Monthly State Let Maintenance Report For Houston District As Of Dec 10, 2014 Page 4 Of 5

Last Update: Wednesday, December 10, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHARRIS
Highway IH0610
From VARIOUS HWYS HOUSTON DISTRICT
To VARIOUS HWYS HOUSTON DISTRICT
CSJ 6268-32-001
Proj ID RMC - 626832001
Work Type MNT OF TRAFFIC SGNLS
 
0.001 1554570.00 61599.50 171532.00 11.0
Work Order 08-06-14
Work Began 09-02-14
Work Completed  
Time Computed 09-02-14
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 81
Percent Time Used 11
Contractor(s)
LINDSEY ELECTRIC, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6268-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06144007
Totals 1554570.00 61599.50 171532.00 11.0

CountyBRAZORIA
Highway SH0288
From VARIOUS HWYS WITHIN BRAZORIA COUNTY
To VARIOUS HWYS WITHIN BRAZORIA COUNTY
CSJ 6268-52-001
Proj ID RMC - 626852001
Work Type FLEXIBLE PAVEMENT REPAIR
 
0.001 435800.00 0.00 317709.05 72.9
Work Order 05-14-14
Work Began 06-01-14
Work Completed  
Time Computed 06-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 173
Percent Time Used 47
Contractor(s)
MAIN LANE INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6268-52-001
REGIONAL TRAFFIC SERVICES LLC(0.86%)
Contract # 04144005
Totals 435800.00 0.00 317709.05 72.9

CountyGALVESTON
Highway SH0087
From BOLIVAR FERRY LANDING
To BOLIVAR FERRY LANDING
CSJ 6269-70-001
Proj ID RMC - 626970001
Work Type DREDGING
 
0.010 5125000.00 463932.00 1105654.00 21.5
Work Order 08-28-14
Work Began 09-26-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 42
Percent Time Used 35
Contractor(s)
WEEKS MARINE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6269-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06144205
Totals 5125000.00 463932.00 1105654.00 21.5

CountyMONTGOMERY
Highway US0059
From VARIOUS HWYS IN MONTGOMERY COUNTY
To VARIOUS HWYS IN MONTGOMERY COUNTY
CSJ 6269-82-001
Proj ID RMC - 626982001
Work Type CONCRETE STRUCTURE REPAIR
 
0.001 311300.00 2336.00 12353.17 3.9
Work Order 08-11-14
Work Began 08-11-14
Work Completed  
Time Computed 08-11-14
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 103
Percent Time Used 14
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6269-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05144012
Totals 311300.00 2336.00 12353.17 3.9

CountyBRAZORIA
Highway SH0288
From VARIOUS HWYS WITHIN BRAZORIA COUNTY
To VARIOUS HWYS WITHIN BRAZORIA COUNTY
CSJ 6270-23-001
Proj ID RMC - 627023001
Work Type REFL PAV MRKS (LONG LINE)
 
0.001 294371.60 0.00 158792.22 53.9
Work Order 00-00-00
Work Began 07-01-14
Work Completed  
Time Computed 07-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 143
Percent Time Used 39
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 6270-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05144027
Totals 294371.60 0.00 158792.22 53.9

CountyHARRIS
Highway IH0010
From AT SJOLANDER
To .
CSJ 6270-41-001
Proj ID RMC - 627041001
Work Type ACCEL / DECEL LANES WIDENING
 
0.001 779525.24 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MAR-CON SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6270-41-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09144003
Totals 779525.24 0.00 0.00 0.0

CountyHARRIS
Highway SL0008
From VARIOUS HWYS IN SOUTH HARRIS COUNTY
To VARIOUS HWYS IN SOUTH HARRIS COUNTY
CSJ 6271-43-001
Proj ID RMC - 627143001
Work Type CLEANING AND SWEEPING HIGHWAYS
 
0.001 609950.00 29499.00 29499.00 4.8
Work Order 10-14-14
Work Began 11-01-14
Work Completed  
Time Computed 11-01-14
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 30
Percent Time Used 4
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6271-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08144003
Totals 609950.00 29499.00 29499.00 4.8

CountyHARRIS
Highway SH0225
From VARIOUS HWYS IN EAST HARRIS COUNTY
To VARIOUS HWYS IN EAST HARRIS COUNTY
CSJ 6271-49-001
Proj ID RMC - 627149001
Work Type CLEANING AND SWEEPING HIGHWAYS
 
0.001 699600.00 19702.67 96650.61 13.8
Work Order 00-00-00
Work Began 08-01-14
Work Completed  
Time Computed 08-01-14
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 113
Percent Time Used 15
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6271-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06144207
Totals 699600.00 19702.67 96650.61 13.8

CountyHARRIS
Highway BU0290H
From WALLER C/L
To WEST OF BADTKE ROAD
CSJ 6271-71-001
Proj ID RMC - 627171001
Work Type PLN, SL CT, THIN O - L MIX (TOM) , PV MRK
 
5.635 1675064.21 0.00 1956145.46 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-07-14
Work Began 07-08-14
Work Completed  
Time Computed 07-07-14
Contract Working Days 45
Addl Days Granted 7
Working Days Charged 50
Percent Time Used 96
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 6271-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05144024
Totals 1675064.21 0.00 1956145.46 99.9

CountyGALVESTON
Highway SH0275
From 1.238 MI WEST OF 51ST ST.
To 0.2 MI WEST OF 51ST ST.
CSJ 6271-72-001
Proj ID RMC - 627172001
Work Type ACP OVERLAY
 
