Monthly State Let Construction Report For Lubbock District As Of Aug 12, 2014 Page 2 Of 2

Last Update: Tuesday, August 12, 2014
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyLUBBOCK
Highway VA
From US84, BNSF OVERPASS
To IN POST, TEXAS
CSJ 0905-00-085
Proj ID STP 2014(776)
Work Type PAVEMENT REPAIR
 
0.001 1205066.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 68
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0905-00-085
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143222
Totals 1205066.00 0.00 0.00 0.0

CountyLUBBOCK
Highway VA
From VARIOUS LOCATIONS IN
To THE LUBBOCK DISTRICT
CSJ 0905-00-087
Proj ID STP 2014(777)
Work Type MISCELLANOUS CONSTRUCTION
 
0.001 133232.60 48314.50 128979.40 96.8
Work Order 05-22-14
Work Began 06-16-14
Work Completed  
Time Computed 07-22-14
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 32
Percent Time Used 71
Contractor(s)
ADVANCED TRANSOL CONSULTANTS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0905-00-087
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04143033
Totals 133232.60 48314.50 128979.40 96.8

CountyHALE
Highway CS
From US 70
To 13TH STREET
CSJ 0905-12-042
Proj ID C 905-12-42
Work Type PLANE, ACP, SURFACE COURSE
 
0.335 864043.60 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0905-12-042
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143052
Totals 864043.60 0.00 0.00 0.0

CountyLUBBOCK
Highway FM 1730
From 200 FEET NORTH OF 98TH ST.
To 1000 FEET SOUTH OF FM 1585
CSJ 1344-02-019
Proj ID STP 2014(479)MM
Work Type GRAD, BASE, ACP, STR, SET, C & G
 
2.246 14189419.37 181464.45 1147366.10 8.0
Work Order 05-14-14
Work Began 06-02-14
Work Completed  
Time Computed 07-10-14
Contract Working Days 340
Addl Days Granted 0
Working Days Charged 40
Percent Time Used 11
Contractor(s)
ALLEN BUTLER CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1344-02-019
ARTEX ELECTRIC CO. (1.06%)
BARRICADES UNLIMITED (1.39%)
CMT ENGINEERING, INC.(0.40%)
TEX OP CONSTRUCTION, LP(0.54%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.99%)
FLOYD TRUCKING, INC. (5.10%)
V-TECH ENVIRONMENTAL SERVICES(0.48%)
VANN/ELLI, INC.(0.78%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.16%)
DOUBLE R LAWN AND LANDSCAPE(0.02%)
UTILITY CONTRACTORS OF AMERICA, LTD(6.67%)
Contract # 03143002
Totals 14189419.37 181464.45 1147366.10 8.0

CountyHOCKLEY
Highway FM 1585
From FM 303
To US 385
CSJ 2182-02-008
Proj ID STP 2014(263)
Work Type MILL, STABILIZE, 2 COURSE SURF TREAT
 
6.529 3762234.84 331315.25 1672922.89 44.4
Work Order 01-17-14
Work Began 04-07-14
Work Completed  
Time Computed 06-30-14
Contract Working Days 149
Addl Days Granted 0
Working Days Charged 57
Percent Time Used 38
Contractor(s)
ALLEN BUTLER CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2182-02-008
BARRICADES UNLIMITED (2.28%)
FLOYD TRUCKING, INC. (9.18%)
HJC FARMS, INC.(0.24%)
V-TECH ENVIRONMENTAL SERVICES(0.81%)
ROAD TRAC, INC.(0.03%)
Contract # 10133025
Totals 3762234.84 331315.25 1672922.89 44.4

CountyCASTRO
Highway FM 145
From FM 1055
To US 385
CSJ 2419-01-010
Proj ID STP 2014(009)
Work Type WIDEN, SALVAGE BASE, BASE, 2 CST
 
6.100 1987950.29 200265.08 1039877.67 52.3
Work Order 10-10-13
Work Began 04-08-14
Work Completed  
Time Computed 12-09-13
Contract Working Days 89
Addl Days Granted 0
Working Days Charged 64
Percent Time Used 71
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2419-01-010
BARRICADES UNLIMITED (3.26%)
Contract # 09133214
Totals 1987950.29 200265.08 1039877.67 52.3

CountyPARMER
Highway FM 1172
From FM 2397
To SH 86
CSJ 2444-01-009
Proj ID STP 2013(092)
Work Type BASE, CEMENT STAB, TWO CRSE
 
6.729 3262223.62 139976.01 1673826.16 51.3
Work Order 01-17-14
Work Began 02-17-14
Work Completed  
Time Computed 04-01-14
Contract Working Days 139
Addl Days Granted 0
Working Days Charged 98
Percent Time Used 70
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2444-01-009
E. DIAZ TRUCKING (3.86%)
TEXAS ALTERNATIVE GRASSER, INC.(0.73%)
DOUBLE A CONTRACTING, L.P. (1.54%)
Contract # 10133019
Totals 3262223.62 139976.01 1673826.16 51.3

page 1 | page 2