Monthly State Let Construction Report For Lubbock District As Of Apr 10, 2015 Page 2 Of 2

Last Update: Friday, April 10, 2015
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHOCKLEY
Highway FM 597
From FM 168
To LUBBOCK COUNTY LINE
CSJ 0874-07-006
Proj ID STP 2015(766)
Work Type MILL, STABILIZE, 2 COURSE SURF TREAT
 
5.302 3845414.81 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 139
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0874-07-006
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03153228
Totals 3845414.81 0.00 0.00 0.0

CountyLUBBOCK
Highway VA
From VARIOUS LOCATIONS IN
To THE LUBBOCK DISTRICT
CSJ 0905-00-065
Proj ID STP 2014(396)
Work Type FY 2014 PAVEMENT MARKERS
 
0.001 1723815.96 0.00 1729907.75 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-11-14
Work Began 05-13-14
Work Completed 01-28-15
Time Computed 05-05-14
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 100
Percent Time Used 100
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0905-00-065
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02143025
Totals 1723815.96 0.00 1729907.75 100.0

CountyLUBBOCK
Highway VA
From VARIOUS LOCATIONS IN
To THE LUBBOCK DISTRICT
CSJ 0905-00-072
Proj ID STP 2015(596)
Work Type PAVEMENT MARKINGS
 
0.001 2605518.67 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-16-15
Work Began 00-00-00
Work Completed  
Time Computed 04-01-15
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0905-00-072
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02153012
Totals 2605518.67 0.00 0.00 0.0

CountyLUBBOCK
Highway VA
From VARIOUS LOCATIONS IN
To ALONG IH 27
CSJ 0905-00-083
Proj ID STP 2015(229)
Work Type PUMP STATION REPAIR
 
0.001 2562040.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 190
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AUSTIN ENGINEERING CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0905-00-083
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04153027
Totals 2562040.00 0.00 0.00 0.0

CountyLUBBOCK
Highway VA
From US84, BNSF OVERPASS
To IN POST, TEXAS
CSJ 0905-00-085
Proj ID STP 2014(776)
Work Type PAVEMENT REPAIR
 
0.001 1205066.00 0.00 991710.08 100.0
Work Order 08-13-14
Work Began 09-16-14
Work Completed 02-24-15
Time Computed 09-02-14
Contract Working Days 68
Addl Days Granted 15
Working Days Charged 78
Percent Time Used 93
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0905-00-085
BARRICADES UNLIMITED (9.26%)
ODUM SERVICES, L.P.(3.93%)
V-TECH ENVIRONMENTAL SERVICES(1.21%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.68%)
WEST INFRASTRUCTURE CONSTRUCTION, LLC( 18.52%)
TEX OP CONSTRUCTION, LP(0.45%)
Contract # 06143222
Totals 1205066.00 0.00 991710.08 100.0

CountyLUBBOCK
Highway VA
From VARIOUS LOCATIONS IN
To THE LUBBOCK DISTRICT
CSJ 0905-00-087
Proj ID STP 2014(777)
Work Type MISCELLANOUS CONSTRUCTION
 
0.001 133232.60 0.00 128979.40 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-22-14
Work Began 06-16-14
Work Completed 09-02-14
Time Computed 07-22-14
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 32
Percent Time Used 71
Contractor(s)
ADVANCED TRANSOL CONSULTANTS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0905-00-087
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04143033
Totals 133232.60 0.00 128979.40 100.0

CountyLUBBOCK
Highway VA
From VARIOUS LOCATIONS IN
To THE LUBBOCK DISTRICT
CSJ 0905-06-093
Proj ID NH 2015(474)
Work Type DYNAMIC MESSAGE SIGNS
 
0.002 1419480.83 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-26-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0905-06-093
DRILL PIER CONSTRUCTION, LLC (1.79%)
O. TREVINO CONSTRUCTION, LLC ( 10.01%)
BARRICADES UNLIMITED (1.29%)
NETWORK CABLING SERVICES, INC. (4.20%)
RICE ENVIRONMENTAL SERVICES(3.55%)
Contract # 01153017
Totals 1419480.83 0.00 0.00 0.0

CountyHALE
Highway VA
From LUBBOCK COUNTY LINE
To SWISHER COUNTY LINE
CSJ 0905-12-041
Proj ID NH 2015(399)
Work Type REMOVAL & INSTALL OF LG GUIDE SIGNS
 
