Monthly State Let Construction Report For Lubbock District As Of Jul 13, 2015 Page 2 Of 2

Last Update: Monday, July 13, 2015
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyLUBBOCK
Highway LP 289
From 990 FEET EAST OF SLIDE ROAD
To 2585 FEET EAST OF QUAKER AVENUE
CSJ 0783-02-084
Proj ID C 783-2-84
Work Type GR, BASE, STR, ASB, ACP, OVERPASS
 
1.620 26923572.74 103464.40 24966394.90 92.7
Work Order 09-24-12
Work Began 11-12-12
Work Completed  
Time Computed 11-12-12
Contract Working Days 581
Addl Days Granted 64
Working Days Charged 602
Percent Time Used 93
Contractor(s)
HAYDON BUILDING CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0783-02-084
RICE ENVIRONMENTAL SERVICES(1.84%)
WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED(0.31%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.14%)
DRILL PIER CONSTRUCTION, LLC (0.00%)
ARTEX ELECTRIC, INC. (0.01%)
MICA CORPORATION (0.95%)
A & A CONSTRUCTION (0.36%)
BUILDER SERVICES CO. (0.24%)
TEX OP CONSTRUCTION, LP(0.59%)
WEST TEXAS PAVING, INC.( 15.59%)
CMT ENGINEERING, INC.(0.07%)
FARR FOUNDATION, INC.(0.53%)
W. W. FOUNDATION DRILLING, LTD.(1.34%)
TRUMBLE CRANE & RIGGING(0.32%)
NORTH TEXAS REBAR, LLC (3.61%)
WILLIS ELECTRIC CO., LP(5.48%)
FLOYD TRUCKING, INC. (0.00%)
W.O.E. CONSTRUCTION(0.08%)
BRUNDAGE-BONE(0.00%)
SOUTHEAST GRINDING & GROOVING, LLC (0.05%)
COLTON GRADING & EXCAVATION(0.00%)
BILL AYRES LAWN & TREE SERVICE (0.01%)
DUSTIN ALLEN, INC. (0.45%)
COMBS CONSTRUCTION COMPANY, INC. (1.35%)
ROAD REPAIR, LLC (0.13%)
TEXAS FAR WEST CONSTRUCTION & ENGINEERING(0.18%)
AUI CONTRACTORS, LLC (0.01%)
S & S BRIDGE PAINTING, INC.(0.12%)
WEST INFRASTRUCTURE CONSTRUCTION, LLC(0.13%)
WALLACE SPRINKLERS, INC. (0.14%)
WEST TEXAS SERVICES, INC. DBA TOM"S TREE PLACE PATTERENED(1.08%)
JORDAN"S POWER SWEEP (0.00%)
CHOLLA PAVEMENT MAINTENANCE, INC (1.35%)
Contract # 07123204
Totals 26923572.74 103464.40 24966394.90 92.7

CountyHOCKLEY
Highway FM 597
From FM 168
To LUBBOCK COUNTY LINE
CSJ 0874-07-006
Proj ID STP 2015(766)
Work Type MILL, STABILIZE, 2 COURSE SURF TREAT
 
5.302 3845414.81 26980.00 26980.00 0.7
Work Order 05-08-15
Work Began 00-00-00
Work Completed  
Time Computed 06-08-15
Contract Working Days 139
Addl Days Granted 0
Working Days Charged 7
Percent Time Used 5
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0874-07-006
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03153228
Totals 3845414.81 26980.00 26980.00 0.7

CountyLUBBOCK
Highway VA
From VARIOUS LOCATIONS IN
To THE LUBBOCK DISTRICT
CSJ 0905-00-065
Proj ID STP 2014(396)
Work Type FY 2014 PAVEMENT MARKERS
 
0.001 1723815.96 0.00 1729907.75 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-11-14
Work Began 05-13-14
Work Completed 01-28-15
Time Computed 05-05-14
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 100
Percent Time Used 100
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0905-00-065
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02143025
Totals 1723815.96 0.00 1729907.75 100.0

CountyLUBBOCK
Highway VA
From VARIOUS LOCATIONS IN
To THE LUBBOCK DISTRICT
CSJ 0905-00-072
Proj ID STP 2015(596)
Work Type PAVEMENT MARKINGS
 
0.001 2605518.67 538748.46 2293134.08 88.0
Work Order 03-16-15
Work Began 04-08-15
Work Completed  
Time Computed 04-01-15
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 51
Percent Time Used 51
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0905-00-072
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02153012
Totals 2605518.67 538748.46 2293134.08 88.0

