Monthly State Let Construction Report For Odessa District As Of Jun 15, 2016 Page 2 Of 2

Last Update: Wednesday, June 15, 2016
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyPECOS
Highway FM 11
From AT PECOS RIVER
To .
CSJ 0629-03-037
Proj ID BR 2015(578)
Work Type REPLACE BRIDGE 06 - 186 - 0 - 0629 - 03 - 001
 
0.170 1978959.25 212597.67 1531761.43 77.4
Work Order 04-28-15
Work Began 09-29-15
Work Completed  
Time Computed 08-27-15
Contract Working Days 160
Addl Days Granted 0
Working Days Charged 145
Percent Time Used 90
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0629-03-037
A. H. BECK FOUNDATION CO., INC.( 16.74%)
Contract # 02153016
Totals 1978959.25 212597.67 1531761.43 77.4

CountyPECOS
Highway FM 11
From 2 MILES NORTH OF FM 1901
To FM 1901
CSJ 0629-04-010
Proj ID C 629-4-10
Work Type PAVEMENT STRUCTURE RESTORATION
 
1.987 1325351.35 83117.50 937386.90 70.7
Work Order 05-14-15
Work Began 04-04-16
Work Completed  
Time Computed 02-01-16
Contract Working Days 80
Addl Days Granted 0
Working Days Charged 36
Percent Time Used 45
Contractor(s)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0629-04-010
BARRICADES UNLIMITED (3.33%)
RPV CONSTRUCTION (2.46%)
LPZ ENTERPRISES, LLC ( 12.43%)
R.E.B. TRUCKING(1.33%)
WILLIS ELECTRIC CO., LP(0.99%)
Contract # 04153250
Totals 1325351.35 83117.50 937386.90 70.7

CountyECTOR
Highway VA
From VARIOUS PROJECT LOCATIONS
To .
CSJ 0906-00-153
Proj ID STP 2016(856)
Work Type NON - IH PAVEMENT MARKINGS (2016)
 
393.305 1024337.14 332957.70 332957.70 32.5
Work Order 04-20-16
Work Began 05-17-16
Work Completed  
Time Computed 05-17-16
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 7
Percent Time Used 11
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0906-00-153
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03163012
Totals 1024337.14 332957.70 332957.70 32.5

CountyECTOR
Highway VA
From DISTRICTWIDE
To .
CSJ 0906-00-169
Proj ID C 906-00-169
Work Type NON - SITE SPECIFIC TRAFFIC SIGNALS
 
0.001 3256207.30 371046.50 491953.66 15.1
Work Order 10-22-15
Work Began 05-12-16
Work Completed  
Time Computed 02-20-16
Contract Working Days 240
Addl Days Granted 0
Working Days Charged 24
Percent Time Used 10
Contractor(s)
WILLIS ELECTRIC CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0906-00-169
BARRICADES UNLIMITED (2.34%)
DESERT PAVING, INC.(6.04%)
MICA CORPORATION (6.28%)
CONTRACTORS SERVICE COMPANY(2.19%)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.(1.68%)
Contract # 07153220
Totals 3256207.30 371046.50 491953.66 15.1

CountyECTOR
Highway VA
From DISTRICTWIDE
To .
CSJ 0906-00-171
Proj ID NH 2016(857)
Work Type IH PAVEMENT MARKINGS (2016)
 
131.391 519081.07 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-07-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 39
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FLAT LINE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0906-00-171
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03163016
Totals 519081.07 0.00 0.00 0.0

CountyMIDLAND
Highway CS
From FAIRGROUNDS RD FROM LP 250
To EAST PECAN AVE.
CSJ 0906-32-049
Proj ID STP 1502(406)
Work Type HMAC, STRM DRN, C & G, SIGN, SIGNALS, PVMK
 
1.487 6205048.00 622267.23 2308705.68 37.2
Work Order 10-20-15
Work Began 02-29-16
Work Completed  
Time Computed 02-18-16
Contract Working Days 160
Addl Days Granted 20
Working Days Charged 63
Percent Time Used 35
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0906-32-049
CONTRACTORS SERVICE COMPANY(0.49%)
ALTEX LANDSCAPE CONSTRUCTION, INC. (2.86%)
BARRICADES UNLIMITED (1.06%)
HJC FARMS, INC.(0.21%)
WILLIS ELECTRIC CO., LP(5.07%)
LPZ ENTERPRISES, LLC (6.12%)
Contract # 07153049
Totals 6205048.00 622267.23 2308705.68 37.2