37.717 246777.34 0.00 0.00 0.0
Work Order 01-07-15
Work Began 00-00-00
Work Completed  
Time Computed 03-08-15
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DFB CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0905-12-041
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12143215
Totals 246777.34 0.00 0.00 0.0

CountyHALE
Highway CS
From US 70
To 13TH STREET
CSJ 0905-12-042
Proj ID C 905-12-42
Work Type PLANE, ACP, SURFACE COURSE
 
0.335 864043.60 198867.10 206906.70 23.9
Work Order 09-30-14
Work Began 03-16-15
Work Completed  
Time Computed 10-16-14
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 11
Percent Time Used 27
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0905-12-042
BARRICADES UNLIMITED (1.63%)
WILLIS ELECTRIC CO., LP(0.46%)
ALAMO BROTHERS CONCRETE(7.16%)
BILL AYRES LAWN & TREE SERVICE (2.12%)
Contract # 07143052
Totals 864043.60 198867.10 206906.70 23.9

CountyLUBBOCK
Highway FM 1730
From 200 FEET NORTH OF 98TH ST.
To 1000 FEET SOUTH OF FM 1585
CSJ 1344-02-019
Proj ID STP 2014(479)MM
Work Type GRAD, BASE, ACP, STR, SET, C & G
 
2.246 14189419.37 697176.75 4738931.01 33.3
Work Order 05-14-14
Work Began 06-02-14
Work Completed  
Time Computed 07-10-14
Contract Working Days 340
Addl Days Granted 20
Working Days Charged 174
Percent Time Used 48
Contractor(s)
ALLEN BUTLER CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1344-02-019
ARTEX ELECTRIC CO. (1.06%)
BARRICADES UNLIMITED (1.39%)
CMT ENGINEERING, INC.(0.40%)
TEX OP CONSTRUCTION, LP(0.54%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.99%)
FLOYD TRUCKING, INC. (5.10%)
V-TECH ENVIRONMENTAL SERVICES(0.48%)
VANN/ELLI, INC.(0.78%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.16%)
DOUBLE R LAWN AND LANDSCAPE(0.02%)
UTILITY CONTRACTORS OF AMERICA, LTD(6.67%)
Contract # 03143002
Totals 14189419.37 697176.75 4738931.01 33.3

CountyHOCKLEY
Highway FM 1585
From FM 303
To US 385
CSJ 2182-02-008
Proj ID STP 2014(263)
Work Type MILL, STABILIZE, 2 COURSE SURF TREAT
 
6.529 3762234.84 0.00 2382391.72 63.3
Work Order 01-17-14
Work Began 04-07-14
Work Completed  
Time Computed 06-30-14
Contract Working Days 149
Addl Days Granted 0
Working Days Charged 88
Percent Time Used 59
Contractor(s)
ALLEN BUTLER CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2182-02-008
BARRICADES UNLIMITED (2.28%)
FLOYD TRUCKING, INC. (9.18%)
HJC FARMS, INC.(0.24%)
V-TECH ENVIRONMENTAL SERVICES(0.81%)
ROAD TRAC, INC.(0.03%)
Contract # 10133025
Totals 3762234.84 0.00 2382391.72 63.3

CountyCASTRO
Highway FM 145
From FM 1055
To US 385
CSJ 2419-01-010
Proj ID STP 2014(009)
Work Type WIDEN, SALVAGE BASE, BASE, 2 CST
 
6.100 1987950.29 0.00 1842914.16 94.2
Work Order 10-10-13
Work Began 04-08-14
Work Completed  
Time Computed 12-09-13
Contract Working Days 89
Addl Days Granted 0
Working Days Charged 129
Percent Time Used 144
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2419-01-010
BARRICADES UNLIMITED (3.26%)
Contract # 09133214
Totals 1987950.29 0.00 1842914.16 94.2

CountyPARMER
Highway FM 1172
From FM 2397
To SH 86
CSJ 2444-01-009
Proj ID STP 2013(092)
Work Type BASE, CEMENT STAB, TWO CRSE
 
6.729 3262223.62 32000.00 3034550.39 100.0
Work Order 01-17-14
Work Began 02-17-14
Work Completed 01-08-15
Time Computed 04-01-14
Contract Working Days 139
Addl Days Granted 0
Working Days Charged 138
Percent Time Used 99
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2444-01-009
E. DIAZ TRUCKING (3.86%)
TEXAS ALTERNATIVE GRASSER, INC.(0.73%)
DOUBLE A CONTRACTING, L.P. (1.54%)
Contract # 10133019
Totals 3262223.62 32000.00 3034550.39 100.0

page 1 | page 2