AVERAGE LOW BID UNIT PRICE - CONSTRUCTION - LAREDO DISTRICT

Last Update: Friday, June 26, 2015
ITEMS 1003 2001 TO 1150 2001
Items Items Bid Code Range
0100 - 0192
0216 - 0247
0310 - 0360
0400 - 0499
0500 - 0550
0610 - 0690
0780 - 0780
1003 - 1150
2280 - 2323
3002 - 3278
5367 - 5445
6001 - 6834
8020 - 8961
1003 2001 - 1150 2001
Item No Description Units June 30, 2015 Twelve Month Moving Usage
Quantity Avg Bid Quantity Avg Bid
1003 2001 LANDSCAPE BOULDERS EA     1.000 2,675.00000 1
1018 2003 TREE PROTECTION LF     320.000 10.70000 1
1122 2001 ROCK FILTER DAMS (INSTALL) (TY 1) LF     459.000 25.70000 1
1122 2002 ROCK FILTER DAMS (INSTALL) (TY 2) LF     1,268.000 25.70000 1
1122 2003 ROCK FILTER DAMS (INSTALL) (TY 3) LF     248.000 80.00000 1
1122 2009 ROCK FILTER DAMS (REMOVE) LF     1,516.000 5.72322 2
1122 2016 CONSTRUCTION EXITS (INSTALL) (TY 1) SY     733.000 20.82128 2
1122 2019 CONSTRUCTION EXITS (REMOVE) SY     733.000 5.11937 2
1122 2037 TEMPORARY SEDIMENT CONTROL FENCE INSTL LF     15,925.000 2.17850 3
1122 2038 TEMP SDMT CONT FENCE (INLET PROTECTION LF     5,895.000 2.92299 2
1122 2047 BIOGRD EROSN CONT LOGS (8" DIA) INSTAL LF     1,038.000 15.40000 1
1122 2048 BIOGRD EROSN CONT LOGS (12" DIA) INSTAL LF     2,980.000 20.50000 1
1122 2056 BIODEGRADBLE EROSION CONTROL LOGS REMO LF     4,018.000 2.10000 1
1122 2057 TEMPORARY SEDIMENT CONTROL FENCE REMOV LF     21,595.000 1.16219 3
1150 2001 LANDSCAPE MAINTENANCE MO     12.000 5,350.00000 1