CountyLUBBOCK
Highway VA
From VARIOUS LOCATIONS IN
To THE LUBBOCK DISTRICT
CSJ 0905-00-079
Proj ID STP 1502(337)
Work Type CONSTRUCT CURB RAMPS
 
0.001 2988537.45 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 213
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0905-00-079
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153048
Totals 2988537.45 0.00 0.00 0.0

CountyLUBBOCK
Highway VA
From VARIOUS LOCATIONS IN
To ALONG IH 27
CSJ 0905-00-083
Proj ID STP 2015(229)
Work Type PUMP STATION REPAIR
 
0.001 2141840.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 190
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AUSTIN ENGINEERING CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0905-00-083
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153263
Totals 2141840.00 0.00 0.00 0.0

CountyLUBBOCK
Highway VA
From US84, BNSF OVERPASS
To IN POST, TEXAS
CSJ 0905-00-085
Proj ID STP 2014(776)
Work Type PAVEMENT REPAIR
 
0.001 1205066.00 0.00 991710.08 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-13-14
Work Began 09-16-14
Work Completed 02-24-15
Time Computed 09-02-14
Contract Working Days 68
Addl Days Granted 15
Working Days Charged 78
Percent Time Used 93
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0905-00-085
BARRICADES UNLIMITED (9.26%)
ODUM SERVICES, L.P.(3.93%)
V-TECH ENVIRONMENTAL SERVICES(1.21%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.68%)
WEST INFRASTRUCTURE CONSTRUCTION, LLC( 18.52%)
TEX OP CONSTRUCTION, LP(0.45%)
Contract # 06143222
Totals 1205066.00 0.00 991710.08 100.0

CountyLUBBOCK
Highway VA
From VARIOUS LOCATIONS IN
To THE LUBBOCK DISTRICT
CSJ 0905-00-086
Proj ID STP 1502(380)
Work Type PAVEMENT REPAIR
 
0.001 880616.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 52
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0905-00-086
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07153246
Totals 880616.00 0.00 0.00 0.0

CountyLUBBOCK
Highway VA
From VARIOUS LOCATIONS IN
To THE LUBBOCK DISTRICT
CSJ 0905-00-087
Proj ID STP 2014(777)
Work Type MISCELLANOUS CONSTRUCTION
 
0.001 133232.60 800.00 129779.40 100.0
Work Order 05-22-14
Work Began 06-16-14
Work Completed 09-02-14
Time Computed 07-22-14
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 32
Percent Time Used 71
Contractor(s)
ADVANCED TRANSOL CONSULTANTS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0905-00-087
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04143033
Totals 133232.60 800.00 129779.40 100.0

CountyLUBBOCK
Highway VA
From VARIOUS LOCATIONS IN
To THE LUBBOCK DISTRICT
CSJ 0905-06-093
Proj ID NH 2015(474)
Work Type DYNAMIC MESSAGE SIGNS
 
0.002 1419480.83 11725.00 25695.00 1.8
Work Order 02-26-15
Work Began 00-00-00
Work Completed  
Time Computed 06-26-15
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 3
Percent Time Used 1
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0905-06-093
DRILL PIER CONSTRUCTION, LLC (1.79%)
O. TREVINO CONSTRUCTION, LLC ( 10.01%)
BARRICADES UNLIMITED (1.29%)
NETWORK CABLING SERVICES, INC. (4.20%)
RICE ENVIRONMENTAL SERVICES(3.55%)
ATLAS GROUP, LLC ( 15.21%)
Contract # 01153017
Totals 1419480.83 11725.00 25695.00 1.8

CountyHALE
Highway VA
From LUBBOCK COUNTY LINE
To SWISHER COUNTY LINE
CSJ 0905-12-041
Proj ID NH 2015(399)
Work Type REMOVAL & INSTALL OF LG GUIDE SIGNS
 
37.717 246777.34 30146.30 207853.50 84.2
Work Order 01-07-15
Work Began 04-14-15
Work Completed  
Time Computed 03-09-15
Contract Working Days 90
Addl Days Granted 20
Working Days Charged 22
Percent Time Used 20
Contractor(s)
DFB CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0905-12-041
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12143215
Totals 246777.34 30146.30 207853.50 84.2

