Monthly State Let Construction Report For Odessa District As Of Apr 12, 2024 Page 2 Of 4

Last Update: Friday, April 12, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyUPTON
HighwayUS 67
FromWEST OF US 385
To0.7 MI W OF CR 450
CSJ0076-06-037
Proj IDSTP 1902(150)
Work TypeSUPER-2 HIGHWAY
 
26727484.844776452.4017.8
Work Order10-06-22
Work Began09-21-23
Work Completed
Time Computed01-04-23
Contract Working Days451
Addl Days Granted0
Working Days Charged118
Percent Time Used26
Contractor(s)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0076-06-037
CONTRACTORS SERVICE, LTD. (0.49)
DK CONTRACTING, LLC (0.42)
DOUBLE A CONTRACTING, L.P. (1.49)
HJC FARMS, INC. (0.53)
R.E.B.D. TRUCKING LLC (4.07)
RELMCO, INC. (20.96)
TEXOP CONSTRUCTION (0.89)
WILLIS ELECTRIC CO., LP (0.53)
FIBERTEX, LLC (0.02)
Contract #09223041
Totals26727484.84909012.744776452.4017.8

CountyUPTON ETC
HighwayUS 67 ETC
From0.2 MILES WEST OF SH 329
ToREAGAN COUNTY LINE
CSJ0076-07-038
Proj IDC 76-7-38
Work TypeSEAL COAT
 
18404584.6714871855.2080.8
Work Order10-11-22
Work Began05-30-23
Work Completed
Time Computed05-30-23
Contract Working Days92
Addl Days Granted0
Working Days Charged82
Percent Time Used89
Contractor(s)
COX PAVING OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0076-07-038
TRP CONSTRUCTION GROUP, LLC (1.85)
BARRICADES PLUS, LLC (0.45)
Contract #09223203
Totals18404584.670.0014871855.2080.8

CountyREEVES
HighwaySH 17
FromN OF COTTON ST
To3/4 MI S OF CR 206
CSJ0103-01-044
Proj IDSTP 2023(307)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
6972496.492548683.8636.5
Work Order09-13-23
Work Began11-06-23
Work Completed
Time Computed10-30-23
Contract Working Days155
Addl Days Granted0
Working Days Charged92
Percent Time Used59
Contractor(s)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0103-01-044
CONTRACTORS SERVICE, LTD. (1.99)
DK CONTRACTING, LLC (0.00)
DOUBLE A CONTRACTING, L.P. (0.00)
DUSTROL, INC. (0.97)
W. S. CONSTRUCTION COMPANY (0.00)
R.E.B.D. TRUCKING LLC (0.00)
Contract #08233014
Totals6972496.49107545.002548683.8636.5

CountyREEVES
HighwayUS 285
FromRM 652
ToCR 232
CSJ0139-03-041
Proj IDC 139-3-41
Work TypeSUPER-2 HIGHWAY
 
10.71343106369.487343445.5917.0
CountyREEVES
HighwayUS 285
FromAT FOUR MILE DRAW
To.
CSJ0139-03-048
Proj IDBR 2022(580)
Work TypeBRIDGE REPLACEMENT
 
2936873.311359127.0446.2
Work Order07-27-22
Work Began03-06-23
Work Completed
Time Computed10-25-22
Contract Working Days360
Addl Days Granted0
Working Days Charged259
Percent Time Used71
Contractor(s)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0139-03-041
BARRICADES UNLIMITED (0.26)
COPPELL CONSTRUCTION CO., INC. (7.22)
DESERT PAVING, INC. (0.46)
DOUBLE A CONTRACTING, L.P. (0.66)
HJC FARMS, INC. (2.62)
R.E.B.D. TRUCKING LLC (4.33)
RELMCO, INC. (11.41)
TEXOP CONSTRUCTION (0.52)
WILLIS ELECTRIC CO., LP (0.57)
J. H. ODEN CONTRACTING COMPANY (1.08)
FIBERTEX, LLC (0.02)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.01)
TEXAS SHAFTS, INC. (0.90)
PENHALL COMPANY (0.02)
Contract #06223403
Totals46043242.79261523.608702572.6318.9

