Monthly State Let Construction Report For Lufkin District As Of Jul 14, 2017 Page 3 Of 4

Last Update: Monday, July 17, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyNACOGDOCHES
HighwaySH 7
FromAT FM 2782
To.
CSJ0553-03-033
Proj IDSTP 1702(111)HES
Work TypeINSTALL FLASHING BEACON
 
0.20044900.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-21-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days15
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LUDCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0553-03-033
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05173008
Totals44900.000.000.000.0

CountyNACOGDOCHES
HighwayFM 95
FromAT PARALLEL CREEK
To.
CSJ0706-03-020
Proj IDBR 1502(622)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.2891783241.531721596.6396.5
Work Order10-30-15
Work Began03-01-16
Work Completed
Time Computed03-01-16
Contract Working Days120
Addl Days Granted18
Working Days Charged138
Percent Time Used100
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0706-03-020
AMERICAN REMEDIATION OPTIONS, INC. (5.48)
PANOLA SIGN & BARRICADE, INC. (0.67)
STRIPING TECHNOLOGY, L.P. (0.70)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.29)
Contract #08153239
Totals1783241.5356971.521721596.6396.5

CountySAN AUGUSTINE
HighwayUS 96
FromSHELBY COUNTY LINE
ToFM 3451
CSJ0809-03-038
Proj IDNH 2013(514)
Work TypeADD PASSING LANES AND RECONST PVMT
 
3.8047319958.624805642.9365.6
Work Order11-12-15
Work Began03-30-16
Work Completed
Time Computed03-21-16
Contract Working Days149
Addl Days Granted0
Working Days Charged152
Percent Time Used102
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0809-03-038
PANOLA SIGN & BARRICADE, INC. (0.19)
COLD CREEK CONSTRUCTION, LTD (1.64)
AMERICAN REMEDIATION OPTIONS, INC. (2.74)
A R BROTHERS CONSTRUCTION SERVICES, INC. (4.64)
DUSTROL, INC. (1.52)
LONGVIEW BRIDGE AND ROAD, LTD. (42.07)
STRIPING TECHNOLOGY, L.P. (1.93)
WEST TEXAS RUMBLE STRIP (0.06)
STRIPING SYSTEMS, INC. (0.02)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.89)
Contract #08153048
Totals7319958.62160923.244805642.9365.6

CountySAN AUGUSTINE
HighwayUS 96
FromAT AYISH BAYOU
To.
CSJ0809-04-046
Proj IDBR 1502(202)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.5453951203.543880735.7798.2
Work Order07-02-15
Work Began11-18-15
Work Completed
Time Computed08-02-15
Contract Working Days152
Addl Days Granted26
Working Days Charged174
Percent Time Used97
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0809-04-046
PANOLA SIGN & BARRICADE, INC. (0.26)
MOORE BROTHERS CONSTRUCTION COMPANY (13.90)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.73)
MCL CONTRACTING, LLC (0.14)
CRABTREE BARRICADE SYSTEMS, INC. (0.65)
AMERICAN REMEDIATION OPTIONS, INC. (2.06)
MAC TRANSPORTATION, LTD, L.L.P. (0.00)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.18)
Contract #05153241
Totals3951203.540.003880735.7798.2

CountySHELBY
HighwayFM 417
FromSH 87
ToFM 139
CSJ0810-02-019
Proj IDSTP 2016(808)
Work TypeRECONSTRUCT AND WIDEN PAVEMENT
 
11.2925757568.554003424.7869.5
Work Order05-23-16
Work Began06-22-16
Work Completed
Time Computed06-22-16
Contract Working Days155
Addl Days Granted0
Working Days Charged117
Percent Time Used75
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0810-02-019
DREWERY BROS TREE SERVICE, INC. (3.09)
JE CASEY, LLC (1.42)
PANOLA SIGN & BARRICADE, INC. (0.77)
STRIPING TECHNOLOGY, L.P. (2.28)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (2.29)
FREDONIA CONSTRUCTION SERVICES (0.17)
STRIPING SYSTEMS, INC. (0.03)
AMERICAN REMEDIATION OPTIONS, INC. (1.85)
Contract #03163021
Totals5757568.55637972.274003424.7869.5

CountyPOLK
HighwayCR
FromBLUEWATER RD OVER BLUE BRANCH
To.
CSJ0911-04-034
Proj IDBR 2001(480)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.231885751.00630918.4971.2
Work Order06-02-16
Work Began09-12-16
Work Completed
Time Computed09-01-16
Contract Working Days128
Addl Days Granted0
Working Days Charged97
Percent Time Used75
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0911-04-034
AMERICAN REMEDIATION OPTIONS, INC. (6.59)
PANOLA SIGN & BARRICADE, INC. (1.53)
Contract #04163212
Totals885751.0014700.00630918.4971.2

CountyPOLK
HighwayVA
FromWITHIN LAKE LIVINGSTON STATE PARK
To.
CSJ0911-04-054
Proj IDC 911-4-54
Work TypeREPAIR AND RESURFACE PAVED AREAS
 
