Monthly Local Let Maintenance Report For Lufkin District As Of Mar 10, 2015 Page 3 Of 6

Last Update: Wednesday, March 11, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountySAN JACINTO
Highway SH0150
From VARIOUS ROADS IN
To SAN JACINTO COUNTY
CSJ 6269-10-001
Proj ID RMC - 626910001
Work Type DITCH AND CULVERT CLEANING
 
0.100 218860.00 0.00 218750.00 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-23-14
Work Began 06-30-14
Work Completed 09-02-14
Time Computed 07-01-14
Contract Working Days 80
Addl Days Granted 0
Working Days Charged 25
Percent Time Used 31
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6269-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141102
Totals 218860.00 0.00 218750.00 100.0

CountyPOLK
Highway US0059
From VARIOUS ROADS IN
To POLK COUNTY
CSJ 6269-41-001
Proj ID RMC - 626941001
Work Type REPAIR / UPGRADE METAL BEAM GUARD FENCE
 
0.010 227738.50 2282.00 89769.16 39.4
Work Order 06-25-14
Work Began 07-24-14
Work Completed  
Time Computed 07-01-14
Contract Working Days 200
Addl Days Granted 0
Working Days Charged 35
Percent Time Used 17
Contractor(s)
CKORP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6269-41-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141109
Totals 227738.50 2282.00 89769.16 39.4

CountyNACOGDOCHES
Highway US0059
From VARIOUS LOCATIONS IN THE NACOGDOCHES
To MAINTENANCE AREA
CSJ 6269-42-001
Proj ID RMC - 626942001
Work Type TREE TRIM AND REMOVAL OF TREES & LIMBS
 
0.100 249875.00 0.00 35395.00 14.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-21-14
Work Began 07-22-14
Work Completed  
Time Computed 07-22-14
Contract Working Days 175
Addl Days Granted 0
Working Days Charged 98
Percent Time Used 56
Contractor(s)
DEREK CRAWFORD
SUBCONTRACTOR(S) FOR CCSJ: 6269-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04141104
Totals 249875.00 0.00 35395.00 14.1

CountyPOLK
Highway US0059
From VARIOUS LOCATIONS IN POLK,
To SAN JACINTO AND TRINITY CO.
CSJ 6270-39-001
Proj ID RMC - 627039001
Work Type INSTALLATION OF RAISED PAVEMENT MARKERS
 
0.010 236350.00 0.00 77206.78 32.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 08-11-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 202
Percent Time Used 55
Contractor(s)
BRYDL CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6270-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07141103
Totals 236350.00 0.00 77206.78 32.6

CountyHOUSTON
Highway SH0021
From VARIOUS LOCATIONS ALONG SH 21 W
To AND US 287 N IN HOUSTON COUNTY
CSJ 6271-50-001
Proj ID RMC - 627150001
Work Type DITCH AND CULVERT CLEANING
 
0.100 96560.00 0.00 185250.00 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-28-14
Work Began 08-01-14
Work Completed  
Time Computed 08-01-14
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 25
Percent Time Used 62
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6271-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141104
Totals 96560.00 0.00 185250.00 99.9

CountySABINE
Highway US0096
From VARIOUS LOCATIONS ALONG US 96, SH 103
To FM 1592 AND SH 184 IN SABINE COUNTY
CSJ 6271-51-001
Proj ID RMC - 627151001
Work Type DITCH AND CULVERT CLEANING
 
0.100 142310.00 0.00 161900.00 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-18-14
Work Began 09-02-14
Work Completed  
Time Computed 09-02-14
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 24
Percent Time Used 26
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6271-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141105
Totals 142310.00 0.00 161900.00 99.9

CountySABINE
Highway US0096
From VARIOUS LOCATIONS WITHIN
To SABINE MAINTENANCE AREAS
CSJ 6271-52-001
Proj ID RMC - 627152001
Work Type REMOVAL OF TREES AND BRUSH CONTROL
 
0.100 231955.00 17337.00 190156.00 81.9
Work Order 08-18-14
Work Began 09-15-14
Work Completed  
Time Computed 09-02-14
Contract Working Days 175
Addl Days Granted 0
Working Days Charged 86
Percent Time Used 49
Contractor(s)
ALARCON CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6271-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141106
Totals 231955.00 17337.00 190156.00 81.9

CountyANGELINA
Highway US0059
From VARIOUS LOCATIONS IN ANGELINA,
To HOUSTON AND NACOGDOCHES CO.
CSJ 6271-87-001
Proj ID RMC - 627187001
Work Type INSTALLATION OF RAISED PAVEMENT MARKERS
 
0.010 231600.00 0.00 89341.68 38.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 08-11-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 202
Percent Time Used 55
Contractor(s)
BRYDL CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6271-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07141102
Totals 231600.00 0.00 89341.68 38.5

CountySHELBY
Highway US0059
From VARIOUS LOCATIONS IN SHELBY,
To SAN AUGUSTINE AND SABINE CO.
CSJ 6271-88-001
Proj ID RMC - 627188001
Work Type INSTALLATION OF RAISED PAVEMENT MARKERS
 
0.010 231600.00 0.00 32955.64 14.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 08-11-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 202
Percent Time Used 55
Contractor(s)
BRYDL CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6271-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07141101
Totals 231600.00 0.00 32955.64 14.2

CountyANGELINA
Highway US0059
From VARIOUS LOCATIONS WITHIN
To LUFKIN DISTRICT
CSJ 6271-89-001
Proj ID RMC - 627189001
Work Type DISTRICT WIDE SIGNAL MAINTENANCE
 