CountyREEVES
HighwayUS 285
From2.0 MI SOUTH OF CR 113
ToPECOS COUNTY LINE
CSJ0139-06-021
Proj IDC 139-6-21
Work TypeSUPER-2 HIGHWAY
 
13.93229734403.8829283666.1298.4
CountyPECOS
HighwayUS 285
FromREEVES COUNTY LINE
To0.3 MI SOUTH OF FM 1776
CSJ0139-07-025
Proj IDC 139-7-25
Work TypeSUPER-2 HIGHWAY
 
13.99828794096.8924781369.5886.0
Work Order08-18-21
Work Began09-20-21
Work Completed
Time Computed09-20-21
Contract Working Days805
Addl Days Granted0
Working Days Charged673
Percent Time Used83
Contractor(s)
KIEWIT INFRASTRUCTURE SOUTH CO.
SUBCONTRACTOR(S) FOR CCSJ: 0139-06-021
BEAVER CONTRACTORS, LLC (11.53)
BARRICADES UNLIMITED (0.73)
MOBILE ENTERPRISES, INC. (0.12)
DOUBLE A CONTRACTING, L.P. (2.43)
LONE STAR EROSION CONTROL (0.29)
MARCOM"S MOWING SERVICE, LLC (0.20)
S&S BRIDGE PAINTING (0.06)
TEX OP CONSTRUCTION, LP (1.13)
WILLIS ELECTRIC CO., LP (0.82)
BLACKLIDGE EMULSIONS, INC. (0.37)
AREA WIDE, INC. (0.15)
HUNTER LOGISTICS LLC (2.19)
CACTUS ASPHALT, A DIVISION OF CACTUS TRANSPORT, INC. (1.64)
W. S. CONSTRUCTION COMPANY (2.13)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.09)
PENHALL COMPANY (0.03)
AARON CONCRETE CONTRACTORS, L.P. (0.15)
KL POWELL, LLC (3.82)
WILD WEST TRUCKING, LLC (3.97)
ELITE TRANSPORTS, LLP (0.23)
MARTIN IBARRA M & J TRUCKING INC. (0.23)
DUSTROL, INC. (0.01)
J & M CONTRACTING, COMPANY (0.64)
Contract #07213002
Totals58528500.77273040.0554065035.7092.3

CountyPECOS ETC
HighwayIH 10 ETC
FromSH 18
To0.759 MI E OF US 67
CSJ0140-01-081
Proj IDF 2024(017)
Work TypeSEAL COAT
 
14363577.761533429.0810.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-08-23
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days67
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
COX PAVING OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0140-01-081
BARRICADES PLUS, LLC (0.42)
DOUBLE A CONTRACTING, L.P. (2.46)
Contract #09233212
Totals14363577.76421349.431533429.0810.6

CountyPECOS
HighwayIH 10
FromREFERENCE MARKER 285
ToREFERENCE MARKER 293
CSJ0140-02-050
Proj IDSTP 2023(306)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1938518.001082683.5055.8
Work Order10-12-23
Work Began02-26-24
Work Completed
Time Computed01-11-24
Contract Working Days124
Addl Days Granted0
Working Days Charged24
Percent Time Used19
Contractor(s)
HJC FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0140-02-050
FC TRAFFIC CONTROL, INC. (0.82)
Contract #09233039
Totals1938518.00804095.541082683.5055.8

CountyPECOS ETC
HighwayIH 10
FromAT FM 2023.
To.
CSJ0140-02-052
Proj IDBR 2022(636)
Work TypeBRIDGE MAINTENANCE
 
1622640.001636905.0099.9
Work Order07-14-22
Work Began01-11-23
Work Completed
Time Computed10-13-22
Contract Working Days217
Addl Days Granted0
Working Days Charged289
Percent Time Used133
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0140-02-052
S&S BRIDGE PAINTING (8.31)
Contract #06223009
Totals1622640.0056940.001636905.0099.9