0.1002009215.001991296.2599.1
Work Order03-01-16
Work Began04-04-16
Work Completed
Time Computed04-01-16
Contract Working Days127
Addl Days Granted10
Working Days Charged127
Percent Time Used92
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0911-04-054
DREWERY BROS TREE SERVICE, INC. (1.20)
AMERICAN REMEDIATION OPTIONS, INC. (4.01)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.58)
Contract #01163025
Totals2009215.0022587.001991296.2599.1

CountyPOLK
HighwayCR
FromUPPER LEGGETT RD
ToAT TRIB OF BIG SANDY CREEK
CSJ0911-04-060
Proj IDBR 1402(189)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.4411889227.891807743.0895.6
Work Order03-08-16
Work Began07-11-16
Work Completed
Time Computed07-11-16
Contract Working Days177
Addl Days Granted0
Working Days Charged142
Percent Time Used80
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0911-04-060
PANOLA SIGN & BARRICADE, INC. (0.46)
AMERICAN REMEDIATION OPTIONS, INC. (4.65)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.51)
Contract #08153046
Totals1889227.890.001807743.0895.6

CountyPOLK
HighwayCR
FromCARMONA RD AT BRUSHY CREEK
To.
CSJ0911-04-067
Proj IDBR 1502(205)
Work TypeBRIDGE REPLACEMENT
 
0.2251019437.73935029.5091.7
Work Order08-03-16
Work Began11-29-16
Work Completed
Time Computed10-26-16
Contract Working Days121
Addl Days Granted0
Working Days Charged95
Percent Time Used78
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0911-04-067
AMERICAN REMEDIATION OPTIONS, INC. (6.28)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.88)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.00)
MCL CONTRACTING, LLC (0.78)
Contract #06163027
Totals1019437.7384118.95935029.5091.7

CountyPOLK
HighwayCR
FromWELLS LANDING RD AT KICKAPOO CREEK
To.
CSJ0911-04-072
Proj IDBR 2016(770)
Work TypeBRIDGE REPLACEMENT
 
0.2041452873.79774338.9353.2
Work Order01-04-17
Work Began02-22-17
Work Completed
Time Computed02-22-17
Contract Working Days252
Addl Days Granted0
Working Days Charged63
Percent Time Used25
Contractor(s)
CDM HOLDINGS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0911-04-072
SOUTHWEST ENVIRONMENT SERVICES LLC (1.03)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (2.31)
COMEN ENTERPRISE LLC (4.90)
W. W. FOUNDATION DRILLING, LTD. (13.49)
Contract #11163213
Totals1452873.79299610.27774338.9353.2

CountyPOLK
HighwayCR
FromROCK ISLAND RD AT BUNDIX CREEK
To.
CSJ0911-04-080
Proj IDBR 2016(778)
Work TypeBRIDGE REPLACEMENT
 
0.1661091491.65812145.9174.4
Work Order11-22-16
Work Began02-27-17
Work Completed
Time Computed02-20-17
Contract Working Days150
Addl Days Granted0
Working Days Charged72
Percent Time Used48
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0911-04-080
N-LINE TRAFFIC MAINTENANCE, L.P. (0.64)
AMERICAN REMEDIATION OPTIONS, INC. (4.37)
HEMPHILL WBE PILE DRIVING CO. (4.50)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.47)
MCL CONTRACTING, LLC (0.39)
FREDONIA CONSTRUCTION (0.91)
Contract #10163220
Totals1091491.6576848.32812145.9174.4

CountyPOLK
HighwayCR
FromOLD HWY 35 N
ToAT TRIB OF LONG KING CREEK
CSJ0911-04-083
Proj IDBR 2016(781)
Work TypeBRIDGE REPLACEMENT
 
0.067351199.32354039.6099.9
CountyPOLK
HighwayCR
FromOAKDALE LOOP AT KIBBLE CREEK
To.
CSJ0911-04-084
Proj IDBR 2016(782)
Work TypeBRIDGE REPLACEMENT
 
0.096460983.46386125.5083.7
Work Order08-18-16
Work Began11-25-16
Work Completed
Time Computed11-16-16
Contract Working Days83
Addl Days Granted0
Working Days Charged86
Percent Time Used103
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0911-04-083
AMERICAN REMEDIATION OPTIONS, INC. (6.37)
LONESTAR TRAFFIC SAFETY, LLC (0.46)
Contract #07163229
Totals812182.78130219.60740165.1091.3

CountySAN JACINTO
HighwayVA
FromVARIOUS LOCATIONS
ToWITHIN THE CITY OF COLDSPRING
CSJ0911-07-038
Proj IDSTP 2017(251)
Work TypeCONSTRUCT CURB RAMPS
 
0.100646827.00532157.2082.2
Work Order01-10-17
Work Began02-09-17
Work Completed
Time Computed02-09-17
Contract Working Days116
Addl Days Granted0
Working Days Charged70
Percent Time Used60
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0911-07-038
INTERSTATE BARRICADES & MARKINGS, INC. (1.21)
LONESTAR TRAFFIC SAFETY, LLC (0.63)
HOUSTON TREE & LAWN SERVICE (0.46)
WASHBURN PAVING COMPANY (1.68)
Contract #11163021
Totals646827.003640.00532157.2082.2

