AVERAGE LOW BID UNIT PRICE - MAINTENANCE - LUFKIN DISTRICT

Last Update: Friday, March 27, 2015
ITEMS 500 2001 TO 545 2005
Items Items Bid Code Range
0100 - 0168
0400 - 0496
0500 - 0545
0618 - 0690
0712 - 0778
1122 - 1138
3267 - 3267
4581 - 4581
6007 - 6044
7210 - 7210
8835 - 8835
500 2001 - 545 2005
Item No Description Units February 28, 2015 Twelve Month Moving Usage
Quantity Avg Bid Quantity Avg Bid
500 2001 MOBILIZATION LS 2.000 37,500.50000 16.000 14,978.29000 16
500 2010 MOBILIZATION (PER CALL OUT) EA     78.000 534.61538 5
500 6001 MOBILIZATION LS 1.000 7,500.00000 1.000 7,500.00000 1
500 6033 MOBILIZATION (CALLOUT) EA 6.000 150.00000 6.000 150.00000 1
502 2001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 4.000 905.00000 51.000 2,032.82353 17
506 2034 TEMPORARY SEDIMENT CONTROL FENCE LF     30.000 1.00000 1
529 2010 CONC CURB AND GUTTER (TY II) (REINF) LF 328.000 23.00000 656.000 23.00000 2
529 2069 CONC CURB AND GUTTER (TY I) (REINF) LF 140.000 17.00000 280.000 17.00000 2
531 2005 CURB RAMPS (TY 1) EA 2.000 1,000.00000 4.000 1,000.00000 2
531 2010 CURB RAMPS (TY 7) EA 1.000 1,159.00000 2.000 1,159.00000 2
531 2015 CONC SIDEWALKS (4") SY     20.000 56.95000 1
531 2041 CURB RAMPS (TY 10) EA 1.000 1,230.00000 2.000 1,230.00000 2
531 2054 CURB RAMPS SY     70.000 102.68000 1
536 2004 CONC DIRECTIONAL ISLAND SY     100.000 74.20000 1
540 2001 MTL W - BEAM GD FEN (TIM POST) LF     3,575.040 22.36359 4
540 2005 TERMINAL ANCHOR SECTION EA     14.000 1.00000 3
540 2010 TRANSITION ADJUSTMENT EA     14.000 2.42857 3
540 2011 MTL BEAM GD FEN TRANS (THRIE - BEAM) EA     34.000 1,004.41176 6
540 2013 MTL BEAM GD FEN TRANS (T101) EA     26.000 900.00000 4
540 2014 MTL W - BEAM GD FEN (LOW FILL CULVERT) LF     225.000 5.33333 3
540 2030 MTL BEAM GD FEN (MOVE AND RESET) LF     300.000 2.33333 3
540 2036 DRIVEWAY TERMINAL ANCHOR SECTION EA     6.000 8.66667 3
540 2037 MTL W - BEAM GD FEN (CRT POST) (SHRT RAD LF     150.000 17.00000 3
540 2038 MTL BM GD FN (TIM POST) (W - BEAM FURN) LF     150.000 2.33333 3
540 2044 DOWNSTREAM ANCHOR TERMINAL (DAT) SECTION EA     24.000 350.00000 3
540 2045 MTL BM GD FEN (LONG SPAN SYSTEM) LF     425.000 2.41176 3
540 2046 MTL BM GD FEN TRANS (NON - SYM) EA     28.000 718.14286 3
540 6001 MTL W - BEAM GD FEN (TIM POST) LF 875.000 25.00000 875.000 25.00000 1
540 6006 MTL BEAM GD FEN TRANS (THRIE - BEAM) EA 10.000 1,000.00000 10.000 1,000.00000 1
540 6008 MTL BEAM GD FEN TRANS (T101) EA 10.000 1,000.00000 10.000 1,000.00000 1
542 2001 REMOVING METAL BEAM GUARD FENCE LF     6,675.000 1.74906 5
542 2002 REMOVING TERMINAL ANCHOR SECTION EA     26.000 51.92308 3
542 2003 RM MTL BM GD FEN TRANS (THRIE - BEAM) EA     26.000 2.53846 3
542 6001 REMOVE METAL BEAM GUARD FENCE LF 100.000 3.00000 100.000 3.00000 1
544 2002 GUARDRAIL END TREATMENT (MOVE & RESET) EA     26.000 77.53846 3
544 2006 GDRAIL END TRT (INST) (WOOD POST) (TY III EA     34.000 2,476.47059 4
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 50.000 500.00000 50.000 500.00000 1
545 2003 CRASH CUSH ATTEN (REMOVE) EA     14.000 339.28571 3
545 2005 CRASH CUSH ATTEN (MOVE & RESET) (FASTRACC EA     12.000 1,500.00000 3