CountyANDREWS
HighwayUS 385
FromAVE K
ToGAINES CO LINE
CSJ0228-04-043
Proj IDC 228-4-43
Work TypeREHABILITATION OF EXISTING ROAD
 
14.12037642802.4733053873.2587.8
CountyZERO COUNTIES
Highway
From
To
CSJ0228-05-071
Proj ID
Work Type
 
0.00612596.010.0
Work Order02-16-22
Work Began05-31-22
Work Completed
Time Computed05-17-22
Contract Working Days373
Addl Days Granted49
Working Days Charged412
Percent Time Used97
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0228-04-043
SURFACE PREPARATION TECHNOLOGIES, LLC (0.03)
CONTRACTORS SERVICE, LTD. (0.33)
DOUBLE A CONTRACTING, L.P. (1.34)
J. H. ODEN CONTRACTING COMPANY (0.31)
MARCOM"S MOWING SERVICE, LLC (0.99)
SCR CIVIL CONSTRUCTION, LLC (6.90)
K. L. DURHAM CONSTRUCTION, L.L.C. (2.69)
D & E LOGISTICS, LLC (0.06)
LONG LEGACY ENTERPRISES, LLC (0.28)
BADGER DAYLIGHTING CORP. (0.32)
Contract #01223204
Totals37642802.47802252.4933666469.2689.4

CountyUPTON
HighwayUS 385
FromCRANE COUNTY LINE
ToNIMITZ STREET IN MCCAMEY
CSJ0229-04-057
Proj IDC 229-4-57
Work TypeWIDEN NON-FREEWAY
 
7.05849428878.7713404368.9527.1
Work Order04-26-23
Work Began06-15-23
Work Completed
Time Computed06-15-23
Contract Working Days501
Addl Days Granted0
Working Days Charged205
Percent Time Used40
Contractor(s)
DELHUR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0229-04-057
FC TRAFFIC CONTROL, INC. (0.17)
CEDAR EATERS OF TEXAS (0.27)
SCR CIVIL CONSTRUCTION, LLC (0.93)
4-WAY HAULERS, LLC (15.69)
J H TRUCKING (1.01)
TRP CONSTRUCTION GROUP, LLC (0.63)
TUCAN CONTRACTING, LLC (2.38)
Contract #03233202
Totals49428878.771531876.6313404368.9527.1

CountyUPTON
HighwayUS 385
FromNIMITZ STREET
ToUS 67
CSJ0229-04-060
Proj IDF 2022(979)
Work TypeREHABILITATION OF EXISTING ROAD
 
5995947.225741691.3295.7
Work Order03-13-23
Work Began07-19-23
Work Completed
Time Computed05-29-23
Contract Working Days120
Addl Days Granted68
Working Days Charged185
Percent Time Used98
Contractor(s)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0229-04-060
BOLER EQUIPMENT SERVICE, INC (14.70)
CONTRACTORS SERVICE, LTD. (1.19)
TEXOP CONSTRUCTION (1.67)
R.E.B.D. TRUCKING LLC (0.00)
DOUBLE A CONTRACTING, L.P. (2.00)
DK CONTRACTING, LLC (0.74)
A L CONCRETE CONSTRUCTION, LLC (10.96)
Contract #01233036
Totals5995947.22913668.215741691.3295.7

CountyWINKLER
HighwaySH 18
FromNM STATE LINE
ToSH 115
CSJ0292-01-034
Proj IDF 2022(583)
Work TypeREHABILITATION OF EXISTING ROAD
 