CountyHOUSTON
HighwayCR
FromCR 1155 AT NECHES RIVER RELIEF
To.
CSJ0911-28-033
Proj IDBR 2014(435)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.070619443.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-16-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days62
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0911-28-033
SOUTHWEST ENVIRONMENT SERVICES LLC (0.75)
DUSTIN ALLEN, INC. (4.06)
PANOLA SIGN & BARRICADE, INC. (0.70)
Contract #04173012
Totals619443.500.000.000.0

CountyHOUSTON
HighwayCR
FromCR 1585 AT SAN PEDRO CREEK
To.
CSJ0911-28-036
Proj IDBR 2014(436)
Work TypeBRIDGE REPLACEMENT
 
0.146763544.08733847.6996.5
Work Order07-28-16
Work Began12-09-16
Work Completed
Time Computed10-26-16
Contract Working Days88
Addl Days Granted0
Working Days Charged93
Percent Time Used105
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0911-28-036
AMERICAN REMEDIATION OPTIONS, INC. (6.74)
FLEX SUPPLY, LLC (0.85)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (7.32)
Contract #06163019
Totals763544.0864146.73733847.6996.5

CountyHOUSTON
HighwayVA
FromWITHIN MISSION TEJAS ST HIST SITE
To.
CSJ0911-28-037
Proj IDC 911-28-37
Work TypeCNSTR NEW ENTRANCE RD & PARKING LOT
 
0.100746460.56732175.6898.0
Work Order12-06-16
Work Began01-03-17
Work Completed
Time Computed01-03-17
Contract Working Days164
Addl Days Granted11
Working Days Charged81
Percent Time Used46
Contractor(s)
PINTO CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0911-28-037
PANOLA SIGN & BARRICADE, INC. (1.11)
AMERICAN REMEDIATION OPTIONS, INC. (1.10)
MOORE BROTHERS CONSTRUCTION COMPANY (24.42)
STRIPING TECHNOLOGY, L.P. (1.07)
COX CONTRACTORS, INC. (12.79)
Contract #11163018
Totals746460.5610010.00732175.6898.0

CountyHOUSTON
HighwayCR
FromCR 1765 AT RICH CREEK
To.
CSJ0911-28-040
Proj IDBR 1602(206)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.066461059.20414164.6489.8
CountyHOUSTON
HighwayCR
FromCR 1680 AT SILVER CREEK
To.
CSJ0911-28-044
Proj IDBR 1602(212)
Work TypeBRIDGE REPLACEMENT
 
0.061346469.10332091.8095.8
CountyHOUSTON
HighwayCR
FromCR 1750 AT RICH CREEK
To.
CSJ0911-28-045
Proj IDBR 1602(205)
Work TypeBRIDGE REPLACEMENT
 
0.073273448.9084900.0031.0
Work Order08-29-16
Work Began12-12-16
Work Completed
Time Computed11-28-16
Contract Working Days168
Addl Days Granted0
Working Days Charged99
Percent Time Used58
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0911-28-040
MORRIS COUNTY CONTRACTORS, L.L.C. (5.17)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.94)
LONESTAR TRAFFIC SAFETY, LLC (0.63)
Contract #07163221
Totals1080977.20124188.64831156.4476.8

CountySHELBY
HighwayCR
FromCR 4059 AT POOR JOE CREEK
To.
CSJ0911-39-038
Proj IDBR 1602(393)
Work TypeBRIDGE REPLACEMENT
 
0.119619833.680.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days144
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0911-39-038
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07173220
Totals619833.680.000.000.0

CountySHELBY
HighwayCR
FromACCESS RD AT TOLEDO BEND RESERVOIR
To.
CSJ0911-39-046
Proj IDBR 2016(605)
Work TypeBRIDGE REPLACEMENT
 
0.2141129593.90905700.9880.1
Work Order12-06-16
Work Began02-06-17
Work Completed
Time Computed02-06-17
Contract Working Days220
Addl Days Granted0
Working Days Charged88
Percent Time Used40
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0911-39-046
PANOLA SIGN & BARRICADE, INC. (1.24)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.48)
HEMPHILL WBE PILE DRIVING CO. (4.30)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.49)
ISAACS CONSTRUCTION SERVICES, LLC. (1.24)
MORRIS COUNTY CONTRACTORS, L.L.C. (5.40)
MCL CONTRACTING, LLC (0.44)
Contract #10163209
Totals1129593.90130812.95905700.9880.1

CountySHELBY
HighwayCR
FromCR 4855 AT BYFIELD CREEK
To.
CSJ0911-39-048
Proj IDBR 1602(394)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.074432714.0065329.0015.0
Work Order05-09-17
Work Began06-26-17
Work Completed
Time Computed06-26-17
Contract Working Days103
Addl Days Granted0
Working Days Charged5
Percent Time Used4
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0911-39-048
HEMPHILL WBE PILE DRIVING CO. (2.49)
Contract #04173224
Totals432714.0065329.0065329.0015.0

page 1 | page 2 | page 3 | page 4