Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyTRINITY
Highway SH 94
From US 287
To 1.659 MI W OF FM 358
CSJ 0319-02-029
Proj ID STP 2015(241)HES
Work Type SAFETY TREAT FIXED OBJECTS
 
20.409 1785216.75 4149.20 1854956.07 99.9
Work Order 12-05-14
Work Began 12-16-14
Work Completed  
Time Computed 12-21-14
Contract Working Days 180
Addl Days Granted 26
Working Days Charged 201
Percent Time Used 97
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 0319-02-029
ODUM SERVICES, L.P.(8.97%)
Contract # 10143222
Totals 1785216.75 4149.20 1854956.07 99.9

CountyHOUSTON
Highway SH 7
From 0.2 MI E OF FM 232
To KENNARD
CSJ 0336-01-046
Proj ID NH 2015(156)
Work Type GRADING, STRUT, BASE, HMAC SURFACE
 
7.057 10296162.55 433599.23 4602728.33 44.7
Work Order 10-28-14
Work Began 01-07-15
Work Completed  
Time Computed 11-13-14
Contract Working Days 390
Addl Days Granted 4
Working Days Charged 160
Percent Time Used 40
Contractor(s)
PINTO CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0336-01-046
INTERSTATE BARRICADES & MARKINGS, INC. (0.87%)
TEX OP CONSTRUCTION, LP(0.06%)
WEST TEXAS RUMBLE STRIP(0.04%)
PANOLA SIGN & BARRICADE, INC.(0.43%)
RICE ENVIRONMENTAL SERVICES(1.77%)
J & M CONTRACTING, COMPANY (9.35%)
SANDHILL FOUNDATION, LLC (1.69%)
MOORE BROTHERS CONSTRUCTION COMPANY( 26.16%)
AMERICAN REMEDIATION OPTIONS, INC. (0.55%)
Contract # 09143203
Totals 10296162.55 433599.23 4602728.33 44.7

CountyHOUSTON
Highway US 287
From LP 304
To TRINITY COUNTY LINE
CSJ 0340-01-040
Proj ID STP 2014(637)HES
Work Type IMPROVE GUARDRAIL AND SAFETY TREAT
 
14.369 1379201.46 0.00 1413898.07 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-10-14
Work Began 08-18-14
Work Completed 12-18-15
Time Computed 07-26-14
Contract Working Days 217
Addl Days Granted 11
Working Days Charged 225
Percent Time Used 98
Contractor(s)
CDM HOLDINGS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0340-01-040
PANOLA SIGN & BARRICADE, INC.(0.97%)
DUSTIN ALLEN, INC. ( 12.41%)
BAHENA CONSTRUCTION CO.,INC. ( 43.28%)
Contract # 05143216
Totals 1379201.46 0.00 1413898.07 100.0

CountyPOLK
Highway US 287
From 2.50 MI W OF US 59
To 2.0 MI W OF US 59
CSJ 0341-02-046
Proj ID STP 1502(212)
Work Type ADD TURN LANES
 
0.593 1220777.00 61671.58 1218970.95 99.8
Work Order 07-22-15
Work Began 08-24-15
Work Completed  
Time Computed 08-22-15
Contract Working Days 55
Addl Days Granted 3
Working Days Charged 52
Percent Time Used 89
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0341-02-046
COWBELL TRAFFIC SERVICES, INC. (0.47%)
STRIPING TECHNOLOGY, L.P.(1.82%)
DREWERY & WHEATON, LLC (2.36%)
TEX OP CONSTRUCTION, LP(1.10%)
FLEX SUPPLY, LLC (0.34%)
J & M CONTRACTING, COMPANY (3.23%)
Contract # 05153252
Totals 1220777.00 61671.58 1218970.95 99.8

CountyPOLK
Highway US 287
From US 59
To TYLER COUNTY LINE
CSJ 0341-03-037
Proj ID STP 2014(925)HESG
Work Type IMPROVE GUARDRAIL AND SAFETY TREAT
 
23.125 928912.62 5758.50 906868.42 97.6
Work Order 09-09-14
Work Began 10-15-14
Work Completed  
Time Computed 09-25-14
Contract Working Days 219
Addl Days Granted 0
Working Days Charged 212
Percent Time Used 96
Contractor(s)
A R BROTHERS CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0341-03-037
PANOLA SIGN & BARRICADE, INC.(1.55%)
RICE ENVIRONMENTAL SERVICES(7.74%)
J.P. ABNER STUMP GRINDING & TREE SERVICE (0.16%)
ACE CONTRACTORS, INC.(7.85%)
FREDONIA CONSTRUCTION SERVICES (0.00%)
Contract # 07143213
Totals 928912.62 5758.50 906868.42 97.6

