Monthly Local Let Maintenance Report For Odessa District As Of Sep 15, 2016 Page 6 Of 7

Last Update: Thursday, September 15, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyUPTON
Highway US0067
From VARIOUS
To VARIOUS
CSJ 6295-19-001
Proj ID SUP - 629519001
Work Type PICNIC AREA MAINTENANCE
 
0.001 110904.00 4812.00 46176.00 41.6
Work Order 10-21-15
Work Began 11-03-15
Work Completed  
Time Computed 11-01-15
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 305
Percent Time Used 41
Contractor(s)
FRESH START OF MONROE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6295-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10150632
Totals 110904.00 4812.00 46176.00 41.6

CountyECTOR
Highway IH0020
From VARIOUS
To VARIOUS
CSJ 6295-24-001
Proj ID RMC - 629524001
Work Type ROADSIDE MOWING
 
0.001 266703.00 42872.50 101924.50 38.4
Work Order 03-07-16
Work Began 05-04-16
Work Completed  
Time Computed 03-16-16
Contract Working Days 78
Addl Days Granted 0
Working Days Charged 25
Percent Time Used 32
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6295-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01160606
Totals 266703.00 42872.50 101924.50 38.4

CountyUPTON
Highway US0067
From MCCAMEY MAINTENANCE OFFICE
To MCCAMEY MAINTENANCE OFFICE
CSJ 6295-63-001
Proj ID SUP - 629563001
Work Type JANITORIAL AND GROUNDS MAINTENANCE
 
0.001 23261.58 906.88 8550.46 36.7
Work Order 10-28-15
Work Began 11-01-15
Work Completed  
Time Computed 11-01-15
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 305
Percent Time Used 41
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6295-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10150633
Totals 23261.58 906.88 8550.46 36.7

CountyMARTIN
Highway SH0137
From STANTON MAINTENANCE OFFICE
To STANTON MAINTENANCE OFFICE
CSJ 6296-58-001
Proj ID SUP - 629658001
Work Type JANITORIAL MAINTENANCE
 
0.001 13380.72 557.53 5017.77 37.5
Work Order 12-01-15
Work Began 12-01-15
Work Completed  
Time Computed 12-01-15
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 275
Percent Time Used 37
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6296-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11150651
Totals 13380.72 557.53 5017.77 37.5

CountyPECOS
Highway IH0010
From VARIOUS
To VARIOUS
CSJ 6296-59-001
Proj ID SUP - 629659001
Work Type PICNIC AREA MAINTENANCE
 
0.001 91170.00 4105.00 30200.00 33.1
Work Order 12-15-15
Work Began 01-01-16
Work Completed  
Time Computed 01-01-16
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 244
Percent Time Used 33
Contractor(s)
TIBH INDUSTRIES, INC.
PERMIAN BASIN COMMUNITY CENTERS
SUBCONTRACTOR(S) FOR CCSJ: 6296-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12150631
Totals 91170.00 4105.00 30200.00 33.1

CountyPECOS
Highway IH0010
From VARIOUS
To VARIOUS
CSJ 6296-84-001
Proj ID RMC - 629684001
Work Type LANDSCAPE MAINTENANCE
 
0.001 104567.20 6680.25 16136.75 15.4
Work Order 02-11-16
Work Began 06-01-16
Work Completed  
Time Computed 06-01-16
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 92
Percent Time Used 12
Contractor(s)
CM COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6296-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01160607
Totals 104567.20 6680.25 16136.75 15.4

CountyPECOS
Highway IH0010
From VARIOUS
To VARIOUS
CSJ 6297-40-001
Proj ID RMC - 629740001
Work Type INSTALL / REMOVE RPMS
 
0.001 108672.50 0.00 101921.88 93.7
Work Order 02-24-16
Work Began 02-26-16
Work Completed  
Time Computed 02-24-16
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 188
Percent Time Used 51
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6297-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01160608
Totals 108672.50 0.00 101921.88 93.7

CountyECTOR
Highway IH0020
From VARIOUS
To VARIOUS
CSJ 6297-42-001
Proj ID RMC - 629742001
Work Type INSTALL / REMOVAL OF RPMS
 
0.001 98610.00 0.00 47753.24 48.4
Work Order 03-01-16
Work Began 04-27-16
Work Completed  
Time Computed 03-01-16
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 184
Percent Time Used 50
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6297-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01160609
Totals 98610.00 0.00 47753.24 48.4

CountyMIDLAND
Highway BI0020E
From VARIOUS
To VARIOUS
CSJ 6297-51-001
Proj ID RMC - 629751001
Work Type PUMP STATION MAINTENANCE
 
0.001 162164.00 31219.00 31219.00 19.2
Work Order 02-26-16
Work Began 08-22-16
Work Completed  
Time Computed 04-01-16
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 153
Percent Time Used 20
Contractor(s)
CLEAN SERVE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6297-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01160610
Totals 162164.00 31219.00 31219.00 19.2

CountyWARD
Highway BI0020D
From VARIOUS
To VARIOUS
CSJ 6297-63-001
Proj ID RMC - 629763001
Work Type RETROREFLECTIVITY MEASUREMENT
 
0.001 21323.87 0.00 21323.88 99.9
Work Order 05-16-16
Work Began 05-16-16
Work Completed  
Time Computed 05-16-16
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 28
Percent Time Used 46
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6297-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03160602
Totals 21323.87 0.00 21323.88 99.9

