Monthly State Let Construction Report For Lubbock District As Of Jan 13, 2015 Page 2 Of 2

Last Update: Tuesday, January 13, 2015
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyLUBBOCK
Highway LP 289
From 990 FEET EAST OF SLIDE ROAD
To 2585 FEET EAST OF QUAKER AVENUE
CSJ 0783-02-084
Proj ID C 783-2-84
Work Type GR, BASE, STR, ASB, ACP, OVERPASS
 
1.620 26923572.74 1891998.41 22224368.60 82.5
Work Order 09-24-12
Work Began 11-12-12
Work Completed  
Time Computed 11-12-12
Contract Working Days 581
Addl Days Granted 0
Working Days Charged 534
Percent Time Used 91
Contractor(s)
HAYDON BUILDING CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0783-02-084
RICE ENVIRONMENTAL SERVICES(1.84%)
TOM"S TREE PLACE (1.09%)
WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED(0.31%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.14%)
DRILL PIER CONSTRUCTION, LLC (0.00%)
ARTEX ELECTRIC, INC. (0.01%)
MICA CORPORATION (0.95%)
A & A CONSTRUCTION (0.36%)
BUILDER SERVICES CO. (0.24%)
TEX OP CONSTRUCTION, LP(0.59%)
WEST TEXAS PAVING, INC.( 15.59%)
CMT ENGINEERING, INC.(0.07%)
FARR FOUNDATION, INC.(0.53%)
W. W. FOUNDATION DRILLING, LTD.(1.34%)
TRUMBLE CRANE & RIGGING(0.32%)
NORTH TEXAS REBAR, LLC (3.61%)
WILLIS ELECTRIC CO., LP(5.48%)
FLOYD TRUCKING, INC. (0.00%)
W.O.E. CONSTRUCTION(0.08%)
BRUNDAGE-BONE(0.00%)
SOUTHEAST GRINDING & GROOVING, LLC (0.05%)
COLTON GRADING & EXCAVATION(0.00%)
BILL AYRES LAWN & TREE SERVICE (0.01%)
DUSTIN ALLEN, INC. (0.45%)
COMBS CONSTRUCTION COMPANY, INC. (1.35%)
ROAD REPAIR, LLC (0.13%)
TEXAS FAR WEST CONSTRUCTION & ENGINEERING(0.18%)
AUI CONTRACTORS, LLC (0.01%)
S & S BRIDGE PAINTING, INC.(0.12%)
WEST INFRASTRUCTURE CONSTRUCTION, LLC(0.13%)
Contract # 07123204
Totals 26923572.74 1891998.41 22224368.60 82.5

CountyCROSBY
Highway FM 378
From W FM 40
To SOUTH END OF STATE MAINTENANCE
CSJ 0800-04-009
Proj ID C 800-4-9
Work Type WIDEN, GRADING, BASE, SURFACE, TREAT
 
5.193 2664168.23 26500.00 2494090.55 100.0
Work Order 11-20-13
Work Began 03-24-14
Work Completed 10-31-14
Time Computed 04-01-14
Contract Working Days 124
Addl Days Granted 0
Working Days Charged 121
Percent Time Used 97
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0800-04-009
E. DIAZ TRUCKING (0.00%)
BARRICADES UNLIMITED (0.99%)
Contract # 10133217
Totals 2664168.23 26500.00 2494090.55 100.0

CountyLUBBOCK
Highway VA
From VARIOUS LOCATIONS IN
To THE LUBBOCK DISTRICT
CSJ 0905-00-065
Proj ID STP 2014(396)
Work Type FY 2014 PAVEMENT MARKERS
 
0.001 1723815.96 4392.00 1729907.65 99.9
Work Order 04-11-14
Work Began 05-13-14
Work Completed  
Time Computed 05-05-14
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 100
Percent Time Used 100
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0905-00-065
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02143025
Totals 1723815.96 4392.00 1729907.65 99.9

CountyLUBBOCK
Highway VA
From VARIOUS LOCATIONS IN
To THE LUBBOCK DISTRICT
CSJ 0905-00-070
Proj ID STP 2013(154)
Work Type FY 2013 ADA COMPLIANCE
 
