Monthly State Let Construction Report For Lubbock District As Of Mar 10, 2015 Page 2 Of 2

Last Update: Wednesday, March 11, 2015
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyDAWSON
Highway FM 26
From US 87
To FM 828
CSJ 0637-01-011
Proj ID STP 2015(768)
Work Type SUBGRADE WIDENING BASE SC PAVE MRKS
 
5.273 2978473.01 0.00 0.00 0.0
CountyDAWSON
Highway FM 26
From FM 828
To MARTIN CO LINE
CSJ 1749-01-007
Proj ID C 1749-1-7
Work Type SUBGRADEWIDE BASE SURF TREAT & PVEMRK
 
4.146 2551788.51 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 124
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0637-01-011
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03153031
Totals 5530261.52 0.00 0.00 0.0

CountyLUBBOCK
Highway SL 289
From INTERSECTION OF 50TH STREET
To IN LUBBOCK
CSJ 0783-01-096
Proj ID NH 2015(073)
Work Type RELOCATE MEDIAN, SIGNAL, AND STRIPE
 
0.078 106833.90 0.00 100156.40 93.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-14-14
Work Began 11-03-14
Work Completed  
Time Computed 10-30-14
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 18
Percent Time Used 40
Contractor(s)
M & S CONCRETE CO.
SUBCONTRACTOR(S) FOR CCSJ: 0783-01-096
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143031
Totals 106833.90 0.00 100156.40 93.7

CountyLUBBOCK
Highway LP 289
From 990 FEET EAST OF SLIDE ROAD
To 2585 FEET EAST OF QUAKER AVENUE
CSJ 0783-02-084
Proj ID C 783-2-84
Work Type GR, BASE, STR, ASB, ACP, OVERPASS
 
1.620 26923572.74 606477.19 23019170.44 85.7
Work Order 09-24-12
Work Began 11-12-12
Work Completed  
Time Computed 11-12-12
Contract Working Days 581
Addl Days Granted 0
Working Days Charged 569
Percent Time Used 97
Contractor(s)
HAYDON BUILDING CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0783-02-084
RICE ENVIRONMENTAL SERVICES(1.84%)
TOM"S TREE PLACE (1.09%)
WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED(0.31%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.14%)
DRILL PIER CONSTRUCTION, LLC (0.00%)
ARTEX ELECTRIC, INC. (0.01%)
MICA CORPORATION (0.95%)
A & A CONSTRUCTION (0.36%)
BUILDER SERVICES CO. (0.24%)
TEX OP CONSTRUCTION, LP(0.59%)
WEST TEXAS PAVING, INC.( 15.59%)
CMT ENGINEERING, INC.(0.07%)
FARR FOUNDATION, INC.(0.53%)
W. W. FOUNDATION DRILLING, LTD.(1.34%)
TRUMBLE CRANE & RIGGING(0.32%)
NORTH TEXAS REBAR, LLC (3.61%)
WILLIS ELECTRIC CO., LP(5.48%)
FLOYD TRUCKING, INC. (0.00%)
W.O.E. CONSTRUCTION(0.08%)
BRUNDAGE-BONE(0.00%)
SOUTHEAST GRINDING & GROOVING, LLC (0.05%)
COLTON GRADING & EXCAVATION(0.00%)
BILL AYRES LAWN & TREE SERVICE (0.01%)
DUSTIN ALLEN, INC. (0.45%)
COMBS CONSTRUCTION COMPANY, INC. (1.35%)
ROAD REPAIR, LLC (0.13%)
TEXAS FAR WEST CONSTRUCTION & ENGINEERING(0.18%)
AUI CONTRACTORS, LLC (0.01%)
S & S BRIDGE PAINTING, INC.(0.12%)
WEST INFRASTRUCTURE CONSTRUCTION, LLC(0.13%)
Contract # 07123204
Totals 26923572.74 606477.19 23019170.44 85.7

CountyCROSBY
Highway FM 378
From W FM 40
To SOUTH END OF STATE MAINTENANCE
CSJ 0800-04-009
Proj ID C 800-4-9
Work Type WIDEN, GRADING, BASE, SURFACE, TREAT
 
5.193 2664168.23 0.00 2494090.55 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-20-13
Work Began 03-24-14
Work Completed 10-31-14
Time Computed 04-01-14
Contract Working Days 124
Addl Days Granted 0
Working Days Charged 121
Percent Time Used 97
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0800-04-009
E. DIAZ TRUCKING (0.00%)
BARRICADES UNLIMITED (0.99%)
Contract # 10133217
Totals 2664168.23 0.00 2494090.55 100.0

CountyHOCKLEY
Highway FM 597
From FM 168
To LUBBOCK COUNTY LINE
CSJ 0874-07-006
Proj ID STP 2015(766)
Work Type MILL, STABILIZE, 2 COURSE SURF TREAT
 
