Monthly State Let Maintenance Report For Houston District As Of Sep 15, 2014 Page 3 Of 4

Last Update: Monday, September 15, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHARRIS
Highway IH0010
From VARIOUS HIGHWAYS WITHIN THE HOUSTON
To DISTRICT
CSJ 6262-40-001
Proj ID RMC - 626240001
Work Type PAVEMENT MARKINGS AND OVERHEAD SIGNS
 
0.001 663840.82 185232.80 482454.48 72.6
Work Order 04-04-14
Work Began 05-15-14
Work Completed  
Time Computed 04-12-14
Contract Working Days 152
Addl Days Granted 0
Working Days Charged 103
Percent Time Used 67
Contractor(s)
ROADSAFE TRAFFIC SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6262-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02144022
Totals 663840.82 185232.80 482454.48 72.6

CountyHARRIS
Highway IH0610
From VARIOUS HIGHWAYS
To INSIDE LOOP 8
CSJ 6262-50-001
Proj ID RMC - 626250001
Work Type PERFORMANCE BASED TOTAL MAINTENANCE
 
0.001 23084824.00 970718.43 3186983.57 13.8
Work Order 03-03-14
Work Began 00-00-00
Work Completed  
Time Computed 06-01-14
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 92
Percent Time Used 12
Contractor(s)
DBI SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6262-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01144042
Totals 23084824.00 970718.43 3186983.57 13.8

CountyHARRIS
Highway SL0008
From VARIOUS HWYS IN SOUTH HARRIS COUNTY
To VARIOUS HWYS IN SOUTH HARRIS COUNTY
CSJ 6263-16-001
Proj ID RMC - 626316001
Work Type SPALL REPAIR / RAISING & UNDERSEALING JT / C
 
0.001 532350.00 0.00 348793.14 65.5
Work Order 03-19-14
Work Began 04-01-14
Work Completed  
Time Computed 04-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 153
Percent Time Used 41
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6263-16-001
SCR CONSTRUCTION CO., INC. (8.64%)
URETEK USA, INC. ( 18.44%)
Contract # 01144030
Totals 532350.00 0.00 348793.14 65.5

CountyHARRIS
Highway US0290
From VARIOUS HIGHWAYS IN WEST HARRIS CO.
To .
CSJ 6263-35-001
Proj ID RMC - 626335001
Work Type STORM SEWER SYSTEM CLEANING
 
0.001 374525.00 9711.00 114803.75 30.6
Work Order 03-13-14
Work Began 03-19-14
Work Completed  
Time Computed 03-19-14
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 129
Percent Time Used 17
Contractor(s)
CLEANSERVE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6263-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01144036
Totals 374525.00 9711.00 114803.75 30.6

CountyHARRIS
Highway US0290
From VARIOUS HIGHWAYS IN WEST HARRIS CO.
To .
CSJ 6263-36-001
Proj ID RMC - 626336001
Work Type PAVEMENT MARKINGS
 
0.001 822207.00 41514.00 255053.28 31.0
Work Order 04-10-14
Work Began 04-18-14
Work Completed  
Time Computed 04-18-14
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 136
Percent Time Used 18
Contractor(s)
ROADSAFE TRAFFIC SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6263-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02144021
Totals 822207.00 41514.00 255053.28 31.0

CountyHARRIS
Highway IH0610
From VARIOUS HWYS IN HOUSTON DISTRICT
To VARIOUS HWYS IN HOUSTON DISTRICT
CSJ 6264-07-001
Proj ID RMC - 626407001
Work Type LOOP DET REP AND / OR REPLCMNT
 
0.001 1241612.50 142230.80 333541.45 26.8
Work Order 03-12-14
Work Began 03-17-14
Work Completed  
Time Computed 03-17-14
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 168
Percent Time Used 22
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6264-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01144037
Totals 1241612.50 142230.80 333541.45 26.8

CountyMONTGOMERY
Highway US0059
From VARIOUS HWYS IN MONTGOMERY
To VARIOUS HWYS IN MONTGOMERY
CSJ 6264-28-001
Proj ID RMC - 626428001
Work Type ASPHALT PAVEMENT REPAIR
 