10.40037268535.8134267645.8792.8
Work Order07-27-22
Work Began12-06-22
Work Completed
Time Computed10-25-22
Contract Working Days265
Addl Days Granted100
Working Days Charged334
Percent Time Used91
Contractor(s)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0292-01-034
FC TRAFFIC CONTROL, INC. (0.29)
DESERT PAVING, INC. (3.36)
DK CONTRACTING, LLC (0.33)
DOUBLE A CONTRACTING, L.P. (1.39)
HJC FARMS, INC. (0.09)
K. L. DURHAM CONSTRUCTION, L.L.C. (1.45)
WILLIS ELECTRIC CO., LP (1.71)
R.E.B.D. TRUCKING LLC (0.77)
MICA CORPORATION (0.13)
FUSION COMMUNICATIONS, LLC (0.04)
FIBERTEX, LLC (0.04)
Contract #06223605
Totals37268535.811902177.4734267645.8792.8

CountyWARD
HighwaySH 18
FromWINKLER CO LINE
ToBI 20-D
CSJ0292-03-032
Proj IDF 2022(591)
Work TypeREHABILITATION OF EXISTING ROAD
 
7.75032902552.4019621533.4759.6
Work Order03-06-23
Work Began07-17-23
Work Completed
Time Computed06-05-23
Contract Working Days244
Addl Days Granted0
Working Days Charged153
Percent Time Used62
Contractor(s)
FNF CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0292-03-032
DIAMOND C LOGISTICS TX LLC (2.09)
DK CONTRACTING, LLC (0.35)
DOUBLE A CONTRACTING, L.P. (1.62)
FIBERTEX, LLC (0.04)
V-TECH ENVIROMENTAL SERVICES (0.03)
WEST TEXAS ROCK RESOURCES, LLC (0.02)
WILLIS ELECTRIC CO., LP (1.27)
K. L. DURHAM CONSTRUCTION, L.L.C. (2.17)
TEXAS GUARDRAIL CONTRACTORS LLC (1.71)
FC TRAFFIC CONTROL, INC. (0.04)
PEYSON TRANSPORT, LLC (3.34)
Contract #02233203
Totals32902552.401753213.3019621533.4759.6

CountyWARD ETC
HighwaySH 18 ETC
From0.22 MI S OF FM 1776
ToPECOS COUNTY LINE
CSJ0292-04-072
Proj IDF 2024(005)
Work TypeSEAL COAT
 
13110325.392620281.3319.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-21-23
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days83
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RONALD R. WAGNER & CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0292-04-072
VIZCAINO, L.P. (5.47)
BARRICADES PLUS, LLC (0.51)
Contract #09233214
Totals13110325.39815763.912620281.3319.9

CountyWINKLER
HighwaySH 115
FromFM 874
To1.5 MILES N OF CR 301
CSJ0354-04-040
Proj IDC 354-4-40
Work TypeREHABILITATION OF EXISTING ROAD
 
8225180.167875318.10100.0
Work Order11-09-22
Work Began06-08-23
Work Completed04-04-24
Time Computed02-07-23
Contract Working Days112
Addl Days Granted0
Working Days Charged90
Percent Time Used80
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0354-04-040
BARRICADES UNLIMITED (0.20)
DK CONTRACTING, LLC (0.51)
DOUBLE A CONTRACTING, L.P. (0.16)
DUSTROL, INC. (0.15)
TRP CONSTRUCTION GROUP, LLC (1.21)
WILLIS ELECTRIC CO., LP (3.44)
FIBERTEX, LLC (0.02)
Contract #10223020
Totals8225180.160.007875318.10100.0

CountyANDREWS
HighwaySH 115
FromAT FM 181
To.
CSJ0354-06-030
Proj IDSTP 2022(582)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.62836740466.7520423568.0655.5
Work Order09-15-22
Work Began03-27-23
Work Completed
Time Computed01-13-23
Contract Working Days640
Addl Days Granted0
Working Days Charged224
Percent Time Used35
Contractor(s)
FNF CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0354-06-030
AARON CONCRETE CONTRACTORS, L.P. (1.76)
DK CONTRACTING, LLC (0.33)
DUSTROL, INC. (0.49)
1 PRIORITY ENVIRONMENTAL SERVICES, LLC (0.27)
WILLIS ELECTRIC CO., LP (2.64)
TORO BRAVO CONSTRUCTION, LLC (0.00)
DOUBLE A CONTRACTING, L.P. (0.96)
HB FARMER FOUNDATION, LLC (0.58)
LONE STAR EROSION CONTROL (0.65)
FIBERTEX, LLC (0.03)
MAKIN" IT MOVE TRANSPORT,LLC (3.63)
A-CORE CONCRETE CUTTING OF TEXAS, INC. (0.03)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.62)
PEYSON TRANSPORT, LLC (0.72)
FC TRAFFIC CONTROL, INC. (0.00)
BROADHEAD BORING LLC (0.09)
Contract #08223212
Totals36740466.752337754.3520423568.0655.5

