Monthly State Let Construction Report For Lubbock District As Of Apr 11, 2016 Page 2 Of 2

Last Update: Monday, April 11, 2016
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyLAMB
Highway FM 54
From US 84
To SUNSET AVE IN LITTLEFIELD
CSJ 0563-03-014
Proj ID STP 2015(767)HES
Work Type PLANE, CEM TRT, SURF TRT, HOT MIX
 
0.524 785899.15 0.00 0.00 0.0
Work Order 04-10-15
Work Began 00-00-00
Work Completed  
Time Computed 05-11-15
Contract Working Days 38
Addl Days Granted 0
Working Days Charged 27
Percent Time Used 71
Contractor(s)
DUININCK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0563-03-014
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03153025
Totals 785899.15 0.00 0.00 0.0

CountyDAWSON
Highway FM 26
From US 87
To FM 828
CSJ 0637-01-011
Proj ID STP 2015(768)
Work Type SUBGRADE WIDENING BASE SC PAVE MRKS
 
5.273 2978473.01 0.00 2635184.91 88.4
CountyDAWSON
Highway FM 26
From FM 828
To MARTIN CO LINE
CSJ 1749-01-007
Proj ID C 1749-1-7
Work Type SUBGRADEWIDE BASE SURF TREAT & PVEMRK
 
4.146 2551788.51 0.00 2370354.32 92.8
Work Order 06-01-15
Work Began 07-06-15
Work Completed  
Time Computed 07-02-15
Contract Working Days 124
Addl Days Granted 0
Working Days Charged 124
Percent Time Used 100
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0637-01-011
E. DIAZ TRUCKING (1.16%)
BARRICADES UNLIMITED (1.29%)
BLACK JACK ENERGY SERVICES ( 49.56%)
W.S. CONSTRUCTION COMPANY(1.84%)
Contract # 03153031
Totals 5530261.52 0.00 5005539.23 90.5

CountyLUBBOCK
Highway SL 289
From 1000 FEET NORTH OF US 84
To 1000 FEET SOUTH OF US 84
CSJ 0783-01-100
Proj ID NH 2016(886)
Work Type BRIDGE REPAIR
 
0.378 199534.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-08-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 14
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0783-01-100
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03163029
Totals 199534.00 0.00 0.00 0.0

CountyHOCKLEY
Highway FM 597
From FM 168
To LUBBOCK COUNTY LINE
CSJ 0874-07-006
Proj ID STP 2015(766)
Work Type MILL, STABILIZE, 2 COURSE SURF TREAT
 
5.302 3845414.81 100000.00 393735.00 10.2
Work Order 05-08-15
Work Began 07-06-15
Work Completed  
Time Computed 06-08-15
Contract Working Days 139
Addl Days Granted 0
Working Days Charged 53
Percent Time Used 38
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0874-07-006
BARRICADES UNLIMITED (1.29%)
E. DIAZ TRUCKING (6.00%)
Contract # 03153228
Totals 3845414.81 100000.00 393735.00 10.2

CountyLUBBOCK
Highway VA
From VARIOUS LOCATIONS IN
To THE LUBBOCK DISTRICT
CSJ 0905-00-074
Proj ID STP 2016(691)
Work Type PAVEMENT MARKERS
 
0.001 3617791.56 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-15-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
PMI PAVEMENT MARKING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0905-00-074
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02163021
Totals 3617791.56 0.00 0.00 0.0

CountyLUBBOCK
Highway VA
From VARIOUS LOCATIONS IN
To THE LUBBOCK DISTRICT
CSJ 0905-00-079
Proj ID STP 1502(337)
Work Type CONSTRUCT CURB RAMPS
 
0.001 2988537.45 377945.90 649823.06 21.7
Work Order 08-26-15
Work Began 01-18-16
Work Completed  
Time Computed 09-25-15
Contract Working Days 213
Addl Days Granted 0
Working Days Charged 119
Percent Time Used 55
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0905-00-079
W.S. CONSTRUCTION COMPANY(9.29%)
Contract # 06153048
Totals 2988537.45 377945.90 649823.06 21.7

CountyLUBBOCK
Highway VA
From VARIOUS LOCATIONS IN
To ALONG IH 27
CSJ 0905-00-083
Proj ID STP 2015(229)
Work Type PUMP STATION REPAIR
 