0.001 437399.00 0.00 331304.48 75.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-16-14
Work Began 04-16-14
Work Completed  
Time Computed 04-16-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 101
Percent Time Used 27
Contractor(s)
FORDE CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6264-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02144003
Totals 437399.00 0.00 331304.48 75.7

CountyBRAZORIA
Highway SH0288
From VARIOUS HWYS IN BRAZORIA COUNTY
To VARIOUS HWYS IN BRAZORIA COUNTY
CSJ 6264-83-001
Proj ID RMC - 626483001
Work Type SPALL REPAIR
 
0.001 416279.07 263807.07 374545.66 89.9
Work Order 05-23-14
Work Began 06-01-14
Work Completed  
Time Computed 06-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 89
Percent Time Used 24
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6264-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01144020
Totals 416279.07 263807.07 374545.66 89.9

CountyWALLER
Highway US0290
From VARIOUS ROADWAYS IN WALLER COUNTY
To VARIOUS ROADWAYS IN WALLER COUNTY
CSJ 6265-49-001
Proj ID RMC - 626549001
Work Type REFLECTIVE PAVEMENT MARKINGS
 
0.001 358791.73 7500.16 131582.72 36.6
Work Order 05-13-14
Work Began 05-20-14
Work Completed  
Time Computed 05-20-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 104
Percent Time Used 28
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 6265-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02144005
Totals 358791.73 7500.16 131582.72 36.6

CountyFORT BEND
Highway US0059
From VARIOUS HIGHWAYS IN FORT BEND COUNTY
To VARIOUS HIGHWAYS IN FORT BEND COUNTY
CSJ 6265-80-001
Proj ID RMC - 626580001
Work Type CLEANING AND SEALING JOINTS AND CRACKS
 
0.001 190000.00 0.00 235514.50 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-01-14
Work Began 04-01-14
Work Completed  
Time Computed 04-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 91
Percent Time Used 24
Contractor(s)
KUNTZ CONTRACTING CORP.
SUBCONTRACTOR(S) FOR CCSJ: 6265-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01144029
Totals 190000.00 0.00 235514.50 99.9

CountyGALVESTON
Highway FM2094
From CONSTELLATION BLVD
To SOUTH SHORE BLVD
CSJ 6266-04-001
Proj ID RMC - 626604001
Work Type FULL DEPTH REPAIR
 
0.663 786000.78 202554.85 383849.60 48.9
Work Order 04-22-14
Work Began 06-11-14
Work Completed  
Time Computed 06-09-14
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 46
Percent Time Used 102
Contractor(s)
MAIN LANE INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6266-04-001
KOSSMAN CONTRACTING CO., INC.(0.43%)
Contract # 02144004
Totals 786000.78 202554.85 383849.60 48.9

CountyHARRIS
Highway IH0610
From VARIOUS HWYS IN HOUSTON DIST
To VARIOUS HWYS IN HOUSTON DIST
CSJ 6266-11-001
Proj ID RMC - 626611001
Work Type MAINT OF VIVDS
 
0.001 499320.50 11147.25 11147.25 2.2
Work Order 08-06-14
Work Began 08-11-14
Work Completed  
Time Computed 08-11-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 21
Percent Time Used 5
Contractor(s)
SOUTHWEST SIGNAL SUPPLY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6266-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06144006
Totals 499320.50 11147.25 11147.25 2.2

CountyHARRIS
Highway IH0610
From VARIOUS HWYS HARRIS COUNTY
To VARIOUS HWYS HARRIS COUNTY
CSJ 6266-38-001
Proj ID RMC - 626638001
Work Type RETRACE & REPL PAVEMENT MARKINGS
 
1.000 385641.00 385548.24 411878.23 99.9
Work Order 07-14-14
Work Began 07-14-14
Work Completed  
Time Computed 07-14-14
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 46
Percent Time Used 6
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 6266-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03144025
Totals 385641.00 385548.24 411878.23 99.9

