Monthly State Let Construction Report For Odessa District As Of Apr 10, 2015 Page 2 Of 2

Last Update: Friday, April 10, 2015
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyMIDLAND
Highway FM 307
From CR 1150
To FM 1379
CSJ 0887-01-036
Proj ID C 887-1-36
Work Type PLANING, UNDERSEAL, HOT MIX & PV MARK
 
7.095 6382355.12 16656.00 2194196.27 34.3
Work Order 01-17-14
Work Began 06-17-14
Work Completed  
Time Computed 05-18-14
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 132
Percent Time Used 73
Contractor(s)
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0887-01-036
A BROTHERS MILLING, LLC(1.33%)
CONTRACTORS SERVICE COMPANY(0.33%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.76%)
WILLIS ELECTRIC CO., LP(0.09%)
W.S. CONSTRUCTION COMPANY(2.69%)
Contract # 12133225
Totals 6382355.12 16656.00 2194196.27 34.3

CountyECTOR
Highway VA
From DISTRICTWIDE
To .
CSJ 0906-00-141
Proj ID NH 2015(746)
Work Type IH PAVEMENT MARKINGS (2015)
 
43.030 193241.53 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 21
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
VIZCAINO, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0906-00-141
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03153212
Totals 193241.53 0.00 0.00 0.0

CountyECTOR
Highway VA
From DISTRICTWIDE PROJECT LOCATIONS
To .
CSJ 0906-00-152
Proj ID STP 2015(747)
Work Type NON - IH PAVEMENT MARKINGS (2015)
 
247.159 711132.85 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 43
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
VIZCAINO, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0906-00-152
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03153008
Totals 711132.85 0.00 0.00 0.0

CountyPECOS
Highway CR
From AT CANAL NO. 2
To .
CSJ 0906-17-007
Proj ID BR 2014(906)
Work Type STRUCTURE, GRADING, FLEX BASE, & MBGF
 
0.070 228610.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-18-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0906-17-007
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02153219
Totals 228610.00 0.00 0.00 0.0

CountyMARTIN
Highway FM 846
From SH 137
To HOWARD COUNTY LINE
CSJ 1155-01-016
Proj ID STP 2015(491)
Work Type RESTORATION OF EXISTING ROAD
 
11.080 8167618.40 0.00 48523.90 0.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-13-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 220
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1155-01-016
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01153002
Totals 8167618.40 0.00 48523.90 0.5

CountyMIDLAND
Highway SH 158
From IH 20 N & S FRONTAGE ROADS @ SH 158
To .
CSJ 1188-02-088
Proj ID STP 2014(614)G
Work Type TRF SIGNALS, VIVDS, SIGNS, PAV MARKING
 
0.331 600782.63 66460.79 298395.65 49.6
Work Order 07-08-14
Work Began 02-17-15
Work Completed  
Time Computed 11-06-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 31
Percent Time Used 51
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1188-02-088
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC(0.84%)
BARRICADES UNLIMITED (3.57%)
B & B UNDERGROUND, LLC (4.16%)
PEAK COMMUNICATIONS LLC(1.93%)
BIG DOG DRILLING, LLC(1.54%)
DYNAMIC VISION CO., INC. (4.80%)
Contract # 05143227
Totals 600782.63 66460.79 298395.65 49.6

CountyMIDLAND
Highway LP 250
From IH 20
To 0.3 MI WEST OF BS 349-C
CSJ 1188-02-090
Proj ID NH 2014(704)
Work Type PLANING, HOTMIX, PAVEMENT MARKINGS
 
9.592 8767244.31 5480.00 7454657.69 85.0
Work Order 09-09-14
Work Began 09-16-14
Work Completed  
Time Computed 09-25-14
Contract Working Days 80
Addl Days Granted 0
Working Days Charged 53
Percent Time Used 66
Contractor(s)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1188-02-090
BARRICADES UNLIMITED (2.35%)
CHEROKEE SERVICES(0.17%)
COX PAVING COMPANY, L.P. ( 25.69%)
DESERT PAVING, INC.(0.33%)
HJC FARMS, INC.(6.85%)
TEX OP CONSTRUCTION, LP(1.55%)
WILLIS ELECTRIC CO., LP(2.87%)
LPZ ENTERPRISES, LLC ( 10.61%)
R.E.B. TRUCKING(0.00%)
BLACKTOPPER TECHNOLOGY, INC. ( 25.87%)
Contract # 06143029
Totals 8767244.31 5480.00 7454657.69 85.0

CountyECTOR
Highway LP 338
From AT YUKON ROAD (IN ODESSA)
To .
CSJ 2224-01-011
Proj ID STP 2014(075)HES
Work Type TRAFFIC SIGNALS
 
0.101 362379.30 585.00 446940.45 100.0
Work Order 11-20-13
Work Began 08-11-14
Work Completed 02-09-15
Time Computed 03-21-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 60
Percent Time Used 100
Contractor(s)
WILLIS ELECTRIC CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 2224-01-011
BARRICADES UNLIMITED (6.53%)
DESERT PAVING, INC.( 20.95%)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.(3.02%)
Contract # 10133008
Totals 362379.30 585.00 446940.45 100.0

CountyECTOR
Highway LP 338
From YUKON ROAD
To 0.5 MI W OF US 385
CSJ 2224-01-085
Proj ID C 2224-1-85
Work Type WIDEN TO 4 - LANE DIVIDED
 
5.252 5516623.81 290288.16 1877014.54 34.0
Work Order 05-01-14
Work Began 11-18-14
Work Completed  
Time Computed 10-29-14
Contract Working Days 200
Addl Days Granted 0
Working Days Charged 70
Percent Time Used 35
Contractor(s)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2224-01-085
WILLIS ELECTRIC CO., LP(8.21%)
DESERT PAVING, INC.(0.21%)
DOUBLE A CONTRACTING, L.P. (2.94%)
REECE CONSTRUCTION CO., INC. ( 13.09%)
CONTRACTORS SERVICE COMPANY(0.38%)
ALTEX LANDSCAPE CONSTRUCTION, INC. (0.54%)
LPZ ENTERPRISES, LLC (5.16%)
DTM TRUCKING, INC. (9.20%)
Contract # 03143005
Totals 5516623.81 290288.16 1877014.54 34.0