AVERAGE LOW BID UNIT PRICE - MAINTENANCE - LAREDO DISTRICT

Last Update: Friday, October 3, 2014
ITEMS 500 2001 TO 550 2012
Items Items Bid Code Range
0100 - 0150
0247 - 0247
0310 - 0360
0401 - 0479
0500 - 0550
0610 - 0690
0712 - 0788
1122 - 1122
3035 - 3035
5845 - 5845
6006 - 6834
7224 - 7224
8835 - 8942
500 2001 - 550 2012
Item No Description Units Septembe 30, 2014 Twelve Month Moving Usage
Quantity Avg Bid Quantity Avg Bid
500 2001 MOBILIZATION LS     15.000 48,731.88067 15
500 2010 MOBILIZATION (PER CALL OUT) EA     3.000 1,000.00000 1
502 2001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO     81.000 2,714.54963 15
506 2004 ROCK FILTER DAMS (INSTALL) (TY 4) LF     180.000 50.00000 1
506 2009 ROCK FILTER DAMS (REMOVE) LF     180.000 20.00000 1
506 2016 CONSTRUCTION EXITS (INSTALL) (TY 1) SY     556.000 52.50000 2
506 2019 CONSTRUCTION EXITS (REMOVE) SY     556.000 20.00000 2
510 2001 ONE - WAY TRAFFIC CONTROL HR     206.000 36.40971 4
512 2011 PORT CTB (DES SOURCE) (SAFETY SH) (TY 2) LF     120.000 65.00000 1
512 2020 PORT CTB (MOVE) (SAFETY SH) (TY 2) LF     120.000 15.00000 1
512 2029 PORT CTB (STKPL) (SAFETY SH) (TY 2) LF     120.000 10.00000 1
528 2004 LANDSCAPE PAVERS SY     725.000 31.72414 3
529 2002 CONC CURB (TY II) LF     4,800.000 10.75000 2
529 2003 CONC CURB & GUTTER (TY I) LF     110.000 27.00000 2
529 2004 CONC CURB & GUTTER (TY II) LF     3,510.000 22.78000 1
529 2006 CONC CURB (MONO) (TY II) LF     550.000 18.00000 3
529 2007 CONC CURB (DOWEL) LF     86.500 92.77399 4
530 2010 DRIVEWAYS (CONC) SY     50.000 55.75000 1
531 2004 CONC SIDEWALKS (6") SY     200.000 59.25000 2
531 2005 CURB RAMPS (TY 1) EA     16.000 1,237.50000 4
531 2006 CURB RAMPS (TY 2) EA     16.000 1,287.50000 4
531 2011 CURB RAMPS (TY 8) EA     8.000 2,225.00000 2
531 2015 CONC SIDEWALKS (4") SY     226.000 57.96460 4
531 2024 CONC SIDEWALK (5") SY     2,428.333 30.59000 1
540 2001 MTL W - BEAM GD FEN (TIM POST) LF     100.000 20.00000 1
540 2002 MTL W - BEAM GD FEN (STEEL POST) LF     100.000 19.00000 1
540 2003 MTL THRIE - BEAM GD FEN (TIM POST) LF     75.000 10.00000 1
540 2005 TERMINAL ANCHOR SECTION EA     2.000 300.00000 1
540 2010 TRANSITION ADJUSTMENT EA     12.000 1,000.00000 1
540 2011 MTL BEAM GD FEN TRANS (THRIE - BEAM) EA     4.000 1,500.00000 1
540 2015 MTL W - BEAM GD FEN (TIM POST) RADIUS RAIL LF     50.000 15.00000 1
540 2017 MTL W - BEAM GD FEN (ROUND TIMBER POST) LF     11,700.000 19.50000 1
540 2032 MTL BM GD FN TRANSITION (REMOVE & RESET) EA     4.000 1,000.00000 1
540 2036 DRIVEWAY TERMINAL ANCHOR SECTION EA     1.000 989.00000 1
540 2044 DOWNSTREAM ANCHOR TERMINAL (DAT) SECTION EA     5.000 920.00000 2
540 2045 MTL BM GD FEN (LONG SPAN SYSTEM) LF     500.000 26.00000 1
540 2046 MTL BM GD FEN TRANS (NON - SYM) EA     4.000 1,400.00000 1
542 2001 REMOVING METAL BEAM GUARD FENCE LF     12,200.000 2.95902 2
542 2002 REMOVING TERMINAL ANCHOR SECTION EA     4.000 262.75000 2
544 2003 GUARDRAIL END TREATMENT (REMOVE) EA     69.000 500.00000 1
544 2006 GDRAIL END TRT (INST) (WOOD POST) (TY III EA     4.000 2,400.00000 1
544 2019 GUARDRAIL END TREATMENT (INSTALL) (OPT2) EA     69.000 2,200.00000 1
545 2002 CRASH CUSH ATTEN (MOVE & RESET) EA     4.000 500.00000 1
545 2003 CRASH CUSH ATTEN (REMOVE) EA     4.000 2,000.00000 1
550 2012 CHAIN LINK FENCE (REPAIR) (4') LF     50.000 20.00000 1