0.010 309710.98 26850.83 134365.83 43.3
Work Order 09-25-14
Work Began 10-02-14
Work Completed  
Time Computed 10-02-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 150
Percent Time Used 41
Contractor(s)
SOUTH TEXAS ILLUMINATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6271-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07141104
Totals 309710.98 26850.83 134365.83 43.3

CountyANGELINA
Highway US0059
From VARIOUS LOCATIONS WITHIN
To THE LUFKIN DISTRICT
CSJ 6271-90-001
Proj ID RMC - 627190001
Work Type ILLUMINATION MAINTENANCE
 
0.010 151904.00 13079.96 225332.73 99.9
Work Order 08-11-14
Work Began 08-11-14
Work Completed  
Time Computed 08-18-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 202
Percent Time Used 55
Contractor(s)
LUDCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6271-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07141105
Totals 151904.00 13079.96 225332.73 99.9

CountyHOUSTON
Highway SH0021
From VARIOUS LOCATIONS IN THE HOUSTON
To COUNTY MAINTENANCE AREA
CSJ 6272-19-001
Proj ID RMC - 627219001
Work Type TREE TRIMMING, BRUSH AND TREE REMOVAL
 
0.010 169330.00 0.00 198023.00 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-16-14
Work Began 08-04-14
Work Completed 10-31-14
Time Computed 08-01-14
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 46
Percent Time Used 30
Contractor(s)
ALARCON CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6272-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141110
Totals 169330.00 0.00 198023.00 100.0

CountySABINE
Highway SH0087
From VARIOUS LOCATIONS IN THE SABINE
To COUNTY MAINTENANCE AREA
CSJ 6272-20-001
Proj ID RMC - 627220001
Work Type REP AND MAINT OF MBGF
 
0.010 138755.40 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-26-15
Work Began 02-02-15
Work Completed  
Time Computed 02-01-15
Contract Working Days 200
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6272-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07141108
Totals 138755.40 0.00 0.00 0.0

CountySHELBY
Highway SH0007
From VARIOUS LOCATIONS WITHIN
To SHELBY COUNTY
CSJ 6273-29-001
Proj ID SUP - 627329001
Work Type REMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.010 150166.20 6787.73 72202.25 48.0
Work Order 05-25-14
Work Began 06-02-14
Work Completed  
Time Computed 06-02-14
Contract Working Days 190
Addl Days Granted 0
Working Days Charged 97
Percent Time Used 51
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6273-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141135
Totals 150166.20 6787.73 72202.25 48.0

CountyPOLK
Highway US0059
From VARIOUS LOCATION IN
To POLK COUNTY
CSJ 6273-30-001
Proj ID SUP - 627330001
Work Type REMOVAL AND DISPOSAL OF LITTER FROM ROW
 
0.010 100617.11 13164.13 78033.60 77.5
Work Order 05-30-14
Work Began 06-02-14
Work Completed  
Time Computed 06-02-14
Contract Working Days 190
Addl Days Granted 0
Working Days Charged 95
Percent Time Used 50
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6273-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141130
Totals 100617.11 13164.13 78033.60 77.5

CountyHOUSTON
Highway US0287
From VARIOUS LOCATIONS WITHIN
To HOUSTON COUNTY
CSJ 6273-31-001
Proj ID SUP - 627331001
Work Type REMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.010 53966.10 2749.56 24103.36 44.6
Work Order 05-25-14
Work Began 06-02-14
Work Completed  
Time Computed 06-02-14
Contract Working Days 190
Addl Days Granted 0
Working Days Charged 61
Percent Time Used 32
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6273-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141136
Totals 53966.10 2749.56 24103.36 44.6

CountyTRINITY
Highway SH0019
From VARIOUS LOCATIONS WITHIN
To TRINITY COUNTY
CSJ 6273-32-001
Proj ID SUP - 627332001
Work Type REMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.010 30679.43 3077.01 19906.41 64.8
Work Order 05-25-14
Work Began 06-02-14
Work Completed  
Time Computed 06-02-14
Contract Working Days 190
Addl Days Granted 0
Working Days Charged 51
Percent Time Used 26
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6273-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141134
Totals 30679.43 3077.01 19906.41 64.8

CountySAN JACINTO
Highway US0059
From VARIOUS LOCATIONS WITHIN
To SAN JACINTO COUNTY
CSJ 6273-33-001
Proj ID SUP - 627333001
Work Type REMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.010 103857.18 7702.57 71173.09 68.5
Work Order 05-25-14
Work Began 06-02-14
Work Completed  
Time Computed 06-02-14
Contract Working Days 190
Addl Days Granted 0
Working Days Charged 84
Percent Time Used 44
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6273-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141137
Totals 103857.18 7702.57 71173.09 68.5

CountyNACOGDOCHES
Highway US0059
From VARIOUS LOCATIONS WITHIN
To NACOGDOCHES COUNTY
CSJ 6273-34-001
Proj ID SUP - 627334001
Work Type REMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.010 91651.16 4702.89 43250.44 47.1
Work Order 05-30-14
Work Began 06-02-14
Work Completed  
Time Computed 06-02-14
Contract Working Days 190
Addl Days Granted 0
Working Days Charged 109
Percent Time Used 57
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6273-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141132
Totals 91651.16 4702.89 43250.44 47.1

CountySAN AUGUSTINE
Highway US0096
From VARIOUS LOCATIONS WITHIN
To SAN AUGUSTINE COUNTY
CSJ 6273-35-001
Proj ID SUP - 627335001
Work Type REMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.010 78790.92 4970.99 41359.26 52.4
Work Order 05-30-14
Work Began 06-02-14
Work Completed  
Time Computed 06-02-14
Contract Working Days 190
Addl Days Granted 0
Working Days Charged 82
Percent Time Used 43
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6273-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141131
Totals 78790.92 4970.99 41359.26 52.4