Monthly Local Let Maintenance Report For Lufkin District As Of Mar 13, 2024 Page 3 Of 6

Last Update: Wednesday, March 13, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyNACOGDOCHES
HighwayFM0343
FromNACOGDOCHES COUNTY MAINTENANCE YARD
ToNACOGDOCHES COUNTY MAINTENANCE YARD
CSJ6438-85-001
Proj IDMMC - 643885001
Work TypeFLEXIBLE BASE
 
0.010200000.00235506.5099.9
Work Order00-00-00
Work Began05-01-23
Work Completed
Time Computed05-01-23
Contract Working Days120
Addl Days Granted240
Working Days Charged305
Percent Time Used84
Contractor(s)
TOUCHSTONE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6438-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04231161
Totals200000.000.00235506.5099.9

CountyTRINITY
HighwayUS0287
FromVARIOUS LIMITS IN TRINITY
ToCOUNTY MAINTENANCE SECTIONS
CSJ6439-84-001
Proj IDRMC - 643984001
Work TypeCULVERT CLEANING
 
0.010228040.00247813.5099.9
Work Order09-25-23
Work Began09-25-23
Work Completed
Time Computed09-25-23
Contract Working Days47
Addl Days Granted0
Working Days Charged33
Percent Time Used70
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6439-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08231103
Totals228040.000.00247813.5099.9

CountySHELBY
HighwayFM3343
FromSHELBY COUNTY MAINTENANCE YARD
ToSHELBY COUNTY MAINTENANCE YARD
CSJ6439-96-001
Proj IDMMC - 643996001
Work TypeFLEXIBLE BASE
 
0.010299460.00774140.3799.9
Work Order06-14-23
Work Began06-15-23
Work Completed
Time Computed06-15-23
Contract Working Days120
Addl Days Granted240
Working Days Charged260
Percent Time Used72
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6439-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05231160
Totals299460.000.00774140.3799.9

CountySAN JACINTO
HighwaySH0150
FromSAN JACINTO COUNTY MAINTENANCE YARD
ToSAN JACINTO COUNTY MAINTENANCE YARD
CSJ6440-10-001
Proj IDMMC - 644010001
Work TypeHYDRAULIC CEMENT
 
0.01060180.000.000.0
Work Order00-00-00
Work Began06-01-23
Work Completed
Time Computed06-01-23
Contract Working Days120
Addl Days Granted240
Working Days Charged274
Percent Time Used76
Contractor(s)
TOUCHSTONE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6440-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05231161
Totals60180.000.000.000.0

CountySHELBY
HighwayFM3343
FromSHELBY COUNTY MAINTENANCE YARD
ToSHELBY COUNTY MAINTENANCE YARD
CSJ6440-13-001
Proj IDMMC - 644013001
Work TypeHYDRAULIC CEMENT
 
0.010105825.00130414.0299.9
Work Order06-14-23
Work Began06-15-23
Work Completed
Time Computed06-15-23
Contract Working Days120
Addl Days Granted240
Working Days Charged260
Percent Time Used72
Contractor(s)
AKA-MATERIALS
SUBCONTRACTOR(S) FOR CCSJ: 6440-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05231162
Totals105825.000.00130414.0299.9

CountySHELBY
HighwayUS0084
FromSHELBY COUNTY MAINTENANCE YARD
ToSHELBY COUNTY MAINTENANCE YARD
CSJ6441-70-001
Proj IDMMC - 644170001
Work TypeAGGREGATE
 
0.01080580.00791398.3599.9
Work Order06-14-23
Work Began06-15-23
Work Completed
Time Computed06-15-23
Contract Working Days120
Addl Days Granted240
Working Days Charged260
Percent Time Used72
Contractor(s)
ARCOSA LWS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6441-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05231163
Totals80580.00293726.89791398.3599.9