5.302 3845414.81 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 139
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0874-07-006
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03153228
Totals 3845414.81 0.00 0.00 0.0

CountyLUBBOCK
Highway VA
From VARIOUS LOCATIONS IN
To THE LUBBOCK DISTRICT
CSJ 0905-00-065
Proj ID STP 2014(396)
Work Type FY 2014 PAVEMENT MARKERS
 
0.001 1723815.96 0.10 1729907.75 100.0
Work Order 04-11-14
Work Began 05-13-14
Work Completed 01-28-15
Time Computed 05-05-14
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 100
Percent Time Used 100
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0905-00-065
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02143025
Totals 1723815.96 0.10 1729907.75 100.0

CountyLUBBOCK
Highway VA
From VARIOUS LOCATIONS IN
To THE LUBBOCK DISTRICT
CSJ 0905-00-070
Proj ID STP 2013(154)
Work Type FY 2013 ADA COMPLIANCE
 
0.001 1488393.00 0.00 1618525.68 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-17-13
Work Began 03-11-13
Work Completed 08-06-14
Time Computed 02-02-13
Contract Working Days 188
Addl Days Granted 9
Working Days Charged 164
Percent Time Used 83
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0905-00-070
ONE WAY CONCRETE ( 41.09%)
WEST TEXAS BARRICADES, LLC DBA BARRICADES UNLIMITED(0.63%)
HIGHWAY TECHNOLOGIES, INC. (0.97%)
FAASS TRUCKING, INC. (1.46%)
Contract # 11123015
Totals 1488393.00 0.00 1618525.68 100.0

CountyLUBBOCK
Highway VA
From VARIOUS LOCATIONS IN
To THE LUBBOCK DISTRICT
CSJ 0905-00-071
Proj ID STP 2014(397)
Work Type RRPMS AND SPECIALITY MARKINGS
 
0.001 778423.00 1500.00 771120.00 100.0
Work Order 03-13-14
Work Began 05-27-14
Work Completed 09-02-14
Time Computed 05-05-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 67
Percent Time Used 111
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0905-00-071
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02143215
Totals 778423.00 1500.00 771120.00 100.0

CountyLUBBOCK
Highway VA
From VARIOUS LOCATIONS IN
To THE LUBBOCK DISTRICT
CSJ 0905-00-072
Proj ID STP 2015(596)
Work Type PAVEMENT MARKINGS
 
0.001 2605518.67 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0905-00-072
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02153012
Totals 2605518.67 0.00 0.00 0.0

CountyLUBBOCK
Highway VA
From VARIOUS LOCATIONS IN
To THE LUBBOCK DISTRICT
CSJ 0905-00-077
Proj ID STP 2013(877)
Work Type MISCELLANOUS CONSTRUCTION
 
0.001 239588.36 2385.82 256032.16 100.0
Work Order 07-24-13
Work Began 11-05-13
Work Completed 08-19-14
Time Computed 08-09-13
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 73
Percent Time Used 81
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0905-00-077
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06133214
Totals 239588.36 2385.82 256032.16 100.0

CountyLUBBOCK
Highway VA
From US84, BNSF OVERPASS
To IN POST, TEXAS
CSJ 0905-00-085
Proj ID STP 2014(776)
Work Type PAVEMENT REPAIR
 
0.001 1205066.00 124272.85 991710.08 82.2
Work Order 08-13-14
Work Began 09-16-14
Work Completed  
Time Computed 09-02-14
Contract Working Days 68
Addl Days Granted 15
Working Days Charged 78
Percent Time Used 93
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0905-00-085
BARRICADES UNLIMITED (9.26%)
ODUM SERVICES, L.P.(3.93%)
V-TECH ENVIRONMENTAL SERVICES(1.21%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.68%)
WEST INFRASTRUCTURE CONSTRUCTION, LLC( 18.52%)
TEX OP CONSTRUCTION, LP(0.45%)
Contract # 06143222
Totals 1205066.00 124272.85 991710.08 82.2

CountyLUBBOCK
Highway VA
From VARIOUS LOCATIONS IN
To THE LUBBOCK DISTRICT
CSJ 0905-00-087
Proj ID STP 2014(777)
Work Type MISCELLANOUS CONSTRUCTION
 
0.001 133232.60 0.00 128979.40 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-22-14
Work Began 06-16-14
Work Completed 09-02-14
Time Computed 07-22-14
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 32
Percent Time Used 71
Contractor(s)
ADVANCED TRANSOL CONSULTANTS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0905-00-087
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04143033
Totals 133232.60 0.00 128979.40 100.0

CountyLUBBOCK
Highway VA
From VARIOUS LOCATIONS IN
To THE LUBBOCK DISTRICT
CSJ 0905-06-093
Proj ID NH 2015(474)
Work Type DYNAMIC MESSAGE SIGNS
 