0.001 1488393.00 0.00 1618525.68 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-17-13
Work Began 03-11-13
Work Completed 08-06-14
Time Computed 02-02-13
Contract Working Days 188
Addl Days Granted 9
Working Days Charged 164
Percent Time Used 83
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0905-00-070
ONE WAY CONCRETE ( 41.09%)
WEST TEXAS BARRICADES, LLC DBA BARRICADES UNLIMITED(0.63%)
HIGHWAY TECHNOLOGIES, INC. (0.97%)
FAASS TRUCKING, INC. (1.46%)
Contract # 11123015
Totals 1488393.00 0.00 1618525.68 100.0

CountyLUBBOCK
Highway VA
From VARIOUS LOCATIONS IN
To THE LUBBOCK DISTRICT
CSJ 0905-00-071
Proj ID STP 2014(397)
Work Type RRPMS AND SPECIALITY MARKINGS
 
0.001 778423.00 0.00 769620.00 100.0
Work Order 03-13-14
Work Began 05-27-14
Work Completed 09-02-14
Time Computed 05-05-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 67
Percent Time Used 111
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0905-00-071
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02143215
Totals 778423.00 0.00 769620.00 100.0

CountyLUBBOCK
Highway VA
From VARIOUS LOCATIONS IN
To THE LUBBOCK DISTRICT
CSJ 0905-00-077
Proj ID STP 2013(877)
Work Type MISCELLANOUS CONSTRUCTION
 
0.001 239588.36 0.00 253646.34 100.0
Work Order 07-24-13
Work Began 11-05-13
Work Completed 08-19-14
Time Computed 08-09-13
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 73
Percent Time Used 81
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0905-00-077
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06133214
Totals 239588.36 0.00 253646.34 100.0

CountyLUBBOCK
Highway VA
From US84, BNSF OVERPASS
To IN POST, TEXAS
CSJ 0905-00-085
Proj ID STP 2014(776)
Work Type PAVEMENT REPAIR
 
0.001 1205066.00 60561.23 640115.47 53.1
Work Order 08-13-14
Work Began 09-16-14
Work Completed  
Time Computed 09-02-14
Contract Working Days 68
Addl Days Granted 0
Working Days Charged 52
Percent Time Used 76
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0905-00-085
BARRICADES UNLIMITED (9.26%)
ODUM SERVICES, L.P.(3.93%)
V-TECH ENVIRONMENTAL SERVICES(1.21%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.68%)
WEST INFRASTRUCTURE CONSTRUCTION, LLC( 18.52%)
TEX OP CONSTRUCTION, LP(0.45%)
Contract # 06143222
Totals 1205066.00 60561.23 640115.47 53.1

CountyLUBBOCK
Highway VA
From VARIOUS LOCATIONS IN
To THE LUBBOCK DISTRICT
CSJ 0905-00-087
Proj ID STP 2014(777)
Work Type MISCELLANOUS CONSTRUCTION
 
0.001 133232.60 0.00 128979.40 100.0
Work Order 05-22-14
Work Began 06-16-14
Work Completed 09-02-14
Time Computed 07-22-14
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 32
Percent Time Used 71
Contractor(s)
ADVANCED TRANSOL CONSULTANTS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0905-00-087
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04143033
Totals 133232.60 0.00 128979.40 100.0

CountyLUBBOCK
Highway VA
From VARIOUS LOCATIONS IN
To THE LUBBOCK DISTRICT
CSJ 0905-06-093
Proj ID NH 2015(474)
Work Type DYNAMIC MESSAGE SIGNS
 
0.002 1419480.83 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0905-06-093
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01153017
Totals 1419480.83 0.00 0.00 0.0

CountyHALE
Highway VA
From LUBBOCK COUNTY LINE
To SWISHER COUNTY LINE
CSJ 0905-12-041
Proj ID NH 2015(399)
Work Type REMOVAL & INSTALL OF LG GUIDE SIGNS
 
37.717 246777.34 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-07-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DFB CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0905-12-041
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12143215
Totals 246777.34 0.00 0.00 0.0