CountyHALE
Highway CS
From US 70
To 13TH STREET
CSJ 0905-12-042
Proj ID C 905-12-42
Work Type PLANE, ACP, SURFACE COURSE
 
0.335 864043.60 1925.00 767578.23 88.8
Work Order 09-30-14
Work Began 03-16-15
Work Completed  
Time Computed 10-16-14
Contract Working Days 40
Addl Days Granted 2
Working Days Charged 36
Percent Time Used 85
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0905-12-042
BARRICADES UNLIMITED (1.63%)
WILLIS ELECTRIC CO., LP(0.46%)
ALAMO BROTHERS CONCRETE(7.16%)
BILL AYRES LAWN & TREE SERVICE (2.12%)
Contract # 07143052
Totals 864043.60 1925.00 767578.23 88.8

CountyLUBBOCK
Highway FM 1730
From 200 FEET NORTH OF 98TH ST.
To 1000 FEET SOUTH OF FM 1585
CSJ 1344-02-019
Proj ID STP 2014(479)MM
Work Type GRAD, BASE, ACP, STR, SET, C & G
 
2.246 14189419.37 335443.00 5823095.05 41.0
Work Order 05-14-14
Work Began 06-02-14
Work Completed  
Time Computed 07-10-14
Contract Working Days 340
Addl Days Granted 20
Working Days Charged 227
Percent Time Used 63
Contractor(s)
ALLEN BUTLER CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1344-02-019
ARTEX ELECTRIC CO. (1.06%)
BARRICADES UNLIMITED (1.39%)
CMT ENGINEERING, INC.(0.40%)
TEX OP CONSTRUCTION, LP(0.54%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.99%)
FLOYD TRUCKING, INC. (5.10%)
V-TECH ENVIRONMENTAL SERVICES(0.48%)
VANN/ELLI, INC.(0.78%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.16%)
DOUBLE R LAWN AND LANDSCAPE(0.02%)
UTILITY CONTRACTORS OF AMERICA, LTD(6.67%)
Contract # 03143002
Totals 14189419.37 335443.00 5823095.05 41.0

CountyHOCKLEY
Highway FM 1585
From FM 303
To US 385
CSJ 2182-02-008
Proj ID STP 2014(263)
Work Type MILL, STABILIZE, 2 COURSE SURF TREAT
 
6.529 3762234.84 483521.00 3421050.42 90.9
Work Order 01-17-14
Work Began 04-07-14
Work Completed  
Time Computed 06-30-14
Contract Working Days 149
Addl Days Granted 0
Working Days Charged 134
Percent Time Used 89
Contractor(s)
ALLEN BUTLER CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2182-02-008
BARRICADES UNLIMITED (2.28%)
FLOYD TRUCKING, INC. (9.18%)
HJC FARMS, INC.(0.24%)
V-TECH ENVIRONMENTAL SERVICES(0.81%)
ROAD TRAC, INC.(0.03%)
HARDY TREES, INC.(0.28%)
Contract # 10133025
Totals 3762234.84 483521.00 3421050.42 90.9

CountyCASTRO
Highway FM 145
From FM 1055
To US 385
CSJ 2419-01-010
Proj ID STP 2014(009)
Work Type WIDEN, SALVAGE BASE, BASE, 2 CST
 
6.100 1987950.29 29739.63 1872653.79 96.1
Work Order 10-10-13
Work Began 04-08-14
Work Completed  
Time Computed 12-09-13
Contract Working Days 89
Addl Days Granted 0
Working Days Charged 138
Percent Time Used 155
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2419-01-010
BARRICADES UNLIMITED (3.26%)
Contract # 09133214
Totals 1987950.29 29739.63 1872653.79 96.1

CountyPARMER
Highway FM 1172
From FM 2397
To SH 86
CSJ 2444-01-009
Proj ID STP 2013(092)
Work Type BASE, CEMENT STAB, TWO CRSE
 
6.729 3262223.62 0.00 3034550.39 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-17-14
Work Began 02-17-14
Work Completed 01-08-15
Time Computed 04-01-14
Contract Working Days 139
Addl Days Granted 0
Working Days Charged 138
Percent Time Used 99
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2444-01-009
E. DIAZ TRUCKING (3.86%)
TEXAS ALTERNATIVE GRASSER, INC.(0.73%)
DOUBLE A CONTRACTING, L.P. (1.54%)
Contract # 10133019
Totals 3262223.62 0.00 3034550.39 100.0

page 1 | page 2