0.002 1419480.83 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-26-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0905-06-093
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01153017
Totals 1419480.83 0.00 0.00 0.0

CountyHALE
Highway VA
From LUBBOCK COUNTY LINE
To SWISHER COUNTY LINE
CSJ 0905-12-041
Proj ID NH 2015(399)
Work Type REMOVAL & INSTALL OF LG GUIDE SIGNS
 
37.717 246777.34 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-07-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DFB CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0905-12-041
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12143215
Totals 246777.34 0.00 0.00 0.0

CountyHALE
Highway CS
From US 70
To 13TH STREET
CSJ 0905-12-042
Proj ID C 905-12-42
Work Type PLANE, ACP, SURFACE COURSE
 
0.335 864043.60 0.00 8039.60 0.9
Work Order 09-30-14
Work Began 00-00-00
Work Completed  
Time Computed 10-16-14
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0905-12-042
BARRICADES UNLIMITED (1.63%)
WILLIS ELECTRIC CO., LP(0.46%)
ALAMO BROTHERS CONCRETE(7.16%)
Contract # 07143052
Totals 864043.60 0.00 8039.60 0.9

CountyLUBBOCK
Highway FM 1730
From 200 FEET NORTH OF 98TH ST.
To 1000 FEET SOUTH OF FM 1585
CSJ 1344-02-019
Proj ID STP 2014(479)MM
Work Type GRAD, BASE, ACP, STR, SET, C & G
 
2.246 14189419.37 252002.65 4041754.26 28.4
Work Order 05-14-14
Work Began 06-02-14
Work Completed  
Time Computed 07-10-14
Contract Working Days 340
Addl Days Granted 20
Working Days Charged 157
Percent Time Used 43
Contractor(s)
ALLEN BUTLER CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1344-02-019
ARTEX ELECTRIC CO. (1.06%)
BARRICADES UNLIMITED (1.39%)
CMT ENGINEERING, INC.(0.40%)
TEX OP CONSTRUCTION, LP(0.54%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.99%)
FLOYD TRUCKING, INC. (5.10%)
V-TECH ENVIRONMENTAL SERVICES(0.48%)
VANN/ELLI, INC.(0.78%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.16%)
DOUBLE R LAWN AND LANDSCAPE(0.02%)
UTILITY CONTRACTORS OF AMERICA, LTD(6.67%)
Contract # 03143002
Totals 14189419.37 252002.65 4041754.26 28.4

CountyHOCKLEY
Highway FM 1585
From FM 303
To US 385
CSJ 2182-02-008
Proj ID STP 2014(263)
Work Type MILL, STABILIZE, 2 COURSE SURF TREAT
 
6.529 3762234.84 0.00 2382391.72 63.3
Work Order 01-17-14
Work Began 04-07-14
Work Completed  
Time Computed 06-30-14
Contract Working Days 149
Addl Days Granted 0
Working Days Charged 88
Percent Time Used 59
Contractor(s)
ALLEN BUTLER CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2182-02-008
BARRICADES UNLIMITED (2.28%)
FLOYD TRUCKING, INC. (9.18%)
HJC FARMS, INC.(0.24%)
V-TECH ENVIRONMENTAL SERVICES(0.81%)
ROAD TRAC, INC.(0.03%)
Contract # 10133025
Totals 3762234.84 0.00 2382391.72 63.3

CountyCASTRO
Highway FM 145
From FM 1055
To US 385
CSJ 2419-01-010
Proj ID STP 2014(009)
Work Type WIDEN, SALVAGE BASE, BASE, 2 CST
 
6.100 1987950.29 0.00 1842914.16 94.2
Work Order 10-10-13
Work Began 04-08-14
Work Completed  
Time Computed 12-09-13
Contract Working Days 89
Addl Days Granted 0
Working Days Charged 129
Percent Time Used 144
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2419-01-010
BARRICADES UNLIMITED (3.26%)
Contract # 09133214
Totals 1987950.29 0.00 1842914.16 94.2

CountyPARMER
Highway FM 1172
From FM 2397
To SH 86
CSJ 2444-01-009
Proj ID STP 2013(092)
Work Type BASE, CEMENT STAB, TWO CRSE
 
6.729 3262223.62 0.00 3002550.39 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-17-14
Work Began 02-17-14
Work Completed 01-08-15
Time Computed 04-01-14
Contract Working Days 139
Addl Days Granted 0
Working Days Charged 138
Percent Time Used 99
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2444-01-009
E. DIAZ TRUCKING (3.86%)
TEXAS ALTERNATIVE GRASSER, INC.(0.73%)
DOUBLE A CONTRACTING, L.P. (1.54%)
Contract # 10133019
Totals 3262223.62 0.00 3002550.39 100.0

page 1 | page 2