CountyNACOGDOCHES
Highway SH 204
From CHEROKEE C/L (@ ANGELINA RIVER)
To 0.1 MI E OF FM 2783
CSJ 0450-04-044
Proj ID STP 2014(840)
Work Type OCST AND SUPERPAVE
 
2.556 1010920.03 0.00 989177.48 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-13-14
Work Began 09-30-14
Work Completed 03-25-15
Time Computed 08-29-14
Contract Working Days 28
Addl Days Granted 0
Working Days Charged 47
Percent Time Used 167
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0450-04-044
AMERICAN REMEDIATION OPTIONS, INC. (7.72%)
L. S. EQUIPMENT CO., INC.( 16.08%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.44%)
STRIPING TECHNOLOGY, L.P.(2.38%)
EXPRESS PERSONNEL SERVICES (0.49%)
SPHERION (0.29%)
Contract # 06143031
Totals 1010920.03 0.00 989177.48 100.0

CountyNACOGDOCHES
Highway FM 95
From RUSK COUNTY LINE
To 0.5 MI W OF US 59 IN GARRISON
CSJ 0706-01-013
Proj ID STP 2013(519)HES
Work Type RECONSTRUCT AND WIDEN PAVEMENT
 
3.938 1382155.18 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-10-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 70
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
PINTO CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0706-01-013
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153240
Totals 1382155.18 0.00 0.00 0.0

CountyNACOGDOCHES
Highway FM 95
From AT PARALLEL CREEK
To .
CSJ 0706-03-020
Proj ID BR 1502(622)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.289 1783241.53 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-30-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0706-03-020
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08153239
Totals 1783241.53 0.00 0.00 0.0

CountySHELBY
Highway FM 139
From SH 7
To SH 87
CSJ 0742-01-052
Proj ID STP 2015(314)HRR
Work Type IMPROVE GUARDRAIL AND SAFETY TREAT
 
28.429 1987837.07 91092.56 1983646.83 99.7
Work Order 01-07-15
Work Began 02-18-15
Work Completed  
Time Computed 02-18-15
Contract Working Days 121
Addl Days Granted 0
Working Days Charged 121
Percent Time Used 100
Contractor(s)
A R BROTHERS CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0742-01-052
DUSTIN ALLEN, INC. ( 13.59%)
LONESTAR TRAFFIC SAFETY, LLC (0.59%)
LONGVIEW BRIDGE AND ROAD, LTD. ( 17.65%)
N-LINE TRAFFIC MAINTENANCE, L.P. (5.60%)
STRIPING TECHNOLOGY, L.P.(0.99%)
PINTO CONSTRUCTION CO., INC. (0.37%)
FREDONIA CONSTRUCTION(0.07%)
Contract # 11143218
Totals 1987837.07 91092.56 1983646.83 99.7

CountySAN AUGUSTINE
Highway US 96
From SHELBY COUNTY LINE
To FM 3451
CSJ 0809-03-038
Proj ID NH 2013(514)
Work Type ADD PASSING LANES AND RECONST PVMT
 
3.804 7319958.62 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-12-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 149
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0809-03-038
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08153048
Totals 7319958.62 0.00 0.00 0.0

CountySAN AUGUSTINE
Highway US 96
From AT AYISH BAYOU
To .
CSJ 0809-04-046
Proj ID BR 1502(202)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.545 3951203.54 326946.33 1237618.88 31.3
Work Order 07-02-15
Work Began 11-18-15
Work Completed  
Time Computed 08-02-15
Contract Working Days 152
Addl Days Granted 0
Working Days Charged 21
Percent Time Used 13
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0809-04-046
PANOLA SIGN & BARRICADE, INC.(0.26%)
MOORE BROTHERS CONSTRUCTION COMPANY( 13.90%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.73%)
MCL CONTRACTING, LLC (0.14%)
CRABTREE BARRICADE SYSTEMS, INC. (0.65%)
AMERICAN REMEDIATION OPTIONS, INC. (2.06%)
Contract # 05153241
Totals 3951203.54 326946.33 1237618.88 31.3

CountyANGELINA
Highway VA
From AT VARIOUS LOCATIONS IN LUFKIN
To DISTRICT
CSJ 0911-00-073
Proj ID STP 2014(928)
Work Type CONSTRUCT CURB RAMPS
 
0.001 556965.00 0.00 567183.75 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-12-14
Work Began 10-07-14
Work Completed 07-21-15
Time Computed 09-28-14
Contract Working Days 126
Addl Days Granted 0
Working Days Charged 84
Percent Time Used 66
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0911-00-073
STRIPING TECHNOLOGY, L.P.(2.25%)
CLASSIC TEJAS CONSTRUCTION, INC. (2.80%)
Contract # 07143009
Totals 556965.00 0.00 567183.75 100.0