2.423 844959.99 0.00 1183839.00 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-25-14
Work Began 07-23-14
Work Completed 11-03-14
Time Computed 07-09-14
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 30
Percent Time Used 100
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 6271-72-001
BATTERSON,LLP(7.12%)
Contract # 05144025
Totals 844959.99 0.00 1183839.00 100.0

CountyHARRIS
Highway SH0225
From VARIOUS HWYS IN EAST HARRIS COUNTY
To VARIOUS HWYS IN EAST HARRIS COUNTY
CSJ 6271-91-001
Proj ID RMC - 627191001
Work Type FULL DEPTH CONCRETE REPAIR
 
0.001 1133300.00 0.00 300545.57 26.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 08-21-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 93
Percent Time Used 12
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6271-91-001
SCR CONSTRUCTION CO., INC. ( 29.55%)
Contract # 06144206
Totals 1133300.00 0.00 300545.57 26.5

CountyHARRIS
Highway US0290
From VARIOUS HIGHWAYS IN WEST HARRIS CO.
To .
CSJ 6271-97-001
Proj ID RMC - 627197001
Work Type FULL DEPTH CONCRETE REPAIR & MISC CONC
 
0.001 864550.00 0.00 0.00 0.0
Work Order 09-25-14
Work Began 10-01-14
Work Completed  
Time Computed 10-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 52
Percent Time Used 14
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6271-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07144014
Totals 864550.00 0.00 0.00 0.0

CountyHARRIS
Highway US0290
From VARIOUS HIGHWAYS IN WEST HARRIS CO.
To .
CSJ 6272-65-001
Proj ID RMC - 627265001
Work Type CRACK & SPALL REPAIR
 
0.001 474200.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-19-14
Work Began 00-00-00
Work Completed  
Time Computed 11-23-14
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6272-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07144205
Totals 474200.00 0.00 0.00 0.0

CountyHARRIS
Highway US0059
From VARIOUS HWYS IN NORTH HARRIS COUNTY
To VARIOUS HWYS IN NORTH HARRIS COUNTY
CSJ 6272-77-001
Proj ID RMC - 627277001
Work Type CLEANING AND SWEEPING HIGHWAYS
 
0.001 447413.00 27950.00 42200.00 9.4
Work Order 10-13-14
Work Began 10-20-14
Work Completed  
Time Computed 10-20-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 33
Percent Time Used 9
Contractor(s)
DEANGELO BROTHERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6272-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08144201
Totals 447413.00 27950.00 42200.00 9.4

CountyFORT BEND
Highway SH0006
From 500' SOUTH OF VOSS ROAD
To 0.56 MILE NORTH OF US 90A
CSJ 6272-84-001
Proj ID RMC - 627284001
Work Type BASE REPAIR, PFC OVERLAY AND PAV MRKS
 
1.477 878488.96 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 6272-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10144203
Totals 878488.96 0.00 0.00 0.0

CountyHARRIS
Highway SH0249
From VARIOUS HIGHWAYS IN NORTH HARRIS COUNTY
To VARIOUS HIGHWAYS IN NORTH HARRIS COUNTY
CSJ 6272-85-001
Proj ID RMC - 627285001
Work Type FULL DEPTH CONCRETE & ASPHALT REPAIR
 
0.001 781855.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MAIN LANE INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6272-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10144204
Totals 781855.00 0.00 0.00 0.0

CountyFORT BEND
Highway US0059
From VARIOUS HWYS IN FORT BEND COUNTY
To VARIOUS HWYS IN FORT BEND COUNTY
CSJ 6273-27-001
Proj ID RMC - 627327001
Work Type CLEANING AND SWEEPING HIGHWAYS
 
0.001 679268.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-23-14
Work Began 11-01-14
Work Completed  
Time Computed 11-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6273-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09144202
Totals 679268.00 0.00 0.00 0.0

CountyWALLER
Highway US0290
From VARIOUS HWYS IN WALLER COUNTY
To VARIOUS HWYS IN WALLER COUNTY
CSJ 6273-98-001
Proj ID RMC - 627398001
Work Type ASPHALT PAVEMENT REPAIR
 
0.001 513125.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-03-14
Work Began 11-03-14
Work Completed  
Time Computed 11-03-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MAIN LANE INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6273-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09144002
Totals 513125.00 0.00 0.00 0.0

CountyWALLER
Highway US0290
From VARIOUS HIGHWAYS IN WALLER COUNTY
To VARIOUS HIGHWAYS IN WALLER COUNTY
CSJ 6274-48-001
Proj ID RMC - 627448001
Work Type CLEANING AND SWEEPING HIGHWAYS
 
0.001 484750.00 6000.00 6000.00 1.2
Work Order 11-05-14
Work Began 11-10-14
Work Completed  
Time Computed 11-10-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 15
Percent Time Used 4
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6274-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09144203
Totals 484750.00 6000.00 6000.00 1.2

CountyHARRIS
Highway IH0010
From VARIOUS HWYS IN EAST HARRIS COUNTY
To VARIOUS HWYS IN EAST HARRIS COUNTY
CSJ 6278-04-001
Proj ID RMC - 627804001
Work Type CLEANING AND SWEEPING HIGHWAYS
 
0.001 790000.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6278-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12144005
Totals 790000.00 0.00 0.00 0.0