Monthly Local Let Maintenance Report For Lufkin District As Of Aug 12, 2014 Page 4 Of 5

Last Update: Tuesday, August 12, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountySHELBY
Highway SH0007
From VARIOUS LOCATIONS WITHIN
To SHELBY COUNTY
CSJ 6273-29-001
Proj ID SUP - 627329001
Work Type REMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.010 150166.20 2241.77 9917.35 6.6
Work Order 05-25-14
Work Began 06-02-14
Work Completed  
Time Computed 06-02-14
Contract Working Days 190
Addl Days Granted 0
Working Days Charged 8
Percent Time Used 4
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6273-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141135
Totals 150166.20 2241.77 9917.35 6.6

CountyPOLK
Highway US0059
From VARIOUS LOCATION IN
To POLK COUNTY
CSJ 6273-30-001
Proj ID SUP - 627330001
Work Type REMOVAL AND DISPOSAL OF LITTER FROM ROW
 
0.010 100617.11 0.00 5025.94 4.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-30-14
Work Began 06-02-14
Work Completed  
Time Computed 06-02-14
Contract Working Days 190
Addl Days Granted 0
Working Days Charged 13
Percent Time Used 6
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6273-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141130
Totals 100617.11 0.00 5025.94 4.9

CountyHOUSTON
Highway US0287
From VARIOUS LOCATIONS WITHIN
To HOUSTON COUNTY
CSJ 6273-31-001
Proj ID SUP - 627331001
Work Type REMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.010 53966.10 1370.58 5156.49 9.5
Work Order 05-25-14
Work Began 06-02-14
Work Completed  
Time Computed 06-02-14
Contract Working Days 190
Addl Days Granted 0
Working Days Charged 11
Percent Time Used 5
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6273-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141136
Totals 53966.10 1370.58 5156.49 9.5

CountyTRINITY
Highway SH0019
From VARIOUS LOCATIONS WITHIN
To TRINITY COUNTY
CSJ 6273-32-001
Proj ID SUP - 627332001
Work Type REMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.010 30679.43 1292.50 2597.90 8.4
Work Order 05-25-14
Work Began 06-02-14
Work Completed  
Time Computed 06-02-14
Contract Working Days 190
Addl Days Granted 0
Working Days Charged 9
Percent Time Used 4
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6273-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141134
Totals 30679.43 1292.50 2597.90 8.4

CountySAN JACINTO
Highway US0059
From VARIOUS LOCATIONS WITHIN
To SAN JACINTO COUNTY
CSJ 6273-33-001
Proj ID SUP - 627333001
Work Type REMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.010 103857.18 6099.68 14033.26 13.5
Work Order 05-25-14
Work Began 06-02-14
Work Completed  
Time Computed 06-02-14
Contract Working Days 190
Addl Days Granted 0
Working Days Charged 18
Percent Time Used 9
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6273-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141137
Totals 103857.18 6099.68 14033.26 13.5

CountyNACOGDOCHES
Highway US0059
From VARIOUS LOCATIONS WITHIN
To NACOGDOCHES COUNTY
CSJ 6273-34-001
Proj ID SUP - 627334001
Work Type REMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.010 91651.16 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-30-14
Work Began 06-02-14
Work Completed  
Time Computed 06-02-14
Contract Working Days 190
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6273-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141132
Totals 91651.16 0.00 0.00 0.0

CountySAN AUGUSTINE
Highway US0096
From VARIOUS LOCATIONS WITHIN
To SAN AUGUSTINE COUNTY
CSJ 6273-35-001
Proj ID SUP - 627335001
Work Type REMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.010 78790.92 5615.68 9734.76 12.3
Work Order 05-30-14
Work Began 06-02-14
Work Completed  
Time Computed 06-02-14
Contract Working Days 190
Addl Days Granted 0
Working Days Charged 18
Percent Time Used 9
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6273-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141131
Totals 78790.92 5615.68 9734.76 12.3

CountyANGELINA
Highway US0059
From VARIOUS LOCATIONS WITHIN
To ANGELINA COUNTY
CSJ 6273-36-001
Proj ID SUP - 627336001
Work Type REMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.010 145010.45 0.00 0.00 0.0
Work Order 05-25-14
Work Began 06-02-14
Work Completed  
Time Computed 06-02-14
Contract Working Days 190
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6273-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141133
Totals 145010.45 0.00 0.00 0.0

CountySABINE
Highway US0096
From VARIOUS LOCATIONS WITHIN
To SABINE COUNTY
CSJ 6273-37-001
Proj ID SUP - 627337001
Work Type REMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.010 60374.52 0.00 0.00 0.0
Work Order 05-25-14
Work Began 06-02-14
Work Completed  
Time Computed 06-02-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6273-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141138
Totals 60374.52 0.00 0.00 0.0

CountySAN JACINTO
Highway US0190
From VARIOUS LOCATIONS IN THE
To SAN JACINTO MAINTENANCE AREA
CSJ 6273-40-001
Proj ID RMC - 627340001
Work Type HIGH EDGE REMOVAL
 