CountySAN JACINTO
HighwayUS0059
FromSAN JACINTO COUNTY
ToVARIOUS LOCATIONS
CSJ6442-56-001
Proj IDRMC - 644256001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
0.010183000.0062540.0034.1
Work Order00-00-00
Work Began09-05-23
Work Completed
Time Computed09-05-23
Contract Working Days365
Addl Days Granted0
Working Days Charged178
Percent Time Used48
Contractor(s)
BA NEWTON'S ENTERPRISES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6442-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07231101
Totals183000.0032050.0062540.0034.1

CountySABINE
HighwayUS0096
FromVARIOUS LOCATIONS WITHIN THE
ToSABINE COUNTY MAINTENANCE SECTION
CSJ6442-70-001
Proj IDRMC - 644270001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010146157.5028025.0019.1
Work Order08-01-23
Work Began08-01-23
Work Completed
Time Computed08-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged213
Percent Time Used58
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6442-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06231104
Totals146157.500.0028025.0019.1

CountyANGELINA
HighwayUS0059
FromANGELINA COUNTY
ToVARIOUS LOCATIONS
CSJ6442-72-001
Proj IDRMC - 644272001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010154770.00111710.0072.1
Work Order00-00-00
Work Began11-01-23
Work Completed
Time Computed11-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged121
Percent Time Used33
Contractor(s)
AUSTIN BARRICADE COMPANY, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6442-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08231104
Totals154770.0010013.00111710.0072.1

CountySHELBY
HighwaySH0007
FromSHELBY COUNTY MAINTENANCE YARD
ToSHELBY COUNTY MAINTENANCE YARD
CSJ6442-76-001
Proj IDMMC - 644276001
Work TypeASPHALTIC PATCHING MATERIAL
 
0.01016533.0030070.7899.9
Work Order06-14-23
Work Began06-15-23
Work Completed
Time Computed06-15-23
Contract Working Days120
Addl Days Granted240
Working Days Charged229
Percent Time Used63
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6442-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05231164
Totals16533.000.0030070.7899.9

CountyNACOGDOCHES
HighwayUS0059
FromNACOGDOCHES COUNTY MAINTENANCE
ToVARIOUS LOCATIONS
CSJ6442-88-001
Proj IDSUP - 644288001
Work TypeCURB & GUTTER MAINT
 
0.01048413.766040.4112.4
Work Order00-00-00
Work Began06-01-23
Work Completed
Time Computed06-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged274
Percent Time Used75
Contractor(s)
WORKQUEST
OAK CREEK DAY HABILITATION/VOCATIONAL CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6442-88-001
OAK CREEK DAY HABILITATION/VOCATION CENTER (0.00)
Contract #05231131
Totals48413.763539.166040.4112.4

CountySHELBY
HighwayUS0096
FromVARIOUS LOCATIONS WITHIN THE SHELBY
ToSHELBY COUNTY MAINTENANCE SECTION
CSJ6443-20-001
Proj IDRMC - 644320001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010168134.0070760.0042.0
Work Order11-01-23
Work Began11-01-23
Work Completed
Time Computed11-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged121
Percent Time Used33
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6443-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09231104
Totals168134.0020720.0070760.0042.0

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS
ToDISTRICTWIDE
CSJ6443-36-001
Proj IDRMC - 644336001
Work TypeILLUMINATION MAINTENANCE
 
0.010255647.00211972.7182.9
Work Order07-18-23
Work Began07-25-23
Work Completed
Time Computed07-25-23
Contract Working Days365
Addl Days Granted0
Working Days Charged220
Percent Time Used60
Contractor(s)
SNOWHILL CONTRACTING LLC
SUBCONTRACTOR(S) FOR CCSJ: 6443-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06231103
Totals255647.0017763.80211972.7182.9

CountySHELBY
HighwaySH0007
FromSHELBY COUNTY MAINTENANCE SECTION
ToVARIOUS LOCATIONS
CSJ6443-64-001
Proj IDRMC - 644364001
Work TypeTREE TRIMMING
 