CountyREEVES
Highway IH0010
From VARIOUS
To VARIOUS
CSJ 6298-12-001
Proj ID SUP - 629812001
Work Type LITTER PICKUP
 
0.001 136500.00 0.00 32275.24 23.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-05-16
Work Began 05-16-16
Work Completed  
Time Computed 05-16-16
Contract Working Days 217
Addl Days Granted 0
Working Days Charged 12
Percent Time Used 5
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6298-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12150632
Totals 136500.00 0.00 32275.24 23.6

CountyREEVES
Highway RM0652
From VARIOUS
To VARIOUS
CSJ 6298-37-001
Proj ID EMC - 629837001
Work Type EPOXY INJECTION AND STRUCTURE REPAIR
 
0.001 289600.00 0.00 308241.10 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-28-15
Work Began 01-04-16
Work Completed 06-23-16
Time Computed 01-04-16
Contract Working Days 20
Addl Days Granted 0
Working Days Charged 22
Percent Time Used 110
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6298-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12150641
Totals 289600.00 0.00 308241.10 100.0

CountyMIDLAND
Highway IH0020
From VARIOUS
To VARIOUS
CSJ 6298-60-001
Proj ID SUP - 629860001
Work Type TREE TRIMMING AND TREE / BRUSH REMOVAL
 
0.001 246901.74 0.00 248010.15 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-07-15
Work Began 12-07-15
Work Completed 05-02-16
Time Computed 12-07-15
Contract Working Days 50
Addl Days Granted 25
Working Days Charged 75
Percent Time Used 100
Contractor(s)
TIBH INDUSTRIES, INC.
RELIEF ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6298-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12150651
Totals 246901.74 0.00 248010.15 100.0

CountyECTOR
Highway IH0020
From VARIOUS
To VARIOUS
CSJ 6298-88-001
Proj ID SUP - 629888001
Work Type TREE REMOVAL AND TREE / BRUSH REMOVAL
 
0.001 245153.67 0.00 245153.68 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-26-16
Work Began 02-03-16
Work Completed 04-07-16
Time Computed 01-27-16
Contract Working Days 65
Addl Days Granted 0
Working Days Charged 46
Percent Time Used 70
Contractor(s)
TIBH INDUSTRIES, INC.
RELIEF ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6298-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12150652
Totals 245153.67 0.00 245153.68 100.0

CountyECTOR
Highway IH0020
From VARIOUS
To VAIOUS
CSJ 6299-49-001
Proj ID SUP - 629949001
Work Type LITTER PICKUP
 
0.001 215357.01 16090.05 112168.23 52.0
Work Order 02-01-16
Work Began 02-09-16
Work Completed  
Time Computed 02-01-16
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 213
Percent Time Used 58
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6299-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01160631
Totals 215357.01 16090.05 112168.23 52.0

CountyPECOS
Highway US0190
From VARIOUS
To VARIOUS
CSJ 6299-60-001
Proj ID SUP - 629960001
Work Type PICNIC AREA MAINTENANCE
 
0.001 40240.00 0.00 8400.00 20.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-29-16
Work Began 04-01-16
Work Completed  
Time Computed 04-01-16
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 153
Percent Time Used 20
Contractor(s)
TIBH INDUSTRIES, INC.
FRESH START OF MONROE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6299-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02160631
Totals 40240.00 0.00 8400.00 20.8

CountyWARD
Highway IH0020
From VARIOUS
To VARIOUS
CSJ 6299-63-001
Proj ID RMC - 629963001
Work Type ROADSIDE MOWING
 
0.001 285440.00 0.00 58368.00 20.4
Work Order 05-23-16
Work Began 05-24-16
Work Completed  
Time Computed 06-01-16
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 100
Percent Time Used 13
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6299-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03160603
Totals 285440.00 0.00 58368.00 20.4

CountyWARD
Highway SH0018
From VARIOUS
To VARIOUS
CSJ 6299-79-001
Proj ID SUP - 629979001
Work Type PICNIC AREA MAINTENANCE
 
0.001 15134.40 910.22 3516.96 23.2
Work Order 03-30-16
Work Began 04-01-16
Work Completed  
Time Computed 04-01-16
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 153
Percent Time Used 20
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6299-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01160632
Totals 15134.40 910.22 3516.96 23.2

CountyANDREWS
Highway US0385
From ANDREWS MAINTENANCE_OFFICE
To ANDREWS MAINTENANCE OFFICE
CSJ 6300-28-001
Proj ID SUP - 630028001
Work Type JANITORIAL MAINTENANCE
 
0.001 15088.00 612.00 4484.00 29.7
Work Order 01-25-16
Work Began 02-02-16
Work Completed  
Time Computed 02-02-16
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 213
Percent Time Used 29
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6300-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01160633
Totals 15088.00 612.00 4484.00 29.7

CountyTERRELL
Highway US0090
From US90 OVERPASS AT SANDERSON CREEK
To US90 OVERPASS AT SANDERSON CREEK
CSJ 6301-00-001
Proj ID RMC - 630100001
Work Type BRIDGE SHORING
 
0.001 111000.00 0.00 96135.03 86.6
Work Order 06-28-16
Work Began 06-28-16
Work Completed  
Time Computed 06-28-16
Contract Working Days 20
Addl Days Granted 0
Working Days Charged 7
Percent Time Used 35
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6301-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04160601
Totals 111000.00 0.00 96135.03 86.6