CountyMARTIN
Highway FM 846
From SH 137
To HOWARD COUNTY LINE
CSJ 1155-01-016
Proj ID STP 2015(491)
Work Type RESTORATION OF EXISTING ROAD
 
11.080 8167618.40 787659.60 5813615.49 71.1
Work Order 03-13-15
Work Began 09-09-15
Work Completed  
Time Computed 07-12-15
Contract Working Days 220
Addl Days Granted 5
Working Days Charged 187
Percent Time Used 83
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1155-01-016
MPB, INC.(0.26%)
CONTRACTORS SERVICE COMPANY(0.51%)
BARRICADES UNLIMITED (1.27%)
HJC FARMS, INC.(0.63%)
BLACKTOPPER TECHNOLOGY, INC. (7.31%)
J.V. CONCRETE CONSTRUCTION (4.23%)
LPZ ENTERPRISES, LLC (4.00%)
Contract # 01153002
Totals 8167618.40 787659.60 5813615.49 71.1

CountyMIDLAND
Highway SL 250
From BS 349-C
To 0.5 MI W OF GARFIELD ST
CSJ 1188-02-091
Proj ID NH 1502(341)
Work Type PLANE, HOTMIX, MBGF, SIGNS, AND PAVMRKS
 
3.228 3174492.40 168502.46 3167239.55 100.0
Work Order 11-02-15
Work Began 11-12-15
Work Completed 06-10-16
Time Computed 11-12-15
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 47
Percent Time Used 78
Contractor(s)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1188-02-091
BARRICADES UNLIMITED (1.77%)
CONTRACTORS SERVICE COMPANY(2.64%)
COX PAVING COMPANY, L.P. ( 14.87%)
DESERT PAVING, INC.(0.27%)
VANN/ELLI, INC.( 16.61%)
WILLIS ELECTRIC CO., LP(1.66%)
R.E.B. TRUCKING(6.03%)
Contract # 08153261
Totals 3174492.40 168502.46 3167239.55 100.0

CountyMIDLAND
Highway FM 1788
From IH 20 SERVICE ROAD
To FM 1787
CSJ 1718-01-033
Proj ID STP 1502(408)
Work Type BASE, HOTMIX, SEAL COAT, SIGNS & PAVMRKS
 
16.237 10991276.15 207575.60 1216189.64 11.0
Work Order 12-22-15
Work Began 03-24-16
Work Completed  
Time Computed 03-24-16
Contract Working Days 360
Addl Days Granted 15
Working Days Charged 38
Percent Time Used 10
Contractor(s)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1718-01-033
BARRICADES UNLIMITED (0.73%)
ALTEX LANDSCAPE CONSTRUCTION, INC. (0.10%)
DESERT PAVING, INC.(1.10%)
DOUBLE A CONTRACTING, L.P. (1.27%)
PERFORMANCE EQUIPMENT SERVICE(0.08%)
WILLIS ELECTRIC CO., LP(0.54%)
R.E.B. TRUCKING(1.72%)
Contract # 11153205
Totals 10991276.15 207575.60 1216189.64 11.0

CountyMIDLAND
Highway SH 349
From AT CR 127
To .
CSJ 1718-01-034
Proj ID STP 1502(162)
Work Type TRAFFIC SIGNALS
 
1.058 521416.65 53812.16 557564.40 99.9
Work Order 07-01-15
Work Began 10-28-15
Work Completed  
Time Computed 10-28-15
Contract Working Days 80
Addl Days Granted 0
Working Days Charged 113
Percent Time Used 141
Contractor(s)
MIDASCO, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1718-01-034
DOWN UNDER CONSTRUCTION(4.47%)
DUSTROL, INC.(1.94%)
M & M STRIPING & POWER WASHING, LLC(4.62%)
UNION ELECTRICAL CONTRACTOR, INC.(5.99%)
DANNY"S ASPHALT PAVING (4.31%)
Contract # 05153233
Totals 521416.65 53812.16 557564.40 99.9

CountyMIDLAND
Highway FM 1788
From SH 191
To NORTH OF SH 158
CSJ 1718-07-037
Proj ID STP 2013(743)
Work Type FL BS, HOTMIX, EXT STR, ILLUM, PAV - MRK
 