191500.00116805.0060.9
Work Order11-01-23
Work Began11-01-23
Work Completed
Time Computed11-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged121
Percent Time Used33
Contractor(s)
K & R CONTRACTORS
SUBCONTRACTOR(S) FOR CCSJ: 6443-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09231105
Totals191500.0057125.00116805.0060.9

CountyHOUSTON
HighwaySL0304
FromHOUSTON COUNTY
ToVARIOUS LOCATIONS
CSJ6443-96-001
Proj IDSUP - 644396001
Work TypeLITTER REMOVAL
 
0.01068553.4423217.4333.8
Work Order00-00-00
Work Began09-01-23
Work Completed
Time Computed09-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged182
Percent Time Used49
Contractor(s)
WORKQUEST
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6443-96-001
BURKE CENTER (0.00)
Contract #08231130
Totals68553.445203.5623217.4333.8

CountySHELBY
HighwaySH0007
FromSHELBY COUNTY MAINTENANCE
ToVARIOUS LOCATIONS
CSJ6443-98-001
Proj IDSUP - 644398001
Work TypeGROUNDS MAINTENANCE
 
0.01073432.4346983.0563.9
Work Order09-01-23
Work Began09-01-23
Work Completed
Time Computed09-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged182
Percent Time Used49
Contractor(s)
WORKQUEST
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6443-98-001
BURKE CENTER (0.00)
Contract #08231131
Totals73432.4313374.6646983.0563.9

CountySHELBY
HighwaySH0007
FromSHELBY COUNTY MAINTENANCE SECTION
ToSHELBY COUNTY MAINTENANCE SECTION
CSJ6444-02-001
Proj IDMMC - 644402001
Work TypeHOT MIX
 
0.010220000.001798811.9799.9
Work Order06-15-23
Work Began06-26-23
Work Completed
Time Computed06-26-23
Contract Working Days120
Addl Days Granted240
Working Days Charged249
Percent Time Used69
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6444-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06231161
Totals220000.00619059.461798811.9799.9

CountyNACOGDOCHES
HighwayFM0343
FromNACOGDOCHES COUNTY MAINTENANCE
ToNACOGDOCHES COUNTY MAINTENANCE
CSJ6444-04-001
Proj IDMMC - 644404001
Work TypeHOT MIX
 
0.010230800.00317553.7199.9
Work Order00-00-00
Work Began07-01-23
Work Completed
Time Computed07-01-23
Contract Working Days120
Addl Days Granted240
Working Days Charged244
Percent Time Used67
Contractor(s)
LONGVIEW ASPHALT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6444-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06231162
Totals230800.0083631.24317553.7199.9

CountyPOLK
HighwayUS0059
FromPOLK COUNTY MAINTENANCE
ToPOLK COUNTY MAINTENANCE
CSJ6444-06-001
Proj IDMMC - 644406001
Work TypeHYDRAULIC CEMENT
 
0.01098600.0084348.4085.5
Work Order00-00-00
Work Began07-01-23
Work Completed
Time Computed07-01-23
Contract Working Days120
Addl Days Granted240
Working Days Charged244
Percent Time Used67
Contractor(s)
AKA-MATERIALS
SUBCONTRACTOR(S) FOR CCSJ: 6444-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06231165
Totals98600.000.0084348.4085.5

CountyANGELINA
HighwayBU0069J
FromANGELINA COUNTY MAINTENANCE YARD
ToANGELINA COUNTY MAINTENANCE YARD
CSJ6445-47-001
Proj IDMMC - 644547001
Work TypeHYDRAULIC CEMENT
 
0.01031050.0014604.8047.0
Work Order00-00-00
Work Began06-27-23
Work Completed
Time Computed06-27-23
Contract Working Days120
Addl Days Granted240
Working Days Charged248
Percent Time Used68
Contractor(s)
AKA-MATERIALS
SUBCONTRACTOR(S) FOR CCSJ: 6445-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06231163
Totals31050.000.0014604.8047.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6