AVERAGE LOW BID UNIT PRICE - CONSTRUCTION - LUBBOCK DISTRICT

Last Update: Friday, March 27, 2015
ITEMS 100 2002 TO 168 2001
Items Items Bid Code Range
0100 - 0168
0216 - 0275
0310 - 0368
0400 - 0496
0500 - 0560
0610 - 0690
0730 - 0760
1122 - 1122
3267 - 3288
5367 - 5926
6001 - 6834
8251 - 8999
100 2002 - 168 2001
Item No Description Units March 31, 2015 Twelve Month Moving Usage
Quantity Avg Bid Quantity Avg Bid
100 2002 PREPARING ROW STA     132.000 11,950.00000 2
100 2017 PREP ROW (TREE) (GREATER THAN 8 IN DIA) EA     1.000 2,000.00000 1
100 6004 PREPARING ROW (TREE) (12" TO 24" DIA) EA     2.000 2,500.00000 1
100 6011 PREPARING ROW (TREE) (24" TO 36" DIA.) EA     7.000 5,000.00000 1
104 2009 REMOVING CONC (RIPRAP) SY     1,968.000 8.02236 2
104 2011 REMOVING CONC (MEDIANS) SY     170.770 36.66276 2
104 2017 REMOVING CONC (DRIVEWAYS) SY     1,543.000 21.94922 3
104 2022 REMOVING CONC (CURB AND GUTTER) LF     3,713.800 7.57724 3
104 2023 REMOVING CONC (CTB) LF     1,712.000 11.00000 1
104 2026 REMOVE CONC (GUTTER) LF     20.000 15.20000 1
104 2027 REMOVING CONC (APPR SLAB) SY     597.040 90.00000 1
104 2028 REMOVING CONC (MISC) SY     749.000 11.00000 1
104 2029 REMOVING CONC (CURB OR CURB & GUTTER) LF     516.000 4.70000 1
104 2032 REMOVING CONC (WHEELCHAIR RAMP) SY     45.000 65.00000 1
104 2034 REMOVING CONC (COPING) LF     750.000 9.95000 1
104 2039 REMOVE CONC (ABUTMENT BACKWALL) CY     4.250 1,400.00000 1
104 2044 REMOVING CONC (FLUME) SY     207.000 15.40000 1
104 2049 REMOVE CONCRETE (MSE PANELS) SF     2,686.000 3.89000 1
104 6028 REMOVING CONC (MISC) SY 34.800 86.81609 34.800 86.81609 2
105 2046 REMOVING STAB BASE & ASPH PAV (0" - 10") SY     16,970.000 3.20000 1
110 2001 EXCAVATION (ROADWAY) CY     148,962.200 6.08149 4
110 6001 EXCAVATION (ROADWAY) CY 828.000 30.00000 828.000 30.00000 1
112 2002 SUBGRADE WIDENING (DENS CONT) STA     6.000 945.00000 1
112 6001 SUBGRADE WIDENING (ORD COMP) STA 476.490 1,500.00000 476.490 1,500.00000 1
112 6002 SUBGRADE WIDENING (DENS CONT) STA 303.300 1,070.22750 2,668.800 846.03675 4
132 2004 EMBANKMENT (FINAL) (DENS CONT) (TY B) CY     190.000 40.40000 1
132 2006 EMBANKMENT (FINAL) (DENS CONT) (TY C) CY     81,883.000 43.98365 2
132 2008 EMBANKMENT (FINAL) (DENS CONT) (TY D) CY     148,957.000 3.50000 1
132 6004 EMBANKMENT (FINAL) (DENS CONT) (TY B) CY 3,142.000 30.00000 3,142.000 30.00000 1
132 6006 EMBANKMENT (FINAL) (DENS CONT) (TY C) CY 750.000 27.16667 750.000 27.16667 2
134 2002 BACKFILL (TY B) STA     789.000 115.73511 2
134 6002 BACKFILL (TY B) STA 782.890 297.14328 3,148.390 197.09375 5
150 2001 BLADING STA     789.000 114.18885 2
150 6001 BLADING STA 303.300 98.17409 303.300 98.17409 2
161 2014 COMPOST MANUF TOPSOIL (BOS OR PB) (4") SY     139,793.000 1.80000 1
161 2026 COMPOST MANUF TOPSOIL (BOS OR PB) (6") SY     1,351.000 14.65000 1
162 2002 BLOCK SODDING SY     9,177.000 5.01022 2
164 2025 CELL FBR MLCH SEED (PERM) (URBAN) (SANDY) SY     141,144.000 .36675 2
164 2033 DRILL SEEDING (PERM) (RURAL) (SANDY) SY     32,066.000 .25000 1
164 2034 DRILL SEEDING (PERM) (RURAL) (SANDY) AC     131.000 325.00000 1
164 2038 DRILL SEEDING (PERM) (URBAN) (SANDY) AC     29.000 700.00000 1
164 2053 DRILL SEEDING (TEMP) (WARM OR COOL) AC     29.000 700.00000 1
168 2001 VEGETATIVE WATERING MG     2,370.000 15.17932 2