5.402 17335339.77 726087.97 4807019.36 27.7
Work Order 11-12-15
Work Began 01-20-16
Work Completed  
Time Computed 01-12-16
Contract Working Days 240
Addl Days Granted 0
Working Days Charged 90
Percent Time Used 37
Contractor(s)
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1718-07-037
BARRICADES UNLIMITED (0.24%)
DOUBLE A CONTRACTING, L.P. (0.65%)
HJC FARMS, INC.(0.37%)
WILLIS ELECTRIC CO., LP(1.26%)
W.S. CONSTRUCTION COMPANY(6.02%)
W.S. CONSTRUCTION COMPANY( 12.23%)
Contract # 08153204
Totals 17335339.77 726087.97 4807019.36 27.7

CountyECTOR
Highway FM 1882 ETC
From 0.16 MI SOUTH OF IH 20
To US 385 SOUTH
CSJ 2005-02-016
Proj ID STP 2016(328)
Work Type SEAL COAT PROGRAM (2016)
 
240.006 10730661.65 514063.55 1034639.68 9.6
Work Order 12-21-15
Work Began 00-00-00
Work Completed  
Time Computed 05-27-16
Contract Working Days 47
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2005-02-016
BARRICADES PLUS, LLC (0.67%)
FLAT LINE, INC.( 12.96%)
Contract # 11153016
Totals 10730661.65 514063.55 1034639.68 9.6

CountyECTOR
Highway LP 338
From YUKON ROAD
To 0.5 MI W OF US 385
CSJ 2224-01-085
Proj ID C 2224-1-85
Work Type WIDEN TO 4 - LANE DIVIDED
 
5.252 5516623.81 10214.20 5397573.74 97.8
Work Order 05-01-14
Work Began 11-18-14
Work Completed  
Time Computed 10-29-14
Contract Working Days 200
Addl Days Granted 48
Working Days Charged 234
Percent Time Used 94
Contractor(s)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2224-01-085
WILLIS ELECTRIC CO., LP(8.21%)
DESERT PAVING, INC.(0.21%)
DOUBLE A CONTRACTING, L.P. (2.94%)
REECE CONSTRUCTION CO., INC. ( 13.09%)
CONTRACTORS SERVICE COMPANY(0.38%)
ALTEX LANDSCAPE CONSTRUCTION, INC. (0.54%)
LPZ ENTERPRISES, LLC (5.16%)
DTM TRUCKING, INC. (9.20%)
DAVID CORRALES DUMPING SERVICE (0.00%)
R.E.B. TRUCKING(0.00%)
Contract # 03143005
Totals 5516623.81 10214.20 5397573.74 97.8

CountyECTOR
Highway SH 191
From BILLY HEXT RD
To MIDLAND COUNTY LINE
CSJ 2296-01-051
Proj ID NH 2016(565)
Work Type RAMP IMPROVEMENTS
 
2.796 4387311.96 43332.50 53031.64 1.2
Work Order 04-19-16
Work Began 06-06-16
Work Completed  
Time Computed 06-06-16
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2296-01-051
WILLIS ELECTRIC CO., LP(9.39%)
HJC FARMS, INC.(2.56%)
BARRICADES UNLIMITED (0.53%)
LPZ ENTERPRISES, LLC (3.27%)
DOUBLE A CONTRACTING, L.P. (1.20%)
BRICK PAVING PLUS, INC.(2.44%)
INCE ENTERPRISES, INC. (7.53%)
Contract # 01163035
Totals 4387311.96 43332.50 53031.64 1.2

CountyMARTIN
Highway FM 3263
From FM 26
To FM 846
CSJ 3067-01-011
Proj ID C 3067-1-11
Work Type FLEX BASE, SEAL COAT, AND PAVMRKS
 
5.967 5923778.45 0.00 3591527.42 60.6
Work Order 08-10-15
Work Began 10-26-15
Work Completed  
Time Computed 10-26-15
Contract Working Days 120
Addl Days Granted 5
Working Days Charged 101
Percent Time Used 80
Contractor(s)
DELHUR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 3067-01-011
ALTUS TRAFFIC MANAGEMENT LLC (0.23%)
BARRICADES UNLIMITED (1.06%)
HJC FARMS, INC.(1.07%)
LIPHAM ASPHALT AND PAVING COMPANY, LLC (3.58%)
SAENZ TRANSPORT, LLC (3.92%)
SOUTH PLAINS CONCRETE PRODUCTS, LP (0.08%)
NOBLES ROAD CONSTRUCTION, INC. (4.96%)
Contract # 06153239
Totals 5923778.45 0.00 3591527.42 60.6

page 1 | page 2