0.010 63250.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-08-14
Work Began 00-00-00
Work Completed  
Time Computed 08-12-14
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6273-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07141107
Totals 63250.00 0.00 0.00 0.0

CountyPOLK
Highway US0059
From VARIOUS LOCATIONS WITHIN
To POLK COUNTY
CSJ 6273-59-001
Proj ID SUP - 627359001
Work Type PICNIC AND GROUNDS MAINTENANCE
 
0.010 36967.12 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-27-14
Work Began 07-01-14
Work Completed  
Time Computed 07-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TIBH INDUSTRIES, INC.
OAK CREEK DAY HABILITATION/VOCATION CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6273-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06141131
Totals 36967.12 0.00 0.00 0.0

CountyNACOGDOCHES
Highway FM1638
From VARIOUS LOCATIONS IN
To NACOGDOCHES COUNTY
CSJ 6274-08-001
Proj ID RMC - 627408001
Work Type DITCH AND CULVERT CLEANING
 
0.010 111960.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6274-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07141106
Totals 111960.00 0.00 0.00 0.0

CountyANGELINA
Highway US0059
From VARIOUS LOCATIONS WITHIN
To LUFKIN DISTRICT
CSJ 6274-25-001
Proj ID RMC - 627425001
Work Type INSTALLATION OF THERMOPLASTIC STRIPING
 
0.010 234861.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
PROFESSIONAL TRAFFIC CONTROL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6274-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07141110
Totals 234861.00 0.00 0.00 0.0

CountyANGELINA
Highway US0059
From VARIOUS LOCATIONS WITHIN
To LUFKIN DISTRICT
CSJ 6274-26-001
Proj ID RMC - 627426001
Work Type INSTALLATION OF WATERBASE STRIPING
 
0.010 244706.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
PROFESSIONAL TRAFFIC CONTROL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6274-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07141111
Totals 244706.00 0.00 0.00 0.0

CountySABINE
Highway SH0087
From VARIOUS LOCATIONS WITHIN
To SABINE COUNTY
CSJ 6275-13-001
Proj ID SUP - 627513001
Work Type PICNIC, GROUNDS, CURB & GUTTER MAINT
 
0.010 71757.41 4394.90 4394.90 6.4
Work Order 06-27-14
Work Began 07-01-14
Work Completed  
Time Computed 07-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 20
Percent Time Used 5
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6275-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06141130
Totals 71757.41 4394.90 4394.90 6.4

CountySABINE
Highway US0096
From VARIOUS LOCTIONS WITHIN
To SABINE COUNTY
CSJ 6275-15-001
Proj ID SUP - 627515001
Work Type MAILBOX AND DELINEATOR MAINTENANCE
 
0.010 100000.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-27-14
Work Began 07-01-14
Work Completed  
Time Computed 07-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6275-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06141132
Totals 100000.00 0.00 0.00 0.0

CountySHELBY
Highway US0096
From VARIOUS LOCATIONS WITHIN
To SHELBY COUNTY
CSJ 6275-16-001
Proj ID SUP - 627516001
Work Type PICNIC, GROUNDS AND TRAFFIC ISLAND MAINT
 
0.010 65773.00 6499.00 6499.00 9.8
Work Order 06-27-14
Work Began 07-01-14
Work Completed  
Time Computed 07-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 15
Percent Time Used 4
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6275-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06141133
Totals 65773.00 6499.00 6499.00 9.8

CountySAN JACINTO
Highway US0059
From VARIOUS LOCATIONS WITHIN
To SAN JACINTO_COUNTY
CSJ 6275-17-001
Proj ID SUP - 627517001
Work Type LANDSCAPE, PICNIC & GROUNDS MAINTENANCE
 
0.010 73633.59 4059.10 4059.10 5.5
Work Order 06-27-14
Work Began 07-01-14
Work Completed  
Time Computed 07-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 31
Percent Time Used 8
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6275-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06141134
Totals 73633.59 4059.10 4059.10 5.5

CountyHOUSTON
Highway US0287
From VARIOUS LOCATIONS WITHIN
To HOUSTON COUNTY
CSJ 6275-18-001
Proj ID SUP - 627518001
Work Type PICNIC & GROUNDS MAINTENANCE
 
0.010 51223.05 4467.36 4467.36 8.7
Work Order 06-27-14
Work Began 07-01-14
Work Completed  
Time Computed 07-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 31
Percent Time Used 8
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6275-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06141135
Totals 51223.05 4467.36 4467.36 8.7

CountyTRINITY
Highway US0287
From VARIOUS LOCATIONS WITHIN
To TRINITY COUNTY
CSJ 6275-19-001
Proj ID SUP - 627519001
Work Type PICNIC, GRDS, CURB AND MAILBOX MAINT
 
0.010 76420.25 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-27-14
Work Began 07-01-14
Work Completed  
Time Computed 07-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6275-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06141136
Totals 76420.25 0.00 0.00 0.0