0.001 2141840.00 118140.00 339187.00 15.8
Work Order 07-16-15
Work Began 10-09-15
Work Completed  
Time Computed 08-16-15
Contract Working Days 190
Addl Days Granted 0
Working Days Charged 80
Percent Time Used 42
Contractor(s)
AUSTIN ENGINEERING CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0905-00-083
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153263
Totals 2141840.00 118140.00 339187.00 15.8

CountyLUBBOCK
Highway CS
From NORTH UNIVERSITY, FROM AMHERST ST.
To US 82 IN LUBBOCK
CSJ 0905-06-090
Proj ID STP 2014(148)TE
Work Type SIDEWALKS, C & G, RAMPS AND LIGHTING
 
0.437 940883.20 443346.61 443346.61 47.1
Work Order 01-29-16
Work Began 02-29-16
Work Completed  
Time Computed 02-29-16
Contract Working Days 82
Addl Days Granted 0
Working Days Charged 24
Percent Time Used 29
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0905-06-090
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08153224
Totals 940883.20 443346.61 443346.61 47.1

CountyLUBBOCK
Highway VA
From VARIOUS LOCATIONS IN
To THE LUBBOCK DISTRICT
CSJ 0905-06-093
Proj ID NH 2015(474)
Work Type DYNAMIC MESSAGE SIGNS
 
0.002 1419480.83 3536.23 1452397.11 99.9
Work Order 02-26-15
Work Began 07-15-15
Work Completed  
Time Computed 06-26-15
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 160
Percent Time Used 88
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0905-06-093
DRILL PIER CONSTRUCTION, LLC (1.79%)
O. TREVINO CONSTRUCTION, LLC ( 10.01%)
BARRICADES UNLIMITED (1.29%)
NETWORK CABLING SERVICES, INC. (4.20%)
RICE ENVIRONMENTAL SERVICES(3.55%)
ATLAS GROUP, LLC ( 15.21%)
Contract # 01153017
Totals 1419480.83 3536.23 1452397.11 99.9

CountySWISHER
Highway VA
From HALE COUNTY LINE
To RANDALL COUNTY LINE
CSJ 0905-17-013
Proj ID NH 2016(692)
Work Type REMOVAL & INSTALL OF LG GUIDE SIGNS
 
30.700 280506.80 51295.00 51295.00 18.2
Work Order 03-18-16
Work Began 03-29-16
Work Completed  
Time Computed 04-18-16
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 3
Percent Time Used 3
Contractor(s)
ODUM SERVICES, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0905-17-013
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02163216
Totals 280506.80 51295.00 51295.00 18.2

CountyLUBBOCK
Highway FM 400
From 0.25 MILES NORTH OF NFDMF BRAZOS
To 0.25 MILES SOUTH OF NFDMF BRAZOS
CSJ 1041-02-039
Proj ID BR 1502(582)
Work Type REMOVE AND REPLACE BRIDGE
 
0.500 2349749.85 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-24-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
KIEWIT INFRASTRUCTURE SOUTH CO.
SUBCONTRACTOR(S) FOR CCSJ: 1041-02-039
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08153042
Totals 2349749.85 0.00 0.00 0.0

CountyLUBBOCK
Highway FM 1730
From 200 FEET NORTH OF 98TH ST.
To 1000 FEET SOUTH OF FM 1585
CSJ 1344-02-019
Proj ID STP 2014(479)MM
Work Type GRAD, BASE, ACP, STR, SET, C & G
 
2.246 14189419.37 909080.82 9555001.18 67.3
Work Order 05-14-14
Work Began 06-02-14
Work Completed  
Time Computed 07-10-14
Contract Working Days 340
Addl Days Granted 167
Working Days Charged 403
Percent Time Used 79
Contractor(s)
ALLEN BUTLER CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1344-02-019
ARTEX ELECTRIC CO. (1.06%)
BARRICADES UNLIMITED (1.39%)
CMT ENGINEERING, INC.(0.40%)
TEX OP CONSTRUCTION, LP(0.54%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.99%)
FLOYD TRUCKING, INC. (5.10%)
V-TECH ENVIRONMENTAL SERVICES(0.48%)
VANN/ELLI, INC.(0.78%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.16%)
DOUBLE R LAWN AND LANDSCAPE(0.02%)
UTILITY CONTRACTORS OF AMERICA, LTD(6.67%)
ROYAL CONCRETE (0.47%)
Contract # 03143002
Totals 14189419.37 909080.82 9555001.18 67.3

page 1 | page 2