Monthly Local Let Maintenance Report For Paris District As Of Sep 15, 2016 Page 12 Of 12
Last Update: Thursday, September 15, 2016
|
|
Contract Identification and Information |
Length |
Contract Amount |
Amount This Estimate |
Total Estimate To Date |
% Comp |
|
County | GRAYSON |
Highway |
US0069 |
From |
VARIOUS |
To |
. |
CSJ |
6308-08-001 |
Proj ID |
SUP - 630808001 |
Work Type |
JANITORIAL, GROUNDS, LANDSCAPING |
|
|
0.001 |
353918.60 |
0.00 |
0.00 |
0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order |
08-26-16 |
Work Began |
09-01-16 |
Work Completed |
|
Time Computed |
09-01-16 |
Contract Working Days |
730 |
Addl Days Granted |
0 |
Working Days Charged |
0 |
Percent Time Used |
0 |
Contractor(s) |
TIBH INDUSTRIES, INC. E.Q.U.I.P. ENTERPRISES |
SUBCONTRACTOR(S) FOR CCSJ: 6308-08-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # |
08160107 |
|
Totals |
353918.60 |
0.00 |
0.00 |
0.0 |
|
County | DELTA |
Highway |
SH0024 |
From |
DELTA COUNTY MAINTENANCE COMPLES |
To |
IN COOPER |
CSJ |
6308-40-001 |
Proj ID |
SUP - 630840001 |
Work Type |
JANITORIAL MAINTENANCE |
|
|
0.001 |
12038.07 |
0.00 |
0.00 |
0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order |
00-00-00 |
Work Began |
00-00-00 |
Work Completed |
|
Time Computed |
00-00-00 |
Contract Working Days |
365 |
Addl Days Granted |
0 |
Working Days Charged |
0 |
Percent Time Used |
0 |
Contractor(s) |
TIBH INDUSTRIES, INC. WORLD TECHNICAL SERVICES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6308-40-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # |
08160131 |
|
Totals |
12038.07 |
0.00 |
0.00 |
0.0 |
|