Monthly Local Let Maintenance Report For Lufkin District As Of Jul 14, 2017 Page 3 Of 6

Last Update: Monday, July 17, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHOUSTON
HighwayUS0287
FromVARIOUS LOCATIONS WITHIN
ToHOUSTON COUNTY
CSJ6302-29-001
Proj IDSUP - 630229001
Work TypeREMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.01058420.6341196.4970.5
Work Order10-01-16
Work Began10-01-16
Work Completed
Time Computed10-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged273
Percent Time Used74
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6302-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09161111
Totals58420.633492.4741196.4970.5

CountyTRINITY
HighwaySH0019
FromVARIOUS LOCATION IN
ToTRINITY COUNTY
CSJ6302-30-001
Proj IDSUP - 630230001
Work TypeREMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.01043866.9032492.8474.0
Work Order10-01-16
Work Began10-01-16
Work Completed
Time Computed10-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged273
Percent Time Used74
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6302-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09161118
Totals43866.903552.6632492.8474.0

CountySAN JACINTO
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToSAN JACINTO COUNTY
CSJ6302-31-001
Proj IDSUP - 630231001
Work TypeREMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.01080384.1161272.9576.2
Work Order10-01-16
Work Began10-01-16
Work Completed
Time Computed10-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged273
Percent Time Used74
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6302-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09161117
Totals80384.115068.9361272.9576.2

CountyNACOGDOCHES
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToNACOGDOCHES COUNTY
CSJ6302-32-001
Proj IDSUP - 630232001
Work TypeREMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.010101283.8256698.4155.9
Work Order10-01-16
Work Began10-01-16
Work Completed
Time Computed10-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged273
Percent Time Used74
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6302-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09161113
Totals101283.823387.8156698.4155.9

CountySAN AUGUSTINE
HighwayUS0096
FromVARIOUS LOCATIONS IN
ToSAN AUGUSTINE COUNTY
CSJ6302-33-001
Proj IDSUP - 630233001
Work TypeREMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.01086182.2644046.3051.1
Work Order10-01-16
Work Began10-01-16
Work Completed
Time Computed10-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged273
Percent Time Used74
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6302-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09161119
Totals86182.263386.8644046.3051.1

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToANGELINA COUNTY
CSJ6302-34-001
Proj IDSUP - 630234001
Work TypeREMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.010100797.8889791.9589.0
Work Order10-01-16
Work Began10-01-16
Work Completed
Time Computed10-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged273
Percent Time Used74
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6302-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09161116
Totals100797.885239.2489791.9589.0

CountySABINE
HighwayUS0096
FromVARIOUS LOCATIONS WITHIN
ToSABINE COUNTY
CSJ6302-35-001
Proj IDSUP - 630235001
Work TypeREMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.01041609.7929936.9371.9
Work Order00-00-00
Work Began10-01-16
Work Completed
Time Computed10-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged273
Percent Time Used74
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6302-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09161110
Totals41609.792131.0529936.9371.9

CountySABINE
HighwaySH0021
FromVARIOUS LOCATIONS THROUGHOUT
ToSABINE COUNTY
CSJ6302-70-001
Proj IDRMC - 630270001
Work TypeTREE REMOVAL AND TREE TRIM
 
0.010246250.00212800.0086.4
Work Order10-04-16
Work Began10-17-16
Work Completed
Time Computed10-17-16
Contract Working Days175
Addl Days Granted0
Working Days Charged62
Percent Time Used35
Contractor(s)
K & R CONTRACTORS
SUBCONTRACTOR(S) FOR CCSJ: 6302-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09161109
Totals246250.0012450.00212800.0086.4

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS
ToDISTRICT WIDE
CSJ6303-27-001
Proj IDRMC - 630327001
Work TypeDISTRICT WIDE LARGE SIGN MAINTENANCE
 
0.001174500.00100801.5857.7
Work Order10-26-16
Work Began11-02-16
Work Completed
Time Computed11-02-16
Contract Working Days365
Addl Days Granted0
Working Days Charged241
Percent Time Used66
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6303-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07161101
Totals174500.001275.00100801.5857.7

CountySAN AUGUSTINE
HighwaySH0103
FromVARIOUS LOCATIONS THROUGHOUT
ToSAN AUGUSTINE COUNTY
CSJ6304-02-001
Proj IDRMC - 630402001
Work TypeSAN AUGUSTINE TREE REMOVAL
 
0.010244075.00206460.0084.5
Work Order00-00-00
Work Began09-06-16
Work Completed
Time Computed09-06-16
Contract Working Days175
Addl Days Granted0
Working Days Charged131
Percent Time Used74
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6304-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161103
Totals244075.000.00206460.0084.5