CountyHARRIS
Highway SH0225
From VARIOUS HWYS IN EAST HARRIS COUNTY
To VARIOUS HWYS IN EAST HARRIS COUNTY
CSJ 6266-42-001
Proj ID RMC - 626642001
Work Type PUMP STATION & DRAINAGE SYSTEM CLEANING
 
0.001 236000.00 7820.25 18965.75 8.0
Work Order 04-01-14
Work Began 04-01-14
Work Completed  
Time Computed 04-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 149
Percent Time Used 20
Contractor(s)
CLEANSERVE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6266-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02144020
Totals 236000.00 7820.25 18965.75 8.0

CountyFORT BEND
Highway SH0006
From HARRIS COUNTY LINE
To VOSS ROAD
CSJ 6266-67-001
Proj ID RMC - 626667001
Work Type BASE REPAIR, PFC OVERLAY, PAV MARKS
 
3.097 1815127.06 101312.78 1824838.71 99.9
Work Order 05-07-14
Work Began 05-07-14
Work Completed  
Time Computed 05-07-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 45
Percent Time Used 75
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 6266-67-001
THIRD COAST SERVICES LLC (1.40%)
WEST TEXAS RUMBLE STRIP(0.25%)
INTERSTATE BARRICADES & MARKINGS, INC. (0.29%)
BATTERSON,LLP(7.98%)
Contract # 03144024
Totals 1815127.06 101312.78 1824838.71 99.9

CountyHARRIS
Highway US0290
From VARIOUS HIGHWAYS IN WEST HARRIS CO.
To .
CSJ 6267-32-001
Proj ID RMC - 626732001
Work Type SWEEPING
 
0.001 507000.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-02-14
Work Began 09-02-14
Work Completed  
Time Computed 09-02-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6267-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07144206
Totals 507000.00 0.00 0.00 0.0

CountyGALVESTON
Highway SH0003
From VARIOUS HWYS IN GALVESTON COUNTY
To VARIOUS HWYS IN GALVESTON COUNTY
CSJ 6267-41-001
Proj ID RMC - 626741001
Work Type REFLECTIVE PAVEMENT MARKERS (LONG LINE)
 
0.001 431585.00 256009.75 332115.49 76.9
Work Order 06-20-14
Work Began 07-19-14
Work Completed  
Time Computed 07-07-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 40
Percent Time Used 66
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 6267-41-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04144006
Totals 431585.00 256009.75 332115.49 76.9

CountyHARRIS
Highway FM1960
From FM 2100 FROM US90 TO HUFFMAN/CLEVELAND
To FM 1960 FROM LEE ROAD TO LIBERTY C/L
CSJ 6267-42-001
Proj ID RMC - 626742001
Work Type CLEANING AND RESHAPING DITCHES
 
0.001 358400.00 44762.88 44762.88 12.4
Work Order 07-15-14
Work Began 07-24-14
Work Completed  
Time Computed 07-22-14
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 10
Percent Time Used 8
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6267-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05144022
Totals 358400.00 44762.88 44762.88 12.4

CountyHARRIS
Highway SH0146
From AT GOOSE BAY
To .
CSJ 6268-13-001
Proj ID RMC - 626813001
Work Type SLOPE REPAIR
 
0.200 1078927.00 123994.98 123994.98 11.4
Work Order 00-00-00
Work Began 07-16-14
Work Completed  
Time Computed 07-23-14
Contract Working Days 24
Addl Days Granted 0
Working Days Charged 4
Percent Time Used 16
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6268-13-001
MB WESTERN INDUSTRIAL CONTRACTING(8.89%)
Contract # 05144026
Totals 1078927.00 123994.98 123994.98 11.4

CountyHARRIS
Highway IH0610
From VARIOUS HWYS HOUSTON DISTRICT
To VARIOUS HWYS HOUSTON DISTRICT
CSJ 6268-32-001
Proj ID RMC - 626832001
Work Type MNT OF TRAFFIC SGNLS
 
0.001 1554570.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-06-14
Work Began 09-02-14
Work Completed  
Time Computed 09-02-14
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LINDSEY ELECTRIC, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6268-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06144007
Totals 1554570.00 0.00 0.00 0.0