CountyANDREWS
HighwaySH 115
FromAT SH 128
To.
CSJ0354-06-038
Proj IDSTP 2023(496)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
57038.250.000.0
CountyANDREWS
HighwaySH 128
FromAT REFERENCE MARKER 230
To.
CSJ1127-01-011
Proj IDSTP 2023(496)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2016118.40221241.5210.9
CountyANDREWS
HighwaySH 128
FromNEW MEXICO STATE LINE
ToSH 115
CSJ1127-01-012
Proj IDF 2B22(010)
Work TypeREHABILITATION OF EXISTING ROAD
 
33923538.058547329.1825.1
Work Order02-16-23
Work Began07-17-23
Work Completed
Time Computed05-17-23
Contract Working Days400
Addl Days Granted10
Working Days Charged155
Percent Time Used37
Contractor(s)
CI CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0354-06-038
BARRICADES UNLIMITED (0.48)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.08)
TRP CONSTRUCTION GROUP, LLC (2.32)
V-TECH ENVIROMENTAL SERVICES (0.06)
WILLIS ELECTRIC CO., LP (0.81)
DESERT DIAMOND TRUCKING, LLC (2.61)
BUILT CONCRETE CONSTRUCTION, LLC (0.60)
DK CONTRACTING, LLC (0.14)
Contract #01233037
Totals35996694.70234604.958768570.7024.3

CountyMIDLAND
HighwayBS 349C
FromSL 250
ToIH 20
CSJ0380-09-098
Proj IDF 2022(585)
Work TypeREHABILITATION OF EXISTING ROAD
 
4.95217997658.137879108.1643.7
Work Order04-12-23
Work Began08-07-23
Work Completed
Time Computed07-12-23
Contract Working Days300
Addl Days Granted17
Working Days Charged147
Percent Time Used46
Contractor(s)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0380-09-098
AARON CONCRETE CONTRACTORS, LLC (1.34)
CONTRACTORS SERVICE, LTD. (1.22)
DESERT PAVING, INC. (18.05)
DK CONTRACTING, LLC (2.52)
DOUBLE A CONTRACTING, L.P. (2.26)
DUSTROL, INC. (1.96)
HJC FARMS, INC. (2.67)
R.E.B.D. TRUCKING LLC (0.32)
O. TREVINO CONSTRUCTION, LLC (2.38)
STREET FOUNDATION DRILLING, INC. (0.07)
ROYAL REBAR (0.04)
Contract #12223211
Totals17997658.13586105.777879108.1643.7

CountyMIDLAND
HighwayBS 349C
FromAT OCCIDENTAL PKWY
To.
CSJ0380-09-102
Proj IDC 380-9-102
Work TypeSAFETY IMPROVEMENT PROJECTS
 
353315.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-06-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days96
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WILLIS ELECTRIC CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0380-09-102
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02243237
Totals353315.000.000.000.0

CountyPECOS
HighwayIH 10
From7.75 MI W OF US 67
To4.75 MI W OF US 67
CSJ0441-07-074
Proj IDC 441-7-74
Work TypeREHABILITATION OF EXISTING ROAD
 
12743572.550.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-11-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days194
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FNF CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0441-07-074
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03243012
Totals12743572.550.000.000.0

page 1 | page 2 | page 3 | page 4