Monthly State Let Construction Report For Lufkin District As Of Nov 20, 2014 Page 3 Of 3

Last Update: Thursday, November 20, 2014
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHOUSTON
Highway FM 227
From BU 287-V
To 0.5 MI E OF CR 1685
CSJ 0937-02-029
Proj ID STP 2013(546)HES
Work Type PROVIDE ADDITIONAL PAVED SURF WIDTH
 
11.160 4278380.79 393517.64 3720071.79 86.9
Work Order 06-19-13
Work Began 07-10-13
Work Completed  
Time Computed 07-10-13
Contract Working Days 168
Addl Days Granted 0
Working Days Charged 168
Percent Time Used 100
Contractor(s)
L. S. EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0937-02-029
STRIPING TECHNOLOGY, L.P.(2.43%)
ROBINSON CONSTRUCTION(4.56%)
ODUM SERVICES, L.P.(3.30%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.66%)
Contract # 04133219
Totals 4278380.79 393517.64 3720071.79 86.9

CountySABINE
Highway FM 1592
From SH 103
To SH 184
CSJ 1510-01-019
Proj ID STP 2014(747)HRR
Work Type SAFETY TREAT FIXED OBJECTS
 
17.157 1226352.49 188542.29 267062.29 21.7
Work Order 08-29-14
Work Began 09-23-14
Work Completed  
Time Computed 09-14-14
Contract Working Days 160
Addl Days Granted 0
Working Days Charged 31
Percent Time Used 19
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 1510-01-019
ODUM SERVICES, L.P.(7.05%)
Contract # 06143233
Totals 1226352.49 188542.29 267062.29 21.7

CountyHOUSTON
Highway FM 1280
From SH 21
To FM 230
CSJ 1676-02-015
Proj ID STP 2013(394)HES
Work Type PROVIDE ADDITIONAL PAVED SURF WIDTH
 
25.772 4387077.87 122739.10 3932412.10 89.6
Work Order 04-10-13
Work Began 05-20-13
Work Completed  
Time Computed 04-26-13
Contract Working Days 254
Addl Days Granted 0
Working Days Charged 228
Percent Time Used 89
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1676-02-015
COLD CREEK CONSTRUCTION, LTD (1.27%)
J & M CONTRACTING, COMPANY ( 13.60%)
MURRAY CONSTRUCTION(0.75%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.77%)
PROFESSIONAL TRAFFIC CONTROL, LLC(2.07%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.17%)
TRAFCO INDUSTRIES, INC.(0.03%)
NIXON ENGINEERING(0.00%)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC.(0.29%)
Contract # 02133020
Totals 4387077.87 122739.10 3932412.10 89.6

CountyHOUSTON
Highway FM 1733
From SH 21
To SH 7
CSJ 1677-01-015
Proj ID STP 2014(210)HES
Work Type PROVIDE ADDITIONAL PAVED SURF WIDTH
 
10.353 3771800.47 446281.26 3635624.78 96.3
Work Order 01-23-14
Work Began 02-17-14
Work Completed  
Time Computed 02-08-14
Contract Working Days 167
Addl Days Granted 0
Working Days Charged 149
Percent Time Used 89
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1677-01-015
ROADSAFE TRAFFIC SYSTEMS, INC. (2.27%)
ODUM SERVICES, L.P.(1.11%)
MURRAY CONSTRUCTION(0.75%)
J & M CONTRACTING, COMPANY (7.25%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.95%)
DREWERY & WHEATON, LLC (1.65%)
BERTLAND-HILL, LLC (0.89%)
Contract # 11133211
Totals 3771800.47 446281.26 3635624.78 96.3

CountyHOUSTON
Highway FM 2022
From ANDERSON COUNTY LINE
To 0.1 MI N OF FM 3313
CSJ 1875-02-021
Proj ID STP 2013(677)HES
Work Type PROVIDE ADDITIONAL PAVED SURF WIDTH
 
38.913 4505244.42 0.00 4539493.79 99.9
Work Order 07-23-13
Work Began 08-13-13
Work Completed  
Time Computed 08-13-13
Contract Working Days 168
Addl Days Granted 6
Working Days Charged 174
Percent Time Used 100
Contractor(s)
PINTO CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1875-02-021
MURRAY CONSTRUCTION(0.64%)
INTERSTATE BARRICADES & MARKINGS, INC. (1.61%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (0.91%)
ODUM SERVICES, L.P.(3.30%)
COLD CREEK CONSTRUCTION, LTD (2.18%)
PANOLA SIGN & BARRICADE, INC.(0.98%)
MOORE BROTHERS CONSTRUCTION COMPANY( 30.94%)
A R BROTHERS CONSTRUCTION SERVICES, INC. ( 20.26%)
SAND HILL FOUNDATION, LLC(0.11%)
Contract # 05133020
Totals 4505244.42 0.00 4539493.79 99.9

