Monthly State Let Construction Report For Lubbock District As Of Sep 15, 2016 Page 2 Of 2

Last Update: Thursday, September 15, 2016
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyLUBBOCK
Highway VA
From VARIOUS LOCATIONS IN
To ALONG IH 27
CSJ 0905-00-083
Proj ID STP 2015(229)
Work Type PUMP STATION REPAIR
 
0.001 2141840.00 136719.84 1926838.35 89.9
Work Order 07-16-15
Work Began 10-09-15
Work Completed  
Time Computed 08-16-15
Contract Working Days 190
Addl Days Granted 0
Working Days Charged 184
Percent Time Used 96
Contractor(s)
AUSTIN ENGINEERING CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0905-00-083
RUCOBA & MAYA CONSTRUCTION (1.46%)
DAKOTA UTILITY CONTRACTORS, INC. (0.49%)
BARRICADES UNLIMITED (1.33%)
T&T ELECTRIC, INC. ( 57.39%)
Contract # 06153263
Totals 2141840.00 136719.84 1926838.35 89.9

CountyLUBBOCK
Highway CS
From N UNIVERSITY, FROM US 84
To AMHERST STREET
CSJ 0905-06-089
Proj ID STP 1502(581)TP
Work Type DEC SDWLK, ACCESS RAMPS, ILLUM
 
0.364 874627.03 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 85
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ALLEN BUTLER CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0905-06-089
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08163232
Totals 874627.03 0.00 0.00 0.0

CountyLUBBOCK
Highway CS
From NORTH UNIVERSITY, FROM AMHERST ST.
To US 82 IN LUBBOCK
CSJ 0905-06-090
Proj ID STP 2014(148)TE
Work Type SIDEWALKS, C & G, RAMPS AND LIGHTING
 
0.437 940883.20 0.00 525146.43 55.8
Work Order 01-29-16
Work Began 02-29-16
Work Completed  
Time Computed 02-29-16
Contract Working Days 82
Addl Days Granted 0
Working Days Charged 81
Percent Time Used 98
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0905-06-090
SPEEDY PAVING(6.60%)
ARTEX ELECTRIC, INC. ( 31.19%)
Contract # 08153224
Totals 940883.20 0.00 525146.43 55.8

CountyLUBBOCK
Highway FM 400
From 0.25 MILES NORTH OF NFDMF BRAZOS
To 0.25 MILES SOUTH OF NFDMF BRAZOS
CSJ 1041-02-039
Proj ID BR 1502(582)
Work Type REMOVE AND REPLACE BRIDGE
 
0.500 2349749.85 386724.39 2011522.48 85.6
Work Order 11-24-15
Work Began 06-01-16
Work Completed  
Time Computed 06-01-16
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 88
Percent Time Used 97
Contractor(s)
KIEWIT INFRASTRUCTURE SOUTH CO.
SUBCONTRACTOR(S) FOR CCSJ: 1041-02-039
BARRICADES UNLIMITED (0.23%)
V-TECH ENVIRONMENTAL SERVICES(0.66%)
W. W. FOUNDATION DRILLING, LTD.(7.11%)
COMEN ENTERPRISE (1.28%)
MCL CONTRACTING, LLC (0.34%)
LONE STAR HIGHWAY PRODUCTS, INC. (2.93%)
S & S BRIDGE PAINTING, INC.(0.21%)
WOLFE CONSTRUCTION GROUP, INC. (0.36%)
TRUMBLE CRANE & RIGGING(1.27%)
PORTER INTERNATIONAL CONSTRUCTION LLC(0.67%)
MCL CONTRACTING, LLC (0.38%)
LONE STAR DIRT & PAVING, LTD.(2.33%)
PENHALL COMPANY(0.16%)
TEXOP CONSTRUCTION (0.74%)
ALLEN BUTLER CONSTRUCTION, INC.(0.78%)
KLP COMMERCIAL, LLC(0.71%)
Contract # 08153042
Totals 2349749.85 386724.39 2011522.48 85.6

CountyLUBBOCK
Highway FM 1730
From 200 FEET NORTH OF 98TH ST.
To 1000 FEET SOUTH OF FM 1585
CSJ 1344-02-019
Proj ID STP 2014(479)MM
Work Type GRAD, BASE, ACP, STR, SET, C & G
 
2.246 14189419.37 242580.87 12355328.84 86.8
Work Order 05-14-14
Work Began 06-02-14
Work Completed  
Time Computed 07-10-14
Contract Working Days 340
Addl Days Granted 167
Working Days Charged 505
Percent Time Used 99
Contractor(s)
ALLEN BUTLER CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1344-02-019
ARTEX ELECTRIC CO. (1.06%)
BARRICADES UNLIMITED (1.39%)
CMT ENGINEERING, INC.(0.40%)
TEX OP CONSTRUCTION, LP(0.54%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.99%)
FLOYD TRUCKING, INC. (5.10%)
V-TECH ENVIRONMENTAL SERVICES(0.48%)
VANN/ELLI, INC.(0.78%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.16%)
DOUBLE R LAWN AND LANDSCAPE(0.02%)
UTILITY CONTRACTORS OF AMERICA, LTD(6.67%)
ROYAL CONCRETE (0.47%)
CEMTECH CONCRETE (0.49%)
STATEWIDE TRANSPORT, LLC (0.68%)
DTM TRUCKING, INC. (0.73%)
Contract # 03143002
Totals 14189419.37 242580.87 12355328.84 86.8

page 1 | page 2