Monthly Local Let Maintenance Report For Laredo District As Of Jan 10, 2023 Page 5 Of 5
Last Update: Tuesday, January 10, 2023
|
Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
County | VAL VERDE |
Highway | UP0277 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6421-25-001 |
Proj ID | RMC - 642125001 |
Work Type | METAL BEAM GUARD FENCE REPAIR |
|
| 0.010 | 236510.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
ROSS SA ENTERPRISE LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6421-25-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 10222202 |
| Totals | 236510.00 | 0.00 | 0.00 | 0.0 |
|