CountyHALE
Highway CS
From US 70
To 13TH STREET
CSJ 0905-12-042
Proj ID C 905-12-42
Work Type PLANE, ACP, SURFACE COURSE
 
0.335 864043.60 0.00 8039.60 0.9
Work Order 09-30-14
Work Began 00-00-00
Work Completed  
Time Computed 10-16-14
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0905-12-042
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143052
Totals 864043.60 0.00 8039.60 0.9

CountyLUBBOCK
Highway FM 1730
From 200 FEET NORTH OF 98TH ST.
To 1000 FEET SOUTH OF FM 1585
CSJ 1344-02-019
Proj ID STP 2014(479)MM
Work Type GRAD, BASE, ACP, STR, SET, C & G
 
2.246 14189419.37 339767.90 3198939.24 22.5
Work Order 05-14-14
Work Began 06-02-14
Work Completed  
Time Computed 07-10-14
Contract Working Days 340
Addl Days Granted 20
Working Days Charged 122
Percent Time Used 33
Contractor(s)
ALLEN BUTLER CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1344-02-019
ARTEX ELECTRIC CO. (1.06%)
BARRICADES UNLIMITED (1.39%)
CMT ENGINEERING, INC.(0.40%)
TEX OP CONSTRUCTION, LP(0.54%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.99%)
FLOYD TRUCKING, INC. (5.10%)
V-TECH ENVIRONMENTAL SERVICES(0.48%)
VANN/ELLI, INC.(0.78%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.16%)
DOUBLE R LAWN AND LANDSCAPE(0.02%)
UTILITY CONTRACTORS OF AMERICA, LTD(6.67%)
Contract # 03143002
Totals 14189419.37 339767.90 3198939.24 22.5

CountyHOCKLEY
Highway FM 1585
From FM 303
To US 385
CSJ 2182-02-008
Proj ID STP 2014(263)
Work Type MILL, STABILIZE, 2 COURSE SURF TREAT
 
6.529 3762234.84 0.00 2382391.72 63.3
Work Order 01-17-14
Work Began 04-07-14
Work Completed  
Time Computed 06-30-14
Contract Working Days 149
Addl Days Granted 0
Working Days Charged 88
Percent Time Used 59
Contractor(s)
ALLEN BUTLER CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2182-02-008
BARRICADES UNLIMITED (2.28%)
FLOYD TRUCKING, INC. (9.18%)
HJC FARMS, INC.(0.24%)
V-TECH ENVIRONMENTAL SERVICES(0.81%)
ROAD TRAC, INC.(0.03%)
Contract # 10133025
Totals 3762234.84 0.00 2382391.72 63.3

CountyCASTRO
Highway FM 145
From FM 1055
To US 385
CSJ 2419-01-010
Proj ID STP 2014(009)
Work Type WIDEN, SALVAGE BASE, BASE, 2 CST
 
6.100 1987950.29 0.00 1842914.16 94.2
Work Order 10-10-13
Work Began 04-08-14
Work Completed  
Time Computed 12-09-13
Contract Working Days 89
Addl Days Granted 0
Working Days Charged 129
Percent Time Used 144
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2419-01-010
BARRICADES UNLIMITED (3.26%)
Contract # 09133214
Totals 1987950.29 0.00 1842914.16 94.2

CountyPARMER
Highway FM 1172
From FM 2397
To SH 86
CSJ 2444-01-009
Proj ID STP 2013(092)
Work Type BASE, CEMENT STAB, TWO CRSE
 
6.729 3262223.62 4327.41 3002550.39 92.0
Work Order 01-17-14
Work Began 02-17-14
Work Completed  
Time Computed 04-01-14
Contract Working Days 139
Addl Days Granted 0
Working Days Charged 138
Percent Time Used 99
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2444-01-009
E. DIAZ TRUCKING (3.86%)
TEXAS ALTERNATIVE GRASSER, INC.(0.73%)
DOUBLE A CONTRACTING, L.P. (1.54%)
Contract # 10133019
Totals 3262223.62 4327.41 3002550.39 92.0

page 1 | page 2