CountyANGELINA
HighwayUS0069
FromVARIOUS LOCATIONS THROUGHOUT ANGELINA
ToCOUNTY
CSJ6304-03-001
Proj IDRMC - 630403001
Work TypeANGELINA COUNTY MBGF
 
0.010272863.30174292.5063.8
Work Order07-29-16
Work Began08-11-16
Work Completed
Time Computed08-01-16
Contract Working Days200
Addl Days Granted0
Working Days Charged25
Percent Time Used12
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6304-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161104
Totals272863.307335.00174292.5063.8

CountyNACOGDOCHES
HighwayUS0059
FromVARIOUS LOCATIONS IN NACOGDOCHES
ToCOUNTY
CSJ6304-40-001
Proj IDRMC - 630440001
Work TypeTREE REMOVAL
 
0.010108750.00205750.0099.9
Work Order08-16-16
Work Began09-06-16
Work Completed
Time Computed09-06-16
Contract Working Days200
Addl Days Granted0
Working Days Charged95
Percent Time Used47
Contractor(s)
K & R CONTRACTORS
SUBCONTRACTOR(S) FOR CCSJ: 6304-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161105
Totals108750.000.00205750.0099.9

CountySABINE
HighwaySH0087
FromVARIOUS LOCATIONS IN
ToSABINE COUNTY
CSJ6304-65-001
Proj IDSUP - 630465001
Work TypePICNIC AREA GRNDS & CURB & GUTTER MAINT
 
0.01071757.4170485.9098.2
Work Order06-28-16
Work Began07-01-16
Work Completed
Time Computed07-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6304-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161132
Totals71757.414758.6370485.9098.2

CountySHELBY
HighwaySH0007
FromVARIOUS LOCATIONS IN
ToSHELBY COUNTY
CSJ6304-67-001
Proj IDSUP - 630467001
Work TypeDELINEATOR, MBOX & CURB & GUTTER MAINT
 
0.010128500.00163734.71100.0
Work Order06-27-16
Work Began07-01-16
Work Completed07-03-17
Time Computed07-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged334
Percent Time Used91
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6304-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161139
Totals128500.0020272.31163734.71100.0

CountyHOUSTON
HighwayUS0287
FromVARIOUS LOCATIONS IN
ToHOUSTON COUNTY
CSJ6304-68-001
Proj IDSUP - 630468001
Work TypePICNIC, GROUNDS & TRAFFIC ISLAND MAINT
 
0.01082013.8028988.5335.3
Work Order12-30-16
Work Began01-01-17
Work Completed
Time Computed01-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged181
Percent Time Used49
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6304-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161102
Totals82013.807314.5828988.5335.3

CountyTRINITY
HighwayUS0287
FromVARIOUS LOCATIONS IN
ToTRINITY COUNTY
CSJ6304-70-001
Proj IDSUP - 630470001
Work TypePICNIC, GROUNDS, TRFC ISLD IN TRINITY CO
 
0.01076420.2565562.0385.7
Work Order00-00-00
Work Began07-01-16
Work Completed
Time Computed07-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6304-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161138
Totals76420.2513780.7265562.0385.7

CountySAN AUGUSTINE
HighwayUS0096
FromVARIOUS LOCATIONS IN
ToSAN AUGUSTINE COUNTY
CSJ6304-74-001
Proj IDSUP - 630474001
Work TypePICNIC AREA GRNDS & C&G MAINT
 
0.01086588.0022501.4025.9
Work Order00-00-00
Work Began07-01-16
Work Completed
Time Computed07-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6304-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161137
Totals86588.002404.9122501.4025.9

CountyPOLK
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToPOLK COUNTY
CSJ6304-76-001
Proj IDSUP - 630476001
Work TypePICNIC & GROUNDS MAINT IN POLK COUNTY
 
0.01036967.1227953.86100.0
Work Order06-27-16
Work Began07-01-16
Work Completed07-03-17
Time Computed07-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6304-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161140
Totals36967.122430.4227953.86100.0

CountySAN AUGUSTINE
HighwayUS0096
FromVARIOUS LOCATIONS IN
ToSAN AUGUSTINE COUNTY
CSJ6305-25-001
Proj IDSUP - 630525001
Work TypeDELINEATOR, OBJ MRK & MAILBOX MAINT
 
0.010100000.00158074.0099.9
Work Order08-25-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged303
Percent Time Used83
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6305-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161142
Totals100000.0018618.00158074.0099.9

CountySABINE
HighwayUS0096
FromVARIOUS LOCATIONS IN
ToSABINE COUNTY
CSJ6305-26-001
Proj IDSUP - 630526001
Work TypeDELINEATOR, OBJ MRK & MAILBOX MAINT
 
0.010100000.00124335.0099.9
Work Order09-01-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged303
Percent Time Used83
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6305-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161141
Totals100000.0011369.00124335.0099.9