CountyANGELINA
Highway VA
From AT VARIOUS LOCATIONS IN LUFKIN DIST
To .
CSJ 0911-00-074
Proj ID STP 1502(258)
Work Type CONSTRUCT CURB RAMPS
 
0.001 1038185.70 0.00 347483.53 33.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-11-15
Work Began 01-05-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 53
Percent Time Used 53
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0911-00-074
N-LINE TRAFFIC MAINTENANCE, L.P. (1.80%)
STRIPE-A-ZONE, INC.(2.33%)
MELS ELECTRIC, L.P.( 19.30%)
Contract # 07153263
Totals 1038185.70 0.00 347483.53 33.4

CountyPOLK
Highway VA
From WITHIN LAKE LIVINGSTON STATE PARK
To .
CSJ 0911-04-054
Proj ID C 911-4-54
Work Type REPAIR AND RESURFACE PAVED AREAS
 
0.100 2009215.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 127
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0911-04-054
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01163025
Totals 2009215.00 0.00 0.00 0.0

CountyPOLK
Highway CR
From KELLEY RD OVER MENARD CREEK
To .
CSJ 0911-04-056
Proj ID BR 2014(692)
Work Type BRIDGE REPLACEMENT
 
0.281 707623.10 0.00 655719.14 92.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-26-15
Work Began 09-14-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 250
Addl Days Granted 0
Working Days Charged 80
Percent Time Used 32
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0911-04-056
PANOLA SIGN & BARRICADE, INC.(1.56%)
AMERICAN REMEDIATION OPTIONS, INC. (9.20%)
Contract # 02153220
Totals 707623.10 0.00 655719.14 92.6

CountyPOLK
Highway CR
From DICK SKINNER RD AT TRIB OF NECHES R
To .
CSJ 0911-04-059
Proj ID BR 1402(188)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.413 1215872.88 0.00 24572.16 2.0
Work Order 08-26-15
Work Began 00-00-00
Work Completed  
Time Computed 11-24-15
Contract Working Days 151
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0911-04-059
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07153052
Totals 1215872.88 0.00 24572.16 2.0

CountyPOLK
Highway CR
From UPPER LEGGETT RD
To AT TRIB OF BIG SANDY CREEK
CSJ 0911-04-060
Proj ID BR 1402(189)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.441 1889227.89 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 177
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0911-04-060
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08153046
Totals 1889227.89 0.00 0.00 0.0

CountyNACOGDOCHES
Highway CR
From CR 706 AT YSELETA CREEK
To .
CSJ 0911-08-044
Proj ID BR 2013(438)
Work Type BRIDGE REPLACEMENT
 
0.041 217515.25 0.00 213932.92 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-13-14
Work Began 01-05-15
Work Completed 06-08-15
Time Computed 11-11-14
Contract Working Days 38
Addl Days Granted 0
Working Days Charged 35
Percent Time Used 92
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0911-08-044
AMERICAN REMEDIATION OPTIONS, INC. (5.95%)
BANNER SIGN & BARRICADE, INC. (HOOKS)(0.91%)
Contract # 07143032
Totals 217515.25 0.00 213932.92 100.0

CountyHOUSTON
Highway CR
From CR 3480 AT BIG CREEK TRIBUTARY
To .
CSJ 0911-28-031
Proj ID BR 2014(433)
Work Type BRIDGE REPLACEMENT
 
0.137 748567.80 0.00 223900.20 29.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-04-15
Work Began 01-20-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 68
Addl Days Granted 0
Working Days Charged 7
Percent Time Used 10
Contractor(s)
HARTBEAT CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0911-28-031
DUSTIN ALLEN, INC. (5.05%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.51%)
HEMPHILL PILE DRIVING CO., A CORP. (4.20%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.75%)
Contract # 06153231
Totals 748567.80 0.00 223900.20 29.9

CountySABINE
Highway CR
From ROCK CREEK RD AT ROCK CREEK
To .
CSJ 0911-29-036
Proj ID BR 2012(488)
Work Type BRIDGE REPLACEMENT
 
0.129 436864.83 0.00 466017.52 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-14-13
Work Began 03-04-14
Work Completed 09-15-14
Time Computed 00-00-00
Contract Working Days 89
Addl Days Granted 0
Working Days Charged 76
Percent Time Used 85
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0911-29-036
AMERICAN REMEDIATION OPTIONS, INC. (6.81%)
CRABTREE BARRICADE SYSTEMS, INC. (2.02%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. ( 10.92%)
MESA ROD BUSTERS, INC. (0.59%)
Contract # 04133226
Totals 436864.83 0.00 466017.52 100.0