11-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 59
Percent Time Used 16
Contractor(s)
TIBH INDUSTRIES, INC.
DAVID & IVORY MINISTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6274-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10141230
Totals 16889.08 1229.34 2458.68 14.5

CountyGALVESTON
Highway 0087
From GALVESTON FERRY LANDING
To PORT BOLIVAR FERRY LANDING
CSJ 6274-91-001
Proj ID RMC - 627491001
Work Type LANDSCAPE MAINTENANCE SERVICES
 
0.010 48000.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-10-14
Work Began 01-02-15
Work Completed  
Time Computed 01-02-15
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BEACH TOWN LAWN SERVICE
SUBCONTRACTOR(S) FOR CCSJ: 6274-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10141201
Totals 48000.00 0.00 0.00 0.0

CountyHARRIS
Highway IH0010
From VARIOUS HWYS IN EAST HARRIS COUNTY
To VARIOUS HWYS IN EAST HARRIS COUNTY
CSJ 6275-12-001
Proj ID RMC - 627512001
Work Type REFLECTIVE PAVEMENT MARKINGS (GRAPHICS)
 
0.001 236547.20 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ROADSAFE TRAFFIC SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6275-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12141201
Totals 236547.20 0.00 0.00 0.0

CountyHARRIS
Highway SH0249
From VARIOUS HIGHWAYS IN N. HARRIS COUNTY
To VARIOUS HIGHWAYS IN N. HARRIS COUNTY
CSJ 6275-29-001
Proj ID RMC - 627529001
Work Type GUARDRAIL REPAIR
 
0.001 294025.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6275-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10141202
Totals 294025.00 0.00 0.00 0.0

CountyMONTGOMERY
Highway US0059
From VARIOUS HWYS IN MONTGOMERY COUNTY
To VARIUOS HWYS IN MONTGOMERY COUNTY
CSJ 6277-41-001
Proj ID SUP - 627741001
Work Type LITTER PICKUP AND DISPOSAL
 
0.001 364324.33 19391.51 131663.73 36.1
Work Order 08-01-14
Work Began 08-01-14
Work Completed  
Time Computed 08-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 143
Percent Time Used 39
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6277-41-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07141230
Totals 364324.33 19391.51 131663.73 36.1

CountyFORT BEND
Highway US0059
From VARIOUS HWYS IN FORT BEND COUNTY
To VARIOUS HWYS IN FORT BEND COUNTY
CSJ 6277-71-001
Proj ID RMC - 627771001
Work Type ASPHALT PAVEMENT REPAIR
 
0.001 274715.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FORDE CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6277-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11141201
Totals 274715.00 0.00 0.00 0.0