CountyHOUSTON
Highway FM 2423
From BU 287-V
To FM 2022
CSJ 2299-01-007
Proj ID STP 2014(336)HES
Work Type PROVIDE ADDITIONAL PAVED SURF WIDTH
 
5.970 1440516.50 4954.42 1356885.46 94.5
Work Order 02-27-14
Work Began 03-18-14
Work Completed  
Time Computed 03-15-14
Contract Working Days 86
Addl Days Granted 0
Working Days Charged 94
Percent Time Used 109
Contractor(s)
PINTO CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 2299-01-007
SOUTHWEST ENVIRONMENT SERVICES LLC (1.42%)
AMERICAN REMEDIATION OPTIONS, INC. (1.15%)
A R BROTHERS CONSTRUCTION SERVICES, INC. ( 18.69%)
BATTERSON,LLP(2.42%)
EROSION CONTROL MANAGEMENT SERVICES(1.24%)
COLD CREEK CONSTRUCTION, LTD (6.12%)
PANOLA SIGN & BARRICADE, INC.(0.76%)
Contract # 01143014
Totals 1440516.50 4954.42 1356885.46 94.5

CountyNACOGDOCHES
Highway LP 224
From SH 7
To US 59 SOUTH
CSJ 2560-01-072
Proj ID STP 2014(750)HESG
Work Type IMPROVE GUARDRAIL AND SAFETY TREAT
 
11.764 1620204.50 98623.28 98623.28 6.0
Work Order 09-09-14
Work Began 10-10-14
Work Completed  
Time Computed 09-25-14
Contract Working Days 95
Addl Days Granted 0
Working Days Charged 20
Percent Time Used 21
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 2560-01-072
DREWERY & WHEATON, LLC ( 21.10%)
RICE ENVIRONMENTAL SERVICES( 19.52%)
DREWERY"S TREE SERVICE AND CONSTRUCTION CO., INC.(1.57%)
ODUM SERVICES, L.P.(4.07%)
PANOLA SIGN & BARRICADE, INC.(0.62%)
Contract # 06143228
Totals 1620204.50 98623.28 98623.28 6.0

CountyANGELINA
Highway FM 1194
From FM 3150
To SH 94
CSJ 2960-01-010
Proj ID STP 2013(876)
Work Type PROVIDE ADDITIONAL PAVED SURF WIDTH
 
1.742 1209728.83 14240.15 1164302.72 100.0
Work Order 10-17-13
Work Began 11-11-13
Work Completed 07-31-14
Time Computed 11-02-13
Contract Working Days 88
Addl Days Granted 0
Working Days Charged 95
Percent Time Used 107
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 2960-01-010
M BROCK INC(2.06%)
L. S. EQUIPMENT CO., INC.(5.20%)
PANOLA SIGN & BARRICADE, INC.(0.59%)
STRIPING TECHNOLOGY, L.P.(1.48%)
AMERICAN REMEDIATION OPTIONS, INC. (3.63%)
A R BROTHERS CONSTRUCTION SERVICES, INC. ( 14.70%)
DUSTROL, INC.(1.36%)
Contract # 07133006
Totals 1209728.83 14240.15 1164302.72 100.0

CountySHELBY
Highway LP 500
From US 96 (N)
To SH 7 EAST OF CENTER
CSJ 3315-01-016
Proj ID STP 2012(648)
Work Type GR, STR, BASE & SURF
 
3.338 11879175.22 440261.57 7983707.11 67.2
Work Order 09-24-12
Work Began 11-01-12
Work Completed  
Time Computed 11-01-12
Contract Working Days 462
Addl Days Granted 224
Working Days Charged 503
Percent Time Used 73
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 3315-01-016
HIGHWAY INTELLIGENT TRAFFIC SYSTEMS, CORP. (0.89%)
MOORE BROTHERS CONSTRUCTION COMPANY( 21.73%)
NORTH TEXAS REBAR, LLC (0.62%)
RICE ENVIRONMENTAL SERVICES(0.31%)
S & S PAINTING (0.11%)
TEX OP CONSTRUCTION, LP(0.02%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.46%)
W. W. FOUNDATION DRILLING, LTD.(1.07%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(2.32%)
HIGHWAY TECHNOLOGIES, INC. (0.00%)
FBL & ASSOCIATES (0.79%)
S & R DOZER, INC.(0.73%)
SILVA CONTRACTING COMPANY, INC.(2.02%)
MCL CONTRACTING, LLC (0.68%)
L. S. EQUIPMENT CO., INC.(0.19%)
Contract # 07123206
Totals 11879175.22 440261.57 7983707.11 67.2

page 1 | page 2 | page 3